PELAKSANAAN
Time Schedule Rencana 45 HARI KERJA
KETERANGAN
M1 M2 M3 M4 M5 M6 M7
No. JENIS PEKERJAAN JUMLAH BIAYA BOBOT
( 17 s.d 21 ) Okt - ( 22 s.d 28 ) Okt ( 29 s.d 04 ) Nov ( 05 s.d 11 ) Nov - ( 12 s.d 18 ) Nov - ( 19 s.d 25 ) Nov ( 26 s.d 30 ) Nov RENCANA
2023 - 2023 - 2023 2023 2023 - 2023 - 2023
I. PEKERJAAN PERSIAPAN 7,620,703.35 4.66 0.67 0.67 0.67 0.67 0.67 0.67 0.67 100
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN 725,058.89 0.44 0.11 0.33
2.2 PEKERJAAN PONDASI DAN STRUKTUR BETON 7,419,606.44 4.54 2.27 2.27
2.3 PEKERJAAN STRUKTUR BAJA DAN PENGECATAN 53,105,967.34 32.48 10.83 10.83 10.83
3.2 PEKERJAAN DINDING, LANTAI DAN PENUTUP 3,716,382.91 2.27 1.14 1.14
4.2 PEKERJAAN PLUMBING 82,274,100.00 50.33 10.07 10.07 10.07 10.07 10.07 0
TRIS TRIBUDIARTI ISNANINGSIH, ST., M.SI., MH. ZAIFU ROCHMAN, ST. IAI
NIP. 19700227 199703 2 003 TEAM LEADER DINA DARNIDA
Direktur
JADWAL PELAKASANAAN
PELAKSANAAN
Time Schedule Rencana Terhadap Realisasi 45 HARI KERJA
KETERANGAN
M1 M2 M3 M4 M5 M6 M7
No. JENIS PEKERJAAN JUMLAH BIAYA BOBOT
( 17 s.d 21 ) Okt - ( 22 s.d 28 ) Okt - ( 29 s.d 04 ) Nov - ( 05 s.d 11 ) Nov - ( 12 s.d 18 ) Nov - ( 19 s.d 25 ) Nov - ( 26 s.d 30 ) Nov -
2023 2023 2023 2023 2023 2023 2023
I. PEKERJAAN PERSIAPAN 7,620,703.35 4.66 0.67 0.67 0.67 0.67 0.67 0.67 0.67 100
2.2 PEKERJAAN PONDASI DAN STRUKTUR BETON 7,419,606.44 4.54 2.27 2.27
2.3 PEKERJAAN STRUKTUR BAJA DAN PENGECATAN 53,105,967.34 32.48 10.83 10.83 10.83
3.2 PEKERJAAN DINDING, LANTAI DAN PENUTUP 3,716,382.91 2.27 1.14 1.14
4.2 PEKERJAAN PLUMBING 82,274,100.00 50.33 10.07 10.07 10.07 10.07 10.07 0
LAPORAN MINGGUAN
I SESUAI DENGAN MUTUAL CHECK - 0 PRESTASI FISIK DAN BIAYA TERHADAP JENIS PEKERJAAN
PRIODA : ( 17 s.d 21 ) Okt - 2023
HARGA
JUMLAH HARGA KUANTITAS
No. URAIAN PEKERJAAN VOL SATUAN SATUAN BOBOT
(Rp) (Rp) MINGGU LALU MINGGU INI S/D MINGGU INI KET
1 2 3 4 5 6
Volume Prestasi Bobot Volume Prestasi Bobot Volume Prestasi Bobot
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 ls 1,000,000.00 1,000,000.00 0.61 0.15 150,000.00 0.09 0.15 150,000.00 0.09
2 Biaya Air dan Listrik Kerja 1.00 ls 349,967.85 349,967.85 0.21 0.15 52,495.18 0.03 0.15 52,495.18 0.03
3 Pek. Papan Nama Proyek (Spanduk Banner) Uk. 80X100 cm 1.00 buah 350,000.00 350,000.00 0.21 0.00 - - 0.00 - -
4 Pek. Pembersihan dan Perataan Tanah 7.50 m² 25,065.00 187,987.50 0.11 1.88 46,996.88 0.03 1.88 46,996.88 0.03
5 Pas. Bowplank dan Pengukuran 7.20 m' 89,340.00 643,248.00 0.39 7.20 643,248.00 0.39 7.20 643,248.00 0.39
6 Tes Uji Geolistrik 1.00 ls 3,000,000.00 3,000,000.00 1.84 1.00 3,000,000.00 1.84 1.00 3,000,000.00 1.84
7 Administrasi dan Dokumen Pelaporan 1.00 ls 900,000.00 900,000.00 0.55 - - - - - -
8 Asbuilt Drawing 1.00 ls 500,000.00 500,000.00 0.31 - - - - - -
9 Keselamatan dan Kesehatan Kerja (k3)
Helm 5.00 bh 58,800.00 294,000.00 0.18 0.75 44,100.00 0.03 0.75 44,100.00 0.03
- Masker 4Ply 1.00 box 175,000.00 175,000.00 0.11 0.15 26,250.00 0.02 0.15 26,250.00 0.02
- Rompi Jaring (safety Vest) 5.00 bh 26,000.00 130,000.00 0.08 0.75 19,500.00 0.01 0.75 19,500.00 0.01
- Sarung Tangan (Wool) 5.00 psg 18,100.00 90,500.00 0.06 0.75 13,575.00 0.01 0.75 13,575.00 0.01
7,620,703.35 4.66 0 0 3,996,165.05 2.44 3,996,165.05 2.44
II. PEKERJAAN MENARA AIR
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN
1 Pek. Galian Tanah u/ Pondasi Telapak dan Sloof 3.46 m³ 106,050.00 366,508.80 0.224 - - - - - -
2 Pek. Urugan Tanah Kembali 2.15 m³ 78,505.00 168,817.15 0.103 - - - - - -
3 Pek. Urugan Pasir Bawah Pondasi Telapak, Sloof dan Plat Lantai 0.42 m³ 260,220.00 108,771.96 0.067 - - - - - -
