Anda di halaman 1dari 81

REKAPITULASI TOTAL

NO URAIAN PEKERJAAN JUMLAH

I 2 3

A PEMBANGUNAN HARD SCAPE LANDMARK TB. KOMARA

B PEMBUATAN SUMUR DALAM

C PEMBANGUNAN KAMAR MANDI/WC UMUM

D PEMBANGUNAN LOKET KARCIS, POS JAGA DAN SCULPTURE


JADWAL WAKTU PELAKSANAAN PEKERJAAN
KURVA "S"
Minggu : Ke 1 (satu) Tanggal : 23/09/2018 -- 30/09/2018
JADWAL PELAKSANAAN 100 ( SERATUS) HARI KALENDER
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN BULAN I BULAN II BULAN III BULAN IV KET.
(Rp) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
A PEMBANGUNAN HARD SCAPE LANDMARK TB. KOMARA
A PEMBANGUNAN SCLUPTURE RAJA-RAJA BERBURU RUSA
1 PEKERJAAN PENDAHULUAN 14,652,897.82 0.65 0.65 0.654 -
100.00
2 PEKERJAAN TANAH DAN PONDASI 230,223,496.52 10.28 1.28 1.28 2.57 2.57 2.57 99.44 10.277 -
3 PEKERJAAN BETON 24,758,434.24 1.11 0.37 0.37 0.37 1.105 -
4 PEKERJAAN DINDING 621,632,180.74 27.75 2.31 2.31 2.31 4.62 4.62 4.62 4.62 2.31 27.750 -
5 PEKERJAAN LANTAI BATU ACAK 155,548,544.30 6.94 1.16 1.16 2.31 2.31 6.944 -
6 PEKERJAAN PENGECATAN 3,080,614.50 0.14 0.14 0.138 -
B PEMBANGUNAN SCLUPTURE PELEPAH DAUN TALA - -
1 PEKERJAAN PENDAHULUAN 1,955,340.47 0.09 0.09 89.56 0.087 -
2 PEKERJAAN TANAH DAN PONDASI 8,104,244.61 0.36 0.18 0.18 0.362 -
3 PEKERJAAN BETON 7,895,031.11 0.35 0.35 0.352 -
4 PEKERJAAN DINDING 49,100,890.74 2.19 0.73 0.73 0.73 2.192 -
5 PEKERJAAN LANTAI BATU ACAK 7,285,746.63 0.33 0.16 0.16 0.325 -
6 PEKERJAAN PENGECATAN 469,118.85 0.02 0.02 0.021 -
C PEMBANGUNAN SCLUPTURE PAJONGA DG. ALLE - -
1 PEKERJAAN PENDAHULUAN 2,002,981.47 0.09 0.09 0.089 -
76.55
2 PEKERJAAN TANAH DAN PONDASI 8,104,244.61 0.36 0.18 0.18 0.362 -
3 PEKERJAAN BETON 7,895,031.11 0.35 0.35 0.352 -
4 PEKERJAAN DINDING 51,100,890.74 2.28 0.57 1.14 0.57 2.281 -
5 PEKERJAAN LANTAI BATU ACAK 7,285,746.63 0.33 0.33 0.325 -
6 PEKERJAAN PENGECATAN 469,118.85 0.02 0.02 0.021 -
D PEMBANGUNAN SCLUPTURE RANGGONG DG ROMO - -
1 PEKERJAAN PENDAHULUAN 1,955,340.47 0.09 0.09 0.087 -
64.80
2 PEKERJAAN TANAH DAN PONDASI 8,104,244.61 0.36 0.18 0.09 0.09 0.362 -

MASA PEMELIHARAAN 180 HARI KALENDER


3 PEKERJAAN BETON 7,895,031.11 0.35 0.18 0.18 0.352 -
4 PEKERJAAN DINDING 51,100,890.74 2.28 0.38 0.38 0.76 0.76 2.281 -
5 PEKERJAAN LANTAI BATU ACAK 7,285,746.63 0.33 0.33 0.325 -
6 PEKERJAAN PENGECATAN 469,118.85 0.02 0.02 0.021 -
E PEMBANGUNAN SCLUPTURE RUSA MOSAIK BATU ALAM - -
PEKERJAAN PENDAHULUAN 4,347,433.75 0.19 0.19 0.194 -
53.09
PEKERJAAN TANAH DAN PONDASI 40,303,719.39 1.80 0.30 0.60 0.60 0.30 1.799 -
PEKERJAAN BETON 11,139,018.87 0.50 0.25 0.12 0.12 0.497 -
PEKERJAAN DINDING 50,249,233.67 2.24 0.37 0.37 0.75 0.75 2.243 -
PEKERJAAN LANTAI BATU ACAK 35,508,884.39 1.59 1.59 1.585 -
PEKERJAAN PENGECATAN 958,458.34 0.04 0.04 0.043 -
B PEMBUATAN SUMUR DALAM 43.17
- -
1 PEKERJAAN PENDAHULUAN 2,034,672.75 0.09 0.09 0.091 -
2 PEKERJAAN RESERVOIR BETON 34,102,970.53 1.52 0.76 0.76 1.522 -
3 PEKERJAAN SUMUR DALAM 116,285,213.00 5.19 1.73 1.73 1.73 5.191 -
C PEMBANGUNAN KAMAR MANDI/WC UMUM - -
1 PEKERJAAN PENDAHULUAN 1,512,010.50 0.07 35.34 0.07 0.067 -
2 PEKERJAAN TANAH, PASIR & PONDASI 20,120,232.37 0.90 0.45 0.45 0.898 -
3 PEKERJAAN BETON 52,012,178.46 2.32 1.16 1.16 2.322 -
4 PEKERJAAN PASANGAN DAN PLESTERAN 42,792,546.77 1.91 30.07 0.96 0.96 1.910 -
5 PEKERJAAN LANTAI DAN KERAMIK 14,932,313.99 0.67 0.33 0.33 0.667 -
6 PEKERJAAN KUSEN, ASSESORIES 13,364,422.71 0.60 0.30 0.30 0.597 -
7 PEKERJAAN RANGKA DAN PLAFOND 23,643,876.78 1.06 0.53 0.53 1.055 -
8 PEKERJAAN SANITAIR 14,563,116.80 0.65 0.33 0.33 0.650 -
9 PEKERJAAN INSTALASI LISTRIK 3,297,998.75 0.15 0.15 0.147 -
20.57
10 PEKERJAAN FINISHING 9,049,184.89 0.40 0.40 0.404 -
D PEMBANGUNAN LOKET KARCIS, POS JAGA DAN SCULPTURE - -
1 PEKERJAAN PENDAHULUAN 4,303,442.00 0.19 0.19 0.192 -
2 PEKERJAAN TANAH, PASIR & PONDASI 26,522,855.90 1.18 0.20 0.39 0.39 0.20 1.184 -
3 PEKERJAAN BETON 88,357,550.37 3.94 13.71 1.97 1.97 3.944 -
4 PEKERJAAN PASANGAN DAN PLESTERAN 43,604,414.89 1.95 0.65 0.65 0.65 1.947 -
5 PEKERJAAN LANTAI DAN KERAMIK 14,209,903.47 0.63 0.32 0.32 0.634 -
6 PEKERJAAN KUSEN, ASSESORIES 16,846,367.74 0.75 0.75 0.752 -
7.25
7 PEKERJAAN RANGKA DAN PLAFOND 7,527,276.11 0.34 0.34 0.336 -
8 PEKERJAAN INSTALASI LISTRIK 2,140,665.00 0.10 0.10 0.096 -
3.94
9 PEKERJAAN FINISHING 11,017,112.69 0.49 0.49 0.492 -
10 PEKERJAAN SCULPTURE 257,000,000.00 11.47 1.34 1.43 1.43 2.87 2.87 2.87 11.473 -
0.48
JUMLAH BOBOT PEKERJAAN 2,240,122,001.27 100.00 1.34 2.60 3.31 6.46 6.86 9.50 5.27 7.83 9.92 11.72 11.75 13.01 9.88 0.56 100.00 -
RENCANA KEMAJUAN PEKERJAAN (%) 1.34 3.94 7.25 13.71 20.57 30.07 35.34 43.17 53.09 64.80 76.55 89.56 99.44 100.00

