REALISASI PELAKSANAAN PEKERJAAN

PROVINSI : BALI
KOTA : DENPASAR
SUB KEGIATAN : OPERASI DAN PEMELIHARAAN SISTEM DRAINASE
PEKERJAAN : PERBAIKAN DRAINASE SISTEM V
TAHUN ANGGARAN : 2022
Bulan I Bulan II Bulan III
NO. URAIAN HARGA TOTAL BOBOT cek
M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12

I PEKERJAAN PERSIAPAN 8.143.000,00 - -


1 Pek. Pengukuran / Uitzet 250.000,00 0,19 0,186
2 Pek. Papan Nama Proyek 500.000,00 0,37 0,372
3 Pek. Rambu Lalu Lintas 370.000,00 0,28 0,138 0,138
4 Pembersihan Site 200.000,00 0,15 0,074 0,074
5 Mobilisai dan Demobilisasi Alat 5.000.000,00 3,72 3,716
6 Biaya K3 1.823.000,00 1,35 1,355

II PEKERJAAN GALIAN 13.505.541,54 - -


1 Galian Tanah Keras/Cadas 9.305.809,92 6,92 0,988 0,988 0,988 0,988 0,988 0,988 0,988
2 Urugan Pasir 197.574,00 0,15 0,021 0,021 0,021 0,021 0,021 0,021 0,021
3 Urugan Sirtu 937.072,50 0,70 0,100 0,100 0,100 0,100 0,100 0,100 0,100
4 Pembuangan Tanah Keluar Lokasi 3.065.085,12 2,28 0,285 0,285 0,285 0,285 0,285 0,285 0,285 0,285

III PEKERJAAN PASANGAN, PLESTERAN, DAN SIARAN 19.455.873,97 - -


1 Pek. Pasangan Batu Kali Camp. 1 SP : 5 PP 16.485.104,90 12,25 2,042 2,042 2,042 2,042 2,042 2,042
2 Plesteran 1 PC : 3 PS Tebal 15 mm 735.468,59 0,55 0,091 0,091 0,091 0,091 0,091 0,091
3 Siaran 2.235.300,48 1,66 0,277 0,277 0,277 0,277 0,277 0,277

IV PEKERJAAN STRUKTUR BETON 93.435.289,31 - -

1 Pek. Pas. UDITCH 800x800x1200 (K350) 15.426.846,50 11,47 2,293 2,293 2,293 2,293 2,293

2 Pek. Pasangan Beton (K250) 35.433.548,86 26,34 3,762 3,762 3,762 3,762 3,762 3,762 3,762

3 Bekisting 14.063.005,80 10,45 1,493 1,493 1,493 1,493 1,493 1,493 1,493

4 Wiremesh 12.804.095,59 9,52 1,360 1,360 1,360 1,360 1,360 1,360 1,360

5 Pembesian 15.707.792,57 11,68 1,668 1,668 1,668 1,668 1,668 1,668 1,668

REAL COST 134.539.704,83 134.539.704,83 100,00 1.035.000,00 8.143.000,00 9.472.401,42 19.793.540,38 30.620.393,09 49.967.100,72 69.313.808,36 88.660.516,00 108.007.223,63 123.277.012,37 129.094.633,64 134.539.704,83
PPN 10 % 14.799.367,53 14.799.367,53 113.850,00 895.730,00 1.041.964,16 2.177.289,44 3.368.243,24 5.496.381,08 7.624.518,92 9.752.656,76 11.880.794,60 13.560.471,36 14.200.409,70 14.799.367,53
JUMLAH 149.339.072,36 149.339.072,36 1.148.850,00 9.038.730,00 10.514.365,57 21.970.829,83 33.988.636,33 55.463.481,80 76.938.327,28 98.413.172,76 119.888.018,23 136.837.483,73 143.295.043,34 149.339.072,36
DIBULATKAN 149.339.000,00 149.339.000,00 1.148.800,00 9.038.700,00 10.514.300,00 21.970.800,00 33.988.600,00 55.463.400,00 76.938.300,00 98.413.100,00 119.888.000,00 136.837.400,00 143.295.000,00 149.339.000,00

Program 0,77 5,28 0,99 7,67 8,05 14,38 14,38 14,38 14,38 11,35 4,32 4,05
Rencana 0,77 6,05 7,04 14,71 22,76 37,14 51,52 65,90 80,28 91,63 95,95 100,00
Progress 0,20 2,30 3,20 10,15 18,26 30,16 43,16
Devisiasi -0,57 -3,75 -3,84 -4,56 -4,50 -6,98 -8,36