REKAPITULASI

RENCANA ANGGARAN BIAYA


PEKERJAAN : REHABILITASI BENDUNG DAN SALURAN D.I GEUNTEUT DI KABUPATEN ACEH BESAR
LOKASI : ACEH BESAR
SATKER : SNVT PJPA SUMATERA I
TAHUN ANGGARAN : 2023
( BLG 11 s/d BLG 18 , SAL . PRIMER )

N0. JENIS PEKERJAAN JUMLAH HARGA (RP)

BAGIAN I UMUM 675.559.000,00

BAGIAN II SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK) 48.795.000,00

BAGIAN III PEKERJAAN BENDUNG (MERCU, KOLAM OLAK, DINDING PENAHAN DAN SALURAN) 3.417.547.383,00

BAGIAN IV PEKERJAAN BANGUNAN PENDUKUNG 319.101.356,00

BAGIAN V PEKERJAAN RUMAH JAGA 43.565.372,00

JUMLAH Rp. 4.504.568.111,00


PPN 11% Rp. 495.502.492,21
TOTAL ANGGARAN Rp. 5.000.070.603,21
DIBULATKAN Rp. 5.000.000.000,00

TERBILANG : lima milyar rupiah

Banda Aceh, Februari 2023


Mengetahui
KEPALA SUBDIT BIMBINGAN TEKNIS Ka. SNVT PJPA SUMATERA I PEJABAT PEMBUAT KOMITMEN
SNVT PJPA SUMATERA I IRIGASI DAN RAWA I
SNVT PJPA SUMATERA I

Ir. Muradi, ME Ir. Mauluddin Alim, Sp Nizamuddin S.T.,M.T


NIP. 19630325 199203 1 006 NIP. 19610822 199301 1 001 NIP. 197506252009111002

KEPALA SUBDIT PERENCANAAN KEPALA SUBDIT WILAYAH BARAT


RENCANA ANGGARAN BIAYA
PEKERJAAN : REHABILITASI BENDUNG DAN SALURAN D.I GEUNTEUT DI KABUPATEN ACEH BESAR
LOKASI : ACEH BESAR
SATKER : SNVT PJPA SUMATERA I
TAHUN ANGGARAN : 2023

SATUAN KODE (Rp.)


NO URAIAN PEKERJAAN KUANTITAS HARGA SATUAN
UKURAN ANALISA 7=5x6
1 2 3 4 5 6 7
BAGIAN I
A. UMUM

A.1 Mobilisasi dan Demobilisasi Alat Ls Dihitung 1,00 41.200.000,00 41.200.000,00


A.2 Fasilitas untuk Penyedia Jasa (Sewa) Ls Dihitung 1,00 48.300.000,00 48.300.000,00
A.3 Pengujian Laboratorium Ls Dihitung 1,00 40.350.000,00 40.350.000,00
A.4 Pembuatan Papan Nama Pekerjaan Bh 1.1.4.a.(a) 1,00 1.915.000,00 1.915.000,00
A.5 Investigasi lapangan Ls 1.1.5.a.(a) 1,00 1.550.000,00 1.550.000,00
A.6 Stake out trase saluran/infrastruktur di lapangan m2 1.7.4.a (a) 7.500,00 5.900,00 44.250.000,00
A.7 Pasang 1 m' profil melintang galian tanah saluran M 1.7.4.c (a) 120,00 25.200,00 3.024.000,00
A.8 Saluran pengelak
A.8.1 Galian Tanah (Alb) M³ Dihitung 4.500,00 22.400,00 100.800.000,00
A.8.2 Pembuangan tanah hasil galian dengan jarak angkut 50 m - 1000 m M³ Dihitung 2.250,00 41.200,00 92.700.000,00
A.8.3 Sewa lahan Ls Dihitung 1,00 25.000.000,00 25.000.000,00
Timbunan Tanah dari Galian tanpa jarak angkut (Penghamparan 0 - 50 m)
A.8.4 M³ Dihitung 450,00 12.900,00 5.805.000,00
(ALB) - Kistdam
A.8.5 Pengoperasian per-jam pompa air diesel daya 15 KW (Dewatering) jam 1.2.4.(a) 700,00 131.300,00 91.910.000,00
A.8.6 Kistdam Pasir (Perkuatan tebing saluran pengelak) Ls Dihitung 1,00 25.000.000,00 25.000.000,00
A.8.7 Kayu Cerucuk ø10cm M' Dihitung 150,00 54.500,00 8.175.000,00
A.8.8 Pembuatan jalan sementara Ls Dihitung 1,00 15.800.000,00 15.800.000,00
Timbunan Tanah dari Galian tanpa jarak angkut (Penghamparan 0 - 50 m)
A.8.9 M³ Dihitung 2.700,00 18.200,00 49.140.000,00
dipadatkan (ALB)
Timbunan Tanah dari Galian dengan jarak angkut 50 - 1000 m,
A.8.10 M³ Dihitung 1.800,00 44.800,00 80.640.000,00
Diratakan/dipadatkan (ALB)

