#REF! #REF!
PEKERJAAN : Mesjid Al - Kautsar ( 2 Lantai )
LOKASI : Karawang
PEMBULATAN Rp = 1,934,060,000
TERBILANG : SATU MILYAR SEMBILAN RATUS TIGA PULUH EMPAT JUTA ENAM PULUH RIBU RUPIAH
( ........................ )
1 / 1
RENCANA ANGGARAN BIAYA ( RAB )
HARGA BOBOT
NO ITEMS PEKERJAAN SAT VOLUME JUMLAH
SATUAN %
I PEKERJAAN PERSIAPAN
a. Pembersihan dan Perataan m2 186.23 22,275.00 4,148,329 0.21
b. Pengukuran dan bouwplank m1 154.10 83,773.58 12,909,509 0.67
Subjumlah I 17,057,838 0.88
II PEKERJAAN PONDASI
1 Pondasi batu kali menerus
a. Galian tanah m3 77.05 103,537.50 7,977,564 0.41
b. Pondasi batu kali m3 36.98 947,683.00 35,049,108 1.81
c. Pengurugan galian dgn pasir urug m3 3.85 187,143.00 720,968 0.04
d. Pengurugan dgn tanah urug t = 5 cm m3 16.95 187,143.00 3,172,261 0.16
e. Perataan Tanah dengan stemper m2 16.95 153,043.00 2,594,232 0.13
f. Adukan 1:5 tebal 5 cm ( Lt1 ) m3 9.03 147,165.15 1,328,165 0.07
2 Sloof 15 x 20 cm
a. Bekisting m2 61.64 131,529.20 8,107,460 0.42
b. Besi tulangan 4 Ø 12 Kg 549.62 95,669.75 52,582,327 2.72
c. Besi tulangan Cincin Ø8-200 Kg 182.61 95,669.75 17,470,110 0.90
d. Beton Cor K-150 m3 4.62 1,172,476.58 5,420,359 0.28
Subjumlah II 134,422,555 6.95
III PEKERJAAN STRUKTUR
1 Kolom struktur 30 x 30 cm
a. Bekisting m2 29.40 311,650.00 9,162,510 0.47
b. Besi tulangan 4 Ø 12 btg 1,747.67 95,669.75 167,198,833 8.64
c. Besi tulangan Ø8-200 btg 790.79 95,669.75 75,654,682 3.91
d. Beton Cor K-150 m3 22.05 1,172,476.58 25,853,109 1.34
2 Ring Balk 15 x 25 cm ( Lt2 )
a. Bekisting m2 64.30 131,529.20 8,457,328 0.44
b. Besi tulangan 4 Ø 12 btg 715.53 95,669.75 68,454,614 3.54
c. Besi tulangan Ø8-200 btg 271.23 95,669.75 25,948,825 1.34
d. Beton Cor K-150 m3 4.82 1,172,476.58 5,654,268 0.29
2 Ring Balk 15 x 25 cm (Atap)
a. Bekisting m2 64.30 131,529.20 8,457,328 0.44
b. Besi tulangan 4 Ø 12 btg 715.53 95,669.75 68,454,614 3.54
c. Besi tulangan Ø8-200 btg 271.23 95,669.75 25,948,825 1.34
d. Beton Cor K-150 m3 4.82 1,172,476.58 5,654,268 0.29
3 Cor t = 12 cm
Lt 2
a. Bekisting m2 117.64 392,610.00 46,186,640 2.39
b. Besi tulangan Ø10-200 Kg 3,825.77 95,669.75 366,010,527 18.92
c. Beton Cor K-250 m3 14.12 1,394,326.63 19,683,430 1.02
d. Adukan 1:5 tebal 3 cm m3 3.53 147,165.15 519,375 0.03
e. Railing Stainless m' 28.80 257,200.00 7,407,360 0.38
4 Dak Rooftop
a. Bekisting m2 141.00 392,610.00 55,358,010 2.86
b. Besi tulangan Ø10-200 Kg 2,684.92 95,669.75 256,865,860 13.28
c. Beton Cor K-250 m3 16.92 1,394,326.63 23,592,007 1.22
5 Dak Elv 3.5m
a. Bekisting m2 38.20 392,610.00 14,997,702 0.78
b. Besi tulangan Ø10-200 Kg 560.88 95,669.75 53,659,536 2.77
c. Beton Cor K-250 m3 4.58 1,394,326.63 6,391,593 0.33
Subjumlah III 1,345,571,245 69.57
Hal 1 of 2
LOKASI : Karawang
HARGA BOBOT
NO ITEMS PEKERJAAN SAT VOLUME JUMLAH
SATUAN %
IV PEKERJAAN DINDING
a. Pasangan bata m2 353.61 223,698.20 79,101,921 4.09
b. Plesteran m2 707.22 79,741.20 56,394,571 2.92
c. Acian m2 707.22 48,771.25 34,492,003 1.78
d Profil m2 3.11 147,165.15 457,389 0.02
Subjumlah IV 170,445,885 8.81
V PEKERJAAN TANGGA
a. Bekisting m2 2.04 250,654.00 511,334 0.03
b. Besi tulangan Ø8-200 Kg 164.62 95,669.75 15,748,795 0.81
c. Beton Cor K-250 m3 1.89 1,394,326.63 2,631,094 0.14
d Keramik m2 15.31 354,535.94 5,427,502 0.28
e. Railing Stainless m' 12.40 257,200.00 3,189,280 0.16
Subjumlah IV 27,508,006 1.42
VI PEKERJAAN KUSEN
a. Kusen Aluminium m2 35.20 512,935.94 18,055,345 0.93
B. Kaca 5mm polos m2 35.20 177,100.00 6,233,920 0.32
Subjumlah V 24,289,265 1.26
Hal 2 of 2