4 Pek. Urugan Tanah Peninggi Bawah Plat Lantai ±8 cm 0.26 m³ 78,505.00 20,348.50 0.012 - - - - - -
5 Pek. Pembuangan Tanah Bekas Galian 1.31 m³ 46,425.00 60,612.48 0.037 - - - - - -
I. PEKERJAAN PERSIAPAN 7,620,703.35 4.66 3,996,165.05 2.44 405,417.05 0.25 4,401,582.11 2.69
4.2 PEKERJAAN PLUMBING 82,274,100.00 50.33 6,972,640.00 4.27 8,715,800.00 5.33 15,688,440.00 9.60
JUMLAH TOTAL 163,483,580.00 100.00 10,968,805.05 6.71 9,121,217.05 5.58 20,090,022.11 12.29
TRIS TRIBUDIARTI ISNANINGSIH, ST., M.SI., MH. ZAIFU ROCHMAN, ST. IAI
NIP. 19700227 199703 2 003 TEAM LEADER DINA DARNIDA
Direktur
Pekerjaan : Penyediaan Sarana Air Bersih ( PSAB-116 )
Lokasi : Pasantren Sirnamiskin, Jl. KH Wahid Hasim ( Kopo 433 ) Rt. 08 Rw. 07 Kel. Kebon lega Kec. Bojong Loa Kidul
Kontrak Pelaksanaan : CV.CITRA KUSUMA TRADING
Nomor SPK : 050/05/TTI/PSAB-116/DPKP/02/2023
Konsultan Pengawas : PT. SPECTRA ARZA INTERPLAN
Mulai Pelaksanaan : 19-Oktober-2023
LAPORAN MINGGUAN
II SESUAI DENGAN MUTUAL CHECK - 0 PRESTASI FISIK DAN BIAYA TERHADAP JENIS PEKERJAAN
PRIODA : ( 22 s.d 28 ) Okt - 2023
HARGA
JUMLAH HARGA KUANTITAS
No. URAIAN PEKERJAAN VOL SATUAN SATUAN BOBOT
(Rp) (Rp) MINGGU LALU MINGGU INI S/D MINGGU INI KET
1 2 3 4 5 6
Volume Prestasi Bobot Volume Prestasi Bobot Volume Prestasi Bobot
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 ls 1,000,000.00 1,000,000.00 0.61 0.15 150,000.00 0.09 0.15 150,000.00 0.09 0.30 300,000.00 0.18
2 Biaya Air dan Listrik Kerja 1.00 ls 349,967.85 349,967.85 0.21 0.15 52,495.18 0.03 0.15 52,495.18 0.03 0.30 104,990.36 0.06
3 Pek. Papan Nama Proyek (Spanduk Banner) Uk. 80X100 cm 1.00 buah 350,000.00 350,000.00 0.21 - - - 0.15 52,500.00 0.03 0.15 52,500.00 0.03
4 Pek. Pembersihan dan Perataan Tanah 7.50 m² 25,065.00 187,987.50 0.11 1.88 46,996.88 0.03 1.88 46,996.88 0.03 3.75 93,993.75 0.06
5 Pas. Bowplank dan Pengukuran 7.20 m' 89,340.00 643,248.00 0.39 7.20 643,248.00 0.39 - - - 7.20 643,248.00 0.39
6 Tes Uji Geolistrik 1.00 ls 3,000,000.00 3,000,000.00 1.84 1.00 3,000,000.00 1.84 - - - 1.00 3,000,000.00 1.84
7 Administrasi dan Dokumen Pelaporan 1.00 ls 900,000.00 900,000.00 0.55 - - - - - - - - -
8 Asbuilt Drawing 1.00 ls 500,000.00 500,000.00 0.31 - - - - - - - - -
9 Keselamatan dan Kesehatan Kerja (k3)
Helm 5.00 bh 58,800.00 294,000.00 0.18 0.75 44,100.00 0.03 0.75 44,100.00 0.03 1.50 88,200.00 0.05
- Masker 4Ply 1.00 box 175,000.00 175,000.00 0.11 0.15 26,250.00 0.02 0.15 26,250.00 0.02 0.30 52,500.00 0.03
- Rompi Jaring (safety Vest) 5.00 bh 26,000.00 130,000.00 0.08 0.75 19,500.00 0.01 0.75 19,500.00 0.01 1.50 39,000.00 0.02
- Sarung Tangan (Wool) 5.00 psg 18,100.00 90,500.00 0.06 0.75 13,575.00 0.01 0.75 13,575.00 0.01 1.50 27,150.00 0.02
7,620,703.35 4.66 3,996,165.05 2.44 405,417.05 0.25 4,401,582.11 2.69
II. PEKERJAAN MENARA AIR
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN
1 Pek. Galian Tanah u/ Pondasi Telapak dan Sloof 3.46 m³ 106,050.00 366,508.80 0.224 - - - - - - - - -
2 Pek. Urugan Tanah Kembali 2.15 m³ 78,505.00 168,817.15 0.103 - - - - - - - - -
3 Pek. Urugan Pasir Bawah Pondasi Telapak, Sloof dan Plat Lantai 0.42 m³ 260,220.00 108,771.96 0.067 - - - - - - - - -
4 Pek. Urugan Tanah Peninggi Bawah Plat Lantai ±8 cm 0.26 m³ 78,505.00 20,348.50 0.012 - - - - - - - - -
5 Pek. Pembuangan Tanah Bekas Galian 1.31 m³ 46,425.00 60,612.48 0.037 - - - - - - - - -
I. PEKERJAAN PERSIAPAN 7,620,703.35 4.66 4,401,582.11 2.69 405,417.05 0.25 4,806,999.16 2.94
4.2 PEKERJAAN PLUMBING 82,274,100.00 50.33 15,688,440.00 9.60 10,458,960.00 6.40 26,147,400.00 15.99
