JADWAL WAKTU PELAKSANAAN

WAKTU PELAKSANAAN 130 HARI KALENDER


ORIGINAL
NO. DIVISI URAIAN Harga Satuan (Rp) SAT MEI JUNI JULI AGUSTUS SEPTEMBER Keterangan
Kuantitas Harga Bobot (%)
11 - 17 18 - 24 25 - 31 1-7 8 - 14 15 - 22 23 - 30 1-7 8 - 15 16 -23 24 - 31 1-8 9 - 16 17 - 24 25 - 31 1-6 7 - 12 13 - 17

100
2 DRAINASE
4.03 4.03 4.03 4.03 90
2.2.(1) Pasangan Batu Dengan Mortar Rp 750,000 M3 1057 Rp 792,750,000 16.1

5 PERKERASAN BERBUTIR 80
3.42 3.42 3.42 3.42 3.42 3.42
5.1.(1) Lapis Pondasi Agregat Kelas A Rp 800,000 M3 1260 Rp 1,008,000,000 20.5 70

4.48 4.48 4.48 4.48 4.48 4.48 4.48 60


5.1.(2) Lapis Pondasi Agregat Kelas B Rp 700,000 M3 2205 Rp 1,543,500,000 31.4
50
2.56 2.56 40
5.1.(3) Lapis Pondasi Agregat Kelas S Rp 600,000 M3 420 Rp 252,000,000 5.1

6 PERKERASAN ASPAL 30
4.27 4.27 4.27
6.1.(1) Lapis Resap Pengikat - Aspal Cair/Emulsi Rp 100,000 Liter 6300 Rp 630,000,000 12.8
20

3.52 3.52 3.52 3.52 10


6.3.(3) Lataston Lapis Aus (HRS-WC) Rp 1,000,000 Ton 693 Rp 693,000,000 14.1
0
TOTAL Rp 4,919,250,000 100.0
RENCANA MINGGUAN 4.48 4.48 4.48 4.48 4.48 7.90 7.90 3.42 3.42 7.68 11.21 7.79 3.52 6.08 6.59 4.03 4.03 4.03
RENCANA KUMULATIF MINGGUAN 4.48 8.96 13.45 17.93 22.41 30.31 38.21 41.62 45.04 52.72 63.93 71.72 75.24 81.32 87.91 91.94 95.97 100.00
REALISASI MINGGUAN
FISIK (%) REALISASI KUMULATIF MINGGUAN
DEVIASI

0 4.48 8.96 13.45 17.93 22.41 30.31 38.21 41.62 45.04 52.72 63.93 71.72 75.24 81.32 87.91 91.94 95.97 100.00
JADWAL WAKTU PELAKSANAAN
WAKTU PELAKSANAAN 130 HARI KALENDER
ORIGINAL
NO. DIVISI URAIAN Harga Satuan (Rp) SAT MEI JUNI JULI AGUSTUS SEPTEMBER Keterangan
Kuantitas Harga Bobot (%)
11 - 17 18 - 24 25 - 31 1-7 8 - 14 15 - 22 23 - 30 1-7 8 - 15 16 -23 24 - 31 1-8 9 - 16 17 - 24 25 - 31 1-6 7 - 12 13 - 17

100
2 DRAINASE
4.03 4.03 4.03 4.03 90
2.2.(1) Pasangan Batu Dengan Mortar Rp 750,000 M3 1057 Rp 792,750,000 16.1

5 PERKERASAN BERBUTIR 80
3.42 3.42 3.42 3.42 3.42 3.42
5.1.(1) Lapis Pondasi Agregat Kelas A Rp 800,000 M3 1260 Rp 1,008,000,000 20.5 70
4.10 4.10 4.10 4.10 4.10

4.48 4.48 4.48 4.48 4.48 4.48 4.48 60


5.1.(2) Lapis Pondasi Agregat Kelas B Rp 700,000 M3 2205 Rp 1,543,500,000 31.4
5.23 5.23 5.23 5.23 5.23 5.23
50
2.56 2.56 40
5.1.(3) Lapis Pondasi Agregat Kelas S Rp 600,000 M3 420 Rp 252,000,000 5.1

6 PERKERASAN ASPAL 30
4.27 4.27 4.27
6.1.(1) Lapis Resap Pengikat - Aspal Cair/Emulsi Rp 100,000 Liter 6300 Rp 630,000,000 12.8
4.27 20

