TIME SCHEDULE MINGGU 05

KONTRAKTOR PELAKSANA : : CV. PRATAMA JAYA KONSTRUKSI


PEKERJAAN : PEMBANGUNAN GEDUNG ARSIP KANTOR PERTANAHAN KABUPATEN KUTAI KARTANEGARA NO. KONTRAK : : 930/Sperj-64.02.100.UP.04.04/VI/2023
LOKASI : TENGGARONG, KAB. KUTAI KARTANEGARA KONSULTAN PENGAWAS : : CV. MUTIARA DESIGN KONSULTAN
TAHUN ANGGARAN : 2023 PERIODE : : 11-Jul s/d 17-Jul

WAKTU PELAKSANAAN 140 (SERATUS EMPAT PULUH) HARI KALENDER


BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5
No. URAIAN PEKERJAAN JUMLAH HARGA BOBOT M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 KET.
(Rp.) (%)

A PEKERJAAN PENDAHULUAN 22.444.121,20 1,02 0,34 0,34 0,34 100

B PEKERJAAN STRUKTUR
1 PEKERJAAN GALIAN DAN URUGAN 3.567.231,00 0,16 0,16

2 PEKERJAAN PANCANGAN & PONDASI 415.700.033,98 18,96 4,74 4,74 4,74 4,74 75
3 PEKERJAAN BETON LANTAI BASEMENT/BAWAH 120.895.907,96 5,51 1,38 1,38 1,38 1,38

4 PEKERJAAN BETON LANTAI I, Elv. ±0,00 374.658.670,19 17,09 5,70 5,70 5,70

5 PEKERJAAN BETON LANTAI II, Elv. +5,50 255.476.244,38 11,65 3,88 3,88 3,88

6 PEKERJAAN BETON RINGBALK, ELv. +9,60 & GEWEL 45.740.633,15 2,09 1,04 1,04 50
7 PEKERJAAN RANGKA ATAP & PENUTUP ATAP 106.646.488,60 4,86 2,43 2,43

C PEKERJAAN ARSITEKTUR
1 PEKERJAAN DINDING DAN PLESTERAN 269.129.660,01 12,27 3,07 3,07 3,07 3,07

2 PEKERJAAN KUSEN PINTU JENDELA DAN ACC. 50.178.574,50 2,29 1,14 1,14

3 PEKERJAAN PENUTUP LANTAI DAN DINDING 36.471.679,02 1,66 0,83 0,83

4 PEKERJAAN PLAFOND 87.633.151,53 4,00 2,00 2,00

5 PEKERJAAN PENGECATAN 61.190.330,83 2,79 RENCANA 0,70 0,70 0,70 0,70

6 PEKERJAAN LAIN - LAIN 139.705.664,26 6,37 PEKERJAAN 1,59 1,59 1,59 1,59

D PEKERJAAN MEKANIKAL/SANITAIR
1 PEKERJAAN Distribusi Air Bersih Lantai. 01 5.164.114,25 0,24 0,24

2 PEKERJAAN Distribusi Air Bekas, Air Kotor Dan Air Hujan Lantai. 01 22.366.068,85 1,02 0,51 0,51

E PEKERJAAN ELEKTRIKAL
1 Pekerjaan Panel Penerangan 11.000.000,00 0,50 0,50

2 Pekerjaan Kabel Distribusi 6.433.440,00 0,29 0,29

3 Pekerjaan Grounding Dan Penangkal Petir 9.440.000,00 0,43 0,43

ARUS KUAT LT.01 :


4 Pekerjaan Armature Penerangan Dalam Bangunan 9.722.275,00 0,44 REALISASI 0,44

5 Pekerjaan Instalasi Penerangan 19.501.240,00 0,89 PEKERJAAN 0,89

ARUS LEMAH LT.01 :


6 Pekerjaan Armature Fire ALarm 27.900.000,00 1,27 0,64 0,64

7 Pekerjaan Instalasi Fire ALarm 2.539.775,00 0,12 0,12

ARUS KUAT LT.02 :


8 Pekerjaan Armature Penerangan Dalam Bangunan 59.430.187,50 2,71 1,36 1,36

9 Pekerjaan Instalasi Penerangan 19.908.570,00 0,91 0,91

ARUS LEMAH LT.02 :


10 Pekerjaan Armature Fire ALarm 7.700.000,00 0,35 0,35

11 Pekerjaan Instalasi Fire ALarm 2.285.797,50 0,10 0,10

I JUMLAH A- N 2.192.829.858,70 100,00


BOBOT RENCANA (%) 0,50 0,34 5,08 6,12 6,12 6,12 7,07 9,58 9,58 8,23 7,55 8,28 7,95 4,17 3,14 2,93 3,61 2,04 1,59 -
BOBOT KOMULATIF RENCANA (%) 0,50 0,85 5,93 12,04 18,16 24,28 31,35 40,93 50,51 58,74 66,29 74,57 82,52 86,69 89,83 92,76 96,37 98,41 100,00 100,00
BOBOT REALISASI (%) 0,24 15,15 2,44 5,51 10,51
BOBOT REALISASI KOMULATIF (%) 0,24 15,39 17,83 23,10 33,61
DEVIASI +/- (%) -0,26 14,54 11,90 11,06 15,45

Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,


Pejabat Pembuat Komitmen Konsulltan Pengawas Kontraktor Pelaksana
BADAN PERTANAHAN NASIONAL KAB. KUTAI KARTANEGARA CV. MUTIARA DESIGN KONSULTAN CV. PRATAMA JAYA KONSTRUKSI

AMY PRAMDANY, S.IP JUPRI, ST ELPHIN, ST


NIP. 19820903 2000804 1 001 Team Leader Pelaksana Lapangan
LAPORAN MINGGU 05
KONTRAKTOR PELAKSANA : CV. PRATAMA JAYA KONSTRUKSI
PEKERJAAN : PEMBANGUNAN GEDUNG ARSIP KANTOR PERTANHAN KABUPATEN KUTAI KARTANEGARA NO. KONTRAK : 930/Sperj-64.02.100.UP.04.04/VI/2023
LOKASI : TENGGARONG, KAB. KUTAI KARTANEGARA KONSULTAN PENGAWAS : CV. MUTIARA DESIGN KONSULTAN
TAHUN ANGGARAN : 2023 PERIODE : 11 Juli 2023 s/d 17 Juli 2023

