PEKERJAAN
BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR-JASA DESAIN
ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN PEMBANGUNAN PASAR BUNDA
SRI MERSING)
Lokasi
KOTA DUMAI
TAHUN ANGGARAN
2023
KONSULTAN PERENCANA
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR-JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN
PEMBANGUNAN PASAR BUNDA SRI MERSING)
JUMLAH 41,824,910,155.22
PPN 11% 4,600,740,117.07
JUMLAH 46,425,650,272.30
DIBULATKAN 46,425,650,000.00
Terbilang : Empat Puluh Enam Milyar Empat Ratus Dua Puluh Lima Juta Enam Ratus Lima Puluh Ribu Rupiah
Disetujui Oleh :
PEJABAT PEMBUAT KOMITMEN
( PPK )
Page 1
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp )
c. Pembesian Beugeul Ø8 - 150mm Kg 659.70 23,316.92 15,382,272.85
d. Bekisting Kolom Praktis M2 130.00 263,469.53 34,251,038.25
V. PEKERJAAN PLAFOND
a. Pek. Pasang Rangka Hollow 4x4 dan 4x6 M2 1,728.28 225,000.00 388,862,257.50
b. Pek. Plafond Gypsum M2 1,728.28 265,349.04 458,596,563.20
c. Pas. List Plafond M1 776.66 27,206.30 21,129,908.93
JUMLAH V. 868,588,729.63
Page 2
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp )
LANTAI. II
I. PEKERJAAN BETON BERTULANG
1. Pek. Kolom (K1) 35/35 cm
a. Beton K-250 ( Ready Mix ) M3 55.74 3,234,660.00 180,291,861.75
b. Pembesian Tulangan Utama 12 D 19mm Ulir Kg 12,151.58 23,316.92 283,337,532.99
c. Pembesian Beugeul D10 Ulir Kg 3,500.73 23,316.92 81,626,325.29
d. Bekisting Kolom M2 637.00 333,827.73 212,648,260.83
JUMLAH I. 3,788,729,778.10
Page 3
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME
( Rp ) ( Rp )
b. Pek. Pintu Panil (Kusen + Daun Pintu + Acc + Pengecatan) Unit 6.00 2,500,000.00 15,000,000.00
c. Pek. Pintu Fiber Unit 16.00 900,000.00 14,400,000.00
JUMLAH VI. 37,717,874.19
DESTA MASRIKO
Wakil Direktur
Page 4
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR-JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN
PEMBANGUNAN PASAR BUNDA SRI MERSING)
TOTAL PEKERJAAN MEKANIKAL ELEKTRIKAL DAN PLUMBING PASAR BUNDA SRI MERSING Rp 7,380,315,920.00
DESTA MASRIKO
Wakil Direktur
REKAPITULASI RENCANA ANGGARAN BIAYA
- PEKERJAAN STANDARD
Rekapitulasi Standar
REKAPITULASI PEKERJAAN NON STANDARD
V. PEKRJAAN MEKANIKAL
5.1. PEKERJAAN FIRE FIGHTING Rp 409,497,748.00
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR-JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN PEMBAN
LOKASI : KOTA DUMAI
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR -JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN PEMBANGUNAN PASAR BUNDA SRI MERSING)
LOKASI : KOTA DUMAI
4. RISER DI SHAFT
a. Pemipaan BSP Schedule 40 termasuk fitting, sambungan, penggantung & alat bantu lainnya :
- Diameter 100 mm ( Pipa Hydrant ) m' 24.00 344,750.00 8,274,000.00
b. Automatic Air valve ( AAV ) bh 2.00 1,503,865.00 3,007,730.00
-
2. LANTAI DUA -
a. Peralatan Utama
Firedome Speaker with Wall Metal BoxZS-1860F-AS. Set 10.00 1,061,121.00 10,611,210.00
TITIK INSTALLASI SPEAKER Titik 10.00 125,863.00 1,258,630.00
-
JUMLAH 6.1.PEKERJAAN SOUND SYSTEM 117,064,656.00
6.3. PEKERJAAN SISTEM TEKNOLOGI INFORMASI DAN KOMUNIKASI (ICT) & CCTV
1. LANTAI SATU
a. Peralatan Utama
16 Ch. 1080N H.265 Indigo DVRCP-VRA-1E1602 -H Unit 1.00 7,800,000.00 7,800,000.00
Toshiba Surveillance 4 TBTOSHIBA Unit 1.00 3,679,200.00 3,679,200.00
Power Supply for CCTVPSU Set 1.00 1,500,000.00 1,500,000.00
Monitor CCTV 32 Inch c/w AccessoriesSHARP Set 1.00 5,216,400.00 5,216,400.00
Equipment RackINDORACK Set 1.00 4,042,500.00 4,042,500.00
UPS Backup Power 2000 VAUPS Unit 1.00 5,985,000.00 5,985,000.00
2.4 MP Full HD IR Dome Camera - 20 Mtr. (1080 P )CP-VAC-D24L2 Unit 10.00 776,160.00 7,761,600.00
2.4 MP Full HD IR Bullet Camera - 20 Mtr. (1080 P )CP-VAC-T24PL2 Unit 4.00 831,600.00 3,326,400.00
TITIK INSTALLASI CCTV TITIK 20.00 117,696.00 2,353,920.00
-
LANTAI DUA -
2.4 MP Full HD IR Bullet Camera - 20 Mtr. (1080 P )CP-VAC-T24PL2 Unit 10.00 831,600.00 8,316,000.00
TITIK INSTALLASI CCTV TITIK 10.00 117,696.00 1,176,960.00
-
5. JASA TESTING + TESCOM+ DOKUMENTASI ls 1.00 1,000,000.00 1,000,000.00
JUMLAH 6.3.PEKERJAAN SISTEM TEKNOLOGI INFORMASI DAN KOMUNIKASI (ICT) & CCTV 52,157,980.00
PEKERJAAN UTILITAS DAN SITE DEVELOPMENT
BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR-JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN PEMBANGUNAN PASAR
PEKERJAAN :
BUNDA SRI MERSING)
LOKASI : KOTA DUMAI
1. 2. 3. 4. 5. 6 = (4. X 5.)
PEKERJAAN UTILITAS DAN SITE DEVELOPMENT
JUMLAH II.PEKERJAAN AIR KOTOR, AIR BEKAS & VENT (STP) 164,662,006.00
9. Hidder
- Diameter 150 mm bh 1.00 3,702,542.00 3,702,542.00
10. Flexible Joint :
- Diameter 100 mm bh 2.00 1,059,791.00 2,119,582.00
- Diameter 65 mm bh 2.00 726,485.00 1,452,970.00
11. Check Valve :
- Diameter 100 mm bh 2.00 5,682,156.00 11,364,312.00
- Diameter 65 mm bh 2.00 3,156,420.00 6,312,840.00
12. Gate Valve:
- Diameter 100 mm bh 2.00 8,462,477.00 16,924,954.00
- Diameter 65 mm bh 2.00 4,181,284.00 8,362,568.00
13. Safety Valve :
- Diameter 100 mm bh 1.00 29,338,848.00 29,338,848.00
- Diameter 65 mm bh 1.00 9,280,656.00 9,280,656.00
14. Foot Valve :
- Diameter 100 mm bh 1.00 8,083,152.00 8,083,152.00
- Diameter 65 mm bh 1.00 3,293,136.00 3,293,136.00
15. Branch Control Valve
- Diameter 100 mm bh 1.00 7,783,776.00 7,783,776.00
16. Strainer
- Diameter 100 mm bh 1.00 5,164,790.00 5,164,790.00
- Diameter 65 mm bh 1.00 2,766,456.00 2,766,456.00
17. Pressure Gauge bh 2.00 2,544,696.00 5,089,392.00
18. Pressure Switch bh 2.00 1,247,400.00 2,494,800.00
19. Pemipaan BSP Schedule 40 di R.Pompa
- Diameter 100 mm m' 20.00 344,750.00 6,895,000.00
- Diameter 65 mm m' 15.00 116,631.00 1,749,465.00
20. Komponen Hydrant
- Fire Hose Cabinet ( FHC ) (Outdoor) set 11.00 7,397,794.00 81,375,734.00
- Pillar Hydrant bh 3.00 5,351,346.00 16,054,038.00
- Siamise Connection bh 1.00 7,705,938.00 7,705,938.00
- Nozzle Pemadam Kebakaran dia. 65 mm bh 11.00 723,492.00 7,958,412.00
- Gate valve dia. 150 mm bh 11.00 14,164,476.00 155,809,236.00
- Check valve dia. 150 mm bh 11.00 10,890,300.00 119,793,300.00
- Strainer diameter 150 mm bh 11.00 9,702,000.00 106,722,000.00
21. Pemipaan BSP Schedule 40 ke Pillar Hydrant & Siamise
- Pemipaan ke Siamise Connection-Pilar-FHC, BSP Sch.40, dia.150 mm m' 450.00 602,761.00 271,242,450.00
JUMLAH
BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR-JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN PEMBANGUNAN PASAR BUNDA
PEKERJAAN :
SRI MERSING)
LOKASI : KOTA DUMAI
2. LANTAI SATU
1 Pemipaan Polypropylene PN.10 + Fitting dan Material Bantu :
* Diameter 50 mm m' 4.00 143,093.00 572,372.00
* Diameter 40 mm m' 30.00 87,824.00 2,634,720.00
* Diameter 32 mm m' 42.00 56,710.00 2,381,820.00
* Diameter 20 mm m' 25.00 23,016.00 575,400.00
2 Gate Valve (Menuju Shaft)
* Diameter 50 mm bh 1.00 1,850,677.00 1,850,677.00
3. LANTAI DUA
1 Pemipaan Polypropylene PN.10 + Fitting dan Material Bantu :
* Diameter 50 mm m' 4.00 143,093.00 572,372.00
* Diameter 40 mm m' 25.00 87,824.00 2,195,600.00
* Diameter 32 mm m' 23.00 56,710.00 1,304,330.00
* Diameter 20 mm m' 20.00 23,016.00 460,320.00
2 Gate Valve (Menuju Shaft)
* Diameter 40 mm bh 1.00 1,850,677.00 1,850,677.00
6. RISER DI SHAFT
Pemipaan Polypropylene PN.10 + Fitting dan Material Bantu :
- AAV bh 1.00 1,503,865.00 1,503,865.00
2. LANTAI DUA
a. Pemipaan Air kotor Padat PVC Kelas 10 kg/cm2 + Fitting dan Material Bantu:
- Diameter 100 mm + MOF m' 35.00 92,824.00 3,248,840.00
- FCO diameter 100 mm bh 2.00 338,787.00 677,574.00
b. Pemipaan Air kotor bekas PVC Kelas 10 kg/cm2 + Fitting dan Material Bantu:
- Diameter 80 mm + MOF m' 56.00 39,626.00 2,219,056.00
- Diameter 50 mm + MOF m' 30.00 20,857.00 625,710.00
- FCO diameter 50 mm bh 2.00 184,944.00 369,888.00
c. Pemipaan Vent PVC Kelas 10 kg/cm2 + Fitting dan Material Bantu:
- Diameter 50 mm + MOF m' 45.00 20,857.00 938,565.00
4. RISER DI SHAFT
a. Pemipaan Air kotor Padat PVC Kelas 10 kg/cm2 + Fitting dan Material Bantu:
- Diameter 100 mm m' 12.00 92,824.00 1,113,888.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN VOLUME
(Rp.) (Rp.)
