Kalender
-
III PERKERASAN JALAN -
1 Geotextile 5,783 0,578 0,578 0,578 0,578 0,578 0,578 0,578 0,578 0,578 0,578
2 Lapis Pondasi Agregat Kelas A Stone Crusher 75,802 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053 5,053
-
IV PEKERJAAN TAMBAHAN -
1 Berem 9,199 1,314 1,314 1,314 1,314 1,314 1,314 1,314
2 Drain Hole 5,300 0,757 0,757 0,757 0,757 0,757 0,757 0,757
0%
RENCANA KEMAJUAN MINGGUAN 100,00 0,559 1,138 6,948 6,948 6,948 6,948 6,948 6,389 6,389 5,632 6,946 6,368 6,368 6,368 6,368 6,368 6,368 -
RENCANA KOMULATIF MINGGUAN - 0,559 1,697 8,646 15,594 22,542 29,491 36,439 42,828 49,217 54,849 61,795 68,162 74,530 80,897 87,265 93,632 100,00 100,00
DEVIASI