JUMLAH BAGIAN I (dipindahkan ke Rekapitulasi) 675.559.000,00

BAGIAN II
B. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)

Sistem Manajemen Kesehatan, Keselamatan dan Keamanan Kerja


B.1 Ls Dihitung 1,00 48.795.000,00 48.795.000,00
Konstruksi (SMKK)
JUMLAH BAGIAN II (dipindahkan ke Rekapitulasi) 48.795.000,00
BAGIAN III
C PEKERJAAN BENDUNG (MERCU, KOLAM OLAK, DINDING PENAHAN DAN SALURAN)

C.1 PEKERJAAN TANAH


Galian tanah biasa sedalam s.d 1 m volume s.d 200 m3 dalam satu lokasi
C.1.1 M³ 1.7.1.a 94,770 122.400,00 11.599.848,00
(Manual)
C.1.2 Galian Tanah (ALB) M³ Dihitung 2.196,250 22.400,00 49.196.000,00
C.1.3 Pembuangan tanah hasil galian dengan jarak angkut 50 m - 1000 m M³ Dihitung 284,310 41.200,00 11.713.572,00
C.1.4 Pembuangan tanah hasil galian dengan jarak angkut 1000 m - 2000 m M³ Dihitung 379,080 54.400,00 20.621.952,00
C.1.5 Pembuangan tanah hasil galian dengan jarak angkut 2.000 m - 3.000 m M³ Dihitung 473,850 69.700,00 33.027.345,00
Timbunan Tanah dari Galian tanpa jarak angkut (Penghamparan 0 - 50 m)
C.1.6 dipadatkan (ALB) M³ Dihitung 640,960 18.200,00 11.665.472,00

Timbunan Tanah dari Galian dengan jarak angkut 50 - 1000 m,


C.1.7 Diratakan/dipadatkan (ALB) M³ Dihitung 189,540 44.800,00 8.491.392,00

C.1.8 Timbunan Tanah Didatangkan, diratakan dan dipadatkan (ALB) M³ Dihitung 684,000 144.300,00 98.701.200,00
C.1.9 Finishing tanggul sungai M² TM.01.6.g 398,880 27.900,00 11.128.752,00
C.2 PEKERJAAN BETON
C.2.1 Bongkar pasangan lama M³ 2.1.2.a.5.c.(a) 465,200 80.300,00 37.355.560,00
C.2.2 Pembuangan hasil bongkaran dengan jarak angkut 50 m - 1000 m M³ Dihitung 460,320 28.300,00 13.027.056,00
C.2.3 Plastik cor M² Dihitung 1.051,730 9.700,00 10.201.781,00
C.2.4 Additive penyambung beton baru dan beton lama M² Dihitung 740,870 17.200,00 12.742.964,00
C.2.5 Beton untuk lantai kerja/bedding M³ 2.2.1.2.a.(a) 57,380 1.199.400,00 68.821.572,00
C.2.6 Beton Cyclop (60% : 40%) M³ 2.2.12.b.(a) 111,130 1.110.500,00 123.409.865,00
C.2.7 Beton K-300 (Ready Mix) + Pompa M³ Dihitung 144,010 2.242.100,00 322.884.821,00
C.2.8 Beton K-300 (Ready Mix) M³ 2.2.3.a.(a) 219,500 2.130.000,00 467.535.000,00
C.2.9 Pemadatan beton M³ 2.2.5.a.(a) 522,020 57.200,00 29.859.544,00
C.2.10 Wiremesh M8 - 15 Kg 2.2.7.(a) 933,030 17.700,00 16.514.631,00
C.2.11 Pembesian (besi polos) Kg 2.2.6.1.b.(c) 19.370,900 17.900,00 346.739.110,00
C.2.12 Pembesian (besi ulir) (upah + bahan) Kg 2.2.6.1.b.(c) 558,800 19.400,00 10.840.720,00
C.2.13 Bekisting M² B.15.b 947,590 210.000,00 198.993.900,00

C.3 PEKERJAAN BATU


C.3.1 Pasangan Batu 1 PC : 3 PP M³ 2.1.2.a.2.c.(a) 413,610 1.117.400,00 462.167.814,00
C.3.2 Plasteran 1:3 ; t = 15 mm M² 3.2.1.(c) 1.241,440 101.400,00 125.882.016,00
C.3.3 Kayu Cerucuk ø10cm M' Dihitung 198,000 54.500,00 10.791.000,00
C.3.4 Bronjong pabrikasi (2 x 1 x 0,5) m M³ 1.5.7.a.(a) 853,000 957.600,00 816.832.800,00
C.3.5 Geotextile Non-Woven (300 gr) M² 1.6.2.a.(a) 840,913 32.700,00 27.497.850,00
C.3.6 Pengisian Batu Kali pada Con Block (1 x 1 x 1,2m) M³ Dihitung 102,710 382.600,00 39.296.846,00