HARGA SATUAN JUMLAH HARGA BOBOT MINGGU LALU MINGGU INI HINGGA MINGGU INI JUMLAH HARGA
No. URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp) (%) VOL BOBOT (%) VOL BOBOT (%) VOL BOBOT (%) (Rp)

A. PEKERJAAN PENDAHULUAN

1 Pembersihan lokasi (bekas bongkaran, Semak Belukar dll) Ls 1,00 Rp 1.500.000,00 1.500.000,00 0,07 1,00 0,07 - - 1,00 0,07 1.500.000,00
2 Pembuatan Direksi Keet/Serobong Kerja/Gudang Bahan Ls 1,00 Rp 3.700.000,00 3.700.000,00 0,17 1,00 0,17 - - 1,00 0,17 3.700.000,00
3 Pengukuran dan pemasangan bowplank M1 69,80 Rp 82.294,00 5.744.121,20 0,26 69,80 0,26 - - 69,80 0,26 5.744.121,20
4 Papan Nama Proyek ls 1,00 Rp 200.000,00 200.000,00 0,01 1,00 0,01 - - 1,00 0,01 200.000,00
5 Penyediaan Listrik Kerja ls 1,00 Rp 1.500.000,00 1.500.000,00 0,07 1,00 0,07 - - 1,00 0,07 1.500.000,00
6 Penyediaan Air Kerja ls 1,00 Rp 1.500.000,00 1.500.000,00 0,07 1,00 0,07 - - 1,00 0,07 1.500.000,00
7 Penyelenggaraan K3 Paket 1,00 8.300.000,00 8.300.000,00 0,38 1,00 0,38 - - 1,00 0,38 8.300.000,00

JUMLAH 22.444.121,20 1,02 1,02 - 1,02 22.444.121,20


B. PEKERJAAN STRUKTUR
B.I PEKERJAAN GALIAN DAN URUGAN
1 Galian Tanah Pondasi Poerplat m3 19,80 Rp 109.250,00 2.163.150,00 0,10 19,80 0,10 - - 19,80 0,10 2.163.150,00
2 Urugan Tanah Kembali m3 6,60 80.500,00 531.300,00 0,02 - - - - - - -
3 Urugan Pasir Bawah Poerplat t=10cm m3 2,73 Rp 319.700,00 872.781,00 0,04 2,73 0,04 - - 2,73 0,04 872.781,00
-
B.II PEKERJAAN PANCANGAN & PONDASI -
1 Mobilisasi & Demobilisasi Alat Pancang Ls 1,00 Rp 50.000.000,00 50.000.000,00 2,28 1,00 2,28 - - 1,00 2,28 50.000.000,00
2 Pengadaan dan Pemancangan Tiang Pancang Minipile :
- Pengadaan Tiang Pancang Minipile 25x25 m1 630,00 Rp 357.000,00 224.910.000,00 10,26 630,00 10,26 - - 630,00 10,26 224.910.000,00
- Pemancangan dengan Injack 120 Ton m1 630,00 Rp 90.000,00 56.700.000,00 2,59 630,00 2,59 - - 630,00 2,59 56.700.000,00
- Las Joint titik 54,00 Rp 15.000,00 810.000,00 0,04 54,00 0,04 - - 54,00 0,04 810.000,00
- Pemotongan Kepala Tiang titik 54,00 Rp 50.000,00 2.700.000,00 0,12 54,00 0,12 - - 54,00 0,12 2.700.000,00
- Handling Material m1 630,00 20.000,00 12.600.000,00 0,57 630,00 0,57 - - 630,00 0,57 12.600.000,00
3 PDA Test : -
- PDA Test titik 3,00 Rp 3.500.000,00 10.500.000,00 0,48 3,00 0,48 - - 3,00 0,48 10.500.000,00
- Mobilisasi & Demobilisasi Ls 1,00 Rp 1.000.000,00 1.000.000,00 0,05 1,00 0,05 - - 1,00 0,05 1.000.000,00
- Laporan dan Interpretasi Data, dokumentasi Ls 1,00 Rp 1.000.000,00 1.000.000,00 0,05 1,00 0,05 - - 1,00 0,05 1.000.000,00
4 Pasang Pondasi Batu Padas 1pc : 4 ps m3 53,28 1.041.267,50 55.480.033,98 2,53
B.III PEKERJAAN BETON LANTAI BASEMENT/BAWAH - -
1 Cor Lantai Kerja bawah Poer plat t=10cm Mutu K.100 m3 2,73 1.302.260,00 3.555.169,80 0,16 2,73 - - 2,73 0,16 3.555.169,80
2 Cor Beton Pondasi Poer Plat P1.140x140x70cm - -
- Besi Ulir D16-200 kg 1.261,90 22.067,35 27.846.679,51 1,27 1.261,90 - - 1.261,90 1,27 27.846.679,51
- Besi Ulir D13 kg 135,04 22.067,35 2.980.045,56 0,14 135,04 - - 135,04 0,14 2.980.045,56
- Bekisting m2 47,04 273.608,00 12.870.520,32 0,59 47,04 - - 47,04 0,59 12.870.520,32
- Beton fc' = 26,4 Mpa, ( K-300 ) Ready Mix m3 16,46 1.991.058,25 32.780.783,03 1,49 16,46 - - 16,46 1,49 32.780.783,03
3 Cor Beton Pondasi Poer Plat P2.90x140x70cm - -
- Besi Ulir D16-250 kg 235,37 22.067,35 5.194.091,03 0,24 235,37 - - 235,37 0,24 5.194.091,03
- Besi Ulir D13 kg 16,88 22.067,35 372.505,69 0,02 16,88 - - 16,88 0,02 372.505,69
- Bekisting m2 9,66 273.608,00 2.643.053,28 0,12 9,66 - - 9,66 0,12 2.643.053,28
- Beton fc' = 26,4 Mpa, ( K-300 ) Ready Mix m3 2,65 1.991.058,25 5.268.340,13 0,24 2,65 - - 2,65 0,24 5.268.340,13
4 Cor Beton Kolom K1.20x30 cm - -
- Besi Ulir 6D13 kg 15,32 22.067,35 338.014,43 0,02 15,32 - - 15,32 0,02 338.014,43
- Besi Polos Begel Ø8-125 kg 0,65 19.652,35 12.808,42 0,00 0,65 - - 0,65 0,00 12.808,42
- Bekisting m2 1,45 167.618,25 243.046,46 0,01 1,45 - - 1,45 0,01 243.046,46
- Beton fc' = 26,4 Mpa, ( K-300 ) Ready Mix m3 0,09 1.991.058,25 173.222,07 0,01 0,09 - - 0,09 0,01 173.222,07
5 Cor Beton Kolom K2.30x40 cm - -
- Besi Ulir 10D16 kg 463,93 22.067,35 10.237.749,82 0,47 463,93 - - 463,93 0,47 10.237.749,82
- Besi Polos Begel Ø8-125 kg 30,42 19.652,35 597.726,23 0,03 30,42 - - 30,42 0,03 597.726,23
- Bekisting m2 24,36 167.618,25 4.083.180,57 0,19 24,36 - - 24,36 0,19 4.083.180,57
- Beton fc' = 26,4 Mpa, ( K-300 ) Ready Mix m3 2,09 1.991.058,25 4.157.329,63 0,19 2,09 - - 2,09 0,19 4.157.329,63
6 Cor Beton Kolom K3.30x40 cm - -
- Besi Ulir 8D13 kg 122,54 22.067,35 2.704.115,42 0,12 122,54 - - 122,54 0,12 2.704.115,42
- Besi Polos Begel Ø8-125 kg 36,50 19.652,35 717.271,47 0,03 36,50 - - 36,50 0,03 717.271,47
- Bekisting m2 12,18 167.618,25 2.041.590,29 0,09 12,18 - - 12,18 0,09 2.041.590,29
- Beton fc' = 26,4 Mpa, ( K-300 ) Ready Mix m3 1,04 1.991.058,25 2.078.664,81 0,09 1,04 - - 1,04 0,09 2.078.664,81
B.IV PEKERJAAN BETON LANTAI I, Elv. ±0,00
1 Cor Beton Sloof S1.25x50cm
- Besi Ulir D16 kg 1.138,05 22.067,35 25.113.827,11 1,15 1.138,05 1,15 1.138,05 1,15 25.113.827,11
- Besi Ulir D13 kg 187,87 22.067,35 4.145.850,42 0,19 187,87 0,19 187,87 0,19 4.145.850,42
- Besi Polos Begel Ø8-125 kg 368,69 19.652,35 7.245.683,88 0,33 368,69 0,33 368,69 0,33 7.245.683,88
- Bekisting m2 85,26 145.429,00 12.399.640,11 0,57 85,26 0,57 85,26 0,57 12.399.640,11
HARGA SATUAN JUMLAH HARGA BOBOT MINGGU LALU MINGGU INI HINGGA MINGGU INI JUMLAH HARGA
No. URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp) (%) VOL BOBOT (%) VOL BOBOT (%) VOL BOBOT (%) (Rp)

- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 7,85 1.894.458,25 14.877.417,44 0,68 7,85 0,68 7,85 0,68 14.877.417,44
2 Cor Beton Sloof S2.20x40cm
- Besi Ulir D13 kg 694,18 22.067,35 15.318.721,85 0,70 694,18 0,70 694,18 0,70 15.318.721,85
- Besi Polos Begel Ø8-125 kg 287,20 19.652,35 5.644.243,36 0,26 287,20 0,26 287,20 0,26 5.644.243,36
- Bekisting m2 57,84 145.429,00 8.411.249,79 0,38 57,84 0,38 57,84 0,38 8.411.249,79
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 4,13 1.894.458,25 7.826.480,65 0,36 4,13 0,36 4,13 0,36 7.826.480,65
3 Cor Beton Plat Lantai I, t=15 cm, Elv. ±0.00
- Besi Polos Ø10-175 (2 layer) kg 2.273,21 19.652,35 44.673.979,47 2,04 2.273,21 2,04 2.273,21 2,04 44.673.979,47
- Bekisting m2 163,53 185.903,25 30.400.758,47 1,39 163,53 1,39 163,53 1,39 30.400.758,47
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 24,12 1.894.458,25 45.685.807,93 2,08 24,12 2,08 24,12 2,08 45.685.807,93
4 Cor Beton Kolom Praktis KP.13x13cm (Site Mix) m' 65,95 114.597,50 7.557.705,13 0,34 - - - - -
5 Cor Beton Kolom K1.20x30 cm
- Besi Ulir 6D13 kg 25,95 22.067,35 572.555,05 0,03 - - - - -
- Besi Polos Begel Ø8-125 kg 10,31 19.652,35 202.605,90 0,01 - - - - -
- Bekisting m2 3,65 167.618,25 611.806,61 0,03 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 0,22 1.894.458,25 414.886,36 0,02 - - - - -
6 Cor Beton Kolom K2.30x40 cm
- Besi Ulir 10D16 kg 1.117,22 22.067,35 24.654.173,04 1,12 - - - - -
- Besi Polos Begel Ø8-125 kg 246,48 19.652,35 4.843.911,23 0,22 - - - - -
- Bekisting m2 84,00 167.618,25 14.079.933,00 0,64 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 7,20 1.894.458,25 13.640.099,40 0,62 - - - - -
7 Cor Beton Kolom K3.30x40 cm
- Besi Ulir 8D13 kg 75,86 22.067,35 1.673.976,21 0,08 - - - - -
- Besi Polos Begel Ø8-125 kg 29,78 19.652,35 585.305,94 0,03 - - - - -
- Bekisting m2 10,22 167.618,25 1.713.058,52 0,08 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 0,88 1.894.458,25 1.659.545,43 0,08 - - - - -
8 Cor Beton Balok Latai B1.13x25 cm, (atas kusen, bouvent)
- Besi Polos 4Ø10 kg 72,41 19.652,35 1.423.048,67 0,06 - - - - -
- Besi Polos Begel Ø6-125 kg 28,20 19.652,35 554.165,61 0,03 - - - - -
- Bekisting m2 17,54 174.173,25 3.054.859,47 0,14 - - - - -
- Beton Camp. 1Pc : 2Ps : 3Krl (Site Mix) m3 0,90 1.843.277,50 1.667.797,48 0,08 - - - - -
9 Cor Beton Balok B2.20x30 cm, Elv.+4,00
- Besi Ulir D13 kg 88,36 22.067,35 1.949.906,35 0,09 - - - - -
- Besi Polos Begel Ø8-125 kg 25,91 19.652,35 509.231,69 0,02 - - - - -
- Bekisting m2 8,24 174.173,25 1.435.187,58 0,07 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 0,37 1.894.458,25 702.465,12 0,03 - - - - -
10 Cor Beton Balok B3.20x40 cm, Elv.+4,00
- Besi Ulir D13 kg 162,14 22.067,35 3.577.894,21 0,16 - - - - -
- Besi Polos Begel Ø8-125 kg 60,44 19.652,35 1.187.689,77 0,05 - - - - -
- Bekisting m2 19,15 174.173,25 3.335.417,74 0,15 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 1,07 1.894.458,25 2.031.617,03 0,09 - - - - -
11 Cor Beton Plat Dag tebal 12cm, Elv. +4,00
- Besi Polos Ø10-200 (2 layer) kg 470,09 19.652,35 9.238.418,41 0,42 - - - - -
- Bekisting m2 38,60 185.903,25 7.174.935,93 0,33 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 4,51 1.894.458,25 8.547.568,29 0,39 - - - - -
12 Cor Beton Plat Listplank tebal 10cm lebar 70cm
- Besi Polos Ø10 kg 104,03 19.652,35 2.044.359,29 0,09 - - - - -
- Bekisting m2 26,45 185.903,25 4.917.140,96 0,22 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 1,61 1.894.458,25 3.050.077,78 0,14 - - - - -
13 Cor Beton Canopy tebal 10cm lebar 45cm, Elv. +2,80
- Besi Polos Ø10 kg 8,18 19.652,35 160.662,87 0,01 - - - - -
- Bekisting m2 0,79 185.903,25 146.398,81 0,01 - - - - -
- Beton Camp. 1Pc : 2Ps : 3Krl (Site Mix) m3 0,07 1.843.277,50 128.568,61 0,01 - - - - -
14 Cor Beton Plat Bordes & Plat Tangga tebal 12 cm
- Besi Ulir D13 kg 461,81 22.067,35 10.191.020,00 0,46 - - - - -
- Besi Polos Ø10 kg 173,09 19.652,35 3.401.581,05 0,16 - - - - -
- Bekisting m2 25,34 185.903,25 4.709.910,89 0,21 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 2,94 1.894.458,25 5.565.524,29 0,25 - - - - -
B.V PEKERJAAN BETON LANTAI II, Elv. +5,50
1 Cor Beton Balok B2.20x30 cm
- Besi Ulir D13 kg 74,19 22.067,35 1.637.185,52 0,07 - - - - -
- Besi Polos Begel Ø8-125 kg 24,17 19.652,35 475.075,91 0,02 - - - - -
- Bekisting m2 4,25 174.173,25 740.236,31 0,03 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 0,26 1.894.458,25 483.086,85 0,02 - - - - -
2 Cor Beton Balok B3.20x40 cm
- Besi Ulir D13 kg 602,07 22.067,35 13.286.036,45 0,61 - - - - -
- Besi Polos Begel Ø8-125 kg 248,97 19.652,35 4.892.816,10 0,22 - - - - -
- Bekisting m2 50,14 174.173,25 8.732.611,32 0,40 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 3,58 1.894.458,25 6.784.528,61 0,31 - - - - -
3 Cor Beton Balok B4.25x50 cm
- Besi Ulir D16 kg 972,68 22.067,35 21.464.452,34 0,98 - - - - -
- Besi Ulir D13 kg 160,57 22.067,35 3.543.402,94 0,16 - - - - -
HARGA SATUAN JUMLAH HARGA BOBOT MINGGU LALU MINGGU INI HINGGA MINGGU INI JUMLAH HARGA
No. URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp) (%) VOL BOBOT (%) VOL BOBOT (%) VOL BOBOT (%) (Rp)