JUMLAH TOTAL 163,483,580.00 100.00 20,090,022.11 12.29 10,864,377.05 6.65 30,954,399.16 18.93
TRIS TRIBUDIARTI ISNANINGSIH, ST., M.SI., MH. ZAIFU ROCHMAN, ST. IAI
NIP. 19700227 199703 2 003 TEAM LEADER DINA DARNIDA
Direktur
Pekerjaan : Penyediaan Sarana Air Bersih ( PSAB-116 )
Lokasi : Pasantren Sirnamiskin, Jl. KH Wahid Hasim ( Kopo 433 ) Rt. 08 Rw. 07 Kel. Kebon lega Kec. Bojong Loa Kidul
Kontrak Pelaksanaan : CV.CITRA KUSUMA TRADING
Nomor SPK : 050/05/TTI/PSAB-116/DPKP/02/2023
Konsultan Pengawas : PT. SPECTRA ARZA INTERPLAN
Mulai Pelaksanaan : 19-Oktober-2023
LAPORAN MINGGUAN
III SESUAI DENGAN MUTUAL CHECK - 0 PRESTASI FISIK DAN BIAYA TERHADAP JENIS PEKERJAAN
PRIODA : ( 29 s.d 04 ) Nov - 2023
HARGA
JUMLAH HARGA KUANTITAS
No. URAIAN PEKERJAAN VOL SATUAN SATUAN BOBOT
(Rp) (Rp) MINGGU LALU MINGGU INI S/D MINGGU INI
1 2 3 4 5 6
Volume Prestasi Bobot Volume Prestasi Bobot Volume Prestasi Bobot
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 ls 1,000,000.00 1,000,000.00 0.61 0.30 300,000.00 0.18 0.15 150,000.00 0.09 0.45 450,000.00 0.28
2 Biaya Air dan Listrik Kerja 1.00 ls 349,967.85 349,967.85 0.21 0.30 104,990.36 0.06 0.15 52,495.18 0.03 0.45 157,485.53 0.10
3 Pek. Papan Nama Proyek (Spanduk Banner) Uk. 80X100 cm 1.00 buah 350,000.00 350,000.00 0.21 0.15 52,500.00 0.03 0.15 52,500.00 0.03 0.30 105,000.00 0.06
4 Pek. Pembersihan dan Perataan Tanah 7.50 m² 25,065.00 187,987.50 0.11 3.75 93,993.75 0.06 1.88 46,996.88 0.03 5.63 140,990.63 0.09
5 Pas. Bowplank dan Pengukuran 7.20 m' 89,340.00 643,248.00 0.39 7.20 643,248.00 0.39 - - - 7.20 643,248.00 0.39
6 Tes Uji Geolistrik 1.00 ls 3,000,000.00 3,000,000.00 1.84 1.00 3,000,000.00 1.84 - - - 1.00 3,000,000.00 1.84
7 Administrasi dan Dokumen Pelaporan 1.00 ls 900,000.00 900,000.00 0.55 - - - - - - - - -
8 Asbuilt Drawing 1.00 ls 500,000.00 500,000.00 0.31 - - - - - - - - -
9 Keselamatan dan Kesehatan Kerja (k3)
Helm 5.00 bh 58,800.00 294,000.00 0.18 1.50 88,200.00 0.05 0.75 44,100.00 0.03 2.25 132,300.00 0.08
- Masker 4Ply 1.00 box 175,000.00 175,000.00 0.11 0.30 52,500.00 0.03 0.15 26,250.00 0.02 0.45 78,750.00 0.05
- Rompi Jaring (safety Vest) 5.00 bh 26,000.00 130,000.00 0.08 1.50 39,000.00 0.02 0.75 19,500.00 0.01 2.25 58,500.00 0.04
- Sarung Tangan (Wool) 5.00 psg 18,100.00 90,500.00 0.06 1.50 27,150.00 0.02 0.75 13,575.00 0.01 2.25 40,725.00 0.02
7,620,703.35 4.66 4,401,582.11 2.69 405,417.05 0.25 4,806,999.16 2.94
II. PEKERJAAN MENARA AIR
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN
1 Pek. Galian Tanah u/ Pondasi Telapak dan Sloof 3.46 m³ 106,050.00 366,508.80 0.224 - - - - - - - - -
2 Pek. Urugan Tanah Kembali 2.15 m³ 78,505.00 168,817.15 0.103 - - - - - - - - -
3 Pek. Urugan Pasir Bawah Pondasi Telapak, Sloof dan Plat Lantai 0.42 m³ 260,220.00 108,771.96 0.067 - - - - - - - - -
4 Pek. Urugan Tanah Peninggi Bawah Plat Lantai ±8 cm 0.26 m³ 78,505.00 20,348.50 0.012 - - - - - - - - -
5 Pek. Pembuangan Tanah Bekas Galian 1.31 m³ 46,425.00 60,612.48 0.037 - - - - - - - - -
I. PEKERJAAN PERSIAPAN 7,620,703.35 4.66 4,806,999.16 2.94 405,417.05 0.25 5,212,416.21 3.19
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN 725,058.89 0.44 - - 145,409.71 0.09 145,409.71 0.09
2.2 PEKERJAAN PONDASI DAN STRUKTUR BETON 7,419,606.44 4.54 - - 519,825.62 0.32 519,825.62 0.32
4.2 PEKERJAAN PLUMBING 82,274,100.00 50.33 26,147,400.00 15.99 16,715,800.00 10.22 42,863,200.00 26.22
JUMLAH TOTAL 163,483,580.00 100.00 30,954,399.16 18.93 17,786,452.39 10.88 48,740,851.54 29.81
LAPORAN MINGGUAN
IV SESUAI DENGAN MUTUAL CHECK - 0 PRESTASI FISIK DAN BIAYA TERHADAP JENIS PEKERJAAN