KUMULATIF RENCANA KEMAJUAN PEKERJAAN (%) 0.48

NOTASI
kurva rencana
kurva realisasi
REKAPITULASI TOTAL
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
BOBOT VOLUME
NO URAIAN PEKERJAAN
KONTRAK KONTRAK REALISASI
I 2 3 4 5

A PEMBANGUNAN HARD SCAPE LANDMARK TB. KOMARA 63.40 0.76 0.48

B PEMBUATAN SUMUR DALAM 6.81

C PEMBANGUNAN KAMAR MANDI/WC UMUM 8.72

D PEMBANGUNAN LOKET KARCIS, POS JAGA DAN SCULPTURE 21.06

Realisa Pekerjaan Minggu Ini 100.00 0.48


Rencana Minggu Ini 3.94
Deviasi (3.46)

Diajukan Oleh, Diperiksa Oleh, Dibuat Oleh,


Kontraktor Pelaksana Pengelola Teknis Kegiatan Konsultan Pengawas
PT. MUTIARA REJEKI NUSANTARA CV. CIPTA HIRARCHY KONSULTAN

MUHAMMAD ILYAS, ST Ir. IRLAND LAEBA, M.SP AMIRUDDIN ACHMAD, ST


Site Manager Nip. 19670326199510 1 001 Tim Leader

Menyetujui,
Pejabat Pembuat Komitmen
Balai Besar Konservasi Sumber Daya Alam SulSel

HENDRO PRABOWO, S.P.


Nip. 19680310199703 1 003
###

###

###

###

###
0.48
###

###
REKAPITULASI TOTAL PEMBANGUNAN HARDSCAPE LANDMARK

URAIAN PEKERJAAN BOBOT BOBOT


NO
KONTRAK PRESTASI

I 2 3 4

A PEMBANGUNAN SCLUPTURE RAJA-RAJA BERBURU RUSA 100 0.60

B PEMBANGUNAN SCLUPTURE PELEPAH DAUN TALA 100 0.25

C PEMBANGUNAN SCLUPTURE PAJONGA DG. ALLE 100 0.30

D PEMBANGUNAN SCLUPTURE RANGGONG DG ROMO 100 2.55

E PEMBANGUNAN SCLUPTURE RUSA MOSAIK BATU ALAM 100 3.05

6.75
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Raja-Raja Berburu Rusa
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 1.40 0.60
II PEKERJAAN TANAH DAN PONDASI 21.96 -
III PEKERJAAN BETON 2.36 -
IV PEKERJAAN DINDING 59.30 -
V PEKERJAAN LANTAI BATU ACAK 14.84 -
VI PEKERJAAN PENGECATAN 0.29 -

Rencana Kemajuan pekerjaan 100 0.60


Realisa Minggu Ini
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Raja-Raja Berburu Rusa
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 6,322,498 376.900 M2 0.60 ### 100.00 0.603
2 Pengukuran dan Pemasangan Bouwplank 8,330,400 27.520 m' 0.79 - - -
14,652,898 1.40 0.60
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Keras 5,822,066 61.100 M3 0.56 - - -
2 Pek. Timbunan Tanah Kembali 861,410 15.280 M3 0.08 - - -
3 Pek. Timbunan Pasir Bawah Lantai 10,730,335 65.800 M3 1.02 - - -
4 Pek. Timbunan Tanah 77,126,671 592.940 M3 7.36 - - -
5 Pek. Pasir urug Bawah pondasi 448,456 2.750 M3 0.04 - - -
6 Pek. Pondasi Batu Kosong 3,429,942 8.250 M3 0.33 - - -
7 Pek. Pondasi Batu Kali 1 : 4 131,804,617 162.600 M3 12.57 - - -
230,223,497 21.96 -
III PEKERJAAN BETON
1 Pondasi Poer 1 150/150
- Beton K.250 1,015,393 0.900 M3 0.10 - - -
- Bekisting 570,235 3.150 M2 0.05 - - -
- Pembesian 1,254,172 76.500 Kg 0.12 - - -
2 Kolom 50/50
- Beton K.250 1,342,575 1.190 M3 0.13 - - -
- Bekisting 1,827,104 4.750 M2 0.17 - - -
- Pembesian 2,355,711 143.690 Kg 0.22 - - -
3 Balok 25/40
- Beton K.250 1,658,475 1.470 M3 0.16 - - -
- Bekisting 6,126,944 15.400 M2 0.58 - - -
- Pembesian 4,408,454 268.900 Kg 0.42 - - -
4 Pek. Plat Beton t.15 cm
- Beton K.250 654,364 0.580 M3 0.06 - - -
- Bekisting 2,495,436 4.830 M2 0.24 - - -
- Pembesian 1,049,569 64.020 Kg 0.10 - - -
24,758,434 2.36 -
IV PEKERJAAN DINDING
1 Pek. Pas. Batu 1 : 3 1/2 Batu 14,402,840 118.380 M2 1.37 - - -
2 Pek. Plesteran 1 : 3 3,981,543 60.940 M2 0.38 - - -
3 Pek. Acian Semen 3,247,797 60.940 M2 0.31 - - -
4 Pekerjaan Patung Kuda 290,000,000 2.000 Unit 27.66 - - -
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton + Cat
5 Pekerjaan Patung Orang Berdiri (pengawal) 90,000,000 2.000 Unit 8.58 - - -
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton + Cat
6 Pekerjaan Patung Jonga (rusa) 220,000,000 8.000 Unit 20.99 - - -
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton
621,632,181 59.30 -
V PEKERJAAN LANTAI BATU ACAK
1 Pek. Lantai Kerja K. 100 tebal 10 cm 32,189,195 37.310 M3 3.07 - - -
2 Pek. Batu Alam Acak 123,359,350 373.080 M2 11.77 - - -
155,548,544 14.84 -
VI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding 3,080,615 60.940 M2 0.29 - - -
3,080,615 0.29 -

1,048,355,861 100
65.040
REKAPITULASI TOTAL HARSCAPE
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan :2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : REKAPITULASI TOTAL HARSCAPE
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4

A PEMBANGUNAN SCLUPTURE RAJA-RAJA BERBURU RUSA 73.86 0.60 0.45

B PEMBANGUNAN SCLUPTURE PELEPAH DAUN TALA 5.27 0.25 0.01

C PEMBANGUNAN SCLUPTURE PAJONGA DG. ALLE 5.42 -

D PEMBANGUNAN SCLUPTURE RANGGONG DG ROMO 5.41 -

E PEMBANGUNAN SCLUPTURE RUSA MOSAIK BATU ALAM 10.04 3.05 0.31

Realisa Pekerjaan Minggu Ini 100.00 0.76


Rencana Kemajuan pekerjaan
Deviasi

Diajukan Oleh, Dibuat Oleh,


Kontraktor Pelaksana Konsultan Pengawas
PT. MUTIARA REJEKI NUSANTARA CV. CIPTA HIRARCHY KONSULTAN

