JADWAL WAKTU PELAKSANAAN PEKERJAAN ( TIME SCHEDULE )

PEKERJAAN : PEMBANGUNAN MESS PEGAWAI KEJAKSAAN


LOKASI KEGIATAN : KANTOR KEJAKSAAN NEGERI POLEWALI
TAHUN ANGGARAN : 2023

JADWAL PELAKSANAAN

NO. URAIAN JUMLAH HARGA BOBOT BULAN KE - 1 BULAN KE - 2 BULAN KE - 3 BULAN KE - 4


(RUPIAH) (%) KET.

a b f=dxe MING. 1 MING. 2 MING. 3 MING. 4 MING. 5 MING. 6 MING. 7 MING. 8 MING. 9 MING. 10 MING. 11 MING. 12 MING. 13 MING. 14 MING. 15 MING. 16

I. PEKERJAAN PERSIAPAN 16.941.591,54 1,88 0,94 0,94 100


II. PEKERJAAN TANAH DAN PONDASI 171.517.315,28 19,04 9,52 9,52

III. PEKERJAAN STRUKTUR / BETON 212.886.628,99 23,63 4,73 4,73 4,73 4,73 4,73
IV. PEKERJAAN PASANGAN LANTAI,DINDING DAN PLESTERAN 176.579.833,11 19,60 4,90 4,90 4,90 4,90
V. PEKERJAAN KUSEN PINTU & JENDELA 66.087.561,57 7,34 3,67 3,67
VI. PEKERJAAN SANITASI 28.589.525,13 3,17 1,59 1,59
VII. PEKERJAAN ATAP 94.905.281,21 10,53 10,53
VIII. PEKERJAAN PLAFOND 48.857.531,47 5,42 5,42
IX. PEKERJAAN INSTALASI LISTRIK 23.905.601,50 2,65 2,65
X. PEKERJAAN PENGECATAN 25.232.145,11 2,80 2,80
XI. PEKERJAAN GAZEBO 2 UNIT 35.398.092,26 3,93 1,96 1,96
900.901.107,18 100,00 0
Jumlah Harga Pekerjaan (REAL COST) 900.901.107,18

METODE PELAKSANAAN
PPN (11%) 99.099.121,79
100,00
Jumlah Total 1.000.000.228,97

PEKERJAAN
Dibulatkan Rp 1.000.000.000,00
RENCANA 0,94 9,52 9,52 4,73 4,73 4,73 11,21 9,63 4,90 8,57 3,67 10,53 8,08 3,55 1,96 3,74
RENCANA KOMULATIF 0,94 10,46 19,98 24,70 29,43 34,16 45,37 55,00 59,90 68,46 72,13 82,67 90,74 94,29 96,26 100,00
REALISASI
REALISASI KOMULATIF
KEMAJUAN ( + )
DEVIASI
KETERLAMBATAN ( - )

Polewali, 2023