BIAYA
No URAIAN PEKERJAAN
( Rp )
TERBILANG : Tujuh Miliar Seratus Sembilan Puluh Dua Juta Sembilan Ratus Lima Puluh Enam Ribu Lima Ratus Lima Koma Enam Tiga Rupiah ========
HARGA
No URAIAN PEKERJAAN SATUAN VOLUME BIAYA
SATUAN
UPAH
1 Mandor OH 115,877.00
2 Kepala tukang OH 102,427.00
3 Kepala tukang ( kayu, listrik, besi, batu, pipa, cat ) OH 102,427.00
4 Tukang Kayu OH 88,965.00
5 Tukang Khusus Aluminium OH 88,965.00
6 Tukang Besi OH 88,965.00
7 Tukang Batu OH 88,965.00
8 Tukang Gali OH 88,965.00
9 Tukang Listrik OH 88,965.00
10 Tukang Pipa OH 75,528.00
11 Tukang Cat OH 88,965.00
12 Tukang Pancang OH 84,746.00
13 Tukang Las OH 88,965.00
14 Pekerja OH 75,528.00
15 Juru ukur OH 80,968.00
16 Mekanik OH 84,746.00
17 Operator OH 88,965.00
18 Pembantu Operator OH 53,500.00
19 Sopir OH 83,145.00
20 Juru mudi OH 83,746.00
21 Pembantu juru mudi OH 53,500.00
22 Crew kapal keruk OH 75,528.00
23 Crew team pemasang pipa pembuangan OH 75,528.00
24 Juru Gambar OH 87,842.00
BAHAN
1 Air Cor m³ 10,900.00
2 Addetive jenis superplastitizer ( Sikamen LN ) kg 12,500.00
3 Admixture kg 25,000.00
4 Batu belah 15 / 20 cm m³ 191,431.00
5 Batu 10 - 20 kg / unit m³ 282,485.00
6 Batu 40 - 60 kg / unit m³ 180,000.00
7 Batu 80 - 120 kg / unit m³ 200,000.00
8 Batu 200 - 300 kg / unit m³ 250,000.00
8 Batu 300 - 400 kg / unit m³ 275,000.00
9 Batu Ampyang m2 25,000.00
10 Batu pecah 2/3cm m³ 200,000.00
11 Batu pecah 5/7cm m³ 204,533.00
12 Base Coarse Klas B m³ 252,294.00
13 Batu bata bh 458.67
14 Buis Beton Dia 1 m bh 197,500.00
15 Baja tulangan ( Besi beton ) kg 9,000.00
16 Besi beton polos kg 9,000.00
17 Besi Hollow 40x40 m' 24,000.00
18 Besi Hollow 30x40 m' 18,000.00
19 Baja Profil Canal "C" kg 12,835.00
20 Besi Profil WF kg 12,835.00
21 Besi baja Profil Siku ( L ) kg 12,835.00
22 Besi Strip kg 12,520.00
23 Baja Strip ( Plat strip ) kg 12,835.00
24 Baja Plat t = 4 - 6 mm kg 12,835.00
25 Baja Plat t = 8 - 12 mm kg 12,835.00
26 Baja Plat t = 16 - 25 mm kg 12,835.00
27 Baut Angkur Ø8 mm bh 8,239.00
28 Baut Ǿ 5/8"-8" bh 17,762.00
No. URAIAN SATUAN HARGA (Rp)
29 Baut Ǿ 8" bh 4,300.00
30 Angkur Dia 19mm L=60cm bh 83,000.00
31 Baut angkur Ǿ 3/4"-10" bh 17,762.00
32 Baja beton Weremesh M8-15 ( 5.4 m x 2.1 m ) lbr 760,000.00
No. URAIAN SATUAN HARGA (Rp)
33 Baja beton Weremesh M8-15 ( 5.4 m x 2.1 m ) m2 67,019.40
34 Baja beton Weremesh M10-15 ( 5.4 m x 2.1 m ) lbr 965,000.00
35 Baja beton Weremesh M10-15 ( 5.4 m x 2.1 m ) (m2) m2 85,097.00
36 Bollard 15 ton bh 19,400,000.00
37 Bambu dia. 8 - 10 cm btg 18,000.00
38 Baut Ǿ 19 mm - 400 mm ( Stainlessteel ) bh 83,000.00