MUHAMMAD ILYAS, ST AMIRUDDIN ACHMAD, ST


Site Manager Tim Leader
122.4734

21.36887

32.77951
JADWAL WAKTU PELAKSANAAN PEKERJAAN
KURVA "S" Chart Title
JADWAL PELAKSANAAN 100 ( SERATUS) HARI
Row KALENDER
72
JUMLAH HARGA BOBOT
NO URAIAN PEKERJAAN BULAN I BULAN II BULAN III BULAN IV KET.
(Rp) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14

A PEMBANGUNAN HARD SCAPE LANDMARK TB. KOMARA


A PEMBANGUNAN SCLUPTURE RAJA-RAJA BERBURU RUSA
1 PEKERJAAN PENDAHULUAN 14,652,897.82 0.65 0.65
2 PEKERJAAN TANAH DAN PONDASI 230,223,496.52 10.28 1.28 1.28 2.57 2.57 2.57
3 PEKERJAAN BETON 24,758,434.24 1.11 0.37 0.37 0.37
4 PEKERJAAN DINDING 621,632,180.74 27.75 2.31 2.31 2.31 4.62 4.62 4.62 4.62 2.31
5 PEKERJAAN LANTAI BATU ACAK 155,548,544.30 6.94 1.16 1.16 2.31 2.31
6 PEKERJAAN PENGECATAN 3,080,614.50 0.14 0.14
100.00
99.44
B PEMBANGUNAN SCLUPTURE PELEPAH DAUN TALA
1 PEKERJAAN PENDAHULUAN 1,955,340.47 0.09 0.09
2 PEKERJAAN TANAH DAN PONDASI 8,104,244.61 0.36 0.18 0.18
3 PEKERJAAN BETON 7,895,031.11 0.35 0.35
4 PEKERJAAN DINDING 49,100,890.74 2.19 0.73 0.73 0.73
5 PEKERJAAN LANTAI BATU ACAK 7,285,746.63 0.33 0.16 0.16 89.56
6 PEKERJAAN PENGECATAN 469,118.85 0.02 0.02
C PEMBANGUNAN SCLUPTURE PAJONGA DG. ALLE
1 PEKERJAAN PENDAHULUAN 2,002,981.47 0.09 0.09
2 PEKERJAAN TANAH DAN PONDASI 8,104,244.61 0.36 0.18 0.18
3 PEKERJAAN BETON 7,895,031.11 0.35 0.35
4 PEKERJAAN DINDING 51,100,890.74 2.28 0.57 1.14 0.57
5 PEKERJAAN LANTAI BATU ACAK 7,285,746.63 0.33 0.33 76.55
6 PEKERJAAN PENGECATAN 469,118.85 0.02 0.02
D PEMBANGUNAN SCLUPTURE RANGGONG DG ROMO
1 PEKERJAAN PENDAHULUAN 1,955,340.47 0.09 0.09
2 PEKERJAAN TANAH DAN PONDASI 8,104,244.61 0.36 0.18 0.09 0.09

MASA PEMELIHARAAN 180 HARI KALENDER


3 PEKERJAAN BETON 7,895,031.11 0.35 0.18 0.18
4 PEKERJAAN DINDING 51,100,890.74 2.28 0.38 0.38 0.76 0.76
64.80
5 PEKERJAAN LANTAI BATU ACAK 7,285,746.63 0.33 0.33
6 PEKERJAAN PENGECATAN 469,118.85 0.02 0.02
E PEMBANGUNAN SCLUPTURE RUSA MOSAIK BATU ALAM
PEKERJAAN PENDAHULUAN 4,347,433.75 0.19 0.19
PEKERJAAN TANAH DAN PONDASI 40,303,719.39 1.80 0.30 0.60 0.60 0.30
PEKERJAAN BETON 11,139,018.87 0.50 0.25 0.12 0.12
PEKERJAAN DINDING 50,249,233.67 2.24 0.37 0.37 0.75 0.75 53.09
PEKERJAAN LANTAI BATU ACAK 35,508,884.39 1.59 1.59
PEKERJAAN PENGECATAN 958,458.34 0.04 0.04
B PEMBUATAN SUMUR DALAM
1 PEKERJAAN PENDAHULUAN 2,034,672.75 0.09 0.09
2 PEKERJAAN RESERVOIR BETON 34,102,970.53 1.52 0.76 0.76 43.17
3 PEKERJAAN SUMUR DALAM 116,285,213.00 5.19 1.73 1.73 1.73
C PEMBANGUNAN KAMAR MANDI/WC UMUM
1 PEKERJAAN PENDAHULUAN 1,512,010.50 0.07 0.07
2 PEKERJAAN TANAH, PASIR & PONDASI 20,120,232.37 0.90 0.45 0.45
35.34
3 PEKERJAAN BETON 52,012,178.46 2.32 1.16 1.16
4 PEKERJAAN PASANGAN DAN PLESTERAN 42,792,546.77 1.91 0.96 0.96
5 PEKERJAAN LANTAI DAN KERAMIK 14,932,313.99 0.67 0.33 0.33
30.07
6 PEKERJAAN KUSEN, ASSESORIES 13,364,422.71 0.60 0.30 0.30
7 PEKERJAAN RANGKA DAN PLAFOND 23,643,876.78 1.06 0.53 0.53
8 PEKERJAAN SANITAIR 14,563,116.80 0.65 0.33 0.33
9 PEKERJAAN INSTALASI LISTRIK 3,297,998.75 0.15 0.15
10 PEKERJAAN FINISHING 9,049,184.89 0.40 0.40
20.57
D PEMBANGUNAN LOKET KARCIS, POS JAGA DAN SCULPTURE
1 PEKERJAAN PENDAHULUAN 4,303,442.00 0.19 0.19
2 PEKERJAAN TANAH, PASIR & PONDASI 26,522,855.90 1.18 0.20 0.39 0.39 0.20
3 PEKERJAAN BETON 88,357,550.37 3.94 1.97 1.97
13.71
4 PEKERJAAN PASANGAN DAN PLESTERAN 43,604,414.89 1.95 0.65 0.65 0.65
5 PEKERJAAN LANTAI DAN KERAMIK 14,209,903.47 0.63 0.32 0.32
6 PEKERJAAN KUSEN, ASSESORIES 16,846,367.74 0.75 0.75
7 PEKERJAAN RANGKA DAN PLAFOND 7,527,276.11 0.34 7.25 0.34
8 PEKERJAAN INSTALASI LISTRIK 2,140,665.00 0.10 0.10
3.94
9 PEKERJAAN FINISHING 11,017,112.69 0.49 0.49
10 PEKERJAAN SCULPTURE 257,000,000.00 11.47 1.34 1.43 1.43 2.87 2.87 2.87
JUMLAH BOBOT PEKERJAAN 2,240,122,001.27 100.00 1.34 2.60 3.31 6.46 6.86 9.50 5.27 7.83 9.92 11.72 11.75 13.01 9.88 0.56
RENCANA KEMAJUAN PEKERJAAN (%) 1.34 3.94 7.25 13.71 20.57 30.07 35.34 43.17 53.09 64.80 76.55 89.56 99.44 100.00
KUMULATIF RENCANA KEMAJUAN PEKERJAAN (%) - -
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Pelepah Daun Tala
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 2.61 0.25
II PEKERJAAN TANAH DAN PONDASI 10.83 -
III PEKERJAAN BETON 10.55
IV PEKERJAAN DINDING 65.63
V PEKERJAAN LANTAI BATU ACAK 9.74
VI PEKERJAAN PENGECATAN 0.63

