TIME SCHEDULE ( CURVE - S )

Nama Paket : PENINGKATAN JALAN POROS SEKERAT (DAK PENUGASAN)


Nomor Kontrak : 60060/47/DPU-BM/SPK/PNK.JL.PS/DAK/III/2021
Tanggal Kontrak : 10 Maet 2021
Sumber Dana : APBD KAB. KUTAI TIMUR T.A. 2021
Lokasi : Kec. Bengalon - Kutai Timur (Kab.)
KntraktorPelaksana : PT. DIMENSI GLOBAL Sertifikat Bulanan No. : 03
Konsultan Pegawas : CV.ADEF ENGINEERING Periode Bulan : MEI 2021
Tahun Anggaran : 2021

TAHUN 2021

MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER


Nomor
BOBOT 10/03/21 18/03/21 26/03/21 02/04/21 10/04/21 18/04/21 26/04/21 02/05/21 10/05/21 18/05/21 26/05/21 03/06/21 10/06/21 18/06/21 26/06/21 02/07/21 10/07/21 18/07/21 26/07/21 02/08/21 10/08/21 18/08/21 26/08/21 02/09/21 10/09/21 18/09/21 26/09/21 03/10/21
Mata URAIAN KET
(%)
Pemb S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D S/D

17/03/21 25/03/21 01/04/21 09/04/21 17/04/21 25/04/21 01/05/21 09/05/21 17/05/21 25/05/21 02/06/21 09/06/21 17/06/21 25/06/21 01/07/21 09/07/21 17/07/21 25/07/21 01/08/21 09/08/21 17/08/21 25/08/21 01/09/21 09/09/21 17/09/21 25/09/21 02/10/21 10/10/21

M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28

1.2 Mobilisasi 2.000 0.56 0.84 0.60


100%
1.9 Manajemen Keselamatan lalu lintas 0.951 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

1.21 KeselamatanMutu
Manajemen dan Kesehatan Kerja 0.611 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

DIVISI 1. UMUM 3.562

2.1.(1) Galian untuk Selokan Drainase dan Saluran Air 0.950 0.24 0.24 0.24 0.24
75%
2.2.(1) Pasangan Batu dengan Mortar 8.975 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90

DIVISI 2. DRAINASE 9.925


GARIS RENCANA

3.2.(2a) Timbunan Biasa 0.909 0.23 0.23 0.23 0.23

3.3.(1) Penyiapan Badan Jalan 1.820 0.36 0.36 0.36 0.36 0.36

DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 2.729


50%
5.1.(1) Lapis Fondasi Agregat Kelas A 10.836 2.17 2.17 2.17 2.17 2.17

5.1.(1) Lapis Fondasi Agregat Kelas B 13.634 1.95 1.95 1.95 1.95 1.95 1.95 1.95

DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN 24.470

6.1.(1) Lapis Resap Pengikat - Aspal Cair/Emulsi 4.106 0.59 0.59 0.59 0.59 0.59 0.59 0.59
25%
6.3.(6a) Laston Lapis Aus (AC-BC) 40.862 5.11 5.11 5.11 5.11 5.11 5.11 5.11 5.11

DIVISI 6. PERKERASAN ASPAL 44.968


GARIS REALISASI
7.1.(8) Beton, fc15 MPa (Bahu Jalan) 11.672 3.89 3.89 3.89
PROGRESS PELAKSANAAN
DIVISI 7. STRUKTUR 11.672

9.2.(1) Marka Jalan Termoplastik 2.674 2.67


0%
DIVISI 9. PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 2.674

JUMLAH TOTAL BOBOT PEKERJAAN ( % ) 100.000

BOBOT RENCANA PROGRESS FISIK MINGGUAN ( % ) 0.594 0.874 0.271 0.271 1.169 1.197 0.959 1.323 1.323 3.271 3.271 3.271 5.074 5.074 4.177 4.177 7.923 5.756 5.756 5.756 5.756 5.983 5.983 5.397 4.179 3.952 3.952 3.308

JUMLAH BOBOT KOMULATIF RENCANA FISIK MNGGUAN (%) - 0.594 1.468 1.740 2.011 3.180 4.377 5.336 6.659 7.983 11.254 14.525 17.796 22.870 27.944 32.121 36.298 44.221 49.977 55.733 61.489 67.245 73.228 79.211 84.608 88.787 92.740 96.692 100.000

BOBOT REALISASI PROGRESS FISIK MINGGUAN ( % ) 0.297 0.157 0.489 0.675 0.730 0.800 1.691 1.869 1.905 1.933

JUMLAH BOBOT KOMULATIFREALISASI PROGRESS FISIK MNGGUAN (%) 0.297 0.454 0.943 1.618 2.348 3.149 4.839 6.708 8.613 10.546

DEVIASI ( % ) - 0.297 - 1.014 - 0.796 - 0.393 - 0.832 - 1.228 - 0.497 0.049 0.630 - 0.708