- Besi Polos Begel Ø8-125 kg 338,44 19.652,35 6.651.062,72 0,30 - - - - -


- Bekisting m2 72,72 174.173,25 12.666.314,17 0,58 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 6,70 1.894.458,25 12.689.318,17 0,58 - - - - -
4 Cor Beton Plat Lantai II + Canopy, t=15 cm, Elv. +5.50
- Besi Polos Ø10-175 (2 layer) kg 2.048,93 19.652,35 40.266.360,23 1,84 - - - - -
- Bekisting m2 148,00 185.903,25 27.513.681,00 1,25 - - - - -
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 21,75 1.894.458,25 41.204.466,94 1,88 - - - - -
5 Cor Beton Plat Listplank tebal 10cm lebar 50cm
- Besi Polos Ø10 kg 95,23 19.652,35 1.871.449,66 0,09
- Bekisting m2 21,90 185.903,25 4.072.117,74 0,19
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 1,29 1.894.458,25 2.441.009,46 0,11
6 Cor Beton Kolom Praktis KP.13x13cm (Site Mix) m' 34,65 114.597,50 3.970.803,38 0,18
7 Cor Beton Kolom K3.30x40 cm
- Besi Ulir 8D13 kg 435,14 22.067,35 9.602.369,03 0,44
- Besi Polos Begel Ø8-125 kg 288,76 19.652,35 5.674.733,98 0,26
- Bekisting m2 64,68 167.618,25 10.841.548,41 0,49
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 5,54 1.894.458,25 10.502.876,54 0,48
8 Cor Beton Balok Latai B1.13x25 cm, (atas kusen, bouvent)
- Besi Polos 4Ø10 kg 37,02 19.652,35 727.530,00 0,03
- Besi Polos Begel Ø6-125 kg 15,18 19.652,35 298.417,00 0,01
- Bekisting m2 9,07 174.173,25 1.580.099,72 0,07
- Beton Camp. 1Pc : 2Ps : 3Krl (Site Mix) m3 0,47 1.843.277,50 862.653,87 0,04
B.VI PEKERJAAN BETON RINGBALK, ELv. +9,60 & GEWEL
1 Cor Beton Balok B2.20x30 cm
- Besi Ulir D13 kg 650,21 22.067,35 14.348.367,51 0,65
- Besi Polos Begel Ø8-125 kg 293,88 19.652,35 5.775.432,62 0,26
- Bekisting m2 62,08 174.173,25 10.812.675,36 0,49
- Beton fc' = 21,7 Mpa, ( K-250 ) Ready Mix m3 4,66 1.894.458,25 8.820.597,61 0,40
2 Cor Beton Kolom Praktis KP.13x13cm (Site Mix) m' 11,70 114.597,50 1.340.790,75 0,06
3 Cor Beton Balok Latai B1.13x25 cm, (Dinding Gewel)
- Besi Polos 4Ø10 kg 53,80 19.652,35 1.057.343,60 0,05
- Besi Polos Begel Ø6-125 kg 22,38 19.652,35 439.772,43 0,02
- Bekisting m2 10,70 174.173,25 1.863.653,78 0,08
- Beton Camp. 1Pc : 2Ps : 3Krl (Site Mix) m3 0,70 1.843.277,50 1.281.999,50 0,06
B.VII PEKERJAAN RANGKA ATAP & PENUTUP ATAP
1 Pasang Rangka Atap Baja Ringan TASO (C75.75 + R40.45) m2 226,20 288.420,00 65.240.604,00 2,98
2 Pasang Atap Genteng Metal Berpasir m2 226,20 138.690,00 31.371.678,00 1,43
3 Pasang Bubungan Atap Genteng Metal Berpasir m1 17,40 109.997,50 1.913.956,50 0,09
4 Pasang Listplank GRC lebar 30cm tebal 10mm m1 60,80 116.127,00 7.060.521,60 0,32
5 Pengecatan Listplank Eksterior m2 18,24 58.099,15 1.059.728,50 0,05

JUMLAH 1.322.685.209,25 60,32 16,57 10,11 32,19 705.895.499,42


C. PEKERJAAN ARSITEKTUR
C.I PEKERJAAN DINDING DAN PLESTERAN
A LANTAI 1 (Elevasi ± 0.00)
1 Pasangan dinding bata ringan T=7,5cm (KM/WC) m2 24,73 Rp 215.085,19 5.318.519,04 0,24
2 Plesteran dinding 1Pc : 2Ps (KM/WC) m2 49,46 Rp 110.457,50 5.462.675,66 0,25
3 Acian dinding m2 36,23 Rp 53.705,00 1.945.463,63 0,09
4 Pasangan dinding bata ringan T=7,5cm m2 264,22 Rp 215.085,19 56.830.346,61 2,59
5 Plesteran dinding 1Pc : 4Ps m2 528,45 Rp 110.457,50 58.370.713,59 2,66
6 Acian dinding m2 489,23 Rp 53.705,00 26.274.311,97 1,20
7 Benangan Sloof, Kolom, Balok, Listplank, Canopy m1 131,25 Rp 62.105,75 8.151.379,69 0,37
8 Acian Sloof, Kolom, Balok, Listplank, Canopy m2 139,54 Rp 54.337,50 7.582.222,15 0,35
B LANTAI 2 (Elevasi + 5.50)
1 Pasangan dinding bata ringan T=7,5cm m2 163,74 Rp 215.085,19 35.218.049,01 1,61
2 Plesteran dinding 1Pc : 4Ps m2 327,48 Rp 110.457,50 36.172.622,10 1,65
3 Acian dinding m2 298,68 Rp 53.705,00 16.040.555,70 0,73
4 Benangan Kolom, Balok, Listplank m1 95,40 Rp 62.105,75 5.924.888,55 0,27
5 Acian Kolom, Balok, Listplank m2 107,44 Rp 54.337,50 5.837.912,33 0,27
C.II PEKERJAAN KUSEN PINTU JENDELA DAN ACC.
A LANTAI 1 (Elevasi ± 0.00)
1 Pasang Kusen Besi Hollow +Pintu Plat Type P1 + accessoris unit 1,00 Rp 3.500.000,00 3.500.000,00 0,16
2 Pasang Kusen Besi Hollow +Pintu Plat Type P2 + accessoris unit 1,00 Rp 4.000.000,00 4.000.000,00 0,18
3 Pasang Kusen Besi Hollow +Pintu Plat Type P3 + accessoris unit 1,00 Rp 4.000.000,00 4.000.000,00 0,18
4 Pasang Kusen Aluminium+Pintu Type P4 + accessoris unit 1,00 Rp 2.899.192,81 2.899.192,81 0,13
5 Pasang Kusen Besi Hollow +Pintu Plat Type P5 + accessoris unit 1,00 Rp 4.000.000,00 4.000.000,00 0,18
6 Pasang Kusen Aluminium+Jendela Type J1 + accessoris unit 1,00 Rp 3.338.428,36 3.338.428,36 0,15
7 Pasang Kusen Aluminium+Jendela Type J2 + accessoris unit 6,00 Rp 2.204.445,21 13.226.671,25 0,60
8 Pasang Kusen Aluminium+Bouvent Type BV1 + accessoris unit 1,00 Rp 917.319,98 917.319,98 0,04
9 Pasang Kusen Aluminium+Bouvent Type BV2 + accessoris unit 2,00 Rp 535.145,43 1.070.290,86 0,05
B LANTAI 2 (Elevasi + 5.50)
HARGA SATUAN JUMLAH HARGA BOBOT MINGGU LALU MINGGU INI HINGGA MINGGU INI JUMLAH HARGA
No. URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp) (%) VOL BOBOT (%) VOL BOBOT (%) VOL BOBOT (%) (Rp)