Rencana Kemajuan pekerjaan 100 0.25


Realisa Minggu Ini
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Pelepah Daun Tala
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9
I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 184,525.00 11.000 M2 0.25 11.000 100 0.247
2 Pengukuran dan Pemasangan Bouwplank 1,770,815.47 5.850 m' 2.37 - - -
1,955,340.47 2.61 0.25
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Keras 267,757.88 2.810 M3 0.36 - - -
2 Pek. Timbunan Tanah Kembali 39,462.50 0.700 M3 0.05 - - -
3 Pek. Timbunan Pasir Bawah Lantai 84,799.00 0.520 M3 0.11 - - -
4 Pek. Timbunan Tanah 262,751.50 2.020 M3 0.35 - - -
5 Pek. Pondasi Batu Kali 1 : 4 7,449,473.73 9.190 M3 9.96 - - -
8,104,244.61 10.83 -
III PEKERJAAN BETON
1 Pondasi Poer 1 150/150
- Beton K.250 406,157.23 0.360 M3 0.54 - - -
- Bekisting 229,904.29 1.270 M2 0.31 - - -
- Pembesian 386,743.90 23.590 Kg 0.52 - - -
2 Kolom 50/50
- Beton K.250 801,032.32 0.710 M3 1.07 - - -
- Bekisting 1,369,366.46 3.560 M2 1.83 - - -
- Pembesian 1,413,361.22 86.210 Kg 1.89 - - -
3 Balok 25/40
- Beton K.250 361,028.65 0.320 M3 0.48 - - -
- Bekisting 843,449.42 2.120 M2 1.13 - - -
- Pembesian 1,147,444.06 69.990 Kg 1.53 - - -
4 Pek. Plat Beton t.15 cm
- Beton K.250 191,796.47 0.170 M3 0.26 - - -
- Bekisting 439,155.48 0.850 M2 0.59 - - -
- Pembesian 305,591.62 18.640 Kg 0.41 - - -
7,895,031.11 10.55 -
IV PEKERJAAN DINDING
1 Pek. Plesteran 1 : 3 606,313.14 9.280 M2 0.81 - - -
2 Pek. Acian Semen 494,577.60 9.280 M2 0.66 - - -
3 Pek. Dinding Motif Pohon Pohon Tala 16,000,000.00 1.000 ls 21.39 - - -
4 Pekerjaan Pelepah Daun Tala 32,000,000.00 1.000 Unit 42.77 - - -
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton + Cat
49,100,890.74 65.63 -
V PEKERJAAN LANTAI BATU ACAK
1 Pek. Lantai Kerja K. 100 tebal 10 cm 983,534.76 1.140 M3 1.31 - - -
2 Pek. Batu Alam Acak 6,302,211.87 19.060 M2 8.42 - - -
7,285,746.63 9.74 -
VI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding 469,118.85 9.280 M2 0.63 - - -
469,118.85 0.63 -

74,810,372 100
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Pajonga Dg. Alle
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 2.61 0.30
II PEKERJAAN TANAH DAN PONDASI 10.54 -
III PEKERJAAN BETON 10.27 -
IV PEKERJAAN DINDING 66.49 -
V PEKERJAAN LANTAI BATU ACAK 9.48 -
VI PEKERJAAN PENGECATAN 0.61 -

Kemajuan Pekerjaan Minggu ini 100 0.30


Rencana Kemajuan pekerjaan
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Pajonga Dg. Alle
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 232,166.00 13.840 M2 0.30 13.840 100 0.302
2 Pengukuran dan Pemasangan Bouwplank 1,770,815.47 5.850 m' 2.30 - - -
2,002,981.47 2.61 0.30
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Keras 267,757.88 2.810 M3 0.35 - - -
2 Pek. Timbunan Tanah Kembali 39,462.50 0.700 M3 0.05 - - -
3 Pek. Timbunan Pasir Bawah Lantai 84,799.00 0.520 M3 0.11 - - -
4 Pek. Timbunan Tanah 262,751.50 2.020 M3 0.34 - - -
5 Pek. Pondasi Batu Kali 1 : 4 7,449,473.73 9.190 M3 9.69 - - -
8,104,244.61 10.54 -
III PEKERJAAN BETON
1 Pondasi Poer 1 150/150
- Beton K.250 406,157.23 0.360 M3 0.53 - - -
- Bekisting 229,904.29 1.270 M2 0.30 - - -
- Pembesian 386,743.90 23.590 Kg 0.50 - - -
2 Kolom 50/50
- Beton K.250 801,032.32 0.710 M3 1.04 - - -
- Bekisting 1,369,366.46 3.560 M2 1.78 - - -
- Pembesian 1,413,361.22 86.210 Kg 1.84 - - -
3 Balok 25/40
- Beton K.250 361,028.65 0.320 M3 0.47 - - -
- Bekisting 843,449.42 2.120 M2 1.10 - - -
- Pembesian 1,147,444.06 69.990 Kg 1.49 - - -
4 Pek. Plat Beton t.15 cm
- Beton K.250 191,796.47 0.170 M3 0.25 - - -
- Bekisting 439,155.48 0.850 M2 0.57 - - -
- Pembesian 305,591.62 18.640 Kg 0.40 - - -
7,895,031.11 10.27 -
IV PEKERJAAN DINDING
1 Pek. Plesteran 1 : 3 606,313.14 9.280 M2 0.79 - - -
2 Pek. Acian Semen 494,577.60 9.280 M2 0.64 - - -
3 Pek. Dinding Motif Pohon Pohon Tala 16,000,000.00 1.000 ls 20.82 - - -
4 Pekerjaan Patung Orang 34,000,000.00 1.000 Unit 44.24 - - -
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton + Cat
51,100,890.74 66.49 -
V PEKERJAAN LANTAI BATU ACAK
1 Pek. Lantai Kerja K. 100 tebal 10 cm 983,534.76 1.140 M3 1.28 - - -
2 Pek. Batu Alam Acak 6,302,211.87 19.060 M2 8.20 - - -
7,285,746.63 9.48 -
VI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding 469,118.85 9.280 M2 0.61 - - -
469,118.85 0.61 -
76,858,013 100
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Ranggong Dg Romo
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 2.55 2.55
II PEKERJAAN TANAH DAN PONDASI 10.55 -
III PEKERJAAN BETON 10.28 -
IV PEKERJAAN DINDING 66.53 -
V PEKERJAAN LANTAI BATU ACAK 9.49 -
VI PEKERJAAN PENGECATAN 0.61 -

