JADWAL PELAKSANAAN
a b f=dxe MING. 1 MING. 2 MING. 3 MING. 4 MING. 5 MING. 6 MING. 7 MING. 8 MING. 9 MING. 10 MING. 11 MING. 12 MING. 13 MING. 14 MING. 15 MING. 16
III. PEKERJAAN STRUKTUR / BETON 212.886.628,99 23,63 4,73 4,73 4,73 4,73 4,73
IV. PEKERJAAN PASANGAN LANTAI,DINDING DAN PLESTERAN 176.579.833,11 19,60 4,90 4,90 4,90 4,90
V. PEKERJAAN KUSEN PINTU & JENDELA 66.087.561,57 7,34 3,67 3,67
VI. PEKERJAAN SANITASI 28.589.525,13 3,17 1,59 1,59
VII. PEKERJAAN ATAP 94.905.281,21 10,53 10,53
VIII. PEKERJAAN PLAFOND 48.857.531,47 5,42 5,42
IX. PEKERJAAN INSTALASI LISTRIK 23.905.601,50 2,65 2,65
X. PEKERJAAN PENGECATAN 25.232.145,11 2,80 2,80
XI. PEKERJAAN GAZEBO 2 UNIT 35.398.092,26 3,93 1,96 1,96
900.901.107,18 100,00 0
Jumlah Harga Pekerjaan (REAL COST) 900.901.107,18
METODE PELAKSANAAN
PPN (11%) 99.099.121,79
100,00
Jumlah Total 1.000.000.228,97
PEKERJAAN
Dibulatkan Rp 1.000.000.000,00
RENCANA 0,94 9,52 9,52 4,73 4,73 4,73 11,21 9,63 4,90 8,57 3,67 10,53 8,08 3,55 1,96 3,74
RENCANA KOMULATIF 0,94 10,46 19,98 24,70 29,43 34,16 45,37 55,00 59,90 68,46 72,13 82,67 90,74 94,29 96,26 100,00
REALISASI
REALISASI KOMULATIF
KEMAJUAN ( + )
DEVIASI
KETERLAMBATAN ( - )