1 TIME SCHEDULE

JADWAL RENCANA PELAKSANAAN DAN REALISASI KEMAJUAN PEKERJAAN


Nama Paket : Penanganan Long Segment (Pemeliharaan Rutin, Pemeliharaan Berkala, Peningkatan/Rekonstruksi) Jalan Ruas Salutambung - Urekang
Lokasi : Poros Salutambung-Urekang,Kec.Ulumanda,Kab.Majene
No.Kontrak : B-1802.07/1384/III/2023
TGL.Kontrak : 3 Maret 2023
Tahun Anggaran : 2023
Bulan Ke I Bulan Ke II Bulan Ke III Bulan Ke IV Bulan Ke V Bulan Ke VI Bulan Ke VII Bulan Ke VIII
JUMLAH Mg. I Mg. II Mg. III Mg. IV Mg. V Mg. VI Mg. VII Mg. VIII Mg. IX Mg. X Mg. XI Mg. XII Mg. XIII Mg. XIV Mg. XV Mg. XVI Mg. XVII Mg. XVIII Mg. XIX Mg. XX Mg. XXI Mg. XXII Mg. XXIII Mg. XXIV Mg. XXV Mg. XXVI Mg. XXVII Mg. XXVIII Mg. XXIX Mg. XXX Mg. XXXI Mg. XXXII
No. Mata BOBOT
URAIAN PEKERJAAN HARGA 27-Feb 6-Mar 14-Mar 21-Mar 29-Mar 5-Apr 13-Apr 20-Apr 28-Apr 5-May 13-May 20-May 28-May 4-Jun 12-Jun 19-Jun 27-Jun 4-Jul 12-Jul 19-Jul 27-Jul 3-Aug 11-Aug 18-Aug 26-Aug 2-Sep 10-Sep 17-Sep 25-Sep 2-Oct 10-Oct 17-Oct Ket.
Pembayaran (%)
(Rp.) s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d
5-Mar 13-Mar 20-Mar 28-Mar 4-Apr 12-Apr 19-Apr 27-Apr 4-May 12-May 19-May 27-May 3-Jun 11-Jun 18-Jun 26-Jun 3-Jul 11-Jul 18-Jul 26-Jul 2-Aug 10-Aug 17-Aug 25-Aug 1-Sep 9-Sep 16-Sep 24-Sep 1-Oct 9-Oct 16-Oct 24-Oct

DIVISI 1. UMUM
1.2 Mobilisasi
100%
1.2 Mobilisasi 63,410,000.00 0.303 0.101 0.101 0.101

1.21 Manajemen Mutu


1.21 Manajemen Mutu 26,000,000.00 0.124 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004

1.1.22 SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)


1.19 Keselamatan dan Kesehatan Kerja 93,991,783.00 0.449 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014

DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air 38,830,847.50 0.185 0.009 0.019 0.028 0.037 0.037 0.028 0.019 0.009

2.2.(1) Pasangan Batu dengan Mortar 616,012,631.66 2.940 0.147 0.294 0.441 0.588 0.588 0.441 0.294 0.147

DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK


3.1.(1) Galian Biasa 149,712,832.50 0.714 0.048 0.095 0.143 0.191 0.238

3.1.(3) Galian Batu 21,078,045.00 0.101 0.007 0.013 0.020 0.027 0.034

3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter 2,054,525.29 0.010 0.003 0.003 0.003

3.2.(2a) Timbunan Pilihan dari sumber galian 416,641,525.95 1.988 0.199 0.398 0.596 0.795 50%

3.3.(1) Penyiapan Badan Jalan 29,523,548.60 0.141 0.009 0.019 0.028 0.038 0.047

DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON


5.3.(1.a) Perkerasan Beton Semen 9,233,451,920.01 44.064 0.306 0.612 0.918 1.224 1.530 1.836 2.142 2.448 2.754 3.060 3.366 3.672 3.366 3.060 2.754 2.448 2.142 1.836 1.530 1.224 0.918 0.612 0.306

5.3.(3) Lapis Pondasi bawah Beton Kurus 2,020,985,574.66 9.644 0.067 0.134 0.201 0.268 0.335 0.402 0.469 0.536 0.603 0.670 0.737 0.804 0.737 0.670 0.603 0.536 0.469 0.402 0.335 0.268 0.201 0.134 0.067

DIVISI 7. STRUKTUR
7.1 (7a) Beton strukur, fc’20 MPa 14,851,212.20 0.071 0.008 0.016 0.008 0.016 0.008 0.016

7.1 (8) Beton , fc’15 Mpa 3,741,903,779.38 17.857 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190 1.190

7.3 (1) Baja Tulangan Polos-BjTP 280 25,766,277.38 0.123 0.014 0.027 0.000 0.000 0.014 0.027 0.000 0.000 0.014 0.027

7.9.(1) Pasangan Batu 3,894,685,367.49 18.586 0.123 0.246 0.369 0.492 0.615 0.739 0.862 0.985 1.354 1.231 0.985 1.477 1.354 1.231 1.108 0.985 1.354 1.231 0.615 0.492 0.369 0.246 0.123

DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN


9.2.(1) Marka Jalan Termoplastik 108,490,979.44 0.518 0.518

DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA


10.1.(22) Pengendalian Tanaman 457,438,993.54 2.183 0.546 0.546 0.546 0.546
0%

(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 20,954,829,843.61
(B) Pajak Pertambahan Nilai ( PPN ) = 11% x (A) 2,305,031,282.80
100.000 Jangka Waktu Pelaksanaan 240 (Dua Ratus Empat Puluh) Hari Kalender
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 23,259,861,126.40
DIBULATKAN 23,259,861,126.00
BOBOT RENCANA (%) 0 0.119 0.027 0.091 0.155 0.218 0.282 0.488 0.516 1.110 1.805 1.506 2.002 2.498 2.994 3.490 3.986 6.100 6.525 6.765 7.786 7.315 6.681 5.985 5.333 5.198 4.720 3.689 3.193 3.242 2.746 2.250 1.182
BOBOT KOMULATIF RENCANA (%) 0 0.119 0.146 0.237 0.392 0.610 0.892 1.381 1.897 3.008 4.813 6.319 8.321 10.819 13.814 17.304 21.290 27.391 33.915 40.680 48.466 55.780 62.461 68.447 73.780 78.978 83.698 87.386 90.579 93.821 96.568 98.818 100.000
BOBOT AKTUAL (%) 0 0.100 0.230 0.190 0.260
BOBOT KOMULATIF AKTUAL (%) 0 0.100 0.330 0.520 0.780