b. Pemipaan Air kotor bekas PVC Kelas 10 kg/cm2 + Fitting dan Material Bantu:
- Diameter 100 mm m' 12.00 92,824.00 1,113,888.00
c. Pemipaan Vent PVC Kelas 10 kg/cm2 + Fitting dan Material Bantu:
- Diameter 50 mm m' 12.00 20,857.00 250,284.00
2. LANTAI DUA
a. Rak Kabel arus kuat Termasuk Jointing / Connector Tray c/w bolt & Nut H100
- Ukuran 400 x 100 mm btg 177.00 1,230,633.00 217,822,041.00
5. SHAFT
a. Rak Kabel arus kuat Termasuk Jointing / Connector Tray c/w bolt & Nut H100
- Ukuran 400 x 100 mm btg 15.00 1,230,633.00 18,459,495.00
b. Kabel Feeder
- Dari KWH PLN KE MDP NYFGBY 4X1X150+ Grounding m' 30.00 7,026,853.00 210,805,590.00
- Dari MDP ke SP-P.BP (Bangunan Pasar), NYFGBY 4 x95 mm2 + Grounding m' 10.00 1,229,137.00 12,291,370.00
- Dari MDP ke P.POMPA, NYFGBY 4 x70 mm2 + Grounding m' 30.00 1,060,189.00 31,805,670.00
- Dari MDP ke PP.L1 A, NYY 4 x50 mm2 + Grounding m' 15.00 529,034.00 7,935,510.00
- Dari MDP ke PP.L2 B, NYY 4 x50 mm2 + Grounding m' 45.00 529,034.00 23,806,530.00
2. LANTAI DUA
a. Panel Listrik
- P-P.BP (Bangunan Pasar) unit 1.00 26,575,728.00 26,575,728.00
- PP-L2 A unit 1.00 21,500,000.00 21,500,000.00
- PP - L2 B unit 1.00 21,500,000.00 21,500,000.00
b. Kabel Feeder
- Dari MDP ke SP-P.BP (Bangunan Pasar), NYFGBY 4 x95 mm2 + Grounding m' 30.00 1,229,137.00 36,874,110.00
- Dari MDP KE PP-L2 A, NYY 4 x 16 mm2 + Grounding m' 15.00 258,760.00 3,881,400.00
- Dari MDP KE PP-L2 B, NYY 4 x 16 mm2 + Grounding m' 100.00 258,760.00 25,876,000.00
JUMLAH 4.5.PEKERJAAN LAMPU PENERANGAN, SAKLAR, STOP KONTAK DAN INSTALASI 512,377,676.00
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR -JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN
PEMBANGUNAN PASAR BUNDA SRI MERSING)
LOKASI : KOTA DUMAI
T. ANGGARAN : 2023
HARGA
JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME SATUAN
( Rp ) ( Rp )
Page 7
HARGA
JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME SATUAN
( Rp ) ( Rp )
DESTA MASRIKO
Wakil Direktur
Page 8
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR -JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI PERENCANAAN
PEMBANGUNAN PASAR BUNDA SRI MERSING)
LOKASI : KOTA DUMAI
T. ANGGARAN : 2023
HARGA
JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME SATUAN
( Rp ) ( Rp )
Page 9
HARGA
JUMLAH HARGA
NO. URAIAN PEKERJAAN SAT. VOLUME SATUAN
( Rp ) ( Rp )
V. PEKERJAAN PERLENGKAPAN
a. Pengadaan Tanah Humus M3 18.50 280,000.00 5,180,000.00
b. Pengadaan Tanaman Hias Besar (Ketapang Kencana) Tinggi 2 M Btg 10.00 600,000.00 6,000,000.00
c. Pengadaan Tanaman Hias Kecil (Jenis Keladi,Melati Hijau,Asoka Merah,Dll) Bh 450.00 15,000.00 6,750,000.00
d. Pengadaan Tanaman Hias Kecil (Rumput Gajah Mini) M2 370.00 70,000.00 25,900,000.00
e. Pengadaan Bak Sampah Uk. 3x4 Tinggi 2 M Bh 1.00 15,000,000.00 15,000,000.00
JUMLAH V. 58,830,000.00
JUMLAH KESELURUHAN 2,640,320,864.76
DESTA MASRIKO
Wakil Direktur
####
Page 10
JENIS PEKERJAAN : Pekerjaan Penyelenggaraan SMK 3 Konstruksi
SATUAN : Kegiatan
HARGA SATUAN : Rp 200,185,000.00
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
JUMLAH Rp 200,185,000.00
DESTA MASRIKO
Wakil Direktur
PERHITUNGAN VOLUME GEDUNG A
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR-JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI
PERENCANAAN PEMBANGUNAN PASAR BUNDA SRI MERSING)
LOKASI : KOTA DUMAI
T. ANGGARAN : 2023
4. Pengadaan BoredPile Ø 60C m (Diameter Luar) M1 91.00 x 18.00 x 1.00 = 1,638.00 1,638.00
6. Pas. Lantai kerja K-175 M3 3.14 x 0.09 x 91.00 x 0.30 = 7.71 7.71
7. Beton kedap air K.250 (Ready Mix) M3 3.14 x 0.09 x 91.00 x 1.00 = 25.72 25.72
8. Cyclopen beton K-250 + 40% batu kali M3 3.14 x 0.09 x 91.00 x 18.00 = 462.90 462.90
- Pembesian Tulangan Utama D16mm Ulir Kg Keliling = 2.00 x 3.14 x 0.30 = 1.88 31,021.89
c. Pek. Pembesian Beg Anak Tangga Kg 5.86 x 48.00 x 0.62 = 173.41 729.98
Bordes 9.86 x 11.67 x 0.62 = 70.92
Anak Tangga 326.20 x 0.60 x 0.62 = 120.66 +
364.99 x 2.00
1,410.75
b. Stek Besi Ø 8 mm Pengikat Bata P=40 cm Kg 0.40 x 6.00 x 168.00 = 403.20 159.09
403.20 x 0.39 = 159.09
i. Pek. Pasang Relling Tangga Besi Hollow Rangka 40x40x2mm M2 22.00 x 1.00 = 22.00 22.00
j. Pas. Follding Gate t=0,8mm Fins. Cat Untuk Kios Unit 38.00
k. Pas. Follding Gate t=0,8mm Fins. Cat Untuk Akses Pintu Uta Unit 10.00
m. Pas. Cladding ACP Cutting Decoratif Ex. GoodSense M2 Cad Area 1,351.10
n. Pas. Railing Kaca (Handrail Holo Stainless 4x6, Tiang Holo St M1 Panjang 196.00
V. PEKERJAAN PLAFOND
a. Pek. Pasang Rangka Hollow 4x4 dan 4x6 M2 1,728.28
Luas Area Luar ( CAD ) 1,486.44 x 1.00 = 1,486.44
Luas Area Kios 5.49 x 42.00 = 230.66
Luas KM 1.40 x 8.00 = 11.18 +
1,728.28
c. Pek. Coran Lantai ( K-100 ) =t=7Cm M3 100.00 x 28.00 x 0.07 x 1.00 = 196.00 196.00
196.00
d. Pek. Water Proofing BITULINE Ex ONDULINE Tipe TP300 M2 CAD AREA 1,452.88
f. Pek. Pasang Keramik KM/WC 30 x 30 Cm Ex. Ikad M2 1.50 x 1.50 x 8.00 = 18.00 18.00
18.00
g. Pek. Pasang Keramik Dinding KM/WC 30 x 60 Cm Ex. Ikad M2 6.00 x 1.60 x 8.00 = 76.80 76.80
76.80
VII. PEKERJAAN PENGECATAN
a. Pek. Mencat Plafond Baru dgn Cat Tembok Ex. Catilac M2 Luasan Plafond = 1,728.28 1,728.28
b. Pek. Mencat Dinding Baru Exterior dgn Cat Tembok Ex. Nipo M2 Luasan Acian = 2,821.49 4,112.70
c. Pek. Pembesian Beg Anak Tangga Kg 5.86 x 48.00 x 0.62 = 173.41 364.99
Bordes 9.86 x 11.67 x 0.62 = 70.92
Anak Tangga 326.20 x 0.60 x 0.62 = 120.66 +
364.99 x 1.00
b. Stek Besi Ø 8 mm Pengikat Bata P=40 cm Kg 0.40 x 6.00 x 91.00 = 218.40 134.64
218.40 x 0.62 = 134.64
b. Pek. Mencat Dinding Baru dgn Cat Tembok Ex. Propan M2 5,156.47
DESTA MASRIKO
Wakil Direktur
PEKERJAAN : BELANJA JASA KONSULTANSI PERENCANAAN ARSITEKTUR -JASA DESAIN ARSITEKTURAL (JASA KONSULTANSI
PERENCANAAN PEMBANGUNAN PASAR BUNDA SRI MERSING)
LOKASI : KOTA DUMAI
T. ANGGARAN : 2023
4. Pengadaan BoredPile Ø 60C m (Diameter Luar) M1 16.00 x 6.00 x 1.00 = 96.00 96.00
6. Pas. Lantai kerja K-175 M3 3.14 x 0.09 x 16.00 x 0.30 = 1.36 1.36
7. Beton kedap air K.250 (Ready Mix) M3 3.14 x 0.09 x 16.00 x 1.00 = 4.52 4.52
8. Cyclopen beton K-250 + 40% batu kali M3 3.14 x 0.09 x 16.00 x 6.00 = 27.13 27.13
- Pembesian Tulangan Utama D16mm Ulir Kg Keliling = 2.00 x 3.14 x 0.30 = 1.88 5,454.40
b. Stek Besi Ø 8 mm Pengikat Bata P=40 cm Kg 0.40 x 6.00 x 8.00 = 19.20 7.58
19.20 x 0.39 = 7.58
j. Pas. Follding Gate t=0,8mm Fins. Cat M2 2.35 x 2.15 x 2.00 = 10.11 10.11
72.80
c. Pek. Coran Lantai ( K-100 ) =t=7Cm M3 28.00 x 20.00 x 0.07 x 1.00 = 39.20 39.20
39.20
f. Pek. Pasang Keramik Dinding KM/WC 25 x 40 Cm M2 6.00 x 1.60 x 1.00 = 9.60 9.60
9.60
VI. PEKERJAAN PENGECATAN
a. Pek. Mencat Dinding Baru dgn Cat Tembok Ex. Catylac M2 Luasan Acian = 215.28 740.32
Luasan Afwerking Beton = 525.04 +
= 740.32
DESTA MASRIKO
Wakil Direktur
PENATAAN HALAMAN
I. PEKERJAAN PAVING BLOCK HALAMAN
a. Pek. Urugan Tanah dipadatkan T = 60 CM M3 Luas Area Gedung A Gedung B 1,220.00
5,800.00 - 2,800.00 - 560.00 = 2,440.00
e. Pas. Pipa PVC tipe AW diameter 2" dari Bak Resapa M1 160.00
DESTA MASRIKO
Wakil Direktur
- Pek. Pembesian Tulangan Utama 12 Ø 12mm Kg 2.14 x 12.00 x 0.89 x 80.00 = 1,823.81 1,823.81
- Pek. Pembesian Tulangan Utama 6 Ø 12mm Kg 6.00 x 380.40 x 0.89 = 2,026.22 2,026.22
- Pek. Pembesian Tulangan Utama 6 Ø 12mm Kg 6.00 x 2.00 x 80.00 x 0.89 = 852.25 852.25
- Pek. Pembesian Tulangan Utama 4 Ø 12mm Kg 6.00 x 380.40 x 0.89 = 2,026.22 2,026.22
d. Acian M2 1,200.00
f. Mencat Dinding Dgn Cat Tembok Ex. Propan M2 1,200.00 + 520.20 = 1,720.20 1,720.20
DESTA MASRIKO
Wakil Direktur
II PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m 1.7.1.a. M3 Rp 128,810.00
2 Penggalian 1 m3 tanah biasa sedalam 2 m 1.7.7.1.1.e (a) M3 Rp 158,103.00
3 Penggalian 1 m3 tanah biasa sedalam 3 m 1.7.7.1.1.g (a) M3 Rp 187,866.80
4 Penggalian 1 m3 tanah keras sedalam 1 m 1.7.9.1.a M3 Rp 234,300.00
5 Menurunkan Cincin Sumuran Ttk Rp 221,976.56
6 Pengurugan kembali 1 m3 galian tanah 1.7.2.a M3 Rp 93,720.00
7 Pengurugan 1 m3 dengan pasir urug 1.7.2.d M3 Rp 294,404.00
8 Pengurugan 1 m3 dengan tanah urug M3 Rp 384,164.00
9 Pengurugan 1 m3 sirtu padat 1.7.2.e M3 Rp 658,416.00
IV PEKERJAAN BETON
1 Membuat beton mutu f3c = 7,4 Mpa (K 100), slump (12 ± 2) Cm, w/c 0,87 A.4.1.1.1 M3 Rp 8,561,630.31
2 Membuat Lantai kerja beton mutu f3c = 7,4 Mpa (K 100), slump (3 - 6) Cm, w/c 0,8 2.2.2.1.a.(a) M3 Rp 8,437,482.81
3 Membuat beton mutu f3c = 14,5 Mpa (K 175), slump (12 ± 2) Cm, w/c 0,66 A.4.1.1.5 M3 Rp 8,685,178.73
4 Membuat beton mutu f3c = 21,7 Mpa (K 250) Site Mix, slump (12 ± 2) Cm, w/c 0,5 4.1.1.8 M3 Rp 8,778,288.09
5 Membuat beton mutu f3c = 21,7 Mpa (K 250) Ready Mix, slump (12 ± 2) Cm, w/c 0,56 M3 Rp 3,234,660.00
6 Pemasangan 1 m3 pondasi siklop, 60% beton Camp, 1PC : 2 PB : 3 Kr dan 40% batu A.3.2.1.10 M3 Rp 1,873,309.68
7 Pembesian 1 kg dengan besi polos A.4.1.1.17 Kg Rp 14,916.44
8 Pembesian kolom, balok, ring balok dan sloof untuk besi beton Ø ≤ 12 mm 2.2.6.1.d.(a) Kg Rp 19,213.92
9 Pembesian kolom, balok, ring balok dan sloof untuk besi beton Ø ≥ 12 mm 2.2.6.1.e.(a) Kg Rp 23,316.92
10 Pemasangan 1 m2 bekisting untuk pondasi tapak 4.1.1.18 M2 Rp 208,013.30
11 Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung M2 Rp 214,158.18
12 Pemasangan 1 m2 bekisting untuk kolom Praktis M2 Rp 263,469.53
13 Pemasangan 1 m2 bekisting untuk kolom Struktur A.4.1.1.20 M2 Rp 333,827.73
14 Pemasangan 1 m2 bekisting untuk balok Praktis M2 Rp 245,034.90
15 Pemasangan 1 m2 bekisting untuk balok Struktur A.4.1.1.21 M2 Rp 339,972.49
16 Pemasangan 1 m2 bekisting untuk Lantai A.4.1.1.22 M2 Rp 357,587.73
17 Pemasangan 1 m2 bekisting untuk Tangga A.4.1.1.25 M2 Rp 447,535.55
VI PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 Plesteran 1PC : 2 Pasir Pasang tebal 15 mm A.4.4.2.2 M2 Rp 114,962.23
2 Pemasangan 1 m2 Plesteran 1PC : 4 Pasir Pasang tebal 15 mm 4.4.2.4 M2 Rp 107,805.72