39 Bensin ( Premium ) ltr 6,500.00
40 Cat Dasar kg 64,216.00
41 Cat Kayu kg 64,216.00
42 Cat Dinding Eksterior ltr 58,650.00
43 Cat Dinding Interior kg 40,441.00
44 Cat Emco kg 40,441.00
45 Cat Penutup kg 40,441.00
46 Engsel pintu & Jendela bh 20,000.00
47 Bak Mandi PVC bh 200,000.00
48 Pintu PVC bh 250,000.00
49 Fiting Plafond bh 7,500.00
50 Floor Hardtop Natural kg 7,150.00
51 Floor Drain bh 45,000.00
52 Fender Karet V 300H L = 2.5m bh 33,000,000.00
53 Gedeg guling/ sesek bambu m² 30,000.00
54 Genteng Glazur Standard bh 1,100.00
55 Genteng Glazur Wuwung bh 3,250.00
56 GRC ( Glassfiber Reinforced Cement ) m² 57,100.00
57 Lembaran Fiber glass lembar 50,000.00
58 Geotextile Non Woven berat 600 gram/m² t = 5 mm m² 39,552.00
59 Gorong - gorong beton dia. 40 cm m' 80,000.00
60 Grease kg 70,000.00
61 Isolator bh 2,500.00
62 Kayu kelas II balok m³ 5,450,000.00
63 Kayu balok Kamper m³ 5,450,000.00
64 Kayu papan Kamper m³ 8,200,000.00
65 Kayu papan ruiter Kamper m³ 8,200,000.00
66 Kayu Kamper Usuk m³ 7,700,000.00
67 Kayu Kamper reng m³ 7,700,000.00
68 Kayu bekisting m³ 3,000,000.00
69 Kayu Papan Klas II/ III m³ 6,300,000.00
70 Kayu Papan Klas III m³ 6,300,000.00
71 Kayu balok Meranti m³ 3,800,000.00
72 Kayu Merbau ( atau sekelas Merbau ) m³ 11,400,000.00
73 Kayu ulin 20/20 5M btg 2,418,200.00
74 Plywood t=9 mm lbr 125,000.00
75 Dolken kayu galam, φ (8-10) cm btg 25,000.00
76 Kawat beton kg 19,693.00
77 Kawat beton ( Bendrat ) kg 19,693.00
78 Kawat Las ( Electrode ) kg 25,000.00
79 Meni Besi kg 46,820.00
80 MCB bh 130,000.00
81 Olie ltr 39,600.00
82 Rambu suar dengan lampu tipe solar marine light termasuk unit 340,176,375.00
83 Lampu sorot/pemandu dengan lampu tipe solar marine lig unit 312,340,875.00
84 Minyak bekisting ltr 2,500.00
85 Oxygen tabung 600,000.00
86 Air m³ 10,900.00
87 Pasir Urug m³ 240,750.00
88 Pasir m³ 214,283.00
89 Sandbag m³ 214,283.00
90 Kerikil Beton m³ 156,550.00
91 Paku kg 19,053.00
92 Paku 12 cm kg 19,053.00
93 Paku pancing kg 19,053.00
94 Paku seng payung kg 22,733.00
95 Paku Tripleks eternit kg 19,053.00
96 Plastik ( mika ) m2 1,000.00
No. URAIAN SATUAN HARGA (Rp)
97 Plamir / Dempul kg 11,700.00
98 Plamir Kayu / Dempul kg 11,700.00
99 Sirtu m³ 194,066.00
100 Solar ( Industri ) ltr 7,800.00
101 Solar ( SPBU ) ltr 6,500.00
102 Semen ( Portland Cement ) 50 kg zak 60,000.00
103 Semen ( Portland Cement ) kg 1,200.00
104 Semen warna kg 3,000.00
105 Semen Floor hardener kg 5,500.00
106 Epoxy Resin kg 12,000.00
107 T. pancang Beton Spun pile Ǿ400mm t=70mm Type B m' 558,000.00