PRIODA : ( 05 s.d 11 ) Nov - 2023
HARGA
JUMLAH HARGA KUANTITAS
No. URAIAN PEKERJAAN VOL SATUAN SATUAN BOBOT
(Rp) (Rp) MINGGU LALU MINGGU INI S/D MINGGU INI
1 2 3 4 5 6
Volume Prestasi Bobot Volume Prestasi Bobot Volume Prestasi Bobot
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 ls 1,000,000.00 1,000,000.00 0.61 0.45 450,000.00 0.28 0.15 150,000.00 0.09 0.60 600,000.00 0.37
2 Biaya Air dan Listrik Kerja 1.00 ls 349,967.85 349,967.85 0.21 0.45 157,485.53 0.10 0.15 52,495.18 0.03 0.60 209,980.71 0.13
3 Pek. Papan Nama Proyek (Spanduk Banner) Uk. 80X100 cm 1.00 buah 350,000.00 350,000.00 0.21 0.30 105,000.00 0.06 0.15 52,500.00 0.03 0.45 157,500.00 0.10
4 Pek. Pembersihan dan Perataan Tanah 7.50 m² 25,065.00 187,987.50 0.11 5.63 140,990.63 0.09 1.88 46,996.88 0.03 7.50 187,987.50 0.11
5 Pas. Bowplank dan Pengukuran 7.20 m' 89,340.00 643,248.00 0.39 7.20 643,248.00 0.39 - - - 7.20 643,248.00 0.39
6 Tes Uji Geolistrik 1.00 ls 3,000,000.00 3,000,000.00 1.84 1.00 3,000,000.00 1.84 - - - 1.00 3,000,000.00 1.84
7 Administrasi dan Dokumen Pelaporan 1.00 ls 900,000.00 900,000.00 0.55 - - - - - - - - -
8 Asbuilt Drawing 1.00 ls 500,000.00 500,000.00 0.31 - - - - - - - - -
9 Keselamatan dan Kesehatan Kerja (k3)
Helm 5.00 bh 58,800.00 294,000.00 0.18 2.25 132,300.00 0.08 0.75 44,100.00 0.03 3.00 176,400.00 0.11
- Masker 4Ply 1.00 box 175,000.00 175,000.00 0.11 0.45 78,750.00 0.05 0.15 26,250.00 0.02 0.60 105,000.00 0.06
- Rompi Jaring (safety Vest) 5.00 bh 26,000.00 130,000.00 0.08 2.25 58,500.00 0.04 0.75 19,500.00 0.01 3.00 78,000.00 0.05
- Sarung Tangan (Wool) 5.00 psg 18,100.00 90,500.00 0.06 2.25 40,725.00 0.02 0.75 13,575.00 0.01 3.00 54,300.00 0.03
7,620,703.35 4.66 4,806,999.16 2.94 405,417.05 0.25 5,212,416.21 3.19
II. PEKERJAAN MENARA AIR
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN
1 Pek. Galian Tanah u/ Pondasi Telapak dan Sloof 3.46 m³ 106,050.00 366,508.80 0.224 - - - 0.86 91,627.20 0.056 0.86 91,627.20 0.056
2 Pek. Urugan Tanah Kembali 2.15 m³ 78,505.00 168,817.15 0.103 - - - 0.32 25,322.57 0.015 0.32 25,322.57 0.015
3 Pek. Urugan Pasir Bawah Pondasi Telapak, Sloof dan Plat Lantai 0.42 m³ 260,220.00 108,771.96 0.067 - - - 0.06 16,315.79 0.010 0.06 16,315.79 0.010
4 Pek. Urugan Tanah Peninggi Bawah Plat Lantai ±8 cm 0.26 m³ 78,505.00 20,348.50 0.012 - - - 0.04 3,052.27 0.002 0.04 3,052.27 0.002
5 Pek. Pembuangan Tanah Bekas Galian 1.31 m³ 46,425.00 60,612.48 0.037 - - - 0.20 9,091.87 0.006 0.20 9,091.87 0.006
2.2 PEKERJAAN PONDASI DAN STRUKTUR BETON 725,058.89 0.44 - 0.00 145,409.71 0.09 145,409.71 0.09
1 Pas. Lantai Kerja Beton 1PC:3PS:5KR (bawah pondasi, sloof dan plat lantai) 0.44 m³ 951,160.00 417,369.01 0.255 - - - - - - - - -
2 Pek. Pondasi Telapak Uk. 80X80X30 - - -
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.77 m³ 1,182,570.00 908,213.76 0.556 - - - - - - - - -
- Pek. Pembesian U - 24 88.17 kg 14,410.00 1,270,500.88 0.777 - - - 13.23 190,575.13 0.117 13.23 190,575.13 0.117
- Pek. Bekisting Pondasi 2X Pakai 3.84 m² 74,285.00 285,254.40 0.174 - - - - - - - - -
3 Pek. Kolom Pedestal Uk. 20X20 cm - - -
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.20 m³ 1,182,570.00 236,514.00 0.145 - - - - - - - - -
- Pek. Pembesian U - 24 50.62 kg 14,410.00 729,448.61 0.446 - - - 7.59 109,417.29 0.067 7.59 109,417.29 0.067
- Pek. Bekisting Kolom 2X Pakai 4.54 m² 140,492.50 637,273.98 0.390 - - - - - - - - -
4 Pek. Sloof Uk. 20X30 cm - - -
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.43 m³ 1,182,570.00 510,870.24 0.312 - - - - - - - - -