1 Pasang Kusen Aluminium+Jendela Type J2 + accessoris unit 6,00 Rp 2.204.445,21 13.226.671,25 0,60
C.III PEKERJAAN PENUTUP LANTAI DAN DINDING
A LANTAI 1 (Elevasi ± 0.00)
1 Pasang Granite Lantai 60x60 Polish (ruang admin&pelayanan) m2 16,55 Rp 395.904,75 6.552.619,52 0,30
2 Lantai Beton Floor Hardener Fin. Trowel (ruang transit & rg. arsip) m2 125,89 Rp 69.051,75 8.692.786,70 0,40 125,89 0,40 125,89 0,40 8.692.786,70
3 Pasang Granite Lantai 30x60 Unps. step noshing (tangga) m2 23,07 Rp 379.114,75 8.747.542,10 0,40
4 Pasang Granite Lantai 30x30 Unpolisd (KM/WC) m2 2,56 Rp 305.204,25 781.902,77 0,04
5 Pasang Granit Dinding 30x60 Polisd (KM/WC), t=180cm m2 10,26 Rp 375.532,50 3.852.963,45 0,18
B LANTAI 2 (Elevasi + 5.50)
1 Lantai Beton Floor Hardener Fin. Trowel (ruang arsip) m2 113,59 Rp 69.051,75 7.843.864,49 0,36
C.IV PEKERJAAN PLAFOND
A LANTAI 1 (Elevasi +3.00, +3.30, +4.50)
1 Perapihan Plafond Beton Ekspos + Cat (rg.arsip) Ls 1,00 Rp 5.000.000,00 5.000.000,00 0,23
2 Pasang Plafond Gypsum t=9 mm (rg.admin, rg.transit & KM/WC) m2 33,41 Rp 58.977,75 1.970.210,72 0,09
3 Pasang Rangka Plafond Hollow 20x40mm m2 33,41 Rp 197.742,50 6.605.785,96 0,30
4 Pasang List Plafond m1 43,23 Rp 56.718,00 2.451.805,70 0,11
B LANTAI 2 (Elevasi + 9.00)
1 Pasang Plafond Akustik Board 12mm incl. Rangka m2 127,02 Rp 371.843,88 47.231.237,16 2,15
C PLAFOND TRITISAN ATAP
1 Pasang Plafond PVC 8mmx20cm (luar bangunan) m2 72,96 Rp 136.332,50 9.946.819,20 0,45
2 Pasang Rangka Plafond Hollow 20x40mm m2 72,96 Rp 197.742,50 14.427.292,80 0,66
C.V PEKERJAAN PENGECATAN
A LANTAI 1 (Elevasi ± 0.00)
1 Pengecatan Dinding Exsterior m2 403,76 Rp 58.099,15 23.458.223,19 1,07
2 Pengecatan Dinding Interior m2 264,22 Rp 47.634,15 12.586.014,20 0,57
3 Pengecatan Plafond Interior m2 33,41 Rp 47.634,15 1.591.266,41 0,07
B LANTAI 2 (Elevasi + 5.50)
1 Pengecatan Dinding Exterior m2 271,18 Rp 58.099,15 15.755.211,30 0,72
2 Pengecatan Dinding Interior m2 163,74 Rp 47.634,15 7.799.615,72 0,36
C.VI PEKERJAAN LAIN - LAIN
1 Pasang Reiling Tangga (Hollow Galv. 5x5x1,2mm+Plat 8mm Fin.Cat) m2 13,60 Rp 550.000,00 7.480.000,00 0,34
2 Pasang ACP PVDF 0.4mm Ex. SEVEN+incld rangka 2x4+acc. m2 127,68 Rp 828.833,75 105.822.525,98 4,83
3 Pasang Sun Screen aluminium 5x10 jarak 10cm +incld rangka m1 167,80 Rp 50.000,00 8.390.000,00 0,38
4 Pasang Besi Gantung Mesin Electric Hoist +incld rangka Ls 1,00 Rp 2.000.000,00 2.000.000,00 0,09
5 Waterproofing Lantai Dag 2 Lapis m2 37,60 Rp 239.717,50 9.013.138,28 0,41
6 Huruf " GEDUNG ARSIP" (Akrilik) Paket 1,00 Rp 7.000.000,00 7.000.000,00 0,32