Rencana Kemajuan pekerjaan 100 2.55


Realisa Minggu Ini
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Ranggong Dg. Romo
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 184,525.00 11.000 M2 0.24 11.000 100 0.240
2 Pengukuran dan Pemasangan Bouwplank 1,770,815.47 5.850 m' 2.31 5.850 100 2.305
1,955,340.47 2.55 2.55
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Keras 267,757.88 2.810 M3 0.35 - - -
2 Pek. Timbunan Tanah Kembali 39,462.50 0.700 M3 0.05 - - -
3 Pek. Timbunan Pasir Bawah Lantai 84,799.00 0.520 M3 0.11 - - -
4 Pek. Timbunan Tanah 262,751.50 2.020 M3 0.34 - - -
5 Pek. Pondasi Batu Kali 1 : 4 7,449,473.73 9.190 M3 9.70 - - -
8,104,244.61 10.55 -
III PEKERJAAN BETON
1 Pondasi Poer 1 150/150
- Beton K.250 406,157.23 0.360 M3 0.53 - - -
- Bekisting 229,904.29 1.270 M2 0.30 - - -
- Pembesian 386,743.90 23.590 Kg 0.50 - - -
2 Kolom 50/50
- Beton K.250 801,032.32 0.710 M3 1.04 - - -
- Bekisting 1,369,366.46 3.560 M2 1.78 - - -
- Pembesian 1,413,361.22 86.210 Kg 1.84 - - -
3 Balok 25/40
- Beton K.250 361,028.65 0.320 M3 0.47 - - -
- Bekisting 843,449.42 2.120 M2 1.10 - - -
- Pembesian 1,147,444.06 69.990 Kg 1.49 - - -
4 Pek. Plat Beton t.15 cm
- Beton K.250 191,796.47 0.170 M3 0.25 - - -
- Bekisting 439,155.48 0.850 M2 0.57 - - -
- Pembesian 305,591.62 18.640 Kg 0.40 - - -
7,895,031.11 10.28 -
IV PEKERJAAN DINDING
1 Pek. Plesteran 1 : 3 606,313.14 9.280 M2 0.79 - - -
2 Pek. Acian Semen 494,577.60 9.280 M2 0.64 - - -
3 Pek. Dinding Motif Pohon Pohon Tala 16,000,000.00 1.000 ls 20.83 - - -
4 Pekerjaan Patung Orang 34,000,000.00 1.000 Unit 44.26 - - -
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton + Cat
51,100,890.74 66.53 -
V PEKERJAAN LANTAI BATU ACAK
1 Pek. Lantai Kerja K. 100 tebal 10 cm 983,534.76 1.140 M3 1.28 - - -
2 Pek. Batu Alam Acak 6,302,211.87 19.060 M2 8.20 - - -
7,285,746.63 9.49 -
VI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding 469,118.85 9.280 M2 0.61 - - -
469,118.85 0.61 -
76,810,372 100
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Rusa Mosaik Batu Alam
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 3.05 3.05
II PEKERJAAN TANAH DAN PONDASI 28.28 -
III PEKERJAAN BETON 7.82 -
IV PEKERJAAN DINDING 35.26 -
V PEKERJAAN LANTAI BATU ACAK 24.92 -
VI PEKERJAAN PENGECATAN 0.67 -

Rencana Kemajuan pekerjaan 100 3.05


Realisa Minggu Ini
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke IV (empat)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Rusa Mosaik Batu Alam
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 563,640.00 33.600 M2 0.40 33.600 100 0.396
2 Pengukuran dan Pemasangan Bouwplank 3,783,793.75 12.500 m' 2.66 12.500 100 2.655
4,347,433.75 3.05 3.05
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Keras 3,903,928.88 40.970 M3 2.74 - - -
2 Pek. Timbunan Tanah Kembali 577,280.00 10.240 M3 0.41 - - -
3 Pek. Timbunan Pasir Bawah Pondasi Garis 190,797.75 1.170 M3 0.13 - - -
4 Pek. Timbunan Pasir Bawah Lantai 1,694,349.25 10.390 M3 1.19 - - -
5 Pek. Timbunan Tanah 2,453,214.50 18.860 M3 1.72 - - -
6 Pek. Pondasi Batu Kosong 1,459,284.26 3.510 M3 1.02 - - -
7 Pek. Pondasi Batu Kali 1 : 4 30,024,864.76 37.040 M3 21.07 - - -
40,303,719.39 28.28 -
III PEKERJAAN BETON
1 Pondasi Poer 1 150/150
- Beton K.250 406,157.23 0.360 M3 0.29 - - -
- Bekisting 229,904.29 1.270 M2 0.16 - - -
- Pembesian 386,743.90 23.590 Kg 0.27 - - -
2 Kolom 50/50
- Beton K.250 801,032.32 0.710 M3 0.56 - - -
- Bekisting 1,096,262.48 2.850 M2 0.77 - - -
- Pembesian 1,413,361.22 86.210 Kg 0.99 - - -
3 Balok 25/40
- Beton K.250 643,082.28 0.570 M3 0.45 - - -
- Bekisting 1,511,843.30 3.800 M2 1.06 - - -
- Pembesian 2,056,841.42 125.460 Kg 1.44 - - -
4 Pek. Plat Beton t.15 cm
- Beton K.250 530,260.83 0.470 M3 0.37 - - -
- Bekisting 1,214,135.73 2.350 M2 0.85 - - -
- Pembesian 849,393.86 51.810 Kg 0.60 - - -
11,139,018.87 7.82 -
IV PEKERJAAN DINDING
1 Pek. Plesteran 1 : 3 1,238,760.47 18.960 M2 0.87 - - -
2 Pek. Acian Semen 1,010,473.20 18.960 M2 0.71 - - -
3 Pek. Dinding Motif Pohon Pohon Tala 16,000,000.00 1.000 ls 11.23 - - -
4 Pekerjaan Patung Rusa Mosaik Batu Alam 32,000,000.00 1.000 Unit 22.46 - - -
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton + Cat
50,249,233.67 35.26 -
V PEKERJAAN LANTAI BATU ACAK
1 Pek. Lantai Kerja K. 100 tebal 10 cm 7,350,628.20 8.520 M3 5.16 - - -
2 Pek. Batu Alam Acak 28,158,256.19 85.160 M2 19.76 - - -
35,508,884.39 24.92 -
VI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding 958,458.34 18.960 M2 0.67 - - -
958,458.34 0.67 -

142,506,748 100
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Pajonga Dg. Alle
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 2.61 2.61
II PEKERJAAN TANAH DAN PONDASI 10.54
III PEKERJAAN BETON 10.27
IV PEKERJAAN DINDING 66.49
V PEKERJAAN LANTAI BATU ACAK 9.48
VI PEKERJAAN PENGECATAN 0.61