C.4 PEKERJAAN LAIN-LAIN


C.4.1 Drain Hole PVC Ø 2" bh 1.6.3.(a) 153,000 14.000,00 2.142.000,00
C.4.2 Jalan Inspeksi M² Dihitung 150,000 119.100,00 17.865.000,00

JUMLAH BAGIAN III (dipindahkan ke Rekapitulasi) 3.417.547.383,00


SATUAN KODE (Rp.)
NO URAIAN PEKERJAAN KUANTITAS HARGA SATUAN
UKURAN ANALISA 7=5x6
1 2 3 4 5 6 7
BAGIAN VI
BAGIAN
D PEKERJAAN BANGUNAN PENDUKUNG

D.1 PEKERJAAN BETON


D.1.1 Pembongkaran Pintu Air Eksisting Ls Dihitung 1,00 8.750.000,00 8.750.000,00
Penambahan tinggi jagaan dinding bendung 50 cm (cegah back water),
D.1.2 M³ 2.1.2.a.2.c.(a) 20,94 1.117.400,00 23.398.356,00
pas. Batu 1 : 3
D.1.3 Pembongkaran atap beton pintu air M³ 2.1.2.a.5.c.(a) 15,00 80.300,00 1.204.500,00

D.1.4 Cor plat atap beton bertulang pintu air beton K.225 (Ready mix) + Pompa M3 2.2.3.a.(a) 10,00 2.073.000,00 20.730.000,00

Pemasangan plat penahan pintu intake saluran primer beton K.225 (Ready
D.1.5 M3 2.2.3.a.(a) 1,50 2.073.000,00 3.109.500,00
Mix)
D.1.6 Pembesian (besi polos) Kg 2.2.6.1.b.(c) 920,00 17.900,00 16.468.000,00
D.1.7 Pembersihan dan pengikisan cat lama pada tiang dan ralling pagar Ls Dihitung 1,00 2.500.000,00 2.500.000,00
Pengecatan dinding, tiang dan balok pintu air dengan cat Dulux
D.1.8 M² 3.3.11.(c) 81,60 39.500,00 3.223.200,00
Weathershield (tembok lama)
D.1.9 Pengecatan railling besi pagar M² 3.3.17.(c) 32,20 39.000,00 1.255.800,00
D.1.10 Pelapisan atap plat pintu air dengan lapisan waterproof (tembok baru) M² 3.3.10.(c) 5,00 52.400,00 262.000,00

D.2 PEKERJAAN LAIN-LAIN


Pengadaan dan Pemasangan Pintu Pembilas Type Double Stang b=1,5m;
D.2.1 Unit Dihitung 1,00 53.000.000,00 53.000.000,00
h=0,9m; ht=4,4m
Pengadaan dan Pemasangan Pintu Intake Kiri dan Penguras Type Double
D.2.2 Unit Dihitung 2,00 50.000.000,00 100.000.000,00
Stang b=1,2m; h=0,6m; ht=4,4m
Pengadaan dan Pemasangan Pintu Intake Kanan Type Stang Tunggal
D.2.3 Unit Dihitung 1,00 37.200.000,00 37.200.000,00
b=0,75m; h=0,6m; ht=4,4m
Pengadaan dan Pemasangan Pintu Intake Saluran Type Double Stang
D.2.4 Unit Dihitung 1,00 48.000.000,00 48.000.000,00
b=1,0m; h=0,9m; ht=1,8m

JUMLAH BAGIAN V (dipindahkan ke Rekapitulasi) 319.101.356,00


BAGIAN VI
E PEKERJAAN RUMAH JAGA

E.1 Pembongkaran Atap,Kusen Pintu dan jendela Rumah Jaga Eksisting Ls Dihitung 1,00 10.000.000,00 10.000.000,00
E.2 Rehap Atap Rumah Penjaga Bendung M2 Dihitung 36,00 450.000,00 16.200.000,00
E.3 Pemasangan Pintu P1 (UPVC) Unit Dihitung 1,00 1.550.000,00 1.550.000,00
E.4 Pemasangan Pintu P2 (UPVC) Unit Dihitung 1,00 1.550.000,00 1.550.000,00
E.5 Pemasangan Jendela J1 (UPVC) Unit Dihitung 1,00 1.350.000,00 1.350.000,00
E.6 Pemasangan Jendela J2 (UPVC) Unit Dihitung 1,00 1.350.000,00 1.350.000,00
E.7 Cor plat dak beton bertulang - 'Beton K-225 (Ready Mixed) M3 2.2.3.a.(a) 1,73 1.960.900,00 3.392.357,00
E.8 Pembesian (besi polos) Kg 2.2.6.1.b.(c) 135,65 17.900,00 2.428.135,00
E.9 Pengecatan (tembok lama) M² 3.3.11.(c) 145,44 39.500,00 5.744.880,00

JUMLAH BAGIAN VI (dipindahkan ke Rekapitulasi) 43.565.372,00