JUMLAH II 644.309.060,15 29,38 - 0,40 0,40 8.692.786,70


D. PEKERJAAN MEKANIKAL/SANITAIR
D.I PEKERJAAN Distribusi Air Bersih Lantai. 01
1 Pipa PVC Type AW Ø 1" ( Ø 25) m¹ 36,00 106.030,00 3.817.080,00 0,17
2 Pipa PVC Type AW Ø 1/2" ( Ø 15) m¹ 3,00 61.513,50 184.540,50 0,01 - - - - - - -
3 Gate Valve Ø 1" Bh 1,00 45.000,00 45.000,00 0,00 - - - - - - -
4 Kran air Ø3/4" atau Ø1/2" Bh 1,00 217.493,75 217.493,75 0,01 - - - - - - -
5 Kran Wastafel Ex. TOTO Bh 1,00 200.000,00 200.000,00 0,01 - - - - - - -
6 Jet Washer Closet Bh 1,00 200.000,00 200.000,00 0,01 - - - - - - -
7 Fitting - Fitting, Tee, Elbow,Reduser/ Acc, Suport Penggantung Pipa Ls 1,00 500.000,00 500.000,00 0,02 - - - - - - -
D.II PEKERJAAN Distribusi Air Bekas, Air Kotor Dan Air Hujan Lantai. 01
1 Pipa PVC Type AW Ø 4". ( Ø 100 ) m¹ 4,20 194.884,75 818.515,95 0,04
2 Pipa PVC Type AW Ø 2,5". ( Ø 65 ) m¹ 26,40 171.712,25 4.533.203,40 0,21
3 Pipa PVC Type AW Ø 2" ( Ø 50) m¹ 8,00 141.289,00 1.130.312,00 0,05
4 Closet duduk (toto) type CW.660/SW.660J Unit 1,00 3.588.805,00 3.588.805,00 0,16
5 Wastafel Ex Toto. ( Include Acessories ) Unit 1,00 1.685.497,50 1.685.497,50 0,08
6 Pasang Kaca Cermin Uk.60x100cm + assesories lengkap Set 1,00 350.000,00 350.000,00 0,02
7 Floor Drain ex. TOTO Bh 1,00 159.735,00 159.735,00 0,01
8 Roof Drain ( RD ) Bh 3,00 200.000,00 600.000,00 0,03
9 Pasang Tandon Air Kap. 1200Ltr bh 2,00 1.500.000,00 3.000.000,00 0,14
10 Bio Septic Kap. 1,6 m3 + lengkap Dudukan Beton Unit 1,00 6.000.000,00 6.000.000,00 0,27
11 Fitting - Fitting, Tee, Elbow,Reduser/ Acc, Suport Penggantung Pipa Ls 1,00 500.000,00 500.000,00 0,02

JUMLAH 27.530.183,10 1,26 - - - -


E. PEKERJAAN ELEKTRIKAL
E.I Pekerjaan Panel Penerangan
1 Panel Penerangan Lantai - 1 Unit 1,00 4.000.000,00 4.000.000,00 0,18 - - - - - - -
• K: ABB, Scheneider, SIEMENS
• T: 1,8 Pmm
• C: RAL 7032
• F: Powder Coating
• S: 380/415 V, 3 PH, 50 Hz, 4 Wire
• P: Dalam gedung Lt.1
2 Panel Penerangan Lantai 2 Unit 1,00 4.000.000,00 4.000.000,00 0,18 - - - - - - -
HARGA SATUAN JUMLAH HARGA BOBOT MINGGU LALU MINGGU INI HINGGA MINGGU INI JUMLAH HARGA
No. URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp) (%) VOL BOBOT (%) VOL BOBOT (%) VOL BOBOT (%) (Rp)