108 Tiang Beton Minipile r = 280 mm lumpsum m' 621,500.00
109 Wall Sealer ltr 50,000.00
110 Sealant tube 50,000.00
No. URAIAN SATUAN HARGA (Rp)
111 Skrup fixer bh 500.00
112 Zincalume 0.5 mm m² 125,000.00
PERALATAN
1 Excavator Long Arm. Jam 430,000.00
2 Excavator Jam 350,000.00
3 Crane 25 Ton Jam 420,400.00
4 Crane 50 Ton Jam 527,000.00
5 Wheel Loader Jam 380,000.00
6 Diesel hammer K.35 Jam 396,000.00
7 Unit Crane pancang darat. Jam 343,928.57
8 Unit Ponton pancang Laut. Jam 863,600.00
9 Buldozer Jam 229,286.00
10 Vibratory Roller Jam 660,343.00
11 Water Tank Truck Jam 206,800.00
12 Dump Truck Jam 225,000.00
13 Genset 500 Kva Jam 200,000.00
14 Mesin Las ( listrik ) Jam 259,073.00
15 Mesin las karbit ( Balnder ) hari 214,000.00
16 Concrete Mixer ( Molen ) Jam 133,750.00
17 Concrete Vibrator Jam 137,500.00
18 Concrete Screed Jam 40,000.00
19 Jack Hammer Jam 65,000.00
20 Air Compressor Jam 103,571.43
21 Theodolith Hari 401,600.00
22 Waterpass Hari 286,400.00
23 Alat bantu Jam 7,500.00
24 Alat bantu penyambungan tiang pancang ls 20,000.00
25 Stamper 80 kg Jam 40,000.00
26 Ponton 30 ft. jam 785,714.29
27 Ponton Transport jam 392,857.14
28 Bar bender Jam 26,553.00
29 Kapal Keruk ( Cutter Section Dredger Ø 16" ) Bulan 1,265,675,250.00
30 Tug boat jam 621,468.00
31 Pipa pembuangan darat diameter 16" Bulan 213,900.00
32 Pipa pembuangan apung & kelengkapannya 16" Bulan 623,875.00
33 Bar cutter Jam 25,423.00
ANALISA HARGA SATUAN
I.2.c APK (Alat Pelindung Kerja) dan APD (Alat Pelindung Diri) Rp 4,538,800.00
No. URAIAN SATUAN KOEFISIEN HARGA SAT. JUMLAH HARGA
1 Helm Proyek buah 7.00 Rp 135,000 Rp 945,000.00
2 Masker Kerja buah 7.00 Rp 25,000 Rp 175,000.00
3 Sarung Tangan kerja pasang 7.00 Rp 12,500 Rp 87,500.00
4 Sepatu Kerja pasang 7.00 Rp 85,000 Rp 595,000.00
5 Jaket pelampung buah 7.00 Rp 150,000 Rp 1,050,000.00
6 Rompi keselamatan buah 7.00 Rp 100,000 Rp 700,000.00
7 P3K set 1.00 Rp 500,000 Rp 500,000.00
Nilai Rp 4,052,500.00
Over Head dan profit (12%) Rp 486,300.00
Total Rp 4,538,800.00
I.2.f Kegiatan dengan peralatan terkait dengan pengendalian Risiko Keselamatan Konstruksi Rp 896,000.00
No. URAIAN SATUAN KOEFISIEN HARGA SAT. JUMLAH HARGA
1 Alat Pemadam Api Ringan 3 kg Ls 2.00 Rp 300,000 Rp 600,000.00
2 Bendera K3 orang 2.00 Rp 100,000 Rp 200,000.00
Nilai Rp 800,000.00
Over Head dan profit (12%) Rp 96,000.00
Total Rp 896,000.00
I.3 Pengukuran dan Pemasangan Bowplank Rp 356,233.08
No. URAIAN SATUAN KOEFISIEN HARGA SAT. JUMLAH HARGA
1 Bahan
Paku Kg 0.04 Rp 20,000 Rp 834.00
Kayu Kelas II m3 0.03 Rp 6,000,000 Rp 190,200.00