Rencana Kemajuan pekerjaan 100


Realisa Minggu Ini
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pekerjaan Sculture Pajonga Dg. Alle
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 232,166.00 13.840 M2 0.30 13.840 100 0.302
2 Pengukuran dan Pemasangan Bouwplank 1,770,815.47 5.850 m' 2.30 5.850 100 2.304
2,002,981.47 2.61 2.61
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah Keras 267,757.88 2.810 M3 0.35 2.810 100 0.348
2 Pek. Timbunan Tanah Kembali 39,462.50 0.700 M3 0.05 0.700 100 0.051
3 Pek. Timbunan Pasir Bawah Lantai 84,799.00 0.520 M3 0.11 0.520 100 0.110
4 Pek. Timbunan Tanah 262,751.50 2.020 M3 0.34 2.020 100 0.342
5 Pek. Pondasi Batu Kali 1 : 4 7,449,473.73 9.190 M3 9.69 9.190 100 9.693
8,104,244.61 10.54
III PEKERJAAN BETON
1 Pondasi Poer 1 150/150
- Beton K.250 406,157.23 0.360 M3 0.53 0.360 100 0.528
- Bekisting 229,904.29 1.270 M2 0.30 1.270 100 0.299
- Pembesian 386,743.90 23.590 Kg 0.50 23.590 100 0.503
2 Kolom 50/50
- Beton K.250 801,032.32 0.710 M3 1.04 0.710 100 1.042
- Bekisting 1,369,366.46 3.560 M2 1.78 3.560 100 1.782
- Pembesian 1,413,361.22 86.210 Kg 1.84 86.210 100 1.839
3 Balok 25/40
- Beton K.250 361,028.65 0.320 M3 0.47 0.320 100 0.470
- Bekisting 843,449.42 2.120 M2 1.10 2.120 100 1.097
- Pembesian 1,147,444.06 69.990 Kg 1.49 69.990 100 1.493
4 Pek. Plat Beton t.15 cm
- Beton K.250 191,796.47 0.170 M3 0.25 0.170 100 0.250
- Bekisting 439,155.48 0.850 M2 0.57 0.850 100 0.571
- Pembesian 305,591.62 18.640 Kg 0.40 18.640 100 0.398
7,895,031.11 10.27
IV PEKERJAAN DINDING
1 Pek. Plesteran 1 : 3 606,313.14 9.280 M2 0.79 9.280 100 0.789
2 Pek. Acian Semen 494,577.60 9.280 M2 0.64 9.280 100 0.643
3 Pek. Dinding Motif Pohon Pohon Tala 16,000,000.00 1.000 ls 20.82 1.000 100 20.818
4 Pekerjaan Patung Orang 34,000,000.00 1.000 Unit 44.24 1.000 100 44.237
- Rangka Utama Besi Pipa Galvanis Ø2"
- Rangka Anyam Besi Beton Diameter 6, 8 & Kawat
- Kawat Ram
- Penutup Plesteran Beton + Cat
51,100,890.74 66.49
V PEKERJAAN LANTAI BATU ACAK
1 Pek. Lantai Kerja K. 100 tebal 10 cm 983,534.76 1.140 M3 1.28 1.140 100 1.280
2 Pek. Batu Alam Acak 6,302,211.87 19.060 M2 8.20 19.060 100 8.200
7,285,746.63 9.48
VI PEKERJAAN PENGECATAN
1 Pek. Cat Dinding 469,118.85 9.280 M2 0.61 9.280 100 0.610
469,118.85 0.61

76,858,013 100
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pembangunan Sumur Dalam
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 1.33
II PEKERJAAN RESERVOIR BETON 22.37
III PEKERJAAN SUMUR DALAM 76.29

Rencana Kemajuan pekerjaan 100


Realisa Minggu Ini
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pembangunan Sumur Dalam
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 67,100.00 4.000 M2 0.04 4.000 100 0.044
2 Pengukuran dan Pemasangan Bouwplank 1,967,572.75 6.500 M' 1.29 6.500 100 1.291
2,034,672.75 1.33
II PEKERJAAN RESERVOIR BETON
1 Pek. Galian Tanah 329,694.75 3.460 M3 0.22 - - -
2 Pek. Pasir Urug 109,260.25 0.670 M3 0.07 - - -
3 Pek. Batu Kosong 552,948.17 1.330 M3 0.36 - - -
4 Pek. Pondasi Batu Kali 1 : 4 2,423,713.44 2.990 M3 1.59 - - -
5 Pek. Pasir Urug 122,306.25 0.750 M3 0.08 - - -
6 Pek. Sloof Beton 20/30
- Beton K.250 665,646.58 0.590 M3 0.44 - - -
- Pembesian 1,421,886.31 86.730 Kg 0.93 - - -
- Bekisting 1,129,118.76 5.880 M2 0.74 - - -
7 Pek. Plat Lantai T. 20 cm
- Beton K.250 1,128,214.53 1.000 M3 0.74 - - -
- Pembesian 1,967,328.00 120.000 Kg 1.29 - - -
- Bekisting 1,593,824.10 8.300 M2 1.05 - - -
8 Pek. Dinding Beton t. 15 cm
- Beton K.250 1,906,682.56 1.690 M3 1.25 - - -
- Pembesian 6,114,127.54 372.940 Kg 4.01 - - -
- Bekisting 4,226,653.42 10.120 M2 2.77 - - -
9 Pek. Plat Beton (atap)
- Beton K.250 981,546.64 0.870 M3 0.64 - - -
- Pembesian 1,711,575.36 104.400 Kg 1.12 - - -
- Bekisting 3,730,238.27 7.220 M2 2.45 - - -
10 Pek. Plesteran Beton 1 : 2 Sisi Dalam 428,890.83 6.250 M2 0.28 - - -
11 Pek. Acian Semen Dalam 333,093.75 6.250 M2 0.22 - - -
12 Pek. Acian Semen Luar 960,375.90 18.020 M2 0.63 - - -
13 Pek. Plesteran Beton 1 : 3 1,177,345.13 18.020 M2 0.77 - - -
14 Pek. Penutup Dari Besi Siku dan Plat Baja 126,000.00 0.360 M2 0.08 - - -
15 Pek. Water Profing 962,500.00 17.500 M2 0.63 - - -
34,102,970.53 22.37
III PEKERJAAN SUMUR DALAM
1 Ijin Pertambangan 5,000,000.00 1.000 ls 3.28 - - -
2 Penyiapan Alat/Perlengkapan Boring 2,700,000.00 1.000 ls 1.77 - - -
3 Pengeboran Lubang Sumur Ø 4"(kedalaman 100 m' 45,000,000.00 100.000 M' 29.52 - - -
4 Pipa Casing (PVC AW) Ø 6" 4,417,118.75 25.000 M' 2.90 - - -
5 Pipa Screen (PVC AW) Ø 4" 5,715,737.50 50.000 M' 3.75 - - -
6 Pipa Isap pvc Ø 2"(dari Pompa Naik Sampai Ke Grou 4,690,867.50 110.000 M' 3.08 - - -
7 Pompa Submersible Pump + Accessories & Panel 31,000,000.00 1.000 Unit 20.34 - - -
8 Panel Pompa Lengkap + Instalasi 2,700,000.00 1.000 Unit 1.77 - - -
9 Kabel NYFGAN 4x16mm Waterproof Cable 900,000.00 1.000 ls 0.59 - - -
10 Kabel NYFGAN 3x2,5mm Waterproof Cable 650,000.00 1.000 ls 0.43 - - -
11 Skun Cabel Set Q =2,5 lt/dtk, H =125, P =>3kw 1,800,000.00 1.000 ls 1.18 - - -
12 Pek. Stop Kran 2" 150,000.00 1.000 Unit 0.10 - - -
13 Pek. Flange Pipe 750,000.00 1.000 Unit 0.49 - - -
14 Pek. Beton K. 100 387,719.75 0.449 M3 0.25 - - -
15 Pemasangan Penutup Sumur Bor +Bak Kontrol 1,800,000.00 1.000 ls 1.18 - - -
16 Pek. Gravel Pack 6,500,000.00 100.000 M' 4.26 - - -
17 Pek. Pipa Supply PVC AW Ǿ2" 170,577.00 4.000 M' 0.11 - - -
18 Pek. Pipa Supply PVC AW Ǿ1" 253,192.50 9.000 M' 0.17 - - -
19 Pek. Pencucian (Penyemprotan ) Lubang Bor 1,000,000.00 1.000 ls 0.66 - - -
20 Test & Commisioning (Pengujian Pompa ( Debit) 700,000.00 1.000 ls 0.46 - - -
116,285,213.00 76.29
152,422,856 100
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pembangunan Kamar Mandi
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 0.77
II PEKERJAAN TANAH DAN PONDASI 10.30
III. PEKERJAAN BETON 26.63
IV. PEKERJAAN PASANGAN DAN PLESTERAN 21.91
V. PEKERJAAN LANTAI DAN KERAMIK 7.65
VI. PEKERJAAN KUSEN, ASSESORIES 6.84
VII. PEKERJAAN RANGKA DAN PLAFOND 12.11
VIII PEKERJAAN SANITAIR 7.46
IX. PEKERJAAN INSTALASI LISTRIK 1.69
X. PEKERJAAN FINISHING 4.63