3 Pemasangan 1 m2 Acian 4.4.2.27 M2 Rp 65,659.00
4 Pemasangan 1 m2 Afwerking Beton A.4.4.2.28 M2 Rp 124,798.87
5 Pemasangan 1 m2 Screeding Waterprofing t=3Cm A.4.4.2.9 M2 Rp 70,086.98
X PEKERJAAN KAYU
1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II A.4.6.1.2 M3 Rp 10,337,657.00
2 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II A.4.6.1.5 M2 Rp 1,074,440.40
3 Pembuatan dan Pemasangan 1 M2 Pasang Jendela Rangka Kaca, t = 5 mm M2 Rp 926,539.24
4 Pemasangan 1 m2 jalusi kusen, kayu kelas II A.4.6.1.10 M2 Rp 915,113.10
5 Pemasangan 1 m2 rangka langit-langit (60 x 120) Cm, kayu kelas II M2 Rp 131,093.87
6 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kls II A.4.6.1.13 M3 Rp 8,435,603.00
7 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II A.4.6.1.15 M3 Rp 6,932,717.00
DESTA MASRIKO
Wakil Direktur
Page 27
ANALISA HARGA SATUAN PEKERJAAN
PERMEN PUPR NO. 1 TAHUN 2022
A TENAGA
Pekerja L.01 OH 0.1000 149,000.00 14,900.00
Tukang Kayu L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 37,610.00
B BAHAN
Kayu balok 5/7 m3 0.0120 2,234,500.00 26,814.00
Paku biasa 2" - 5" Kg 0.0200 27,700.00 554.00
JUMLAH HARGA BAHAN 27,368.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.1000 149,000.00 14,900.00
Mandor L.04 OH 0.0500 214,000.00 10,700.00
JUMLAH TENAGA KERJA 25,600.00
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 25,600.00
E Overhead & profit 10% x Jumlah 2,560.00
F Harga Satuan Pekerjaan (D+E) 28,160.00
Page 28
HARGA SATUAN PEKERJAAN TANAH
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : 1.7.1.a. Penggalian 1 m3 tanah biasa sedalam 1 m
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 128,810.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7500 149,000.00 111,750.00
Mandor L.04 OH 0.0250 214,000.00 5,350.00
JUMLAH TENAGA KERJA 117,100.00
B BAHAN
A TENAGA
Pekerja L.01 OH 0.9000 149,000.00 134,100.00
Mandor L.04 OH 0.0450 214,000.00 9,630.00
JUMLAH TENAGA KERJA 143,730.00
B BAHAN
A TENAGA
Pekerja L.01 OH 1.0500 149,000.00 156,450.00
Mandor L.04 OH 0.0670 214,000.00 14,338.00
JUMLAH TENAGA KERJA 170,788.00
B BAHAN
Page 29
JENIS PEKERJAAN : 1.7.9.1.a Penggalian 1 m3 tanah keras sedalam 1 m
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 234,300.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2500 149,000.00 186,250.00
Mandor L.04 OH 0.1250 214,000.00 26,750.00
JUMLAH TENAGA KERJA 213,000.00
B BAHAN
A TENAGA
Pekerja L.01 OH 0.7500 149,000.00 111,750.00
Tukang L.02 OH 0.5000 195,000.00 97,500.00
Kepala tukang L.03 OH 0.1000 214,000.00 21,400.00
Mandor L.04 OH 0.0250 214,000.00 5,350.00
JUMLAH TENAGA KERJA 236,000.00
B
Untuk 1 M Pertama 1.0000 179,375.00 179,375.00
Untuk 1 M Kedua 1.2500 179,375.00 224,218.75
JUMLAH HARGA 403,593.75
Rata-rata Untuk 1M 2.000 201,796.88
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.5000 149,000.00 74,500.00
Mandor L.04 OH 0.0500 214,000.00 10,700.00
JUMLAH TENAGA KERJA 85,200.00
B BAHAN
Page 30
JENIS PEKERJAAN : 1.7.2.d Pengurugan 1 m3 dengan pasir urug
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 294,404.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Mandor L.04 OH 0.0100 214,000.00 2,140.00
JUMLAH TENAGA KERJA 46,840.00
B BAHAN
Pasir urug m3 1.2000 184,000.00 220,800.00
JUMLAH HARGA BAHAN 220,800.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Mandor L.04 OH 0.0100 214,000.00 2,140.00
JUMLAH TENAGA KERJA 46,840.00
B BAHAN
Tanah urug m3 1.2000 252,000.00 302,400.00
JUMLAH HARGA BAHAN 302,400.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.2500 149,000.00 37,250.00
Mandor L.04 OH 0.0250 214,000.00 5,350.00
JUMLAH TENAGA KERJA 42,600.00
B BAHAN
Sirtu m3 1.2000 463,300.00 555,960.00
JUMLAH HARGA BAHAN 555,960.00
C PERALATAN
Page 31
HARGA SATUAN PEKERJAAN PONDASI
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : 2.1.3.2.a.a Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 3 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,784,332.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 149,000.00 223,500.00
Tukang L.02 OH 0.7500 195,000.00 146,250.00
Kepala tukang L.03 OH 0.0750 214,000.00 16,050.00
Mandor L.04 OH 0.0750 214,000.00 16,050.00
JUMLAH TENAGA KERJA 401,850.00
B BAHAN
Batu belah m3 1.2000 601,000.00 721,200.00
Semen Portland Kg 202.0000 1,880.00 379,760.00
Pasir Pasang m3 0.4850 246,000.00 119,310.00
JUMLAH HARGA BAHAN 1,220,270.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 1,622,120.00
E Overhead & profit 10% x Jumlah 162,212.00
F Harga Satuan Pekerjaan (D+E) 1,784,332.00
JENIS PEKERJAAN : A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 4 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,713,151.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.5000 149,000.00 223,500.00
Tukang L.02 OH 0.7500 195,000.00 146,250.00
Kepala tukang L.03 OH 0.0750 214,000.00 16,050.00
Mandor L.04 OH 0.0750 214,000.00 16,050.00
JUMLAH TENAGA KERJA 401,850.00
B BAHAN
Batu belah m3 1.2000 601,000.00 721,200.00
Semen Portland kg 163.0000 1,880.00 306,440.00
Pasir Pasang m3 0.5200 246,000.00 127,920.00
JUMLAH HARGA BAHAN 1,155,560.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 1,557,410.00
E Overhead & profit 10% x Jumlah 155,741.00
F Harga Satuan Pekerjaan (D+E) 1,713,151.00
Page 32
JENIS PEKERJAAN : A.3.1.1.9 Pemasangan 1 m3 pondasi batu kosong (Aanstampang)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,110,615.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7800 149,000.00 116,220.00
Tukang Batu L.02 OH 0.3900 195,000.00 76,050.00
Kepala tukang L.03 OH 0.0390 214,000.00 8,346.00
Mandor L.04 OH 0.0390 214,000.00 8,346.00
JUMLAH TENAGA KERJA 208,962.00
B BAHAN
Batu belah m3 1.2000 601,000.00 721,200.00
Pasir urug m3 0.4320 184,000.00 79,488.00
JUMLAH HARGA BAHAN 800,688.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 1.6500 149,000.00 245,850.00
Tukang Batu L.02 OH 0.2750 195,000.00 53,625.00
Kepala tukang L.03 OH 0.0280 214,000.00 5,992.00
Mandor L.04 OH 0.0830 214,000.00 17,762.00
JUMLAH TENAGA KERJA 323,229.00
B BAHAN
Semen Portland kg 247.0000 1,880.00 464,360.00
Pasir beton m3 0.6207 545,000.00 338,289.29
Kerikil Beton m3 0.7400 280,300.00 207,422.00
Air Liter 215.0000 30,000.00 6,450,000.00
JUMLAH HARGA BAHAN 7,460,071.29
C PERALATAN
Page 33
JENIS PEKERJAAN : 2.2.2.1.a.(a) Membuat Lantai kerja beton mutu f3c = 7,4 Mpa (K 100), slump (3 - 6) Cm, w/c 0,87
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 8,437,482.81
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 149,000.00 178,800.00
Tukang Batu L.02 OH 0.2000 195,000.00 39,000.00
Kepala tukang L.03 OH 0.0200 214,000.00 4,280.00
Mandor L.04 OH 0.1200 214,000.00 25,680.00
JUMLAH TENAGA KERJA 247,760.00
B BAHAN
Semen Portland Kg 227.0000 1,880.00 426,760.00
Pasir beton m3 0.6207 545,000.00 338,289.29
Kerikil Beton m3 0.7407 280,300.00 207,629.63
Air Liter 215.0000 30,000.00 6,450,000.00
JUMLAH HARGA BAHAN 7,422,678.92
C PERALATAN
JENIS PEKERJAAN : A.4.1.1.5 Membuat beton mutu f3c = 14,5 Mpa (K 175), slump (12 ± 2) Cm, w/c 0,66
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 8,685,178.73
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 149,000.00 245,850.00
Tukang Batu L.02 OH 0.2750 195,000.00 53,625.00
Kepala tukang L.03 OH 0.0280 214,000.00 5,992.00
Mandor L.04 OH 0.0830 214,000.00 17,762.00
JUMLAH TENAGA KERJA 323,229.00
B BAHAN
Semen Portland Kg 326.0000 1,880.00 612,880.00
Pasir beton m3 0.5429 545,000.00 295,857.14
Kerikil Beton m3 0.7622 280,300.00 213,650.89
Air Liter 215.0000 30,000.00 6,450,000.00
JUMLAH HARGA BAHAN 7,572,388.03
C PERALATAN
Page 34
JENIS PEKERJAAN : 4.1.1.8 Membuat beton mutu f3c = 21,7 Mpa (K 250) Site Mix, slump (12 ± 2) Cm, w/c 0,56
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 8,778,288.09
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 149,000.00 245,850.00
Tukang Batu L.02 OH 0.2750 195,000.00 53,625.00
Kepala tukang L.03 OH 0.0280 214,000.00 5,992.00
Mandor L.04 OH 0.0830 214,000.00 17,762.00
JUMLAH TENAGA KERJA 323,229.00
B BAHAN
Semen Portland Kg 384.0000 1,880.00 721,920.00
Pasir beton m3 0.4943 545,000.00 269,385.71
Kerikil Beton m3 0.7696 280,300.00 215,727.19
Air Liter 215.0000 30,000.00 6,450,000.00
JUMLAH HARGA BAHAN 7,657,032.90
C PERALATAN
JENIS PEKERJAAN : Membuat beton mutu f3c = 21,7 Mpa (K 250) Ready Mix, slump (12 ± 2) Cm, w/c 0,56
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 3,234,660.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4000 149,000.00 59,600.00
Tukang Batu L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0400 214,000.00 8,560.00
JUMLAH TENAGA KERJA 89,800.00
B BAHAN
Ready Mix K-250 M3 1.0000 2,775,800.00 2,775,800.00
Page 35
JENIS PEKERJAAN : A.3.2.1.10 Pemasangan 1 m3 pondasi siklop, 60% beton Camp, 1PC : 2 PB : 3 Kr dan 40%
batu belah
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,873,309.68
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.4000 149,000.00 506,600.00
Tukang Batu L.02 OH 0.8500 195,000.00 165,750.00
Kepala tukang L.03 OH 0.0850 214,000.00 18,190.00
Mandor L.04 OH 0.1700 214,000.00 36,380.00
JUMLAH TENAGA KERJA 726,920.00
B BAHAN
Batu belah m3 0.4800 601,000.00 288,480.00
Semen Portland Kg 194.0000 1,880.00 364,720.00
Pasir beton m3 0.3120 545,000.00 170,040.00
Spilt m3 0.4680 326,600.00 152,848.80
JUMLAH HARGA BAHAN 976,088.80
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0070 149,000.00 1,043.00
Tukang L.02 OH 0.0070 195,000.00 1,365.00
Kepala tukang L.03 OH 0.0007 214,000.00 149.80
Mandor L.04 OH 0.0004 214,000.00 85.60
JUMLAH TENAGA KERJA 2,643.40
B BAHAN
Besi beton Kg 1.0500 10,000.00 10,500.00
Kawat beton Kg 0.0150 27,800.00 417.00
JUMLAH HARGA BAHAN 10,917.00
C PERALATAN
Page 36
JENIS PEKERJAAN : 2.2.6.1.d.(a) Pembesian kolom, balok, ring balok dan sloof untuk besi beton Ø ≤ 12 mm