Kertas rim 0.20 Rp 100,000 Rp 20,000.00
2 Peralatan
Waterpass hari 0.16 Rp 150,000 Rp 23,437.50
Total Station hari 0.16 Rp 300,000 Rp 46,875.00
3 Upah
Juru ukur o/h 0.16 Rp 130,000 Rp 20,312.50
Pekerja o/h 0.16 Rp 105,000 Rp 16,406.25
Nilai Rp 318,065.25
Over Head dan profit (12%) Rp 38,167.83
Total Rp 356,233.08
2 Peralatan
Excavator 1 Jam 0.31 Rp 620,732 Rp 193,978.66
3 Upah
Mandor o/h 0.002 Rp 115,000 Rp 230.00
Pekerja o/h 0.02 Rp 105,000 Rp 2,100.00
Nilai Rp 196,308.66
Over Head dan profit (12%) Rp 23,557.04
Total Rp 219,865.70
2 Peralatan
Excavator 2 Jam 0.10 Rp 620,732 Rp 62,073.17
Excavator 3 Jam 0.13 Rp 620,732 Rp 77,591.46
Dump Truck Jam 0.12 Rp 411,229 Rp 47,949.25
Slim belt 6 meter 3 Ton set 0.06 Rp 1,300,000 Rp 72,222.22
Hook Omega baja dan chainlock 3 Ton set 0.02 Rp 430,000 Rp 8,600.00
3 Upah
Mandor o/h 0.005 Rp 115,000 Rp 575.00
Pekerja o/h 0.05 Rp 105,000 Rp 5,000.00
Nilai Rp 274,011.11
Over Head dan profit (12%) Rp 32,881.33
Total Rp 306,892.44
II.4 Pengadaan dan Pemasangan Batu W = 300 s/d 500 kg (Perbaikan Breakwater 2016) Rp 776,557.48
No. URAIAN SATUAN KOEFISIEN HARGA SAT. JUMLAH HARGA
1 Bahan
Batu W = 300 s/d 500 Kg m3 1.20 Rp 353,000 Rp 423,600.00
2 Peralatan
Excavator 1 Jam 0.09 Rp 620,732 Rp 53,879.51
Excavator 2 Jam 0.10 Rp 620,732 Rp 64,618.17
Excavator 3 Jam 0.12 Rp 620,732 Rp 75,418.90
Dump Truck Jam 0.16 Rp 411,229 Rp 66,043.31
Alat bantu Ls 0.06 Rp 105,000 Rp 6,300.00
3 Upah
Mandor o/h 0.003 Rp 115,000 Rp 345.00
Pekerja o/h 0.03 Rp 105,000 Rp 3,150.00
Nilai Rp 693,354.90
Over Head dan profit (12%) Rp 83,202.59
Total Rp 776,557.48
II.5 Pengadaan dan Pemasangan Batu W = 50 s/d 100 kg (Perbaikan Breakwater 2016) Rp 676,787.35
No. URAIAN SATUAN KOEFISIEN HARGA SAT. JUMLAH HARGA
1 Bahan
Batu W = 50 s/d 100 Kg m3 1.20 Rp 310,000 Rp 372,000.00
2 Peralatan
Excavator 1 Jam 0.07 Rp 620,732 Rp 43,078.78
Excavator 2 Jam 0.09 Rp 620,732 Rp 53,879.51
Excavator 3 Jam 0.10 Rp 620,732 Rp 64,618.17
Dump Truck Jam 0.15 Rp 411,229 Rp 60,902.95
Alat bantu Ls 0.06 Rp 105,000 Rp 6,300.00
3 Upah
Mandor o/h 0.003 Rp 115,000 Rp 345.00
Pekerja o/h 0.03 Rp 105,000 Rp 3,150.00
Nilai Rp 604,274.42
Over Head dan profit (12%) Rp 72,512.93
Total Rp 676,787.35
II.6.1.c Membuat 1m2 bekisting Plat Tetrapod 2,88 Ton ( 10 kali pakai ) Rp 240,477.43
No. URAIAN SATUAN KOEFISIEN HARGA SAT. JUMLAH HARGA
1 Bahan
Siku 50 x 50 x 6 m1 5.82 Rp 30,000 Rp 174,467.21
Plat tebal 2 mm m2 3.05 Rp 220,000 Rp 671,000.00
Resibon Potong (WD) buah 2.73 Rp 15,000 Rp 40,983.61
Electroda Kg 2.50 Rp 55,000 Rp 137,500.00