Realisa Minggu Ini 100


Rencana Kemajuan Pekerjaan
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : Pembangunan Kamar Mandi
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 603,900.00 36.000 M2 0.31 4.000 11 0.034
2 Pengukuran dan Pemasangan Bouwplank 908,110.50 3.000 M' 0.47 6.500 217 1.008
1,512,010.50 0.77 1.04
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah 2,841,031.88 36.570 m3 1.45 - - -
2 Urugan kembali 515,267.50 9.140 m3 0.26 - - -
3 Pek. Pasir Urug
- Bawah pondasi garis 179,382.50 1.100 m3 0.09 - - -
- Bawah Lantai 1,280,138.75 7.850 m3 0.66 - - -
4 pekerjaan Timbunan Tanah 1,360,584.50 10.460 m3 0.70 - - -
5 Pas. batu kosong 3,380,051.57 8.130 m3 1.73 - - -
6 Pondasi batu gunung 1 PC : 4 Psr 9,330,080.82 11.510 m3 4.78 - - -
7 Pondasi Trasram 1 : 3 1,233,694.86 10.140 m2 0.63 - - -
20,120,232.37 10.30
III. PEKERJAAN BETON
1 Sloof - 20/25
- Beton Struktur K.250 2,628,739.87 2.33 m3 1.35 - - -
- Besi Polos 4,507,476.34 274.94 kg 2.31 - - -
- Bekisting 3 x pakai 2,237,114.55 11.65 m2 1.15 - - -
2 Kolom - 12/12
- Beton Struktur K.250 1,545,653.91 1.37 m3 0.79 - - -
- Besi Polos 4,485,507.84 273.60 kg 2.30 - - -
- Bekisting 2 x pakai 2,927,213.14 7.61 m2 1.50 - - -
3 Kolom - 15/30
- Beton Struktur K.250 1,545,653.91 1.37 m3 0.79 - - -
- Besi Polos 2,803,442.40 171.00 kg 1.44 - - -
- Bekisting 2 x pakai 2,788,737.88 7.25 m2 1.43 - - -
4 Kolom Beton K2 - 15/40 -
- Beton Struktur K.250 688,210.87 0.61 m3 0.35 - - -
- Besi Polos 1,322,372.30 80.66 kg 0.68 - - -
- Bekisting 2 x pakai 1,715,554.61 4.46 m2 0.88 - - -
5 Balok Plat 15/25
- Beton Struktur K.250 970,264.50 0.86 m3 0.50 - - -
- Besi Polos 2,872,790.71 175.23 kg 1.47 - - -
- Bekisting 2 x pakai 2,582,707.68 7.47 m2 1.32 - - -
6 Pek. Plat t. 12 cm
- Beton Struktur K.250 1,545,653.91 1.37 m3 0.79 - - -
- Besi Polos 2,248,655.90 137.16 kg 1.15 - - -
- Bekisting 2 x pakai 1,898,134.56 5.49 m2 0.97 - - -
7 Balok Ringbalk 12/20
- Beton Struktur K.250 1,241,035.99 1.10 m3 0.64 - - -
- Besi Polos 2,914,760.38 177.79 kg 1.49 - - -
- Bekisting 2 x pakai 2,537,760.96 7.34 m2 1.30 - - -
8 Pek. Kanopi Beton 12/40
- Beton Struktur K.250 699,493.01 0.62 m3 0.36 - - -
- Besi Polos 1,168,920.72 71.30 kg 0.60 - - -
- Bekisting 2 x pakai 1,220,476.32 3.53 m2 0.62 - - -
9 Pek. Plat Meja Wastafel
- Beton Struktur K.250 203,078.62 0.18 m3 0.10 - - -
- Besi Polos 339,364.08 20.70 kg 0.17 - - -
- Bekisting 2 x pakai 373,403.52 1.08 m2 0.19 - - -
52,012,178.46 26.63
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. batu bata 1 : 5, 1/2 batu 13,966,140.87 118.620 m2 7.15 - - -
2 Plesteran 1 : 3 tebal 15 mm 662,501.65 10.140 m2 0.34 - - -
3 Plesteran 1 : 5, tebal 15 mm 14,980,320.11 237.230 m2 7.67 - - -
4 Acian 13,183,584.15 247.370 m2 6.75 - - -
42,792,546.77 21.91
V. PEKERJAAN LANTAI DAN KERAMIK
1 Pek. Rabat Beton K. 100 T. 6 cm 940,397.27 1.090 m3 0.48 - - -
2 Pek. Lantai Kerja K. 100 T. 6 cm 1,656,479.59 1.920 m3 0.85 - - -
3 Pek. Lantai Keramik 40 x 40 cm 3,325,718.34 22.970 m2 1.70 - - -
4 Pek. Keramik 25x25 cm km&meja wastafel 2,207,014.83 11.110 m2 1.13 - - -
5 Pek. Keramik 25x40 t.1,2 M km&rg.wastafel 6,802,703.95 34.680 m2 3.48 - - -
14,932,313.99 7.65
VI. PEKERJAAN KUSEN, ASSESORIES
1 Pek. Kusen Pintu dan Jendela 2,513,811.30 0.140 M3 1.29 - - -
4 Pek. Kunci Pintu 321,997.50 1.000 Bh 0.16 - - -
5 Pek. Grendel Pintu Panjang 20 Cm 130,000.00 2.000 Bh 0.07 - - -
6 Pek. Engsel Pintu 549,408.75 6.000 Bh 0.28 - - -
7 Kusen Almunium & Pintu Almunium Spanrell 5,700,000.00 6.000 Unit 2.92 - - -
13,364,422.71 6.84
VII. PEKERJAAN RANGKA DAN PLAFOND
8 Rangka Atap Baja Ringan 10,018,256.33 52.500 m2 5.13 - - -
9 Atap Spandek Warna 4,383,225.00 52.500 m2 2.24 - - -
10 Rangka plafond hollow 2x4 + 4x4 6,919,658.35 44.630 m2 3.54 - - -
11 Plafond Klasiboard 120 x 240 x 9 mm 2,322,737.11 44.630 m2 1.19 - - -
23,643,876.78 12.11
VIII PEKERJAAN SANITAIR
1 Pek. Septictank 1,500,000.00 1.000 Unit 0.77 - - -
2 Pipa PVC 3/4 680,271.90 29.400 m' 0.35 - - -
3 Pipa PVC Disposal 4" 3,257,970.38 28.500 m' 1.67 - - -
4 Pipa Air Kotor PVC 3" 893,667.50 10.000 m' 0.46 - - -
5 Pipa Air Kotor PVC 1,5" 294,275.03 9.900 m' 0.15 - - -
6 Pek. Kloset jongkok 2,437,072.00 4.000 Bh 1.25 - - -
7 Pek. Wastafel Lengkap 2,585,550.00 3.000 bh 1.32 - - -
8 Pek. Urinoir Lengkap 1,668,150.00 2.000 bh 0.85 - - -
9 Stop kran PVC dia. 1/2" Toto 374,715.00 9.000 bh 0.19 - - -
10 Kran air Wastafel dia. 1/2" Toto 124,905.00 3.000 bh 0.06 - - -
11 Kran air dia. 1/2" Toto 606,540.00 4.000 bh 0.31 - - -
12 Cermin 60 cm x 100 cm 140,000.00 2.000 Set 0.07 - - -
14,563,116.80 7.46
IX. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Penerangan 1,732,500.00 9.000 titik 0.89 - - -
2 Instalasi Stop Kontak 705,498.75 3.000 titik 0.36 - - -
3 Lampu SL. 23 watt Philips Sumpit 405,000.00 9.000 bh 0.21 - - -
4 Mcb 50,000.00 1.000 bh 0.03 - - -
5 Saklar seri setara panasonic 35,000.00 1.000 bh 0.02 - - -
6 Saklar Tunggal setara panasonic 210,000.00 7.000 bh 0.11 - - -
7 Stop kontak setara panasonic 120,000.00 3.000 bh 0.06 - - -
8 MCB 40,000.00 1.000 bh 0.02 - - -
3,297,998.75 1.69
X. PEKERJAAN FINISHING
1 Cat tembok 5,239,692.39 247.370 m2 2.68 - - -
2 Cat plafond 1,010,997.77 47.730 m2 0.52 - - -
3 Cat Kayu + Lisplank 1,810,494.73 38.200 m2 0.93 - - -
4 Cat Waterproofing dak & kanopi 988,000.00 15.200 m2 0.51 - - -
9,049,184.89 4.63
195,287,882 100
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
195,287,882
REKAPITULASI
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : PEMBANGUNAN GEDUNG LOKET KARCIS, POS JAGA DAN SCULPTURE
NO URAIAN PEKERJAAN BOBOT KONTRAK REALISASI
I 2 3 4
I PEKERJAAN PENDAHULUAN 0.91
II PEKERJAAN TANAH DAN PONDASI 5.62
III. PEKERJAAN BETON 18.74
IV. PEKERJAAN PASANGAN DAN PLESTERAN 9.25
V. PEKERJAAN LANTAI DAN KERAMIK 3.01
VI. PEKERJAAN KUSEN, ASSESORIES 3.57
VII. PEKERJAAN RANGKA DAN PLAFOND 1.60
VIII PEKERJAAN INSTALASI LISTRIK 0.45
IX. PEKERJAAN FINISHING 2.34
X. PEKERJAAN SCULPTURE 54.50

