RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN BULAN LALU BULAN INI BULAN INI BULAN LALU BULAN INI BULAN INI KETERANGAN
PEMBA
BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
YARAN SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi LS 1,00 10,23 - - 0,22 2,27 0,22 2,27 - - 0,30 3,07 0,30 3,07 0,80
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(9) Galian Perkerasan berbutir M3 36,00 4,25 - - 25,00 2,95 25,00 2,95 - - 15,32 1,81 15,32 1,81 (1,14)
DIVISI 7. STRUKTUR
7.1 (8) Beton , fc’15 Mpa M3 36,00 85,52 - - - - - - - - - - - - -
JUMLAH BOBOT PEKERJAAN (%) 100,00 - 5,22 5,22 - 4,88 4,88 (0,35)
RENCANA REALISASI
NO. KONTRAK S/D RENCANA S/D S/D PRESTASI S/D
MATA DEVIASI
URAIAN BULAN LALU BULAN INI BULAN INI BULAN LALU BULAN INI BULAN INI KETERANGAN
PEMBA
BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT BOBOT
YARAN SAT. VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME VOLUME
(%) (%) (%) (%) (%) (%) (%) (%)
DIVISI 1. UMUM
1.2 Mobilisasi LS 1,00 10,23 0,22 2,27 0,44 4,55 0,67 6,82 0,30 3,07 0,70 7,16 1,00 10,23 3,41
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(9) Galian Perkerasan berbutir M3 36,00 4,25 25,00 2,95 11,00 1,30 36,00 4,25 15,32 1,81 20,68 2,44 36,00 4,25 -
DIVISI 7. STRUKTUR
7.1 (8) Beton , fc’15 Mpa M3 36,00 85,52 - - 27,00 64,14 27,00 64,14 - - 36,00 85,52 36,00 85,52 21,38
JUMLAH BOBOT PEKERJAAN (%) 100,00 5,22 69,99 75,21 4,88 95,12 100,00 24,79