Baut 12 mm atau pengunci buah 8.20 Rp 3,500 Rp 28,688.52
Mata Bor buah 0.50 Rp 25,000 Rp 12,500.00
zinkcromate Kg 0.25 Rp 70,000 Rp 17,500.00
Solar (Industri) Liter 8.00 Rp 12,100 Rp 96,800.00
2 Peralatan
Mesin Las Jam 2.37 Rp 250,000 Rp 592,250.00
Genset 10 Kva Jam 2.37 Rp 90,000 Rp 213,210.00
3 Upah
Mandor hari 0.13 Rp 115,000 Rp 14,375.00
Kepala Tukang hari 0.25 Rp 112,000 Rp 28,000.00
Tukang Las hari 0.75 Rp 110,000 Rp 82,500.00
Tukang Besi hari 0.75 Rp 110,000 Rp 82,500.00
Tukang Cat hari 0.50 Rp 110,000 Rp 55,000.00
Pekerja hari 1.50 Rp 105,000 Rp 157,500.00
Total Rp 2,404,774.34
Pemakaian 10 kali Rp 240,477.43
2 Peralatan
Excavator 1 Jam 0.20 Rp 620,732 Rp 124,146.34
Excavator 2 Jam 0.13 Rp 620,732 Rp 77,591.46
Dump Truck Jam 0.44 Rp 411,229 Rp 179,419.03
Crane 35 ton Jam 0.30 Rp 1,026,877 Rp 308,063.14
3 Upah
Mandor o/h 0.03 Rp 115,000 Rp 3,220.00
Pekerja o/h 0.28 Rp 105,000 Rp 29,400.00
Penyelam o/h 0.09 Rp 500,000 Rp 42,500.00
Nilai Rp 764,339.98
Over Head dan profit (12%) Rp 91,720.80
Total Rp 856,060.77
PERALATAN
1 Banner Pencegahan Covid Rp 120,000 buah
2 Concrete Mixer Rp 100,000 Jam
3 Crane 35 ton Rp 1,026,877 Jam
4 Dump Truck Rp 411,229 Jam
5 Excavator 1 Rp 620,732 Jam
6 Excavator 2 Rp 620,732 Jam
7 Excavator 3 Rp 620,732 Jam
8 External Concrete Vibrator Rp 150,000 Jam
9 Face Shield Rp 25,000 buah
10 Genset 10 Kva Rp 90,000 Jam
11 Helm Proyek Rp 135,000 buah
12 Mesin Las Rp 250,000 Jam
13 Mob dan Demob Crane 35 Ton Rp 102,000,000 unit
14 Mob dan Demob Dump Truck Rp 2,500,000 unit
15 Mob dan Demob Excavator Rp 20,000,000 unit
16 Sprayer Rp 100,000 unit
17 Tempat Cuci Tangan Rp 80,000 unit
18 Thermogun Rp 300,000 unit
19 Total Station Rp 300,000 hari
20 Waterpass Rp 150,000 hari
21 Pembuatan dokumen Rencana keselamatan Konstruksi Rp 250,000 eks
22 Pembuatan prosedur dan instruksi kerja Rp 250,000 eks
23 Pengarahan keselamatan konstruksi Rp 100,000 set
24 Alat Pemadam Api Ringan 3 kg Rp 300,000 buah
25 Bendera K3 Rp 100,000 buah
BAHAN
26 Admixture Rp 25,000 Kg
27 Air Rp 50,000 m3
28 Baja Tulangan (Besi Beton) Rp 15,000 Kg
29 Batu Pecah/ Split Rp 300,000 m3
30 Batu W = 50 s/d 100 Kg Rp 310,000 m3
31 Batu W = 300 s/d 500 Kg Rp 353,000 m3
32 Baut 12 mm atau pengunci Rp 3,500 buah
33 Cairan Hand Sanitizer Rp 150,000 Liter
34 Cairan Handwash Rp 100,000 Liter
35 Cairan Karbol/Wipol/Disenfektan Rp 100,000 Liter
36 Cairan Super Pel Rp 80,000 Liter
37 Electroda Rp 55,000 Kg
38 Hook Omega baja dan chainlock 3 Ton Rp 430,000 set
39 Kawat Beton (Bendrat) Rp 18,000 Kg
40 Kayu Kelas II Rp 6,000,000 m3