3.52 3.52 3.52 3.52 10


6.3.(3) Lataston Lapis Aus (HRS-WC) Rp 1,000,000 Ton 693 Rp 693,000,000 14.1
0
TOTAL Rp 4,919,250,000 100.0
RENCANA MINGGUAN 4.48 4.48 4.48 4.48 4.48 7.90 7.90 3.42 3.42 7.68 11.21 7.79 3.52 6.08 6.59 4.03 4.03 4.03
RENCANA KUMULATIF MINGGUAN 4.48 8.96 13.45 17.93 22.41 30.31 38.21 41.62 45.04 52.72 63.93 71.72 75.24 81.32 87.91 91.94 95.97 100.00
REALISASI MINGGUAN 5.23 5.23 5.23 5.23 5.23 9.33 4.10 4.10 4.10 8.37
FISIK (%) REALISASI KUMULATIF MINGGUAN 5.23 10.46 15.69 20.92 26.15 35.47 39.57 43.67 47.77 56.14
DEVIASI 0.75 1.49 2.24 2.99 3.74 5.17 1.37 2.05 2.73 3.42

0 4.48 8.96 13.45 17.93 22.41 30.31 38.21 41.62 45.04 52.72 63.93 71.72 75.24 81.32 87.91 91.94 95.97 100.00
0 5.23 10.46 15.69 20.92 26.15 35.47 39.57 43.67 47.77 56.14
JADW
ORIGI
NO. DIVISI URAIAN Harga Satuan (Rp) SAT
Kuantitas

3 PEKERJAAN TANAH

3.2 (2) Timbunan Pilihan Rp 400,000 m³ 7000

5 PERKERASAN BERBUTIR

5.1 (2) Lapis Pondasi Agregat Kelas B Rp 600,000 m³ 1750

5.1 (1) Lapis Pondasi Agregat Kelas A Rp 750,000 m³ 1050

7 STRUKTUR

7.9 Pasangan Batu Rp 1,250,000 m³ 660

TOTAL
RENCANA MINGGUAN
RENCANA KUMULATIF M
REALISASI MINGGUAN
FISIK (%) REALISASI KUMULATIF M
DEVIASI
JADWAL WAKTU PELAKSANAAN
WAKTU PELAKSANAAN 70 HARI KALENDER
ORIGINAL
MARET APRIL M
Minggu ke
Harga Bobot (%)
1 2 3 4 5 6 7

8.55 8.55 8.55 8.55 8.55 8.55


Rp 2,800,000,000 51.3
6.00 6.00 6.00 4.50 4.50

4.80 4.80 4.80 4.80


Rp 1,050,000,000 19.2
5.00 5.00 5.00

3.60 3.60 3.60


Rp 787,500,000 14.4
3.50 3.50

3.02 3.02
Rp 825,000,000 15.1
3.00

Rp 5,462,500,000 100
RENCANA MINGGUAN 8.55 8.55 8.55 13.35 16.95 19.97 11.42
RENCANA KUMULATIF MINGGUAN 8.55 17.10 25.65 39.00 55.95 75.92 87.34
REALISASI MINGGUAN 6.00 6.00 11.00 13.00 16.00
REALISASI KUMULATIF MINGGUAN 6.00 12.00 23.00 36.00 52.00
DEVIASI 2.55 5.10 2.65 3.00 3.95

0 8.55 17.1 25.65 39 55.95 75.92 87.34


0 6 12 23 36 52
KALENDER
MEI
Keterangan

8 9 10
100
90
80
70
60
50
3.60 40
30
20
3.02 3.02 3.02
10
0

6.62 3.02 3.02


93.96 96.98 100.00

93.96 96.98 100


Diketahui :
Rencana pembangunan jalan Kabupaten sepanjang 1.400 m , dengan data harga satuan sebagai berikut :
a. Pasangan batu dengan mortar = Rp. 750.000 / m3
b. Agregat S untuk bahu jalan = Rp. 600.000 / m3
c. Agregat Kelas B = Rp.700.000 / m3
d. Agregat kelas A = Rp. 800.000/m3
e. HRS-WC = Rp.1.000.000 / ton ( Kepadatan / density aspal = 2,20 Ton/ m3)
an sebagai berikut :