- Pek. Pembesian U - 24 61.99 kg 14,410.00 893,285.51 0.546 - - - 9.30 133,992.83 0.082 9.30 133,992.83 0.082
- Pek. Bekisting Sloof 2X Pakai 4.46 m² 128,910.00 575,454.24 0.352 - - - - - - - - -
5 Pek. Plat Lantai Tebal 10 cm - - -
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.32 m³ 1,182,570.00 383,152.68 0.234 - - - - - - - - -
- Pek. Pembesian U - 24 39.71 kg 14,410.00 572,269.13 0.350 - - - 5.96 85,840.37 0.053 5.96 85,840.37 0.053
2.3 PEKERJAAN STRUKTUR BAJA DAN PENGECATAN 7,419,606.44 4.54 - 0.00 519,825.62 0.32 519,825.62 0.32
1 Pek. Pas. Baseplate T.12 mm Uk. 20X20 cm dan Angkur Mur Baut dia. 16 mm P. 60 cm 4.00 bh 263,315.00 1,053,260.00 0.644 - - - - - - - - -
2 Pek. Pasangan Besi Siku 70.70.6 mm 715.46 kg 39,490.00 28,253,449.58 17.282 - - - - - - - - -
3 Pek. Pasangan Besi Siku 50.50.5 mm (dudukn Filter dan tangga) 106.89 kg 39,490.00 4,221,086.10 2.582 - - - - - - - - -
4 Pek. Pasangan Plat Bordes Tebal 2 mm 174.15 kg 29,860.00 5,200,021.50 3.181 - - - - - - - - -
5 Pek. Pasangan Endplate Tebal 10 mm 16.44 kg 29,495.00 485,043.92 0.297 - - - - - - - - -
6 Pek. Pengelasan 2469.00 cm 2,595.00 6,407,055.00 3.919 - - - - - - - - -
7 Pek. Pemasangan Mur Baut HTB dia. 10 s/d 16 mm Panjang 5 cm 155.00 bh 11,600.00 1,798,000.00 1.100 - - - - - - - - -
8 Pek. Pengecatan Cat Dasar Bidang Besi 46.78 m² 41,670.00 1,949,427.11 1.192 - - - - - - - - -
9 Pek. Pengecatan Bidang Besi 3X Lapis Cat Penutup 46.78 m² 79,915.00 3,738,624.13 2.287 - - - - - - - - -
I. PEKERJAAN PERSIAPAN 7,620,703.35 4.66 5,212,416.21 3.19 358,420.18 0.22 5,570,836.39 3.41
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN 725,058.89 0.44 145,409.71 0.09 579,649.17 0.35 725,058.89 0.44
2.2 PEKERJAAN PONDASI DAN STRUKTUR BETON 7,419,606.44 4.54 519,825.62 0.32 1,459,491.38 0.89 1,979,317.00 1.21
2.3 PEKERJAAN STRUKTUR BAJA DAN PENGECATAN 53,105,967.34 32.48 - - 7,405,101.48 4.53 7,405,101.48 4.53
3.1 PEKERJAAN TANAH GALIAN DAN URUGAN 38,289.08 0.02 - - 5,743.36 0.00 5,743.36 0.00
3.2 PEKERJAAN DINDING, LANTAI DAN PENUTUP 3,716,382.91 2.27 - - 557,457.44 0.34 557,457.44 0.34
4.1 PEKERJAAN MEKANIKAL ELEKTRIKAL 8,583,472.00 5.25 - - 4,291,736.00 2.63 4,291,736.00 2.63
4.2 PEKERJAAN PLUMBING 82,274,100.00 50.33 42,863,200.00 26.22 3,819,730.00 2.34 46,682,930.00 28.56
JUMLAH TOTAL 163,483,580.00 100.00 48,740,851.54 29.81 18,477,329.01 11.30 67,218,180.55 41.12
LAPORAN MINGGUAN
V SESUAI DENGAN MUTUAL CHECK - 0 PRESTASI FISIK DAN BIAYA TERHADAP JENIS PEKERJAAN
PRIODA : ( 12 s.d 18 ) Nov - 2023
HARGA
JUMLAH HARGA KUANTITAS
No. URAIAN PEKERJAAN VOL SATUAN SATUAN BOBOT
(Rp) (Rp) MINGGU LALU MINGGU INI S/D MINGGU INI
1 2 3 4 5 6
Volume Prestasi Bobot Volume Prestasi Bobot Volume Prestasi Bobot
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 ls 1,000,000.00 1,000,000.00 0.61 0.60 600,000.00 0.37 0.15 150,000.00 0.09 0.75 750,000.00 0.46
2 Biaya Air dan Listrik Kerja 1.00 ls 349,967.85 349,967.85 0.21 0.60 209,980.71 0.13 0.15 52,495.18 0.03 0.75 262,475.89 0.16
3 Pek. Papan Nama Proyek (Spanduk Banner) Uk. 80X100 cm 1.00 buah 350,000.00 350,000.00 0.21 0.45 157,500.00 0.10 0.15 52,500.00 0.03 0.60 210,000.00 0.13
4 Pek. Pembersihan dan Perataan Tanah 7.50 m² 25,065.00 187,987.50 0.11 7.50 187,987.50 0.11 0.00 - - 7.50 187,987.50 0.11
5 Pas. Bowplank dan Pengukuran 7.20 m' 89,340.00 643,248.00 0.39 7.20 643,248.00 0.39 - - - 7.20 643,248.00 0.39
6 Tes Uji Geolistrik 1.00 ls 3,000,000.00 3,000,000.00 1.84 1.00 3,000,000.00 1.84 - - - 1.00 3,000,000.00 1.84
7 Administrasi dan Dokumen Pelaporan 1.00 ls 900,000.00 900,000.00 0.55 0.00 - - - - - - - -