SATUAN : Kg
HARGA SATUAN : Rp 19,213.92
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0160 149,000.00 2,384.00
Tukang L.02 OH 0.0160 195,000.00 3,120.00
Kepala tukang L.03 OH 0.0016 214,000.00 342.40
Mandor L.04 OH 0.0016 214,000.00 342.40
JUMLAH TENAGA KERJA 6,188.80
B BAHAN
Besi beton Kg 1.0500 10,000.00 10,500.00
Kawat beton Kg 0.0280 27,800.00 778.40
JUMLAH HARGA BAHAN 11,278.40
C PERALATAN
JENIS PEKERJAAN : 2.2.6.1.e.(a) Pembesian kolom, balok, ring balok dan sloof untuk besi beton Ø ≥ 12 mm
SATUAN : Kg
HARGA SATUAN : Rp 23,316.92
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0160 149,000.00 2,384.00
Tukang L.02 OH 0.0160 195,000.00 3,120.00
Kepala tukang L.03 OH 0.0016 214,000.00 342.40
Mandor L.04 OH 0.0016 214,000.00 342.40
JUMLAH TENAGA KERJA 6,188.80
B BAHAN
Besi beton Kg 1.0500 12,600.00 13,230.00
Kawat beton Kg 0.0280 27,800.00 778.40
JUMLAH HARGA BAHAN 14,008.40
C PERALATAN
Cutter besi beton To.25.c Hari 0.0400 25,000.00 1,000.00
Bender besi beton To.25.a Hari 0.0400 25,000.00 1,000.00
JUMLAH HARGA ALAT 1,000.00
D JUMLAH (A+B+C) 21,197.20
E Overhead & profit 10% x Jumlah 2,119.72
F Harga Satuan Pekerjaan (D+E) 23,316.92
Page 37
JENIS PEKERJAAN : 4.1.1.18 Pemasangan 1 m2 bekisting untuk pondasi tapak
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 208,013.30
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5200 149,000.00 77,480.00
Tukang L.02 OH 0.2600 195,000.00 50,700.00
Kepala tukang L.03 OH 0.0260 214,000.00 5,564.00
Mandor L.04 OH 0.0260 214,000.00 5,564.00
JUMLAH TENAGA KERJA 139,308.00
B BAHAN
Kayu kelas III Perancah m3 0.0400 2,234,500.00 89,380.00
Paku 5 - 10 Cm Kg 0.3000 27,700.00 8,310.00
Minyak bekisting Liter 0.1000 19,000.00 1,900.00
JUMLAH HARGA BAHAN 99,590.00
UNTUK 2 KALI PEMAKAIAN BAHAN 49,795.00
C PERALATAN
JENIS PEKERJAAN : A.4.1.1.19 Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 214,158.18
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5200 149,000.00 77,480.00
Tukang L.02 OH 0.2600 195,000.00 50,700.00
Kepala tukang L.03 OH 0.0260 214,000.00 5,564.00
Mandor L.04 OH 0.0260 214,000.00 5,564.00
JUMLAH TENAGA KERJA 139,308.00
B BAHAN
Kayu kelas III m3 0.0450 2,234,500.00 100,552.50
Paku 5 - 10 Cm Kg 0.3000 27,700.00 8,310.00
Minyak bekisting Liter 0.1000 19,000.00 1,900.00
JUMLAH HARGA BAHAN 110,762.50
UNTUK 2 KALI PEMAKAIAN BAHAN 55,381.25
C PERALATAN
Page 38
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk kolom Praktis
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 263,469.53
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 149,000.00 98,340.00
Tukang L.02 OH 0.3300 195,000.00 64,350.00
Kepala tukang L.03 OH 0.0330 214,000.00 7,062.00
Mandor L.04 OH 0.0330 214,000.00 7,062.00
JUMLAH TENAGA KERJA 176,814.00
B BAHAN
Balok Kayu kelas III m3 0.0150 2,234,500.00 33,517.50
Paku 5 - 10 Cm Kg 0.4000 27,700.00 11,080.00
Minyak bekisting Liter 0.2000 19,000.00 3,800.00
multiplek tebal 9 mm Lbr 0.3500 204,600.00 71,610.00
Dolken kayu φ 8-10 Cm Batang 0.5000 10,800.00 5,400.00
JUMLAH HARGA BAHAN 125,407.50
UNTUK 2 KALI PEMAKAIAN BAHAN 62,703.75
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.6600 149,000.00 98,340.00
Tukang L.02 OH 0.3300 195,000.00 64,350.00
Kepala tukang L.03 OH 0.0330 214,000.00 7,062.00
Mandor L.04 OH 0.0330 214,000.00 7,062.00
JUMLAH TENAGA KERJA 176,814.00
B BAHAN
Kayu kelas III m3 0.0400 2,234,500.00 89,380.00
Paku 5 - 10 Cm Kg 0.4000 27,700.00 11,080.00
Minyak bekisting Liter 0.2000 19,000.00 3,800.00
Balok Kayu kelas II m3 0.0150 3,724,100.00 55,861.50
multiplek tebal 9 mm Lbr 0.3500 204,600.00 71,610.00
Dolken kayu φ 8-10 Cm Batang 2.0000 10,800.00 21,600.00
JUMLAH HARGA BAHAN 253,331.50
UNTUK 2 KALI PEMAKAIAN BAHAN 126,665.75
C PERALATAN
Page 39
JENIS PEKERJAAN : Pemasangan 1 m2 bekisting untuk balok Praktis
SATUAN : M2
HARGA SATUAN : Rp 245,034.90
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 149,000.00 98,340.00
Tukang L.02 OH 0.3300 195,000.00 64,350.00
Kepala tukang L.03 OH 0.0330 214,000.00 7,062.00
Mandor L.04 OH 0.0330 214,000.00 7,062.00
JUMLAH TENAGA KERJA 176,814.00
B BAHAN
Paku 5 - 10 Cm Kg 0.4000 27,700.00 11,080.00
Minyak bekisting Liter 0.2000 19,000.00 3,800.00
multiplek tebal 9 mm Lbr 0.3500 204,600.00 71,610.00
Dolken kayu φ 8-10 Cm Batang 0.5000 10,800.00 5,400.00
JUMLAH HARGA BAHAN 91,890.00
UNTUK 2 KALI PEMAKAIAN BAHAN 45,945.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.6600 149,000.00 98,340.00
Tukang L.02 OH 0.3300 195,000.00 64,350.00
Kepala tukang L.03 OH 0.0330 214,000.00 7,062.00
Mandor L.04 OH 0.0330 214,000.00 7,062.00
JUMLAH TENAGA KERJA 176,814.00
B BAHAN
Kayu kelas III m3 0.0400 2,234,500.00 89,380.00
Paku 5 - 10 Cm Kg 0.4000 27,700.00 11,080.00
Minyak bekisting Liter 0.2000 19,000.00 3,800.00
multiplek tebal 9 mm Lbr 0.3500 204,600.00 71,610.00
Balok Kayu kelas II m3 0.0180 3,724,100.00 67,033.80
Dolken kayu φ 8-10 Cm Batang 2.0000 10,800.00 21,600.00
JUMLAH HARGA BAHAN 264,503.80
UNTUK 2 KALI PEMAKAIAN BAHAN 132,251.90
C PERALATAN
Page 40
JENIS PEKERJAAN : A.4.1.1.22 Pemasangan 1 m2 bekisting untuk Lantai
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 357,587.73
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.6600 149,000.00 98,340.00
Tukang L.02 OH 0.3300 195,000.00 64,350.00
Kepala tukang L.03 OH 0.0330 214,000.00 7,062.00
Mandor L.04 OH 0.0330 214,000.00 7,062.00
JUMLAH TENAGA KERJA 176,814.00
B BAHAN
Kayu kelas III m3 0.0400 2,234,500.00 89,380.00
Paku 5 - 10 Cm Kg 0.4000 27,700.00 11,080.00
Minyak bekisting Liter 0.2000 19,000.00 3,800.00
multiplek tebal 9 mm Lbr 0.3500 204,600.00 71,610.00
Balok Kayu kelas II m3 0.0150 3,724,100.00 55,861.50
Dolken kayu φ 8-10 Cm Batang 6.0000 10,800.00 64,800.00
JUMLAH HARGA BAHAN 296,531.50
UNTUK 2 KALI PEMAKAIAN BAHAN 148,265.75
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.6600 149,000.00 98,340.00
Tukang L.02 OH 0.3300 195,000.00 64,350.00
Kepala tukang L.03 OH 0.0330 214,000.00 7,062.00
Mandor L.04 OH 0.0330 214,000.00 7,062.00
JUMLAH TENAGA KERJA 176,814.00
B BAHAN
Kayu kelas III m3 0.0300 2,234,500.00 67,035.00
Paku 5 - 10 Cm Kg 0.4000 27,700.00 11,080.00
Minyak bekisting Liter 0.1500 19,000.00 2,850.00
multiplek tebal 9 mm Lbr 0.3500 204,600.00 71,610.00
Balok Kayu kelas II m3 0.0150 3,724,100.00 55,861.50
Dolken kayu φ 8-10 Cm Batang 2.0000 10,800.00 21,600.00
JUMLAH HARGA BAHAN 230,036.50
UNTUK 2 KALI PEMAKAIAN BAHAN 115,018.25
C PERALATAN
Page 41
HARGA SATUAN PEKERJAAN PASANGAN DINDING
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : A.4.4.1.7 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1 : 2
SATUAN : M2
HARGA SATUAN : Rp 179,876.40
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0150 214,000.00 3,210.00
JUMLAH TENAGA KERJA 69,550.00
B BAHAN
Bata Merah buah 70.0000 700.00 49,000.00
Semen Portland Kg 18.9500 1,880.00 35,626.00
Pasir Pasang m3 0.0380 246,000.00 9,348.00
JUMLAH HARGA BAHAN 93,974.00
C PERALATAN
JENIS PEKERJAAN : A.4.4.1.9 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1 : 4
SATUAN : M2
HARGA SATUAN : Rp 165,822.80
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0150 214,000.00 3,210.00
JUMLAH TENAGA KERJA 69,550.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 11.5000 1,880.00 21,620.00
Pasir Pasang m3 0.0430 246,000.00 10,578.00
JUMLAH HARGA BAHAN 81,198.00
C PERALATAN
Page 42
JENIS PEKERJAAN : A.4.4.1.23 Pemasangan 1 m2 dinding terawang (roster) 12x20x20Cm Camp. 1PC: 4 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 801,724.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0150 214,000.00 3,210.00
JUMLAH TENAGA KERJA 69,550.00
B BAHAN
Batu Kerawang Bh 25.0000 25,200.00 630,000.00
Semen Portland Kg 11.0000 1,880.00 20,680.00
Pasir Pasang m3 0.0350 246,000.00 8,610.00
JUMLAH HARGA BAHAN 659,290.00
C PERALATAN
Page 43
JENIS PEKERJAAN : Pemasangan 1 m2 Batu Alam Andesit
SATUAN : M2
HARGA SATUAN : Rp 442,607.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4500 149,000.00 67,050.00
Tukang L.02 OH 0.5000 195,000.00 97,500.00
Kepala tukang L.03 OH 0.0400 214,000.00 8,560.00
Mandor L.04 OH 0.0400 214,000.00 8,560.00
JUMLAH TENAGA KERJA 181,670.00
B BAHAN
Batu Alam Andesit m3 1.0000 190,000.00 190,000.00
Semen Portland Kg 11.7500 1,880.00 22,090.00
Pasir Pasang m3 0.0350 246,000.00 8,610.00
JUMLAH HARGA BAHAN 220,700.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.1500 149,000.00 22,350.00
Tukang L.02 OH 0.0500 195,000.00 9,750.00
Kepala tukang L.03 OH 0.0250 214,000.00 5,350.00
Mandor L.04 OH 0.0250 214,000.00 5,350.00
JUMLAH TENAGA KERJA 42,800.00
B BAHAN
Waterproofing coating waterbase Kg 0.4480 90,000.00 40,320.00
JUMLAH HARGA BAHAN 40,320.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 83,120.00
E Overhead & profit 10% x Jumlah 8,312.00
F Harga Satuan Pekerjaan (D+E) 91,432.00
JENIS PEKERJAAN : A.4.4.2.2 Pemasangan 1 m2 Plesteran 1PC : 2 Pasir Pasang tebal 15 mm
SATUAN : M2
HARGA SATUAN : Rp 114,962.23
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0150 214,000.00 3,210.00
JUMLAH TENAGA KERJA 80,370.00
B BAHAN
Semen Portland Kg 10.2240 1,880.00 19,221.12
Pasir Pasang m3 0.0200 246,000.00 4,920.00
JUMLAH HARGA BAHAN 24,141.12
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 104,511.12
E Overhead & profit 10% x Jumlah 10,451.11
F Harga Satuan Pekerjaan (D+E) 114,962.23
Page 44
JENIS PEKERJAAN : 4.4.2.4 Pemasangan 1 m2 Plesteran 1PC : 4 Pasir Pasang tebal 15 mm
SATUAN : M2
HARGA SATUAN : Rp 107,805.72
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0150 214,000.00 3,210.00
JUMLAH TENAGA KERJA 80,370.00
B BAHAN
Semen Portland Kg 6.2400 1,880.00 11,731.20
Pasir Pasang m3 0.0240 246,000.00 5,904.00
JUMLAH HARGA BAHAN 17,635.20
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.2000 149,000.00 29,800.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0100 214,000.00 2,140.00
