B )
KEGIATAN : PEKERJAAN PEMBUATAN SELASAR RUANG PEMULASARAN DAN RUANG JENAZAH
PEKERJAAN : PERENCANAAN PEKERJAAN PEMBUATAN SELASAR RUANG PEMULASARAN DAN RUANG JENAZAH
LOKASI : RSUD Dr. R. SOEPRAPTO CEPU
SUMBER DANA : BLUD
TAHUN ANGGARAN : 2022
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT. VOLUME ANALIS SATUAN PPN 11% HARGA + PPN 11%
( Rp. ) ( Rp ) ( Rp. )
1 2 3 4 5 6 7 8
PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan (Pengadaan Air kerja dan listrik kerja) ls 1.00 Ls 5,000,000.00 550,000.00 Rp 5,550,000.00
2 Pemasangan Papan Nama Proyek ls 1.00 Ls 150,000.00 16,500.00 Rp 166,500.00
3 Keselamatan Dan Kesehatan Kerja ls 1.00 1.19 2,660,000.00 292,600.00 Rp 2,952,600.00
JUMLAH PEK. PERSIAPAN Rp 8,669,100.00
I FOOTPLATE
1 Galian m3 4.03 A.2.3.1 77,308.00 8,503.88 Rp 345,993.50
2 Urugan Pasir m3 0.50 A.2.3.1.11 225,803.20 24,838.35 Rp 126,323.34
3 Rabat Beton / Lantai Kerja m3 0.25 A.4.1.1.4 978,348.46 107,618.33 Rp 273,663.63
4 Cor Beton Bertulang Footplat
- Pembesian kg 226.80 A.4.1.1.17.a 16,093.17 1,770.25 Rp 4,051,422.86
- Bekisting m2 5.04 A.4.1.1.20 172,206.72 18,942.74 Rp 963,393.27
- Cor Beton f'c=19,3 MPa (K225) m3 1.51 A.4.1.1.7 1,203,261.05 132,358.72 Rp 2,019,457.08
JUMLAH PEK. FOOTPLATE Rp 7,780,253.69
II KOLOM PEDESTAL
- Bekisting m2 8.40 A.4.1.1.22.a 208,346.69 22,918.14 Rp 1,942,624.53
- Pembesian kg 318.17 A.4.1.1.17.a 16,093.17 1,770.25 Rp 5,683,660.10
- Cor Beton f'c=19,3 MPa (K225) m3 1.26 A.4.1.1.7 1,203,261.05 132,358.72 Rp 1,682,880.90
JUMLAH PEK. KOLOM PEDESTAL Rp 9,309,165.53
III PONDASI
1 Galian Tanah m3 5.40 A.2.3.1 77,308.00 8,503.88 Rp 463,384.15
2 Urugan Pasir m3 2.25 A.2.3.1.11 225,803.20 24,838.35 Rp 563,943.49
3 Pasangan Batu m3 4.05 A.3.2.1.3 894,617.61 98,407.94 Rp 4,021,753.45
JUMLAH PEK. PONDASI Rp 5,049,081.09
IV SLOOF
- Pembesian kg 249.68 A.4.1.1.17.a 16,093.17 1,770.25 Rp 4,460,182.49
- Bekisting m2 13.50 A.4.1.1.21.a 118,535.76 13,038.93 Rp 1,776,258.36
- Cor Beton f'c=19,3 MPa (K225) m3 2.70 A.4.1.1.7 1,203,261.05 132,358.72 Rp 3,606,173.36
JUMLAH PEK. SLOOF Rp 9,842,614.20
VI PEKERJAAN ATAP
1 Gording CNP 100 x 50 x 20 x 3.2 kg 539.78 A.4.2.1.1 35710.88 3,928.20 Rp 21,396,539.43
2 Usuk Reng Rangka Baja Ringan C 75 m2 155.61 dihitung 189,055.50 20,796.11 Rp 32,655,008.25
3 Genteng Keramik m2 155.61 A.4.5.2.3.B 187,569.76 20,632.67 Rp 32,398,380.69
4 Nok Bubung Atap Genteng Keramik m1 31.50 A.4.5.2.6A 198,022.90 21,782.52 Rp 6,923,870.67
5 Listplang Kalsiboard lebar 20 cm m1 63.00 dihitung 47,503.13 5,225.34 Rp 3,321,893.53
6 Atap Kanopi Parkir Ambulan m2 10.00 dihitung 500,000.00 55,000.00 Rp 5,550,000.00
JUMLAH PEK. ATAP Rp 102,245,692.58
IX KOLOM
1 Pasangan Bata m2 50.40 A.4.4.1.11 12,293.48 1,352.28 Rp 687,746.45
2 Plester m2 50.40 A.4.4.2.4 69,039.10 7,594.30 Rp 3,862,323.48
3 Aci m2 50.40 A.4.4.2.27 38,472.19 4,231.94 Rp 2,152,288.06
4 Cat m2 30.24 A.4.7.1.10 53,384.63 5,872.31 Rp 1,791,929.68
JUMLAH PEK. KOLOM Rp 8,494,287.66
X PEKERJAAN LISTRIK
1 Instalasi titik 10.00 ME.01 249,300.00 27,423.00 Rp 2,767,230.00
2 Armature Lampu & Aksesoris bh 10.00 dihitung 150,000.00 16,500.00 Rp 1,665,000.00
3 Saklar Ganda bh 2.00 dihitung 13 68,750.00 7,562.50 Rp 152,625.00
JUMLAH PEK. LISTRIK Rp 4,584,855.00
Blora, 2022
Megetahui Dibuat Oleh :
Pejabat Pembuat Komitmen Konsultan Perencana
CV. STATIKAGISTA