8 Asbuilt Drawing 1.00 ls 500,000.00 500,000.00 0.31 0.00 - - - - - - - -
9 Keselamatan dan Kesehatan Kerja (k3)
Helm 5.00 bh 58,800.00 294,000.00 0.18 3.00 176,400.00 0.11 0.75 44,100.00 0.03 3.75 220,500.00 0.13
- Masker 4Ply 1.00 box 175,000.00 175,000.00 0.11 0.60 105,000.00 0.06 0.15 26,250.00 0.02 0.75 131,250.00 0.08
- Rompi Jaring (safety Vest) 5.00 bh 26,000.00 130,000.00 0.08 3.00 78,000.00 0.05 0.75 19,500.00 0.01 3.75 97,500.00 0.06
- Sarung Tangan (Wool) 5.00 psg 18,100.00 90,500.00 0.06 3.00 54,300.00 0.03 0.75 13,575.00 0.01 3.75 67,875.00 0.04
7,620,703.35 4.66 5,212,416.21 3.19 358,420.18 0.22 5,570,836.39 3.41
II. PEKERJAAN MENARA AIR
2.1 PEKERJAAN TANAH GALIAN DAN URUGAN
1 Pek. Galian Tanah u/ Pondasi Telapak dan Sloof 3.46 m³ 106,050.00 366,508.80 0.224 0.86 91,627.20 0.06 2.59 274,881.60 0.168 3.46 366,508.80 0.224
2 Pek. Urugan Tanah Kembali 2.15 m³ 78,505.00 168,817.15 0.103 0.32 25,322.57 0.02 1.83 143,494.58 0.088 2.15 168,817.15 0.103
3 Pek. Urugan Pasir Bawah Pondasi Telapak, Sloof dan Plat Lantai 0.42 m³ 260,220.00 108,771.96 0.067 0.06 16,315.79 0.01 0.36 92,456.17 0.057 0.42 108,771.96 0.067
4 Pek. Urugan Tanah Peninggi Bawah Plat Lantai ±8 cm 0.26 m³ 78,505.00 20,348.50 0.012 0.04 3,052.27 0.00 0.22 17,296.22 0.011 0.26 20,348.50 0.012
5 Pek. Pembuangan Tanah Bekas Galian 1.31 m³ 46,425.00 60,612.48 0.037 0.20 9,091.87 0.01 1.11 51,520.61 0.032 1.31 60,612.48 0.037
2.2 PEKERJAAN PONDASI DAN STRUKTUR BETON 725,058.89 0.44 145,409.71 0.09 579,649.17 0.35 725,058.89 0.44
1 Pas. Lantai Kerja Beton 1PC:3PS:5KR (bawah pondasi, sloof dan plat lantai) 0.44 m³ 951,160.00 417,369.01 0.255 - - - 0.07 62,605.35 0.038 0.07 62,605.35 0.038
2 Pek. Pondasi Telapak Uk. 80X80X30
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.77 m³ 1,182,570.00 908,213.76 0.556 - - - 0.12 136,232.06 0.083 0.12 136,232.06 0.083
- Pek. Pembesian U - 24 88.17 kg 14,410.00 1,270,500.88 0.777 13.23 190,575.13 0.12 22.04 317,625.22 0.194 35.27 508,200.35 0.311
- Pek. Bekisting Pondasi 2X Pakai 3.84 m² 74,285.00 285,254.40 0.174 - - - 0.58 42,788.16 0.026 0.58 42,788.16 0.026
3 Pek. Kolom Pedestal Uk. 20X20 cm
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.20 m³ 1,182,570.00 236,514.00 0.145 - - - 0.03 35,477.10 0.022 0.03 35,477.10 0.022
- Pek. Pembesian U - 24 50.62 kg 14,410.00 729,448.61 0.446 7.59 109,417.29 0.07 12.66 182,362.15 0.112 20.25 291,779.44 0.178
- Pek. Bekisting Kolom 2X Pakai 4.54 m² 140,492.50 637,273.98 0.390 - - - 0.68 95,591.10 0.058 0.68 95,591.10 0.058
4 Pek. Sloof Uk. 20X30 cm
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.43 m³ 1,182,570.00 510,870.24 0.312 - - - 0.06 76,630.54 0.047 0.06 76,630.54 0.047
- Pek. Pembesian U - 24 61.99 kg 14,410.00 893,285.51 0.546 9.30 133,992.83 0.08 15.50 223,321.38 0.137 24.80 357,314.20 0.219
- Pek. Bekisting Sloof 2X Pakai 4.46 m² 128,910.00 575,454.24 0.352 - - - 0.67 86,318.14 0.053 0.67 86,318.14 0.053
5 Pek. Plat Lantai Tebal 10 cm
- Pek. Beton Tumbuk 1PC:2PS:3KR 0.32 m³ 1,182,570.00 383,152.68 0.234 - - - 0.05 57,472.90 0.035 0.05 57,472.90 0.035
- Pek. Pembesian U - 24 39.71 kg 14,410.00 572,269.13 0.350 5.96 85,840.37 0.05 9.93 143,067.28 0.088 15.89 228,907.65 0.140
2.3 PEKERJAAN STRUKTUR BAJA DAN PENGECATAN 7,419,606.44 4.54 519,825.62 0.32 1,459,491.38 0.89 1,979,317.00 1.21
1 Pek. Pas. Baseplate T.12 mm Uk. 20X20 cm dan Angkur Mur Baut dia. 16 mm P. 60 cm 4.00 bh 263,315.00 1,053,260.00 0.644 - - - 0.60 157,989.00 0.097 0.60 157,989.00 0.097
2 Pek. Pasangan Besi Siku 70.70.6 mm 715.46 kg 39,490.00 28,253,449.58 17.282 - - - 107.32 4,238,017.44 2.592 107.32 4,238,017.44 2.592