JUMLAH TENAGA KERJA 53,580.00
B BAHAN
Semen Portland Kg 3.2500 1,880.00 6,110.00
JUMLAH HARGA BAHAN 6,110.00
C PERALATAN
Page 45
JENIS PEKERJAAN : A.4.4.2.28 Pemasangan 1 m2 Afwerking Beton
SATUAN : M2
HARGA SATUAN : Rp 124,798.87
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 149,000.00 44,700.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0150 214,000.00 3,210.00
JUMLAH TENAGA KERJA 80,370.00
B BAHAN
Semen Portland Kg 15.5040 1,880.00 29,147.52
Pasir Pasang m3 0.0160 246,000.00 3,936.00
JUMLAH HARGA BAHAN 33,083.52
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.2000 149,000.00 29,800.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0100 214,000.00 2,140.00
JUMLAH TENAGA KERJA 53,580.00
B BAHAN
Semen Portland Kg 0.2880 1,880.00 541.44
Pasir Pasang m3 0.0390 246,000.00 9,594.00
JUMLAH HARGA BAHAN 10,135.44
C PERALATAN
Page 46
HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : A.4.4.3.36 Pemasangan 1 m2 Lantai keramik ukuran 40 Cm x 40 Cm (Unpolsh) Ex. Ikad
SATUAN : M2
HARGA SATUAN : Rp 391,413.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 149,000.00 104,300.00
Tukang L.02 OH 0.3500 195,000.00 68,250.00
Kepala tukang L.03 OH 0.0350 214,000.00 7,490.00
Mandor L.04 OH 0.0350 214,000.00 7,490.00
JUMLAH TENAGA KERJA 187,530.00
B BAHAN
keramik ukuran 40 Cm x 40 Cm Unpolish Motif Bh 1.0500 126,600.00 132,930.00
Semen Portland Kg 10.0000 1,880.00 18,800.00
Pasir Pasang m3 0.0450 246,000.00 11,070.00
Semen warna (tepung affa) Kg 0.5000 11,000.00 5,500.00
JUMLAH HARGA BAHAN 168,300.00
C PERALATAN
JENIS PEKERJAAN : A.4.4.3.36. (a) Pemasangan 1 m2 Lantai keramik ukuran 40 Cm x 40 Cm (Polish) Ikad
SATUAN : M2
HARGA SATUAN : Rp 370,045.50
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 149,000.00 104,300.00
Tukang L.02 OH 0.3500 195,000.00 68,250.00
Kepala tukang L.03 OH 0.0350 214,000.00 7,490.00
Mandor L.04 OH 0.0350 214,000.00 7,490.00
JUMLAH TENAGA KERJA 187,530.00
B BAHAN
keramik ukuran 40 Cm x 40 Cm Duss 1.0500 108,100.00 113,505.00
Semen Portland Kg 10.0000 1,880.00 18,800.00
Pasir Pasang m3 0.0450 246,000.00 11,070.00
Semen warna (tepung affa) Kg 0.5000 11,000.00 5,500.00
JUMLAH HARGA BAHAN 148,875.00
C PERALATAN
Page 47
JENIS PEKERJAAN : Pemasangan 1 m2 Lantai Granit ukuran 60 Cm x 60 Cm (Polish) Granito
SATUAN : M2
HARGA SATUAN : Rp 577,390.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7000 149,000.00 104,300.00
Tukang L.02 OH 0.3500 195,000.00 68,250.00
Kepala tukang L.03 OH 0.0350 214,000.00 7,490.00
Mandor L.04 OH 0.0350 214,000.00 7,490.00
JUMLAH TENAGA KERJA 187,530.00
B BAHAN
Granit ukuran 60 Cm x 60 Cm Polish Motif Bh 3.0000 97,000.00 291,000.00
Semen Portland Kg 10.0000 1,880.00 18,800.00
Pasir Pasang m3 0.0450 246,000.00 11,070.00
Semen warna (tepung affa) Kg 1.5000 11,000.00 16,500.00
JUMLAH HARGA BAHAN 337,370.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.7000 149,000.00 104,300.00
Tukang L.02 OH 0.3500 195,000.00 68,250.00
Kepala tukang L.03 OH 0.0350 214,000.00 7,490.00
Mandor L.04 OH 0.0350 214,000.00 7,490.00
JUMLAH TENAGA KERJA 187,530.00
B BAHAN
keramik ukuran 30 Cm x 30 Cm Doss 1.0500 111,000.00 116,550.00
Semen Portland Kg 10.4000 1,880.00 19,552.00
Pasir Pasang m3 0.0450 246,000.00 11,070.00
Semen warna (tepung affa) Kg 0.5000 11,000.00 5,500.00
JUMLAH HARGA BAHAN 152,672.00
C PERALATAN
Page 48
JENIS PEKERJAAN : Pemasangan 1 m2 Dinding keramik ukuran 30 Cm x 60 Cm (Polish) Ikad
SATUAN : M2
HARGA SATUAN : Rp 454,285.70
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.9000 149,000.00 134,100.00
Tukang L.02 OH 0.4500 195,000.00 87,750.00
Kepala tukang L.03 OH 0.0450 214,000.00 9,630.00
Mandor L.04 OH 0.0450 214,000.00 9,630.00
JUMLAH TENAGA KERJA 241,110.00
B BAHAN
Dinding Keramik 25x40 Cm Doss 1.0500 122,500.00 128,625.00
Semen Portland Kg 9.3000 1,880.00 17,484.00
Pasir Pasang m3 0.0180 246,000.00 4,428.00
Semen warna (tepung affa) Kg 1.9400 11,000.00 21,340.00
JUMLAH HARGA BAHAN 171,877.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.2500 149,000.00 37,250.00
Tukang L.02 OH 0.5000 195,000.00 97,500.00
Kepala tukang L.03 OH 0.0500 214,000.00 10,700.00
Mandor L.04 OH 0.0013 214,000.00 278.20
JUMLAH TENAGA KERJA 145,728.20
B BAHAN
Paving Block Hexagonal Warna = 36 Buah Bh 1.0100 109,200.00 110,292.00
Pasir Pasang M3 0.0500 545,000.00 27,250.00
JUMLAH HARGA BAHAN 137,542.00
C PERALATAN
Peralatan % 0.1000 137,542.00 13,754.20
JUMLAH HARGA ALAT 13,754.20
D JUMLAH (A+B+C) 297,024.40
E Overhead & profit 10% x Jumlah 29,702.44
F Harga Satuan Pekerjaan (D+E) 326,726.84
Page 49
JENIS PEKERJAAN : Pemasangan 1 m2 Cladding ACP Cutting Decoratif
SATUAN : M2
HARGA SATUAN : Rp 1,359,961.02
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 149,000.00 149,000.00
Tukang L.02 OH 0.9000 195,000.00 175,500.00
Kepala tukang L.03 OH 0.1500 214,000.00 32,100.00
Mandor L.04 OH 0.0013 214,000.00 278.20
JUMLAH TENAGA KERJA 356,878.20
B BAHAN
ACP PVDF 0.33 mm Alloy 3003 M2 1.0000 346,500.00 346,500.00
Rangka Hollow Alumnium 40x40 : 1 mm M2 1.0000 280,000.00 280,000.00
Selaent, Isolasi, Dan Karet Pengisi Ex Marks M2 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 676,500.00
C PERALATAN
Peralatan % 0.3000 676,500.00 202,950.00
JUMLAH HARGA ALAT 202,950.00
D JUMLAH (A+B+C) 1,236,328.20
E Overhead & profit 10% x Jumlah 123,632.82
F Harga Satuan Pekerjaan (D+E) 1,359,961.02
A TENAGA
Pekerja L.01 OH 0.5000 149,000.00 74,500.00
Tukang L.02 OH 0.8000 195,000.00 156,000.00
Kepala tukang L.03 OH 0.1000 214,000.00 21,400.00
Mandor L.04 OH 0.0013 214,000.00 278.20
JUMLAH TENAGA KERJA 252,178.20
B BAHAN
ACP PVDF 0.33 mm Alloy 3003 M2 1.0000 346,500.00 346,500.00
Rangka Hollow Alumnium 40x40 : 1 mm M2 1.0000 280,000.00 280,000.00
Selaent, Isolasi, Dan Karet Pengisi Ex Marks M2 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 676,500.00
C PERALATAN
Peralatan % 0.3000 676,500.00 202,950.00
JUMLAH HARGA ALAT 202,950.00
D JUMLAH (A+B+C) 1,131,628.20
E Overhead & profit 10% x Jumlah 113,162.82
F Harga Satuan Pekerjaan (D+E) 1,244,791.02
Page 50
HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) Cm, tebal 4 mm
SATUAN : M2
HARGA SATUAN : Rp 84,142.30
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 149,000.00 14,900.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 37,610.00
B BAHAN
Tripleks Lembar 0.3750 100,800.00 37,800.00
Paku triplek Kg 0.0300 36,100.00 1,083.00
JUMLAH HARGA BAHAN 38,883.00
C PERALATAN
Page 51
Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9
JENIS PEKERJAAN : A.4.5.1.7
mm + Rangka
SATUAN : M2
HARGA SATUAN : Rp 265,349.04
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1500 149,000.00 22,350.00
Tukang L.02 OH 0.5000 195,000.00 97,500.00
Kepala tukang L.03 OH 0.0500 214,000.00 10,700.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 131,620.00
B BAHAN
Gypsum board Lembar 0.3640 153,600.00 55,910.40
Hollow Zinggalum 40 x 40 tbl 0,40 mm M1 5.7500 7,500.00 43,125.00
Paku Gypsum Kg 0.1100 96,100.00 10,571.00
JUMLAH HARGA BAHAN 109,606.40
C PERALATAN
JENIS PEKERJAAN : A.4.5.1.1 Pemasangan 1 m2 langit-langit Kalsiboard ukuran (120 x 240 x 9) mm, tebal 6 mm
SATUAN : M2
HARGA SATUAN : Rp 126,428.50
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0300 149,000.00 4,470.00
Tukang L.02 OH 0.0700 195,000.00 13,650.00
Kepala tukang L.03 OH 0.0070 214,000.00 1,498.00
Mandor L.04 OH 0.0040 214,000.00 856.00
JUMLAH TENAGA KERJA 20,474.00
B BAHAN
Kalsiboard t=4mm Lembar 1.1000 85,000.00 93,500.00
Paku Gypsum Kg 0.0100 96,100.00 961.00
JUMLAH HARGA BAHAN 94,461.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 114,935.00
E Overhead & profit 10% x Jumlah 11,493.50
F Harga Satuan Pekerjaan (D+E) 126,428.50
Page 52
JENIS PEKERJAAN : Pemasangan 1 m1 List Plafond Gypsum
SATUAN : M2
HARGA SATUAN : Rp 54,225.60
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0600 149,000.00 8,940.00
Tukang L.02 OH 0.0600 195,000.00 11,700.00
Kepala tukang L.03 OH 0.0060 214,000.00 1,284.00
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 22,566.00
B BAHAN
List Gypsum M 1.0500 24,600.00 25,830.00
Tepung Gypsum Kg 0.1500 6,000.00 900.00
JUMLAH HARGA BAHAN 26,730.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 49,296.00
E Overhead & profit 10% x Jumlah 4,929.60
F Harga Satuan Pekerjaan (D+E) 54,225.60
A TENAGA
Pekerja L.01 OH 0.0500 149,000.00 7,450.00
Tukang L.02 OH 0.0500 195,000.00 9,750.00
Kepala tukang L.03 OH 0.0050 214,000.00 1,070.00
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 18,912.00
B BAHAN
List Kayu Profil m 1.0500 5,200.00 5,460.00
Paku Kg 0.0100 36,100.00 361.00
JUMLAH HARGA BAHAN 5,821.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 24,733.00
E Overhead & profit 10% % x Jumlah 2,473.30
F Harga Satuan Pekerjaan (D+E) 27,206.30
Page 53
HARGA SATUAN PEKERJAAN PENUTUP ATAP
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : 4.5.2.32 Pemasangan 1 m2 genteng metal warna t=0.30mm
SATUAN : M2
HARGA SATUAN : Rp 138,274.40
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.2000 149,000.00 29,800.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0010 214,000.00 214.00
JUMLAH TENAGA KERJA 51,654.00
B BAHAN
Atap Genteng Warna M2 1.3000 52,700.00 68,510.00
Paku Sekrup Kg 0.2000 27,700.00 5,540.00
JUMLAH HARGA BAHAN 74,050.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 125,704.00
E Overhead & profit 10% x Jumlah 12,570.40
F Harga Satuan Pekerjaan (D+E) 138,274.40
A TENAGA
Pekerja L.01 OH 0.2500 149,000.00 37,250.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0130 214,000.00 2,782.00
JUMLAH TENAGA KERJA 72,492.00
B BAHAN
Nok genteng metal panjang 100cm M1 1.1000 38,300.00 42,130.00
Paku Sekrup Kg 0.0500 27,700.00 1,385.00
JUMLAH HARGA BAHAN 43,515.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 116,007.00
