Anda di halaman 1dari 2

TIME SCHEDULE ( CURVE - S )

Nama Paket : PENINGKATAN JALAN POROS SEKERAT (DAK PENUGASAN)


Nomor Kontrak : 60060/47/DPU-BM/SPK/PNK.JL.PS/DAK/III/2021
Tanggal Kontrak : 10 Maet 2021
Sumber Dana : APBD KAB. KUTAI TIMUR T.A. 2021
Lokasi : Kec. Bengalon - Kutai Timur (Kab.)
KntraktorPelaksana : PT. DIMENSI GLOBAL
Konsultan Pegawas : CV.ADEF ENGINEERING
Tahun Anggaran : 2021

TAHUN 2021

MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER


Nomor
BOBOT 10/03/21 18/03/21 26/03/21 02/04/21 10/04/21 18/04/21 26/04/21 02/05/21 10/05/21 18/05/21 26/05/21 03/06/21 10/06/21 18/06/21 26/06/21 02/07/21 10/07/21 18/07/21 26/07/21 02/08/21 10/08/21 18/08/21 26/08/21 02/09/21 10/09/21 18/09/21 26/09/21 03/10/21
Mata URAIAN KET
(%)
Pemb S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D

17/03/21 25/03/21 01/04/21 09/04/21 17/04/21 25/04/21 01/05/21 09/05/21 17/05/21 25/05/21 02/06/21 09/06/21 17/06/21 25/06/21 01/07/21 09/07/21 17/07/21 25/07/21 01/08/21 09/08/21 17/08/21 25/08/21 01/09/21 09/09/21 17/09/21 25/09/21 02/10/21 10/10/21

M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28

1.2 Mobilisasi 2,000 0,70 0,70 0,60 100%


1.9 Manajemen Keselamatan lalu lintas 0,951 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03

1.21 Keselamatan dan Kesehatan Kerja 0,611 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03 0,03

DIVISI 1. UMUM 3,562

2.1.(1) Galian untuk Selokan Drainase dan Saluran Air 0,950 0,16 0,16 0,16 0,16 0,16 0,16 75%
2.2.(1) Pasangan Batu dengan Mortar 8,975 1,28 1,28 1,28 1,28 1,28 1,28 1,28

DIVISI 2. DRAINASE 9,925

3.2.(2a) Timbunan Biasa 0,909 0,15 0,15 0,15 0,15 0,15 0,15

3.3.(1) Penyiapan Badan Jalan 1,820 0,36 0,36 0,36 0,36 0,36

DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 2,729


50%
5.1.(1) Lapis Fondasi Agregat Kelas A 10,836 2,17 2,17 2,17 2,17 2,17

5.1.(1) Lapis Fondasi Agregat Kelas B 13,634 1,95 1,95 1,95 1,95 1,95 1,95 1,95

DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN 24,470

6.1.(1) Lapis Resap Pengikat - Aspal Cair/Emulsi 4,106 0,59 0,59 0,59 0,59 0,59 0,59 0,59 25%
6.3.(6a) Laston Lapis Aus (AC-BC) 40,862 5,11 5,11 5,11 5,11 5,11 5,11 5,11 5,11
GARIS RENCANA PELAKSANAAN
DIVISI 6. PERKERASAN ASPAL 44,968

7.1.(8) Beton, fc15 MPa (Bahu Jalan) 11,672 3,89 3,89 3,89

DIVISI 7. STRUKTUR 11,672

9.2.(1) Marka Jalan Termoplastik 2,674 2,67 0%


DIVISI 9. PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 2,674

100,000

BOBOT RENCANA PROGRESS FISIK MINGGUAN ( % ) 100,000 0,734 0,734 0,192 0,192 1,626 1,654 1,654 2,018 1,859 3,807 3,656 2,374 4,177 4,177 4,177 4,177 7,923 5,756 5,756 5,756 5,756 5,756 5,756 5,170 3,952 3,952 3,952 3,308

JUMLAH BOBOT KOMULATIF RENCANA FISIK MNGGUAN (%) - 0,734 1,468 1,661 1,853 3,479 5,132 6,786 8,804 10,663 14,471 18,126 20,500 24,676 28,853 33,030 37,206 45,129 50,886 56,642 62,398 68,154 73,910 79,666 84,835 88,787 92,740 96,692 100,000

BOBOT REALISASI PROGRESS FISIK MINGGUAN ( % )

JUMLAH BOBOT KOMULATIFREALISASI PROGRESS FISIK MNGGUAN (%)

DEVIASI ( % )
Kutai Trimur, 11 Maret 2021
Diseujui Oleh, Diperiksa Oleh, DiBuat Oleh,
PEMERINTAH KABUPATEN KUTAI TMUR Konsultan Pengawas, Kontraktor Pelaksana,
Dinas Pekerjaan Umum CV.ADEF EGINEERING PT.DIMENSI GLOBAL
Pejabat Pembuat Komitmen

HARRIS AFANDI MD,ST.,MM KOMARUDIN,ST HADITYAN PUTRA PRATAMA,ST


NIP.1980914 200903 003 Site Engineer General Superintendent

Anda mungkin juga menyukai