41 Kertas Rp 100,000 rim
42 Masker Kerja Rp 25,000 buah
43 Masker Kesehatan Rp 75,000 box
44 Mata Bor Rp 25,000 buah
45 Olie Rp 33,000 Liter
46 Paku Rp 20,000 Kg
47 Pasir Beton Rp 250,000 m3
48 Perlengkapan Penerangan Rp 1,500,000 set
49 Plat tebal 2 mm Rp 220,000 m2
50 Rambu Petunjuk Rp 225,000 buah
48 Rambu Larangan Rp 225,000 buah
49 Rambu Peringatan Rp 225,000 buah
50 Rambu Kewajiban Rp 225,000 buah
51 Resibon Potong (WD) Rp 15,000 buah
52 Sarung Tangan Kerja Rp 12,500 pasang
53 Sarung Tangan Medis Rp 12,500 pasang
54 Semen PC Rp 1,400 Kg
55 Sepatu Kerja Rp 85,000 pasang
56 Siku 50 x 50 x 6 Rp 30,000 m1
57 Sirtu Rp 185,000 m3
58 Slim belt 6 meter 3 Ton Rp 1,300,000 set
59 Solar (Industri) Rp 12,100 Liter
60 zinkcromate Rp 70,000 Kg
61 Spanduk Rp 125,000 buah
62 Poster Rp 250,000 buah
63 Rompi keselamatan Rp 100,000 buah
64 Jaket pelampung Rp 150,000 buah
65 Papan informasi K3 Rp 250,000 buah
UPAH
66 Album Photo Rp 400,000 Eks
67 BPJS JKK dan JKM Rp 38,500 orang
68 Buku Gambar (Shopdrawing dan Asbuiltdrawing) Rp 700,000 Eks
69 Buku Laporan (Harian, Mingguan dan Bulanan) Rp 250,000 Eks
70 Iuran Jamsostek Jasa Konstruksi Rp 9,000,000 Ls
71 Juru ukur Rp 130,000 hari
72 Kepala Tukang Rp 112,000 o/h
73 Mandor Rp 115,000 o/h
74 Mekanik Rp 125,000 o/h
75 P3K Rp 500,000 set
76 Pekerja Rp 105,000 hari
77 Pembuatan Buku Pengendalian Resiko Keselamatan Konstruksi Rp 250,000 Eks
78 Penyelam Rp 500,000 o/h
79 Sosialisasi Keselamatan Konstruksi Rp 5,000,000 Ls
80 Spanduk Sosialisasi Keselamatan Konstruksi Rp 300,000 buah
81 Tenaga Penyemprot Min. 2 kali Seminggu Rp 125,000 o/h
82 Tes Antigen Rp 100,000 tes
83 Test Batu dan Transport Material Rp 10,000,000 Ls
84 Test Kuat beton dan Tes Kuat tekan beton Rp 5,000,000 Ls
85 Test Tarik besi dan transport Rp 5,000,000 Ls
86 Tukang Batu Rp 110,000 o/h
87 Tukang Besi Rp 110,000 o/h
88 Tukang Cat Rp 110,000 o/h
89 Tukang Las Rp 110,000 o/h
90 Ahli K3 konstruksi Rp 3,000,000 o/b
91 Konsultasi dengan ahli terkait Keselamatan Konstruksi Rp 500,000 ls
Batu Besar Batu Sedang Pindah batu luar Pindah batu dalam
NAMA CROSS LUAS PANJANG LUAS PANJANG LUAS PANJANG LUAS PANJANG
VOLUME VOLUME VOLUME VOLUME
AREA CROSS AREA CROSS AREA CROSS AREA CROSS
0+572.68 35.446 0.387 0.000 0.000
7.320 246.933 0.000 7.320 6.697 7.320 0.000 7.320 8.785
0+580 32.022 1.443 0.000 2.400
0.000
0+580 32.022 1.443 0.000 2.400
10.000 313.870 0.000 10.000 24.627 10.000 0.000 10.000 27.108
0+590 30.752 3.483 0.000 3.021
3,964.960
panjang lebar tebal
Jalan Kerja 635.244 529.37 4 0.3
635.240
Tetrapod kecil 244