• K: ABB, Scheneider, SIEMENS


• T: 1,8 Pmm
• C: RAL 7032
• F: Powder Coating
• S: 380/415 V, 3 PH, 50 Hz, 4 Wire
• P: Dalam gedung Lt.2
3 Test Comisioning Peralatan dan system Penerangan Ls 1,00 3.000.000,00 3.000.000,00 0,14 - - - - - - -
E.II Pekerjaan Kabel Distribusi
1 Dari Panel SDPg Ke Panel Penerangan Lt. 1 dan Lt. 2, Kabel NYY 4x4mm m¹ 48,00 71.530,00 3.433.440,00 0,16
2 Pek. Terminating Panel. Ls 1,00 1.000.000,00 1.000.000,00 0,05 - - - - - - -
3 Pek. Pemasangan Miniature Cirucuit Braker (MCB) 32A. 3 Phase (SDP) Bh 2,00 1.000.000,00 2.000.000,00 0,09 - - - - - - -
E.III Pekerjaan Grounding Dan Penangkal Petir
1 Kabel BC. 50 mm m¹ 18,80 200.000,00 3.760.000,00 0,17 - - - - - - -
2 Kabel BC. 6 mm m¹ 8,00 85.000,00 680.000,00 0,03 - - - - - - -
3 Split Rod Ǿ 3/4 Set 1,00 500.000,00 500.000,00 0,02
4 Ground Rod Ǿ 5/8 Set 1,00 3.000.000,00 3.000.000,00 0,14 - - - - - - -
5 Bak Kontrol 50 x 50 x 50 Unit 1,00 500.000,00 500.000,00 0,02 - - - - - - -
6 Acessories Grounding dan Penangkal Petir Ls 1,00 1.000.000,00 1.000.000,00 0,05 - - - - - - -
E.IV ARUS KUAT LT.01 :
E.IV.a Pekerjaan Armature Penerangan Dalam Bangunan
1 Pek. Linear Battent T5, Led 14 Watt Bh 16,00 215.625,00 3.450.000,00 0,16
2 Pek. Linear Battent T5, Led 24 Watt Bh 2,00 228.275,00 456.550,00 0,02 - - - - - - -
3 Pek. Freza G2 LED7 D100 9 Watt ( 100 mm ) Bh 5,00 171.350,00 856.750,00 0,04 - - - - - - -
4 Pek. SL LED 9 Watt Bh 17,00 70.000,00 1.190.000,00 0,05 - - - - - - -
5 Exchauz Fan Wall Mounted Kap. 80 Cmh ( Dia 400 mm ) Unit 3,00 696.325,00 2.088.975,00 0,10 - - - - - - -
6 Stop Kontak AC, 16 Amp Bh 6,00 85.000,00 510.000,00 0,02 - - - - - - -
7 Stop Kontak, 16 Amp Bh 7,00 75.000,00 525.000,00 0,02
8 10 A Switch 1 Gang, 2 Way Bh 6,00 70.000,00 420.000,00 0,02 - - - - - - -
9 10 A Switch 2 Gang, 2 Way Bh 3,00 75.000,00 225.000,00 0,01 - - - - - - -
E.IV.b Pekerjaan Instalasi Penerangan
1 Instalasi Titik Lampu ( NYM 3 x 2,5 mm ) Ttk 40,00 330.165,00 13.206.600,00 0,60
2 Instalasi Stop Kontak, Exchauz Fan ( NYM 3 x 2,5 mm ) Ttk 16,00 393.415,00 6.294.640,00 0,29 - - - - - - -
E.V ARUS LEMAH LT.01 :
E.V.a Pekerjaan Armature Fire ALarm
1 Master Control Fire Alarm Unit 1,00 18.000.000,00 18.000.000,00 0,82 - - - - - - -
2 Smoke Detector C/W Base. Bh 4,00 700.000,00 2.800.000,00 0,13 - - - - - - -
3 Rate Of Rise Heat Detector C/W Base. Bh 2,00 800.000,00 1.600.000,00 0,07 - - - - - - -
4 Manual Call Point. Bh 2,00 800.000,00 1.600.000,00 0,07
5 Indicator Lamp. Bh 2,00 400.000,00 800.000,00 0,04 - - - - - - -
6 Alarm Bell. Bh 2,00 800.000,00 1.600.000,00 0,07 - - - - - - -
7 Test Comisioning System Ls 1,00 1.500.000,00 1.500.000,00 0,07 - - - - - - -
E.V.b Pekerjaan Instalasi Fire ALarm
1 Instalasi Smoke Detector C/W Base. ( Kabel NYA, 2 x 1,5mm ) Ttk 4,00 253.977,50 1.015.910,00 0,05 - - - - - - -