E Overhead & profit 10% x Jumlah 11,600.70
F Harga Satuan Pekerjaan (D+E) 127,607.70
Page 54
JENIS PEKERJAAN : A.4.6.1.21 Pemasangan 1 m1 Listplang Papan 3/30 (Doble)
SATUAN : M1
HARGA SATUAN : Rp 112,464.31
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 149,000.00 14,900.00
Tukang L.02 OH 0.2000 195,000.00 39,000.00
Kepala tukang L.03 OH 0.0200 214,000.00 4,280.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Kayu Papan klas II M3 0.0108 3,724,100.00 40,220.28
Paku 5 dan 10 Cm Kg 0.1000 27,700.00 2,770.00
JUMLAH HARGA BAHAN 42,990.28
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.1000 149,000.00 14,900.00
Tukang L.02 OH 0.2000 195,000.00 39,000.00
Kepala tukang L.03 OH 0.0200 214,000.00 4,280.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
GRC Board M3 1.1000 27,500.00 30,250.00
Paku 5 dan 10 Cm Kg 0.0500 27,700.00 1,385.00
JUMLAH HARGA BAHAN 31,635.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 90,885.00
E Overhead & profit 10% x Jumlah 9,088.50
F Harga Satuan Pekerjaan (D+E) 99,973.50
Page 55
HARGA SATUAN PEKERJAAN KAYU
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : A.4.6.1.2 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II
SATUAN : M3
HARGA SATUAN : Rp 10,337,657.00
HARGA SATUAN JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.0000 149,000.00 894,000.00
Tukang L.02 OH 18.0000 195,000.00 3,510,000.00
Kepala tukang L.03 OH 1.8000 214,000.00 385,200.00
Mandor L.04 OH 0.3000 214,000.00 64,200.00
JUMLAH TENAGA KERJA 4,853,400.00
B BAHAN
Balok kayu m3 1.2000 3,724,100.00 4,468,920.00
Paku 10 Cm Kg 1.2500 30,200.00 37,750.00
Lem kayu Kg 1.0000 37,800.00 37,800.00
JUMLAH HARGA BAHAN 4,544,470.00
C PERALATAN
JENIS PEKERJAAN : A.4.6.1.5 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II
SATUAN : M2
HARGA SATUAN : Rp 1,074,440.40
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 149,000.00 149,000.00
Tukang L.02 OH 3.0000 195,000.00 585,000.00
Kepala tukang L.03 OH 0.3000 214,000.00 64,200.00
Mandor L.04 OH 0.0500 214,000.00 10,700.00
JUMLAH TENAGA KERJA 808,900.00
B BAHAN
Papan kayu m3 0.0400 3,724,100.00 148,964.00
Lem kayu Kg 0.5000 37,800.00 18,900.00
JUMLAH HARGA BAHAN 167,864.00
C PERALATAN
Page 56
JENIS PEKERJAAN : A.4.6.1.6 Pembuatan dan Pemasangan 1 M2 Pasang Jendela Rangka Kaca, t = 5 mm
SATUAN : M2
HARGA SATUAN : Rp 926,539.24
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8000 149,000.00 119,200.00
Tukang L.02 OH 2.4000 195,000.00 468,000.00
Kepala tukang L.03 OH 0.2400 214,000.00 51,360.00
Mandor L.04 OH 0.0400 214,000.00 8,560.00
JUMLAH TENAGA KERJA 647,120.00
B BAHAN
Kayu papan kls II m3 0.0240 3,724,100.00 89,378.40
Paku 7 dan 10 Cm Kg 0.3000 27,700.00 8,310.00
Kaca tebal 5 mm m2 1.0000 97,500.00 97,500.00
JUMLAH HARGA BAHAN 195,188.40
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.6700 149,000.00 99,830.00
Tukang L.02 OH 2.0000 195,000.00 390,000.00
Kepala tukang L.03 OH 0.2000 214,000.00 42,800.00
Mandor L.04 OH 0.3350 214,000.00 71,690.00
JUMLAH TENAGA KERJA 604,320.00
B BAHAN
Papan kayu m3 0.0600 3,724,100.00 223,446.00
Paku 1 Cm - 2,5 Cm Kg 0.1500 27,700.00 4,155.00
JUMLAH HARGA BAHAN 227,601.00
C PERALATAN
Page 57
JENIS PEKERJAAN : Pemasangan 1 m2 rangka langit-langit (60 x 120) Cm, kayu kelas II
SATUAN : M2
HARGA SATUAN : Rp 131,093.87
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1700 149,000.00 25,330.00
Tukang L.02 OH 0.2550 195,000.00 49,725.00
Kepala tukang L.03 OH 0.0255 214,000.00 5,457.00
Mandor L.04 OH 0.0085 214,000.00 1,819.00
JUMLAH TENAGA KERJA 82,331.00
B BAHAN
Kaso-kaso 5 x 7 Cm m3 0.0139 2,234,500.00 30,959.00
Paku 7 dan 10 Cm Kg 0.2125 27,700.00 5,886.25
JUMLAH HARGA BAHAN 36,845.25
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 119,176.25
E Overhead & profit 10% x Jumlah 11,917.62
F Harga Satuan Pekerjaan (D+E) 131,093.87
Page 58
HARGA SATUAN PEKERJAAN KUNCI DAN KACA
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : A.4.6.2.2 Pemasangan 1 buah kunci tanam 2 Slaght
SATUAN : Bh
HARGA SATUAN : Rp 427,196.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 149,000.00 1,490.00
Tukang L.02 OH 0.5000 195,000.00 97,500.00
Kepala tukang L.03 OH 0.0500 214,000.00 10,700.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 110,760.00
B BAHAN
Kunci Antik A/C Itali/Seiss set 1.0000 277,600.00 277,600.00
JUMLAH HARGA BAHAN 277,600.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 388,360.00
E Overhead & profit 10% x Jumlah 38,836.00
F Harga Satuan Pekerjaan (D+E) 427,196.00
Page 59
JENIS PEKERJAAN : A.4.6.2.8 Pemasangan 1 buah Grendel Pintu
SATUAN : Bh
HARGA SATUAN : Rp 65,841.05
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 149,000.00 2,235.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0008 214,000.00 160.50
JUMLAH TENAGA KERJA 34,855.50
B BAHAN
Grendel Pintu Bh 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 59,855.50
E Overhead & profit 10% x Jumlah 5,985.55
F Harga Satuan Pekerjaan (D+E) 65,841.05
A TENAGA
Pekerja L.01 OH 0.0150 149,000.00 2,235.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0008 214,000.00 171.20
JUMLAH TENAGA KERJA 34,866.20
B BAHAN
Engsel pintu 4" Bh 1.0000 18,500.00 18,500.00
JUMLAH HARGA BAHAN 18,500.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0100 149,000.00 1,490.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0005 214,000.00 107.00
JUMLAH TENAGA KERJA 23,237.00
B BAHAN
Engsel Jendela 3" Bh 1.0000 16,600.00 16,600.00
JUMLAH HARGA BAHAN 16,600.00
C PERALATAN
Page 60
JENIS PEKERJAAN : A.4.6.2.11 Pemasangan 1 buah grendel jendela
SATUAN : Bh
HARGA SATUAN : Rp 50,662.70
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 149,000.00 2,235.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0080 214,000.00 1,712.00
JUMLAH TENAGA KERJA 36,407.00
B BAHAN
Grendel Jendela Bh 1.0000 9,650.00 9,650.00
JUMLAH HARGA BAHAN 9,650.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0150 149,000.00 2,235.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0080 214,000.00 1,712.00
JUMLAH TENAGA KERJA 36,407.00
B BAHAN
Kait angin Bh 1.0000 11,250.00 11,250.00
JUMLAH HARGA BAHAN 11,250.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0150 149,000.00 2,235.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0080 214,000.00 1,712.00
JUMLAH TENAGA KERJA 36,407.00
B BAHAN
Tarikan Jendela Bh 1.0000 8,400.00 8,400.00
JUMLAH HARGA BAHAN 8,400.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 44,807.00
E Overhead & profit 10% x Jumlah 4,480.70
F Harga Satuan Pekerjaan (D+E) 49,287.70
Page 61
JENIS PEKERJAAN : A.4.6.2.16 Pemasangan 1 m2 kaca tebal 3 mm
SATUAN : M2
HARGA SATUAN : Rp 151,377.82
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0150 149,000.00 2,235.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0008 214,000.00 171.20
JUMLAH TENAGA KERJA 34,866.20
B BAHAN
Kaca tebal 3 mm m2 1.1000 90,000.00 99,000.00
Sealant Kg 0.0500 75,000.00 3,750.00
JUMLAH HARGA BAHAN 102,750.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0150 149,000.00 2,235.00
Tukang L.02 OH 0.1500 195,000.00 29,250.00
Kepala tukang L.03 OH 0.0150 214,000.00 3,210.00
Mandor L.04 OH 0.0008 214,000.00 171.20
JUMLAH TENAGA KERJA 34,866.20
B BAHAN
Kaca tebal 5 mm m2 1.1000 97,500.00 107,250.00
Sealant Kg 0.0500 75,000.00 3,750.00
JUMLAH HARGA BAHAN 111,000.00
C PERALATAN
Page 62
JENIS PEKERJAAN : A.4.2.1.8 Pemasangan 1 m2 pintu lipat (folding gate) t=0.8 mm Fin. Cat
SATUAN : M2
HARGA SATUAN : Rp 1,298,127.16
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.4400 149,000.00 65,560.00
Tukang Las L.02 OH 0.4400 195,000.00 85,800.00
Kepala tukang L.03 OH 0.0440 214,000.00 9,416.00
Mandor L.04 OH 0.0220 214,000.00 4,708.00
JUMLAH TENAGA KERJA 165,484.00
B BAHAN
Folding Gate m2 1.0000 950,000.00 950,000.00
Pengecatan dengan Cat Minyak m2 1.0000 64,631.60 64,631.60
JENIS PEKERJAAN : Pemasangan 1 M1 Talang Air Zinggalum + Dudukan Dari Baja Kanal
SATUAN : M1
HARGA SATUAN : Rp 124,095.40
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0540 149,000.00 8,046.00
Tukang L.02 OH 0.0900 195,000.00 17,550.00
Kepala tukang L.03 OH 0.0090 214,000.00 1,926.00
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 28,164.00
B BAHAN
Talang Air Zinggalum m 1.0000 60,000.00 60,000.00
Kanal Baja Ringan M1 1.0000 23,000.00 23,000.00
Sekru Baja Ringan Kg 0.5000 3,300.00 1,650.00
JUMLAH HARGA BAHAN 84,650.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 112,814.00
E Overhead & profit 10% x Jumlah 11,281.40
F Harga Satuan Pekerjaan (D+E) 124,095.40
Page 63
JENIS PEKERJAAN : 4.2.1.11 Pemasangan 1 M1 Pemasangan Kusen Allumunium 3" Alexindo White
SATUAN : M1
HARGA SATUAN : Rp 136,467.76
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0430 149,000.00 6,407.00
Tukang L.02 OH 0.0430 195,000.00 8,385.00
Kepala tukang L.03 OH 0.0043 214,000.00 920.20
Mandor L.04 OH 0.0021 214,000.00 449.40
JUMLAH TENAGA KERJA 16,161.60
B BAHAN
Profil alluminium m 1.1000 88,000.00 96,800.00
Skrup fixer bh 2.0000 3,300.00 6,600.00
Sealant Tube 0.0600 75,000.00 4,500.00
JUMLAH HARGA BAHAN 107,900.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 124,061.60
E Overhead & profit 10% x Jumlah 12,406.16
F Harga Satuan Pekerjaan (D+E) 136,467.76
A TENAGA
Pekerja L.01 OH 0.0850 149,000.00 12,665.00
Tukang L.02 OH 0.0850 195,000.00 16,575.00
Kepala tukang L.03 OH 0.0085 214,000.00 1,819.00
Mandor L.04 OH 0.0042 214,000.00 898.80
JUMLAH TENAGA KERJA 31,957.80
B BAHAN
Profil alluminium m 4.4000 88,000.00 387,200.00
Alluminium strip m 14.6000 32,500.00 474,500.00
JUMLAH HARGA BAHAN 861,700.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 893,657.80
E Overhead & profit 10% x Jumlah 89,365.78
F Harga Satuan Pekerjaan (D+E) 983,023.58
Page 64
JENIS PEKERJAAN : 4.2.1.13 Pemasangan 1 m2 Pintu Kaca Rangka Aluminium
SATUAN : M2
