JADWAL PELAKSANAAN PEKERJAAN

BIDANG PEMERINTAHAN : DINAS PARIWISATA KABUPATEN LEBAK


KEGIATAN : PENGEMBANGAN OBYEK WISATA UNGGULAN (DAK PENUGASAN 2020)
PEKERJAAN : PERENCANAAN TORIST INFORMATION CENTER (TIC) & SUMBER AIR BERSIH
LOKASI : PANTAI SAWARNA DESA SAWARNA KABUPATEN LEBAK

BOBOT BLN KE- 1 BLN KE- 2 BLN KE- 3 KETERANG


NO. URAIAN PEKERJAAN NILAI
(%) MI M II M III M IV MI M II M III M IV MI M II M III M IV AN

I PEKERJAAN TOURIST INFORMATION CENTER (TIC)


A PEKERJAAN PERSIAPAN 2.575.000,00 0,30 0,30
B PEKERJAAN TANAH & URUGAN 6.498.518,40 0,75 0,75
C PEKERJAAN PONDASI 17.531.325,90 2,02 2,02
D PEKERJAAN STRUKTUR 62.058.724,74 7,14 3,57 3,57
E PEKERJAAN ATAP 54.760.616,84 6,30 3,15 3,15
F PEKERJAAN DINDING 79.231.449,57 9,12 4,56 4,56
G PEKERJAAN KUSEN PINTU & JENDELA 36.098.530,09 4,15 4,15
H PEKERJAAN KUNCI, ALAT PENGGANTUNG DAN KACA 8.383.981,42 0,96 0,96
I PEKERJAAN PLAFOND 33.577.385,80 3,86 3,86
J PEKERJAAN LANTAI 22.990.610,17 2,65 2,65
K PEKERJAAN PENGECATAN 7.707.308,30 0,89 0,89 Pelaksanaan
L PEKERJAAN SANITASI 16.618.107,92 1,91 1,91
Selama 90
M PEKERJAAN ELEKTRIKAL 16.678.570,60 1,92 1,92
(Sembilan
N PEKERJAAN LAIN - LAIN 7.838.227,00 0,90 0,45 0,45
Puluh) Hari
Kalender
II PEKERJAAN SARANA AIR BERSIH 3 PAKET
A PEKERJAAN PERSIAPAN 3.250.000,00 0,37 0,37
B PEKERJAAN TANAH DAN URUGAN 9.523.232,35 1,10 1,10
C PEKERJAAN PONDASI 4.657.498,56 0,54 0,54
D PEKERJAAN STRUKTUR 104.616.672,20 12,04 4,01 4,01 4,01
E PEKERJAAN SANITAIR & INSTALASI 353.470.497,66 40,68 8,14 8,14 8,14 8,14 8,14
F PEKERJAAN ELEKTRIKAL 7.705.861,60 0,89 0,89
G PEKERJAAN FINISHING DAN PENGECATAN 13.155.248,68 1,51 1,51

RENCANA KERJA MINGGUAN 0,30 2,77 3,57 3,95 6,19 15,88 15,30 13,11 10,78 12,00 13,31 2,85
868.927.367,79 100,00
RENCANA KERJA KOMULATIF 0,30 3,06 6,63 10,58 16,77 32,65 47,95 61,06 71,84 83,84 97,15 100,00

Rangkasbitung, 12 Agustus 2020


Dibuat Oleh :
CV. EXTEND

KIKI KRIDA AFFANDI


Direktur