2 Instalasi Rate Of Rise Heat Detector C/W Base. (Kabel NYA, 2 x 1,5mm) Ttk 2,00 253.977,50 507.955,00 0,02 - - - - - - -
3 Instalasi Indicator Lamp. ( Kabel NYA, 2 x 1,5mm ) Ttk 2,00 253.977,50 507.955,00 0,02
4 Instalasi Alarm Bell. ( Kabel NYA, 2 x 1,5mm ) Ttk 2,00 253.977,50 507.955,00 0,02 - - - - - - -
E.VI ARUS KUAT LT.02 :
E.VI.a Pekerjaan Armature Penerangan Dalam Bangunan
1 Pek. Linear Battent T5, Led 14 Watt Bh 17,00 215.625,00 3.665.625,00 0,17 - - - - - - -
2 Pek. Linear Battent T5, Led 24 Watt Bh 2,00 228.275,00 456.550,00 0,02 - - - - - - -
3 Pek. Freza G2 LED7 D100 9 Watt ( 100 mm ) Bh 15,00 171.350,00 2.570.250,00 0,12 - - - - - - -
4 Exchauz Fan Wall Mounted Kap. 80 Cmh ( Dia 400 mm ) Unit 4,00 696.325,00 2.785.300,00 0,13
5 Strip LED Outdoor 10 Watt / m Include Bracket m¹ 24,50 1.961.325,00 48.052.462,50 2,19 - - - - - - -
6 Stop Kontak AC, 16 Amp Bh 5,00 85.000,00 425.000,00 0,02 - - - - - - -
7 Stop Kontak, 16 Amp Bh 3,00 75.000,00 225.000,00 0,01 - - - - - - -
8 10 A Switch 1 Gang, 2 Way Bh 5,00 70.000,00 350.000,00 0,02 - - - - - - -
9 10 A Switch 2 Gang, 2 Way Bh 12,00 75.000,00 900.000,00 0,04 - - - - - - -
E.VI.b Pekerjaan Instalasi Penerangan
1 Instalasi Titik Lampu ( NYM 3 x 2,5 mm ) Ttk 46,00 330.165,00 15.187.590,00 0,69
2 Instalasi Stop Kontak, Exchauz Fan ( NYM 3 x 2,5 mm ) Ttk 12,00 393.415,00 4.720.980,00 0,22 - - - - - - -
E.VII ARUS LEMAH LT.02 :
E.VII.a Pekerjaan Armature Fire ALarm
1 Smoke Detector C/W Base. Bh 3,00 700.000,00 2.100.000,00 0,10 - - - - - - -
2 Rate Of Rise Heat Detector C/W Base. Bh 2,00 800.000,00 1.600.000,00 0,07 - - - - - - -
3 Manual Call Point. Bh 2,00 800.000,00 1.600.000,00 0,07 - - - - - - -
4 Indicator Lamp. Bh 2,00 400.000,00 800.000,00 0,04
5 Alarm Bell. Bh 2,00 800.000,00 1.600.000,00 0,07 - - - - - - -
E.VII.b Pekerjaan Instalasi Fire ALarm
1 Instalasi Smoke Detector C/W Base. ( Kabel NYA, 2 x 1,5mm ) Ttk 3,00 253.977,50 761.932,50 0,03 - - - - - - -
2 Instalasi Rate Of Rise Heat Detector C/W Base. (Kabel NYA, 2 x 1,5mm) Ttk 2,00 253.977,50 507.955,00 0,02 - - - - - - -
3 Instalasi Indicator Lamp. ( Kabel NYA, 2 x 1,5mm ) Ttk 2,00 253.977,50 507.955,00 0,02 - - - - - - -
4 Instalasi Alarm Bell. ( Kabel NYA, 2 x 1,5mm ) Ttk 2,00 253.977,50 507.955,00 0,02 - - - - - - -
HARGA SATUAN JUMLAH HARGA BOBOT MINGGU LALU MINGGU INI HINGGA MINGGU INI JUMLAH HARGA
No. URAIAN PEKERJAAN SATUAN VOLUME
(Rp) (Rp) (%) VOL BOBOT (%) VOL BOBOT (%) VOL BOBOT (%) (Rp)

JUMLAH 175.861.285,00 8,02 - - - -


JUMLAH 2.192.829.858,70 100,00 17,59 10,51 33,61 737.032.407,33

Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,


Pejabat Pembuat Komitmen Konsulltan Pengawas Kontraktor Pelaksana
BADAN PERTANAHAN NASIONAL KAB. KUTAI KARTANEGARA CV. MUTIARA DESIGN KONSULTAN CV. PRATAMA JAYA KONSTRUKSI

AMY PRAMDANY, S.IP JUPRI, ST ELPHIN, ST


NIP. 19820903 2000804 1 001 Team Leader Pelaksana