HARGA SATUAN : Rp 919,254.60
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0850 149,000.00 12,665.00
Tukang L.02 OH 0.0850 195,000.00 16,575.00
Kepala tukang L.03 OH 0.0090 214,000.00 1,926.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 32,236.00
B BAHAN
Profil alluminium m 4.4000 88,000.00 387,200.00
Profil Kaca m 4.5000 88,000.00 396,000.00
Sealent Tube 0.2700 75,000.00 20,250.00
JUMLAH HARGA BAHAN 803,450.00
C PERALATAN
JENIS PEKERJAAN : Pemasangan 1 m2 Teralis Jendela Besi Frame Siku 20x20x2mm Hollow (1.5x1.5) mm
SATUAN : Unit
HARGA SATUAN : Rp 501,269.34
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8350 149,000.00 124,415.00
Tukang L.02 OH 0.8350 195,000.00 162,825.00
Kepala tukang L.03 OH 0.0835 214,000.00 17,869.00
Mandor L.04 OH 0.0415 214,000.00 8,881.00
JUMLAH TENAGA KERJA 313,990.00
B BAHAN
Besi Siku 20.20.2 M' 3.4000 13,500.00 45,900.00
Besi Hollow 20 x 20 x 1.8mm M' 6.2500 7,500.00 46,875.00
Pengelasan Cm 17.0800 2,005.00 34,245.40
Pengecatan M2 0.2500 58,756.00 14,689.00
JUMLAH HARGA BAHAN 141,709.40
C PERALATAN
Page 65
JENIS PEKERJAAN : Pemasangan 1 m2 Teralis Pintu Besi Frame Siku 40x40x2mm Hollow 20x40x1.8mm
SATUAN : Unit
HARGA SATUAN : Rp 2,193,074.62
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.8350 149,000.00 124,415.00
Tukang L.02 OH 0.8350 195,000.00 162,825.00
Kepala tukang L.03 OH 0.0835 214,000.00 17,869.00
Mandor L.04 OH 0.0415 214,000.00 8,881.00
JUMLAH TENAGA KERJA 313,990.00
B BAHAN
Frame Besi Siku 40.40.2 M' 5.6000 15,100.00 84,560.00
Rangka Pintu Besi Hollow 40 x 40 x 1.8mm M' 11.0000 30,000.00 330,000.00
Besi Hollow 20 x 40 x 1.8mm M' 23.6000 25,000.00 590,000.00
Kunci Pintu Bh 1.0000 277,600.00 277,600.00
Engsel Bubut Bh 6.0000 15,000.00 90,000.00
Grendel Pintu Bh 3.0000 25,000.00 75,000.00
Pengelasan Cm 102.8000 2,005.00 206,114.00
Pengecatan M2 0.4500 58,756.00 26,440.20
JUMLAH HARGA BAHAN 1,679,714.20
C PERALATAN
JENIS PEKERJAAN : Pemasangan 1 m2 Pintu Pagar Besi Hollow 40.60.2 dan besi Hollow 20.40.2
SATUAN : M2
HARGA SATUAN : Rp 1,446,478.00
HARGA SATUAN JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFISIEN
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0500 149,000.00 156,450.00
Tukang L.02 OH 1.0500 195,000.00 204,750.00
Kepala tukang L.03 OH 0.1050 214,000.00 22,470.00
Mandor L.04 OH 0.0350 214,000.00 7,490.00
JUMLAH TENAGA KERJA 391,160.00
B BAHAN
Besi Holloow 20 x 40 x 2mm M1 7.9200 30,000.00 237,600.00
Besi Holloow 40 x 60 x 2mm M1 3.7600 52,000.00 195,520.00
Plat 2mm M2 1.0000 293,000.00 293,000.00
Pengelasan Cm 27.0800 2,500.00 67,700.00
Pengecatan Ls 1.0000 30,000.00 30,000.00
Rel dan Aksesoris Ls 1.0000 100,000.00 100,000.00
JUMLAH HARGA BAHAN 923,820.00
C PERALATAN
Page 66
JENIS PEKERJAAN : Pemasangan 1 m2 Besi Pagar Hollow 40.40.2 dan besi Hollow 20.40.2
SATUAN : M2
HARGA SATUAN : Rp 974,886.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0500 149,000.00 156,450.00
Tukang L.02 OH 1.0500 195,000.00 204,750.00
Kepala tukang L.03 OH 0.1050 214,000.00 22,470.00
Mandor L.04 OH 0.0350 214,000.00 7,490.00
JUMLAH TENAGA KERJA 391,160.00
B BAHAN
Besi Holloow 20 x 40 x 2mm M1 7.9200 30,000.00 237,600.00
Besi Holloow 40 x 40 x 2mm M1 3.7600 42,500.00 159,800.00
Pengelasan Cm 27.0800 2,500.00 67,700.00
Pengecatan Ls 1.0000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 495,100.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0700 149,000.00 10,430.00
Tukang L.02 OH 0.0090 195,000.00 1,755.00
Kepala tukang L.03 OH 0.0060 214,000.00 1,284.00
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 14,111.00
B BAHAN
Cat menie Kg 0.2000 37,300.00 7,460.00
Plamuur Kg 0.1500 36,900.00 5,535.00
Cat dasar Kg 0.1700 74,900.00 12,733.00
Cat penutup Kg 0.2600 62,300.00 16,198.00
Kuas Bh 0.0100 27,500.00 275.00
Pengencer Kg 0.0300 14,800.00 444.00
Ampelas Lbr 0.2000 10,000.00 2,000.00
JUMLAH HARGA BAHAN 44,645.00
C PERALATAN
Page 67
JENIS PEKERJAAN : 3.3.8.(c) Peleburan 1 m2 bidang kayu dengan cat residu dan ter
SATUAN : M2
HARGA SATUAN : Rp 36,936.90
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 149,000.00 14,900.00
Mandor L.04 OH 0.0060 214,000.00 1,284.00
JUMLAH TENAGA KERJA 16,184.00
B BAHAN
Residu atau ter Ktr 0.3500 49,700.00 17,395.00
JUMLAH HARGA BAHAN 17,395.00
C PERALATAN
JENIS PEKERJAAN : A.4.7.1.8b Pengecatan 1 m2 permukaan bidang kayu dengan cat meni
SATUAN : M2
HARGA SATUAN : Rp 32,162.90
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.1000 149,000.00 14,900.00
Mandor L.04 OH 0.0060 214,000.00 1,284.00
JUMLAH TENAGA KERJA 16,184.00
B BAHAN
Cat Menie Kg 0.3500 37,300.00 13,055.00
JUMLAH HARGA BAHAN 13,055.00
C PERALATAN
JENIS PEKERJAAN : 3.3.10.(c) Pengecatan 1 m2 tembok baru Interior (1 lapis plamur, 1 lapis cat dasar, 2lapis cat penutup
SATUAN : M2
HARGA SATUAN : Rp 95,474.72
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 149,000.00 2,980.00
Tukang L.02 OH 0.0630 195,000.00 12,285.00
Kepala tukang L.03 OH 0.0063 214,000.00 1,348.20
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 17,255.20
B BAHAN
Plamuur Kg 0.1000 36,600.00 3,660.00
Cat dasar tembok Kg 0.1000 183,000.00 18,300.00
Cat Penutup Interior Mrek Nipon Kg 0.2600 183,000.00 47,580.00
JUMLAH HARGA BAHAN 69,540.00
C PERALATAN
Page 68
JENIS PEKERJAAN : Pengecatan 1 m2 tembok baru Exterior (1 lapis plamur, 1 lapis cat dasar, 2lapis cat penutup
SATUAN : M2
HARGA SATUAN : Rp 101,160.40
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 149,000.00 2,980.00
Tukang L.02 OH 0.0630 195,000.00 12,285.00
Kepala tukang L.03 OH 0.0063 214,000.00 1,348.20
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 17,255.20
B BAHAN
Plamuur Kg 0.1000 36,600.00 3,660.00
Cat alkali resisting primer Kg 0.1000 183,000.00 18,300.00
Cat weather shield Nopon Kg 0.2600 202,880.00 52,748.80
JUMLAH HARGA BAHAN 74,708.80
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 91,964.00
E Overhead & profit 10% x Jumlah 9,196.40
F Harga Satuan Pekerjaan (D+E) 101,160.40
JENIS PEKERJAAN : A.4.7.1.14 Pengecatan 1 m2 Plafond baru (1 lapis cat dasar, 2lapis cat penutup)
SATUAN : M2
HARGA SATUAN : Rp 91,331.02
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0200 149,000.00 2,980.00
Tukang L.02 OH 0.0630 195,000.00 12,285.00
Kepala tukang L.03 OH 0.0063 214,000.00 1,348.20
Mandor L.04 OH 0.0025 214,000.00 535.00
JUMLAH TENAGA KERJA 17,148.20
B BAHAN
Cat Dasar Tembok Kg 0.1000 183,000.00 18,300.00
Cat Penutup Catilac Kg 0.2600 183,000.00 47,580.00
JUMLAH HARGA BAHAN 65,880.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 83,028.20
E Overhead & profit 10% x Jumlah 8,302.82
F Harga Satuan Pekerjaan (D+E) 91,331.02
Page 69
HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
PERMEN PUPR NO. 1 TAHUN 2022
JENIS PEKERJAAN : A.5.1.1.2 Pemasangan 1 buah Klosed Jongkok American Standart
SATUAN : Unit
HARGA SATUAN : Rp 859,393.62
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.0000 149,000.00 149,000.00
Tukang L.02 OH 1.5000 195,000.00 292,500.00
Kepala tukang L.03 OH 0.1500 214,000.00 32,100.00
Mandor L.04 OH 0.1600 214,000.00 34,240.00
JUMLAH TENAGA KERJA 507,840.00
B BAHAN
Closet jongkok American Standart Unit 1.0000 268,000.00 268,000.00
Pasangan Bata 1PC:4PS m2 0.0360 150,748.00 5,426.93
JUMLAH HARGA BAHAN 273,426.93
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 781,266.93
E Overhead & profit 10% x Jumlah 78,126.69
F Harga Satuan Pekerjaan (D+E) 859,393.62
A TENAGA
Pekerja L.01 OH 1.2000 149,000.00 178,800.00
Tukang L.02 OH 1.4500 195,000.00 282,750.00
Kepala tukang L.03 OH 0.1500 214,000.00 32,100.00
Mandor L.04 OH 0.0600 214,000.00 12,840.00
JUMLAH TENAGA KERJA 506,490.00
B BAHAN
Wastafel Unit 1.2000 1,077,800.00 1,293,360.00
Semen Portland Kg 6.0000 1,880.00 112.80
Pasir Pasang m3 0.0100 246,000.00 24.60
JUMLAH HARGA BAHAN 1,293,497.40
C PERALATAN
Page 70
JENIS PEKERJAAN : 5.1.1.14. Pemasangan 1 buah Floordrain
SATUAN : Unit
HARGA SATUAN : Rp 147,367.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0100 149,000.00 1,490.00
Tukang L.02 OH 0.1000 195,000.00 19,500.00
Kepala tukang L.03 OH 0.0100 214,000.00 2,140.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 24,200.00
B BAHAN
Floor Drain Stainlestell Bh 1.0000 109,770.00 109,770.00
JUMLAH HARGA BAHAN 109,770.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0100 149,000.00 1,490.00
Tukang L.02 OH 0.4000 195,000.00 78,000.00
Kepala tukang L.03 OH 0.0400 214,000.00 8,560.00
Mandor L.04 OH 0.0050 214,000.00 1,070.00
JUMLAH TENAGA KERJA 89,120.00
B BAHAN
Kran Air Stainlestell Bh 1.0000 45,000.00 45,000.00
Sealtape Bh 0.0250 7,000.00 175.00
JUMLAH HARGA BAHAN 45,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 134,120.00
E Overhead & profit 10% x Jumlah 13,412.00
F Harga Satuan Pekerjaan (D+E) 147,532.00
Page 71
JENIS PEKERJAAN : A.5.1.1.25 Pemasangan 1 M1 pipa PVC tipe AW diameter 1/2"
SATUAN : M1
HARGA SATUAN : Rp 33,127.60
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0360 149,000.00 5,364.00
Tukang L.02 OH 0.0600 195,000.00 11,700.00
Kepala tukang L.03 OH 0.0060 214,000.00 1,284.00
Mandor L.04 OH 0.0020 214,000.00 428.00
JUMLAH TENAGA KERJA 18,776.00
B BAHAN
Pipa PVC 1/2" set 1.2000 7,000.00 8,400.00
Perlengkapan % 35.0000 2,940.00
JUMLAH HARGA BAHAN 11,340.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0360 149,000.00 5,364.00
Tukang L.02 OH 0.0600 195,000.00 11,700.00
Kepala tukang L.03 OH 0.0060 214,000.00 1,284.00
Mandor L.04 OH 0.0020 214,000.00 428.00
JUMLAH TENAGA KERJA 18,776.00
B BAHAN
Pipa PVC 3/4" set 1.2000 9,000.00 10,800.00
Perlengkapan % 35.0000 3,780.00
JUMLAH HARGA BAHAN 14,580.00
C PERALATAN
Page 72
JENIS PEKERJAAN : A.5.1.1.27 Pemasangan 1 M1 pipa PVC tipe AW diameter 1 "
SATUAN : M1
HARGA SATUAN : Rp 42,394.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0360 149,000.00 5,364.00