3 Pek. Pasangan Besi Siku 50.50.5 mm (dudukn Filter dan tangga) 106.89 kg 39,490.00 4,221,086.10 2.582 - - - 16.03 633,162.91 0.387 16.03 633,162.91 0.387
4 Pek. Pasangan Plat Bordes Tebal 2 mm 174.15 kg 29,860.00 5,200,021.50 3.181 - - - 26.12 780,003.22 0.477 26.12 780,003.22 0.477
5 Pek. Pasangan Endplate Tebal 10 mm 16.44 kg 29,495.00 485,043.92 0.297 - - - 2.47 72,756.59 0.045 2.47 72,756.59 0.045
6 Pek. Pengelasan 2469.00 cm 2,595.00 6,407,055.00 3.919 - - - 370.35 961,058.25 0.588 370.35 961,058.25 0.588
7 Pek. Pemasangan Mur Baut HTB dia. 10 s/d 16 mm Panjang 5 cm 155.00 bh 11,600.00 1,798,000.00 1.100 - - - 23.25 269,700.00 0.165 23.25 269,700.00 0.165
8 Pek. Pengecatan Cat Dasar Bidang Besi 46.78 m² 41,670.00 1,949,427.11 1.192 - - - 7.02 292,414.07 0.179 7.02 292,414.07 0.179
9 Pek. Pengecatan Bidang Besi 3X Lapis Cat Penutup 46.78 m² 79,915.00 3,738,624.13 2.287 - - - - - - - - -
III. PEKERJAAN RUMAH POMPA 53,105,967.34 32.48 - 0.00 7,405,101.48 4.53 7,405,101.48 4.53
3.1 PEKERJAAN TANAH GALIAN DAN URUGAN
1 Pek. Galian Tanah u/ Dinding Bata 0.17 m³ 106,050.00 17,657.32 0.011 - - - 0.02 2,648.60 0.002 0.02 2,648.60 0.002
2 Pek. Urugan Tanah Kembali 0.05 m³ 78,505.00 3,532.73 0.002 - - - 0.01 529.91 0.000 0.01 529.91 0.000
3 Pek. Urugan Pasir Bawah Dinding Bata dan Lantai 0.04 m³ 260,220.00 10,831.66 0.007 - - - 0.01 1,624.75 0.001 0.01 1,624.75 0.001
4 Pek. Pembuangan Tanah Bekas Galian 0.13 m³ 46,425.00 6,267.37 0.004 - - - 0.02 940.11 0.001 0.02 940.11 0.001
3.2 PEKERJAAN DINDING, LANTAI DAN PENUTUP 38,289.08 0.02 - 0.00 5,743.36 0.00 5,743.36 0.00
1 Pas. Lantai Kerja Beton 5 cm, 1PC:3PS:5KR (bawah dinding bata dan lantai) 0.03 m³ 951,160.00 25,146.29 0.015 - - - 0.00 3,771.94 0.002 0.00 3,771.94 0.002
2 Pas. Dinding Bata Tebal 1/2 Bata, camp. 1PC:4PS 2.33 m² 178,050.00 413,966.25 0.253 - - - 0.35 62,094.94 0.038 0.35 62,094.94 0.038
3 Pas. Plesteran Dinding, camp. 1PC:4PS 4.65 m² 86,390.00 401,713.50 0.246 - - - 0.70 60,257.03 0.037 0.70 60,257.03 0.037
4 Pas. Lantai Beton 1PC:3PS:5KR (lantai rumah popa) 0.02 m³ 951,160.00 23,541.21 0.014 - - - 0.00 3,531.18 0.002 0.00 3,531.18 0.002
5 Pas. Acian 4.65 m² 52,420.00 243,753.00 0.149 - - - 0.70 36,562.95 0.022 0.70 36,562.95 0.022
6 Pek. Pasangan Besi Siku 50.50.5 mm 19.13 kg 39,490.00 755,246.25 0.462 - - - 2.87 113,286.94 0.069 2.87 113,286.94 0.069
7 Pek. Penutup Rumah Pompa dengan Plat Bordes tebal 2 mm 21.62 kg 29,860.00 645,488.78 0.395 - - - 3.24 96,823.32 0.059 3.24 96,823.32 0.059
8 Pek. Pengecatan Bidang Dinding 2x Lapis Cat Penutup 4.65 m² 79,915.00 371,604.75 0.227 - - - 0.70 55,740.71 0.034 0.70 55,740.71 0.034
9 Pek. Pengecatan Cat Dasar Bidang Besi 2.47 m² 41,670.00 103,133.25 0.063 - - - 0.37 15,469.99 0.009 0.37 15,469.99 0.009
10 Pek. Pengecatan Bidang Besi 3X Lapis Cat Penutup 2.47 m² 79,915.00 197,789.62 0.121 - - - 0.37 29,668.44 0.018 0.37 29,668.44 0.018
11 Pek. Plakat Identitas Bahan Granit Uk. 30 X 40 cm 1.00 bh 535,000.00 535,000.00 0.327 - - - 0.15 80,250.00 0.049 0.15 80,250.00 0.049
IV. PEKERJAAN MEKANIKAL ELEKTRIKAL DAN PLUMBING 3,716,382.91 2.27 - 0.00 557,457.44 0.34 557,457.44 0.34
4.1 PEKERJAAN MEKANIKAL ELEKTRIKAL
1 Pek. Pasang KWH Baru 3.300 Watt + Lengkap SLO (Sertifikat Laik Operasi) 3300.00 VA 1,220.00 4,026,000.00 2.463 - - - 1,650.00 2,013,000.00 1.231 1,650.00 2,013,000.00 1.231
2 Pek. Panel Listrik Pompa Lengkap dengan Aksesoris dan Instalasi 1.00 ls 1,690,510.00 1,690,510.00 1.034 - - - 0.50 845,255.00 0.517 0.50 845,255.00 0.517
