TIME SHEDULE

STATUS : 19 JUNI S/D 07 JULI 2023


PROGRAM : PENYELENGGARAAN JALAN
KEGIATAN : PENYELENGGARAAN JALAN KABUPATEN/KOTA
SUB KEGIATAN : PEMBANGUNAN JALAN
PEKERJAAN : PENINGKATAN JALAN MUNGGUK - ENGKANYAR
NOMOR KONTRAK : 602.1/04/SPK-T/FSK/BM-DPUPRPERA/2023
TANGGAL KONTRAK : 08 JUNI 2023
NOMOR SPMK : 602.1/04/SPMK-T/FSK/BM-DPUPRPERA/2023
TANGGAL SPMK : 19 JUNI 2023
LOKASI PEKERJAAN : KECAMATAN NGABANG DAN KUALA BEHE KABUPATEN LANDAK

JADWAL WAKTU PELAKSANAAN


%
BOBOT ( % ) BULAN
NO. URAIAN VOLUME
JUNI JULI AGUSTUS SEPTEMBER

KONTRAK ( 19 - 25 ) ( 26 - 02 ) ( 03 - 09 ) ( 10 - 16 ) ( 17 - 23 ) ( 24 - 30) ( 31 - 06 ) ( 07 - 13 ) ( 14 - 20 ) ( 21 - 27) ( 28 - 03) ( 04 - 10 ) ( 11 - 17)

1 DIVISI 1 UMUM 3.44


1.1 Mobilisasi 1.00 3.236 1.000 1.200
98.96 100.00
1.040 100.00
1. Safety Helmet (Perlengkapan K3) 10.00 0.017 0.017
2. Safety Rompi (Perlengkapan K3) 10.00 0.017 0.017 92.35
3. Safety Boot Karet (Perlengkapan K3) 10.00 0.036 0.036
4. Sarung Tangan (Perlengkapan K3) 10.00 0.002
Petugas Keselamatan dan Kesehatan Kerja ( K3 ) Konstruksi 1.00 0.085 0.021 0.021 81.85
0.021 0.021
Rambu Petunjuk Arah 3.00 0.044 0.044

3 DIVISI 4. PEKERJAAN TANAH DAN GEOSINTETIK 60.76 68.17


3.1 Galian Biasa Dengan Mekanik ( Bulldozer ) 7,500.00 4.38 1.094 1.094 1.094 1.094
3.2 Galian Biasa 3,318.76 7.96 1.989 1.989 1.989 1.989
3.3 Timbunan Pilihan dari sumber galian 2,380.00 48.43 4.000 2.000 11.000 12.000 6.000 8.000 5.430 50.00
49.97
5 DIVISI 7. STRUKTUR 34.86
5.1 Beton Struktur f'c 20 Mpa 210.60 20.36 2.500 3.000 1.500 2.500 4.200 3.000 2.500 1.160
5.2 Beton Siklop, fc’15 Mpa 43.23 2.12 1.200 0.920
5.3 Baja Tulangan Sirip BjTS 420 A 7,688.90 5.74 33.73 2.000 3.740
5.4 Pasangan Batu 180.75 6.64 1.000 2.100 2.000 1.540
27.14
6 DIVISI 8. REHABILITASI JEMBATAN 0.94 16.96
6.1 Penggantian Lantai Kayu 1.44 0.51 0.511 12.86
6.2 1.35
Penggantian Gelegar Kayu 0.32 5.42 0.322
6.3 Perbaikan Papan Lajur Kendaraan 0.36 0.10 - 1.07 2.33 0.104 0.00

JUMLAH 100.00

A RENCANA
- Progres Mingguan 1.070 1.265 3.083 7.438 4.105 10.183 6.583 16.240 18.200 13.681 10.500 6.611 1.040
- Komulatif Mingguan - 1.07 2.33 5.42 12.86 16.96 27.14 33.73 49.97 68.17 81.85 92.35 98.96 100.00
- Progres Bulanan 2.334 27.143 92.348 100.00
B REALISASI
- Progres Mingguan - - 1.45
- Komulatif Mingguan - - - 1.45
- Progres Bulanan -
C DEVIASI ( % ) -2.33 -3.96
LAPORAN MINGGUAN KE 3
PROGRAM : PENYELENGGARAAN JALAN
KEGIATAN : PENYELENGGARAAN JALAN KABUPATEN/KOTA
SUB KEGIATAN : PEMBANGUNAN JALAN
PEKERJAAN : PENINGKATAN JALAN MUNGGUK - ENGKANYAR ( 03 - 09 )
NOMOR KONTRAK : 602.1/04/SPK-T/FSK/BM-DPUPRPERA/2023
TANGGAL KONTRAK : 08 JUNI 2023
NOMOR SPMK : 602.1/04/SPMK-T/FSK/BM-DPUPRPERA/2023
TANGGAL SPMK : 19 JUNI 2023
LOKASI PEKERJAAN : KECAMATAN NGABANG DAN KUALA BEHE KABUPATEN LANDAK

KONTRAK KEMAJUAN PEKERJAAN

NO. URAIAN ASAL ADDENDUM 01 S/D MINGGU LALU MINGGU INI SAMPAI MINGGU INI KETERANGAN

QTY BOBOT (%) QTY BOBOT (%) KUANTITAS BOBOT (%) KUANTITAS BOBOT (%) KUANTITAS BOBOT (%)

1 DIVISI 1 UMUM 3.437


1.1 Mobilisasi 1.000 3.236 - - 0.404 1.307 0.404 1.307
1. Safety Helmet (Perlengkapan K3) 10.000 0.017 - - - - -
2. Safety Rompi (Perlengkapan K3) 10.000 0.017 - - - - -
3. Safety Boot Karet (Perlengkapan K3) 10.000 0.036 - - - - -
4. Sarung Tangan (Perlengkapan K3) 10.000 0.002 - - - - -
Petugas Keselamatan dan Kesehatan Kerja ( K3 ) Konstruksi 1.000 0.085 - - - - -
Rambu Petunjuk Arah 3.000 0.044 - - - - -

3 DIVISI 4. PEKERJAAN TANAH DAN GEOSINTETIK 60.761


3.1 Galian Biasa Dengan Mekanik ( Bulldozer ) 7,500.000 4.376 - - - - -
3.2 Galian Biasa 3,318.760 7.957 - - - - -
3.3 Timbunan Pilihan dari sumber galian 2,380.000 48.428 - - - - -

5 DIVISI 7. STRUKTUR 34.865


5.1 Beton Struktur f'c 20 Mpa 210.600 20.362 - - - - -
5.2 Beton Siklop, fc’15 Mpa 43.230 2.124 - - - - -
5.3 Baja Tulangan Sirip BjTS 420 A 7,688.900 5.736 - - - - -
5.4 Pasangan Batu 180.750 6.642 - - 4.000 0.147 4.000 0.147

6 DIVISI 8. REHABILITASI JEMBATAN 0.938


6.1 Penggantian Lantai Kayu 1.440 0.511 - - - - -
6.2 Penggantian Gelegar Kayu 1.350 0.322 - - - - -
6.3 Perbaikan Papan Lajur Kendaraan 0.360 0.104 - - - - -

JUMLAH 100.000
REALISASI ( %) - 1.45 1.45
RENCANA ( % ) 5.418
DEVIASI ( % ) - 3.963