Tukang L.02 OH 0.0600 195,000.00 11,700.00
Kepala tukang L.03 OH 0.0060 214,000.00 1,284.00
Mandor L.04 OH 0.0020 214,000.00 428.00
JUMLAH TENAGA KERJA 18,776.00
B BAHAN
Pipa PVC 1" set 1.2000 12,200.00 14,640.00
Perlengkapan % 35.0000 5,124.00
JUMLAH HARGA BAHAN 19,764.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 38,540.00
E Overhead & profit 10% x Jumlah 3,854.00
F Harga Satuan Pekerjaan (D+E) 42,394.00
A TENAGA
Pekerja L.01 OH 0.0540 149,000.00 8,046.00
Tukang L.02 OH 0.0900 195,000.00 17,550.00
Kepala tukang L.03 OH 0.0090 214,000.00 1,926.00
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 28,164.00
B BAHAN
Pipa PVC 1 1/2" set 1.2000 21,000.00 25,200.00
Perlengkapan % 35.0000 8,820.00
JUMLAH HARGA BAHAN 34,020.00
C PERALATAN
Page 73
JENIS PEKERJAAN : A.5.1.1.29 Pemasangan 1 M1 pipa PVC tipe AW diameter 2"
SATUAN : M1
HARGA SATUAN : Rp 83,014.80
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0540 149,000.00 8,046.00
Tukang L.02 OH 0.0900 195,000.00 17,550.00
Kepala tukang L.03 OH 0.0090 214,000.00 1,926.00
Mandor L.04 OH 0.0030 214,000.00 642.00
JUMLAH TENAGA KERJA 28,164.00
B BAHAN
Pipa PVC 2" set 1.2000 29,200.00 35,040.00
Perlengkapan % 35.0000 12,264.00
JUMLAH HARGA BAHAN 47,304.00
C PERALATAN
A TENAGA
Pekerja L.01 OH 0.0810 149,000.00 12,069.00
Tukang L.02 OH 0.1350 195,000.00 26,325.00
Kepala tukang L.03 OH 0.0135 214,000.00 2,889.00
Mandor L.04 OH 0.0040 214,000.00 856.00
JUMLAH TENAGA KERJA 42,139.00
B BAHAN
Pipa PVC 3" set 1.2000 57,900.00 69,480.00
Perlengkapan % 35.0000 24,318.00
JUMLAH HARGA BAHAN 93,798.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 135,937.00
E Overhead & profit 10% x Jumlah 13,593.70
F Harga Satuan Pekerjaan (D+E) 149,530.70
Page 74
JENIS PEKERJAAN : Pembuatan 1 unit Septick Tank Kap. 50 Orang Lengkap Peresapan
SATUAN : Unit
HARGA SATUAN : Rp 16,305,956.22
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Page 75
JENIS PEKERJAAN : A.5.1.1 18. Pemasangan 1 buah bak kontrol pasangan bata 60 cm x 60 cm tinggi 65 cm
SATUAN : Unit
HARGA SATUAN : Rp 1,293,228.09
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 3.2000 149,000.00 476,800.00
Tukang L.02 OH 1.1500 195,000.00 224,250.00
Kepala tukang L.03 OH 0.0110 214,000.00 2,354.00
Mandor L.04 OH 0.0160 214,000.00 3,424.00
JUMLAH TENAGA KERJA 706,828.00
B BAHAN
Bata merah buah 123.0000 700.00 86,100.00
Semen portland Kg 114.0000 1,880.00 214,320.00
Pasir pasang M3 0.1840 246,000.00 45,264.00
Pasir beton M3 0.1200 545,000.00 65,400.00
Kerikil M3 0.0330 280,300.00 9,249.90
Baja tulangan Kg 4.8500 10,000.00 48,500.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 76
JENIS PEKERJAAN : Pemasangan 1 Instalasi Stop Kontak
SATUAN : Titik
HARGA SATUAN : Rp 227,150.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
JUMLAH TENAGA KERJA 35,000.00
B BAHAN
Kabel NYM 3 x 2,5 mm2 M1 10.0000 13,000.00 130,000.00
PVC Hight Impact dia 20 mm2 M1 10.0000 3,000.00 30,000.00
Coupling/Socket dia 20 mm2 Bh 3.0000 500.00 1,500.00
Clamp Cable dia 20 mm2 Bh 10.0000 500.00 5,000.00
Junction Box Bh 2.0000 2,500.00 5,000.00
JUMLAH HARGA BAHAN 171,500.00
C PERALATAN
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 77
JENIS PEKERJAAN : Pemasangan 1 Stop Kontak
SATUAN : Bh
HARGA SATUAN : Rp 59,950.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 78
JENIS PEKERJAAN : Pemasangan 1 Saklar Triple
SATUAN : Bh
HARGA SATUAN : Rp 73,150.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 79
JENIS PEKERJAAN : Pemasangan 1 Unit MCB 6A + Box
SATUAN : Unit
HARGA SATUAN : Rp 203,500.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
JUMLAH TENAGA KERJA 35,000.00
B BAHAN
MCCB 50A Bh 1.0000 614,260.00 614,260.00
MCB DOMF01104 4A ex. Schneider 1P 6kA Bh 7.0000 94,500.00 661,500.00
MCB DOMF01110 10A ex. Schneider 1P 6 kA Bh 7.0000 75,500.00 528,500.00
MCB DOMF01116 16A ex. Schneider 1P 6 kA Bh 1.0000 75,500.00 75,500.00
Pilot Lamp Bh 3.0000 18,780.00 56,340.00
Busbar Sisir 100 A Pitch 18mm/12 + Insulated Connector SET 1.0000 247,400.00 247,400.00
Control Wiring + aksesori SET 1.0000 145,000.00 145,000.00
Wall Mounted Box Panel 400 x 300 x 200 x 2 mm UNIT 1.0000 1,100,000.00 1,100,000.00
Grounding A LS 1.0000 2,456,830.00 2,456,830.00
Material Bantu LS 0.0250 3,428,500.00 85,712.50
JUMLAH HARGA BAHAN 5,971,042.50
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 6,006,042.50
E Overhead & profit 10% x Jumlah 600,604.25
F Harga Satuan Pekerjaan (D+E) 6,606,646.75
Page 80
JENIS PEKERJAAN : Pemasangan 1 Unit PP-PENERANGAN DAYA GEDUNG B
SATUAN : Unit
HARGA SATUAN : Rp 5,192,889.35
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 81
JENIS PEKERJAAN : Pemasangan 1 Unit MDP- GEDUNG
SATUAN : Unit
HARGA SATUAN : Rp 10,688,560.03
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 82
JENIS PEKERJAAN : Pemasangan 1 M Kabel NYY 4x6mm
SATUAN : M1
HARGA SATUAN : Rp 159,500.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 83
JENIS PEKERJAAN : Pemasangan 1 Instalasi CCTV
SATUAN : Titik
HARGA SATUAN : Rp 309,541.80
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 84
JENIS PEKERJAAN : Pemasangan 1 MONITOR 32"
SATUAN : Unit
HARGA SATUAN : Rp 4,438,500.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 85
JENIS PEKERJAAN : Pemasangan 1 Speaker box dinding
SATUAN : Unit
HARGA SATUAN : Rp 423,500.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 86
JENIS PEKERJAAN : Pemasangan 1 Mic Paging microphone
SATUAN : Unit
HARGA SATUAN : Rp 1,248,500.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 87
JENIS PEKERJAAN : Pemasangan 1 Instalasi WIFI
SATUAN : Titik
HARGA SATUAN : Rp 355,164.75
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
Page 88
JENIS PEKERJAAN : Pemasangan 1 ROUTER MIKROTIK CCR 2116 12G 4S+CCR2116-12G-4S
SATUAN : Unit
HARGA SATUAN : Rp 18,188,500.00
HARGA SATUAN
NO URAIAN KODE SATUAN KOEFISIEN JUMLAH HARGA (Rp)
(Rp)
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
A TENAGA
Upah Pasang OH 1.0000 35,000.00 35,000.00
DESTA MASRIKO
Wakil Direktur
Page 89
DAFTAR HARGA DASAR SATUAN UPAH DAN BAHAN
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
A. KELOMPOK UPAH
1 Pekerja L01 OH Rp 149,000.00
2 Tukang L02 OH Rp 195,000.00
3 Kepala Tukang L03 OH Rp 214,000.00
4 Mandor L04 OH Rp 214,000.00
Page 90
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
12 Kayu 5/7 Cm M.37.b Btg Rp 56,300.00
13 Kayu reng 2 x 3 kelas 2 m3 Rp 2,137,500.00
14 Triplek 4 mm Lbr Rp 100,800.00
15 Plywood 9 mm Lbr Rp 128,000.00
16 Multiplek tebal 9 mm M.33d Lbr Rp 204,600.00
17 Les Profil (3x3.5x400) M' Rp 5,200.00
18 Lem kayu kg Rp 37,800.00
19 Gypsum Board t.9 mm Lbr Rp 153,600.00
20 GRC Board t.6 mm Lbr Rp 145,800.00
21 List Profil Gypsumb 5 cm M1 Rp 24,600.00
22 Waterproofing coating waterbase Kg Rp 90,000.00
23 Kalsiboard t.4 mm M2 Rp 85,000.00
24 GRC Board Lebar 20 Cm M1 Rp 27,500.00
Page 91
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Seng Plat BJLS 20 Biasa Lbr Rp 58,600.00
- Atap Spandek T=0.30mm Lengkung M1 Rp 50,000.00
- Perabung Genteng Metal Lbr Rp 38,300.00
H. PENGGANTUNG/PENGUNCI
- Kunci Seiss Set Rp 277,600.00
- Grendel Pintu Bh Rp 25,000.00
- Grendel Jendela Bh Rp 9,650.00
- Engsel 4" Kuningan Bh Rp 18,500.00
- Engsel 3" Kuningan Bh Rp 16,600.00
- Hak Angin Bh Rp 11,250.00
- Tarikan Jendela Bh Rp 8,400.00
Page 92
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
10 Pipa PVC Vinilon AW Ø4" M1 Rp 82,650.00
Page 93
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
54 MCB 6A + Box Unit Rp 150,000.00
25 Wall Mounted Box Panel 300 x 300 x 200 x 2 mm Unit Rp 800,000.00
26 Wall Mounted Box Panel 400 x 300 x 200 x 2 mm Unit Rp 1,100,000.00
27 Wall Mounted Box Panel 600 x 400 x 250 x 2 mm Unit Rp 1,500,000.00
25 Alat bantu Lot Rp 15,000.00
26 Upah Pasang Ls Rp 35,000.00
IP Kamera CCTV Indoor
27 IP Kamera CCTV Indoor Unit Rp 818,400.00 Hikvision DS-2CD1323G0E-I
2MP
Kabel BELDEN Kabel LAN UTP
28 Kabel Cat-6 M1 Rp 8,295.08
Cat6 Grey 305m ORI
Hikvision DS-7616NI-Q2/16P
29 NVR Unit Rp 5,040,000.00 NVR IP Camera CCTV 16 ch POE
Kamera Onvif - NVR+1TB
DS-2FA1205-D8 Hikvision
30 PSU Unit Rp 330,000.00 Adaptor CCTV Power Supply 8A
12V 8CH
31 Monitor Unit Rp 4,000,000.00 Samsung
32 Kabel NYMHY 2x1.5mm2 Meter Rp 9,900.00
33 Ceiling Mount Speaker ZS-648R Unit Rp 220,000.00
34 Speaker box dinding G ZS062 ZS Unit Rp 350,000.00
35 Mixer amplifier ZA-230 WATT Unit Rp 2,000,000.00
36 Z-MD200-AS Media Player Unit Rp 6,500,000.00
37 Mic Paging microphone Toa ZM-660D ZM 660D Unit Rp 1,100,000.00
38 STANDING CLOSE RACK 19" IR6032G DEPTH 600MM 32U GLASS Unit Rp 9,000,000.00
39 Terminal Box Unit Rp 400,000.00
Ruijie RG-NBS3200-24GT4XS-P
40 SWITCH HUB POE (W)NBS3200-24GT4XS-P Unit Rp 17,500,000.00 24 Gigabit POE 370W Cloud
Managed Switchs
41 ROUTER MIKROTIK CCR 2116 12G 4S+CCR2116-12G-4S Unit Rp 16,500,000.00
RUIJIE RG-AP840-1,WI-FI MIMO
42 WIRLES INDOOR ACCSESS POINT Unit Rp 12,500,000.00
802.11AX
Page 94
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
Pekerjaan Penangkal Petir R 150m
Head penangkal petir non Radioaktif Radius proteksi 150 1 Unit Rp 4,500,000.00
Down Conductor cable NYA 70mm 1 m' Rp 152,972.00
Dudukan tiang penangkal petir 1 Unit Rp 3,942,015.00
Lightning Strike Counter - Analog 1 Unit Rp 7,144,515.00
Bak kontrol 40x40cm 1 Unit Rp 732,000.00
Grounding penangkal petir/ Ground rood komplit 1 ttk Rp 2,625,788.00
Obstruction lamp 1 bh Rp 1,396,875.00
Gali tanah 1 lot Rp 488,000.00
Testing & Commisioning 1 lot Rp 1,000,000.00
Perizinan pemakaian / Depnaker 1 lot Rp 7,000,000.00
Bahan Grounding Sistem
Copper road 5/8" 1 m Rp 728,400.00
Pentanahan & pipa GIP dia. 1 1/2 " 1 m Rp 470,000.00
Bak Kontrol Grounding (45 x 45 cm) Tinggi 60 cm 1 unit Rp 541,273.38
Clamp Cable dia. 20 mm2 1 bh Rp 3,000.00
Kawat BCC dia. 70 mm 1 bh Rp 70,000.00
DESTA MASRIKO
Wakil Direktur
Page 95