3 Pas. Kabel NYY 3X2,5 mm2 u/ Pompa Submersible 80.00 m' 17,025.00 1,362,000.00 0.833 - - - 40.00 681,000.00 0.417 40.00 681,000.00 0.417
4 Pas. Kabel NYY 3X0,75 mm2 u/ Elektroda Pompa Submersible 80.00 m' 16,015.00 1,281,200.00 0.784 - - - 40.00 640,600.00 0.392 40.00 640,600.00 0.392
5 Pek. Instalasi Titik Daya / Stop Kontak 1.00 titik 184,091.00 184,091.00 0.113 - - - 0.50 92,045.50 0.056 0.50 92,045.50 0.056
6 Pas. Stop Kontak 1.00 titik 39,671.00 39,671.00 0.024 - - - 0.50 19,835.50 0.012 0.50 19,835.50 0.012
4.2 PEKERJAAN PLUMBING 8,583,472.00 5.25 - 0.00 4,291,736.00 2.63 4,291,736.00 2.63
1 Pek. Instalasi Air Bersih
- Pas. Pipa PVC dia. 1/2" Tipe AW 2.00 m' 23,760.00 47,520.00 0.029 - - - 0.40 9,504.00 0.006 0.40 9,504.00 0.006
- Pas. Pipa PVC dia. 1" Tipe AW (pipa tekan) 70.00 m' 31,680.00 2,217,600.00 1.356 - - - 14.00 443,520.00 0.271 14.00 443,520.00 0.271
- Pas. Pipa PVC dia. 1" Tipe AW (pipa distribusi) 25.00 m' 31,680.00 792,000.00 0.484 - - - 5.00 158,400.00 0.097 5.00 158,400.00 0.097
- Pas. SDL (Sock Drat Luar) 1" (pipa tekan) 19.00 bh 9,000.00 171,000.00 0.105 - - - 3.80 34,200.00 0.021 3.80 34,200.00 0.021
- Pas. SDD (Sock Drat Dalam) 1" (pipa tekan) 19.00 bh 9,000.00 171,000.00 0.105 - - - 3.80 34,200.00 0.021 3.80 34,200.00 0.021
- Pas. Pipa PVC dia. 4" Tipe AW (Cassing) 72.00 m' 197,715.00 14,235,480.00 8.708 - - - 14.40 2,847,096.00 1.742 14.40 2,847,096.00 1.742
- Pas. Hex Bushing 1¼" X 1" 1.00 bh 37,500.00 37,500.00 0.023 - - - 0.20 7,500.00 0.005 0.20 7,500.00 0.005
- Pas. Knee 1" 1.00 bh 9,000.00 9,000.00 0.006 - - - 0.20 1,800.00 0.001 0.20 1,800.00 0.001
- Pas. Elbow 1" 19.00 bh 9,000.00 171,000.00 0.105 - - - 3.80 34,200.00 0.021 3.80 34,200.00 0.021
- Pas. Tee Y 1" 3.00 bh 9,000.00 27,000.00 0.017 - - - 0.60 5,400.00 0.003 0.60 5,400.00 0.003
- Pas. Tee Y 1/2" 1.00 bh 6,000.00 6,000.00 0.004 - - - 0.20 1,200.00 0.001 0.20 1,200.00 0.001
- Pas. Valve Socket 1" 3.00 bh 12,500.00 37,500.00 0.023 - - - 0.60 7,500.00 0.005 0.60 7,500.00 0.005
- Pas. Tuserklep Dia. 1" (Pompa Dorong) 1.00 bh 35,000.00 35,000.00 0.021 - - - 0.20 7,000.00 0.004 0.20 7,000.00 0.004
- Pas. Valve Dia. 1" 5.00 bh 92,000.00 460,000.00 0.281 - - - 1.00 92,000.00 0.056 1.00 92,000.00 0.056
- Pas. Ball Valve Kuningan Dia. 1" 1.00 bh 175,000.00 175,000.00 0.107 - - - 0.20 35,000.00 0.021 0.20 35,000.00 0.021
- Pas. Kran Air Stainless Dia. 1/2" 1.00 bh 20,000.00 20,000.00 0.012 - - - 0.20 4,000.00 0.002 0.20 4,000.00 0.002
- Pas. Otomatis Pompa Dorong 1.00 bh 65,000.00 65,000.00 0.040 - - - 0.20 13,000.00 0.008 0.20 13,000.00 0.008
2 Pek. Pengeboran Sumur Dia. 4" 80.00 m' 435,790.00 34,863,200.00 21.325 80.00 34,863,200.00 21.33 - - - 80.00 34,863,200.00 21.325
3 Loging Test 1.00 titik 3,000,000.00 3,000,000.00 1.835 1.00 3,000,000.00 1.84 - - - 1.00 3,000,000.00 1.835
4 Pek. Pemasangan Unit Pompa Air Submersible 3", 1,5 PK 1 Phase 1.00 unit 5,000,000.00 5,000,000.00 3.058 1.00 5,000,000.00 3.06 - - - 1.00 5,000,000.00 3.058
5 Pek. Pemasangan tambang plastik uk. 10 mm u/ Pompa Air Submersible 70.00 m' 6,015.00 421,050.00 0.258 - - - 14.00 84,210.00 0.052 14.00 84,210.00 0.052
6 Pek. Pemasangan Unit Pompa Dorong 400 Watt 1.00 unit 2,652,250.00 2,652,250.00 1.622 - - - - - - - - -
7 Pas. Tangki Air Kap. 2.000 liter Bulat 2.00 bh 3,500,000.00 7,000,000.00 4.282 - - - - - - - - -
8 Pas. Filter Air Bersih Dia. 16" (bahan FRP) 2.00 unit 4,680,000.00 9,360,000.00 5.725 - - - - - - - - -
9 Uji Laboratorium Air 1.00 ls 1,300,000.00 1,300,000.00 0.795 - - - - - - - - -
82,274,100.00 50.33 42,863,200.00 26.22 3,819,730.00 2.34 46,682,930.00 28.56