1 EXCAVATOR untuk pembuatan jalan kerja (satuan m³/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
1 Jam kerja efektif per hari Tk 7.00 Jam
2 Faktor pengembangan bahan Fk 1.20
3 Kapasitas bucket V 0.80 M3
4 Factor bucket Fb 0.90
5 Factor efisiensi alat Fa 0.80
6 Waktu siklus = T1 + T2 Ts1 2.00 Menit
7 - Waktu menghampar sirtu T1 1.00 Menit
- Waktu merapikan sirtu T2 0.50 Menit
8 - Lain-lain T3 0.50 Menit
9
Kapasitas produksi / jam = Q2 14.40 M3/Jam
V x Fb x Fa x 60
Fk x Ts1
2 EXCAVATOR untuk Pemindahan dan perapian batu (existing 2016) (satuan m³/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
1 Jam kerja efektif per hari Tk 7.00 Jam
2 Faktor pengembangan bahan Fk 1.20
3 Kapasitas bucket V 0.80 M3
4 Factor bucket Fb 0.90
5 Factor efisiensi alat Fa 0.80
6 Waktu siklus = T1 + T2 Ts1 9.00 Menit
7 - Waktu memindahkan batu T1 3.00 Menit
- Waktu merapikan batu T2 5.00 Menit
8 - Lain-lain T3 1.00 Menit
9
Kapasitas produksi / jam = Q2 3.20 M3/Jam
V x Fb x Fa x 60
Fk x Ts1
V x Fb x Fa x 60
Fk x Ts1
3.b EXCAVATOR untuk Pemasangan dan Perapian Tetrapod W = 2 ton (existing 2017)(satuan bh/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
1 Jam kerja efektif per hari Tk 7.00 Jam
2 Faktor pengembangan bahan Fk 1.20
3 Kapasitas bucket V 1.00 bh
4 Factor bucket Fb 1.00
5 Factor efisiensi alat Fa 0.80
6 Waktu siklus = T1 + T2 Ts1 5.00 Menit
7 - Waktu memindahkan tetrapod dari dump truck T1 1.00 Menit
- Waktu memasang dan merapikan tetrapod T2 3.00 Menit
8 - Lain-lain T3 1.00 Menit
9
Kapasitas produksi / jam = Q2 8.00 buah/jam
V x Fb x Fa x 60
Fk x Ts1
V x Fa x 60
Fk x Ts
V x Fb x Fa x 60
Fk x Ts1
V x Fb x Fa x 60
Fk x Ts1
4.c DUMP TRUCK untuk Pemindahan batu sedang dari stockpile ke lokasi (satuan m3/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
V x Fa x 60
Fk x Ts
Koefisien alat / M3 = 1 : Q2 0.15 Jam
4.d EXCAVATOR untuk memasang dan merapikan batu sedang di breakwater (satuan m³/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
1 Jam kerja efektif per hari Tk 7.00 Jam
2 Faktor pengembangan bahan Fk 1.20
3 Kapasitas bucket V 0.80 M3
4 Factor bucket Fb 0.90
5 Factor efisiensi alat Fa 0.80
6 Waktu siklus = T1 + T2 Ts1 3.00 Menit
7 - Waktu memasang dan merapikan batu di breakwater T1 2.50 Menit
8 - Lain-lain T3 0.50 Menit
9
Kapasitas produksi / jam = Q2 9.60 M3/Jam
V x Fb x Fa x 60
Fk x Ts1
V x Fb x Fa x 60
Fk x Ts1
V x Fb x Fa x 60
Fk x Ts1
5.c DUMP TRUCK untuk Pemindahan batu besar dari stockpile ke lokasi (satuan m3/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
V x Fa x 60
Fk x Ts
Koefisien alat / M3 = 1 : Q2 0.16 Jam
