JUMLAH Rp 73,787,317.31
PPn 11% Rp 8,116,604.90
JUMLAH TOTAL Rp 81,903,922.22
DIBULATKAN Rp 81,903,000.00
Terbilang : Delapan Puluh Satu Juta Sembilan Ratus Tiga Ribu Rupiah
1 2 3 4 5 6
A PEKERJAAN PERSIAPAN
1 Pembersihan 1.00 unit Ls 100,000.00 100,000.00
2 Pengukuran dan Bowplang 1.00 unit Ls 100,000.00 100,000.00
Sub Jumlah 200,000.00
B PEKERJAAN TANAH
1 Galian tanah 6.40 m3 A.2.3.1.1 68,612.50 439,120.00
2 Urugan tanah Kembali Bekas Galian 2.11 m3 A.2.3.1.9 49,225.00 103,864.75
3 Urugan pasir bawah pondasi 0.64 m3 A.2.3.1.11 172,645.00 110,492.80
Sub Jumlah 653,477.55
C PEKERJAAN PASANGAN
1 Pasang Bata Merah Tebal 1/2 Bata , 1 Pc : 5 Pp 19.95 m2 A.4.4.1.10 98,110.10 1,957,296.50
2 Plesteran 1 PC : 5 PP, tebal 15 mm 61.85 m2 A,4,4,2.5 55,803.88 3,451,469.98
3 Acian 61.85 m2 A,4,4,2.27 33,880.00 2,095,478.00
Sub Jumlah 7,504,244.47
2. KOLOM 15/15
1 Beton Dengan Mutu f'c = 14,5 Mpa ( K-175 ) 0.24 m3 A.4.1.1.5 862,458.67 206,990.08
2 Begisting 6.00 m2 A.4.1.1.20 153,010.00 918,060.00
3 Pembesian 59.97 kg A.4.1.1.17 19,144.95 1,148,122.66
3. RINGBALK 15/20
1 Beton Dengan Mutu f'c = 14,5 Mpa ( K-175 ) 0.28 m3 A.4.1.1.5 862,458.67 242,390.30
2 Begisting 5.12 m2 A.4.1.1.20 153,010.00 783,411.20
3 Pembesian 41.79 kg A.4.1.1.17 19,144.95 800,067.45
Sub Jumlah 9,182,417.01
G PEKERJAAN LISTRIK
1 Instalasi Listrik 4.00 ttk Di Hit 1 157,190.00 628,760.00
2 Stop Kontak 1.00 bh Di Hit 2 78,991.00 78,991.00
3 Saklar double 1.00 bh Di Hit 2 78,991.00 78,991.00
4 Lampu SL 10 Watt 4.00 bh Di Hit 3 42,900.00 171,600.00
Sub Jumlah 958,342.00
JUMLAH Rp 73,787,317.31
PPn 11% Rp 8,116,604.90
JUMLAH TOTAL Rp 81,903,922.22
DIBULATKAN Rp 81,903,000.00
Terbilang : Delapan Puluh Satu Juta Sembilan Ratus Tiga Ribu Rupiah
8,115,682.69
Cilacap, 17 Februari 2023
CV ARKEYNO
B PEKERJAAN TANAH
1 Galian tanah 6.40 m3 0.595 0.298 0.298
2 Urugan tanah Kembali Bekas Galian 2.11 m3 0.141 0.056 0.042 0.042
3 Urugan pasir bawah pondasi 0.64 m3 0.150 0.075 0.075
C PEKERJAAN PASANGAN
1 Pasang Bata Merah Tebal 1/2 Bata , 1 Pc : 5 Pp 19.95 m2 2.653 0.796 0.796 0.796 0.265
2 Plesteran 1 PC : 5 PP, tebal 15 mm 61.85 m2 4.678 1.169 1.169 1.169 1.169
3 Acian 61.85 m2 2.840 0.710 0.710 0.710 0.710
BULAN I
NO. URAIAN PEKERJAAN VOLUME BOBOT Minggu Ke- PROSENTASE
1 2 3 4 5 6 7 8 9 10 11 12 13
G PEKERJAAN LISTRIK
1 Instalasi Listrik 4.00 ttk 0.852 0.852
2 Stop Kontak 1.00 bh 0.107 0.107
3 Saklar double 1.00 bh 0.107 0.107
4 Lampu SL 10 Watt 4.00 bh 0.233 0.233
PER MINGGU 100.00 0.27 0.37 1.42 3.44 5.84 3.44 3.35 10.11 6.67 24.16 21.05 16.03 3.84
TARGET (%)
KOMULATIF - 0.27 0.64 2.06 5.51 11.35 14.79 18.14 28.25 34.92 59.08 80.13 96.16 100.00
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
(Rp)
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp
A.4.4.1.10 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata 98,110.10
m3 Tenaga 35,375.00
L.01 0.30 OH Pekerja 80,000.00 24,000.00
L.02 0.1 OH Tukang Batu 90,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 95,000.00 950.00
L.04 0.015 OH Mandor 95,000.00 1,425.00
OH Bahan 53,816.00
70 Buah Bata Merah 5 x 11 x 22 500.00 35,000.00
9.68 Kg Portland Semen 1,200.00 11,616.00
0.045 m3 Pasir Pasang 160,000.00 7,200.00
C PERALATAN
D Jumlah A + B + C 89,191.00
E Overhead & Profit 10% 10% 8,919.10
F Harga Satuan Pekerjaan (D+E) 98,110.10
Rp Rp
A.4.1.1.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 862,458.67
A Tenaga 167,295.00
L.01 1.65 OH Pekerja 80,000.00 132,000.00
L.02 0.275 OH Tukang Batu 90,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 95,000.00 2,660.00
L.04 0.083 OH Mandor 95,000.00 7,885.00
B Bahan 616,758.33
326 Kg Portland Semen 1,200.00 391,200.00
760 Kg Pasir Beton 115.94 88,115.94
1,029 Kg Batu 2/3 130.43 134,217.39
215 ltr Air 15.00 3,225.00
C PERALATAN
D Jumlah A + B + C 784,053.33
E Overhead & Profit 10% 10% 78,405.33
F Harga Satuan Pekerjaan (D+E) 862,458.67
HARGA
JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN BAHAN/UPAH
Rp Rp