5.d EXCAVATOR untuk memasang dan merapikan batu besar di breakwater (satuan m³/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
1 Jam kerja efektif per hari Tk 7.00 Jam
2 Faktor pengembangan bahan Fk 1.20
3 Kapasitas bucket V 0.80 M3
4 Factor bucket Fb 0.90
5 Factor efisiensi alat Fa 0.80
6 Waktu siklus = T1 + T2 Ts1 3.50 Menit
7 - Waktu memasang dan merapikan batu di breakwater T1 3.00 Menit
8 - Lain-lain T3 0.50 Menit
9
Kapasitas produksi / jam = Q2 8.23 M3/Jam
V x Fb x Fa x 60
Fk x Ts1
6.a EXCAVATOR untuk memuat tetrapod W = 2.88 Ton ke dumptruck (satuan buah/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
1 Jam kerja efektif per hari Tk 7.00 Jam
2 Faktor pengembangan bahan Fk 1.20
3 Kapasitas bucket V 1.00 bh
4 Factor bucket Fb 1.00
5 Factor efisiensi alat Fa 0.80
6 Waktu siklus = T1 + T2 Ts1 8.00 Menit
7 - Waktu memindahkan tetrapod ke dump truck T1 6.00 Menit
8 - Lain-lain T3 2.00 Menit
9
Kapasitas produksi / jam = Q2 5.00 buah/Jam
V x Fb x Fa x 60
Fk x Ts1
V x Fa x 60
Fk x Ts
Koefisien alat / buah = 1 : Q2 0.44 Jam
6.c EXCAVATOR untuk Penurunan Tetrapod W = 2.88 ton dari DT (satuan bh/jam)
URAIAN KODE KOEFF SATUAN KETERANGAN
1 Jam kerja efektif per hari Tk 7.00 Jam
2 Faktor pengembangan bahan Fk 1.20
3 Kapasitas bucket V 1.00 bh
4 Factor bucket Fb 1.00
5 Factor efisiensi alat Fa 0.80
6 Waktu siklus = T1 + T2 Ts1 5.00 Menit
7 - Waktu memindahkan tetrapod dari dump truck T1 3.00 Menit
8 - Lain-lain T3 2.00 Menit
9
Kapasitas produksi / jam = Q2 8.00 buah/jam
V x Fb x Fa x 60
Fk x Ts1
V x Fb x Fa x 60
Fk x Ts1
2 EXCAVATOR UNTUK MEMILIH DAN MEMUAT BATU 50-100 KG/UNIT DI BW LAMA Satuan M3/Jam
3 EXCAVATOR UNTUK MEMILIH DAN MEMUAT BATU 300 -500 KG/UNIT DI BW LAMA Satuan M3/Jam
V x Fa x 60
Kapasitas produksi / jam = Q2 6.0377 M3/Jam
Fk x Ts2
Koefisien alat / M3 = 1 : Q2 0.1656 Jam
V x Fb x Fa x 60
Kapasitas Produksi / jam = Q2 2.8800 M 3 / jam
Ts1 x Fk
Koeffisien Alat / M 3 = 1 : Q5 0.3472 Jam
V x Fb x Fa x 60
Kapasitas Produksi / jam = Q4 3.0197 M 3 / jam
Ts1 x Fk
Koeffisien Alat / M 3 = 1 : Q5 0.3311 Jam
V x Fb x Fa x 60
Kapasitas Produksi / jam = Q4 1.5098 M 3 / jam
Ts1 x Fk
Koeffisien Alat / M 3 = 1 : Q5 0.6623 Jam
URAIAN KODE KOEFF SATUAN KETERANGAN
Alat bantu LS
- Linggis
- Bongkotan
Koefisien tenaga / M3
- Pekerja = (Tk x P) : Qt 0.6666 Hari
- Mandor = (Tk x M) : Qt 0.0833 Hari
12 TENAGA PEMASANGAN BATU BERAT 300 - 500 KG/UNIT ( BREAKWATER )
Alat bantu LS
- Linggis
- Bongkotan
Koefisien tenaga / M3
- Pekerja = (Tk x P) : Qt 1.2000 Hari
- Mandor = (Tk x M) : Qt 0.1000 Hari