Realisa Minggu Ini 100


Rencana Kemajuan Pekerjaan Minggu Ini
Deviasi
KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN LAPORAN KEMAJUAN
BALAI BESAR KONSERVASI SUMBER DAYA ALAM SULSEL PELAKSANAAN PEKERJAAN
TAHUN ANGGARAN 2018 Minggu Ke I (satu)
Tanggal 23/09/2018 -- 30/09/2018
Pekerjaan :
PEMBANGUNAN SARANA DAN PRASARANA TAMAN BURU KOMARA (RESORT KO'MARA)
Surat Perjanjian Borongan : PK.2197/K.8/TU/Keu/9/2018 Tanggal 21 September 2018
Harga Borongan : 2.464.130.000,-
Kontraktor Pelaksana : PT. Mutiara Rejeki Nusantara
Pekerjaan Dimulai : 23 September 2018
Rencana Penyerahan Pertama : 31 Desember 2018
Konsultan Pengawas : CV. Cipta Hirarchy Konsultan
Sub Pekerjaan : PEMBANGUNAN GEDUNG LOKET KARCIS, POS JAGA DAN SCULPTURE
JUMLAH BOBOT REALISASI BOBOT
NO URAIAN PEKERJAAN VOL. SAT.
HARGA VOL. % PRESTASI
1 2 3 4 5 6 7 8 9

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 671,000.00 40.000 M2 0.14 4.000 10 0.014
2 Pengukuran dan Pemasangan Bouwplank 3,632,442.00 12.000 M' 0.77 6.500 54 0.417
4,303,442.00 0.91 0.43
II PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian Tanah 1,336,225.00 17.200 m3 0.28 - - -
2 Urugan kembali 323,028.75 5.730 m3 0.07 - - -
3 Pek. Pasir Urug
- Bawah pondasi garis 195,690.00 1.200 m3 0.04 - - -
- Bawah Lantai 587,070.00 3.600 m3 0.12 - - -
4 pekerjaan Timbunan Tanah 936,540.00 7.200 m3 0.20 - - -
5 Pas. batu kosong 3,163,861.31 7.610 m3 0.67 - - -
6 Pondasi batu gunung 1 PC : 4 Psr 17,022,736.50 21.000 m3 3.61 - - -
7 Pondasi Trasram 1 : 3 2,957,704.35 24.310 m2 0.63 - - -
26,522,855.90 5.62
III. PEKERJAAN BETON
1 Pekerjaan Pondasi Poer 80x90
- Beton Struktur K.250 2,400,022.87 2.16 m3 0.51 - - -
- Besi Polos 2,124,714.24 129.60 kg 0.45 - - -
- Bekisting 2 x pakai 977,545.80 5.40 m2 0.21 - - -
2 Pekerjaan Stek Kolom 20/30
- Beton Struktur K.250 866,674.92 0.78 m3 0.18 - - -
- Besi Polos 767,257.92 46.80 kg 0.16 - - -
- Bekisting 2 x pakai 688,529.77 1.79 m2 0.15 - - -
3 Sloof Beton - 20/30
- Beton Struktur K.250 2,166,687.31 1.95 m3 0.46 - - -
- Besi Polos 5,735,252.95 349.83 kg 1.22 - - -
- Bekisting 2 x pakai 2,355,161.27 13.01 m2 0.50 - - -
4 Kolom - 12/12 -
- Beton Struktur K.250 444,448.68 0.40 m3 0.09 - - -
- Besi Polos 1,693,869.41 103.32 kg 0.36 - - -
- Bekisting 2 x pakai 1,280,896.16 3.33 m2 0.27 - - -
5 Kolom Beton K1 - 20/30
- Beton Struktur K.250 2,533,357.47 2.28 m3 0.54 - - -
- Besi Polos 7,497,159.12 457.30 kg 1.59 - - -
- Bekisting 2 x pakai 7,304,569.97 18.99 m2 1.55 - - -
6 Balok Beton 20/30 Bawah
- Beton Struktur K.250 411,115.03 0.37 m3 0.09 - - -
- Besi Polos 1,341,717.70 81.84 kg 0.28 - - -
- Bekisting 2 x pakai 887,213.30 2.23 m2 0.19 - - -
7 Balok Beton 20/30
- Beton Struktur K.250 2,333,355.57 2.10 m3 0.49 - - -
- Besi Polos 7,574,212.80 462.00 kg 1.61 - - -
- Bekisting 10,586,881.64 26.61 m2 2.25 - - -
8 Balok Ringbalk 15/20
- Beton Struktur K.250 200,001.91 0.18 m3 0.04 - - -
- Besi Polos 541,179.14 33.01 kg 0.11 - - -
- Bekisting 978,719.61 2.46 m2 0.21 - - -
9 Pek. Plat Beton T. 12 cm
- Beton Struktur K.250 3,766,702.56 3.39 m3 0.80 - - -
- Besi Polos 6,382,339.92 389.30 kg 1.35 - - -
- Bekisting 14,517,963.35 28.10 m2 3.08 - - -
88,357,550.37 18.74
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. batu bata 1 : 5, 1/2 batu 11,644,337.65 98.900 m2 2.47 - - -
2 Pas. batu bata 1 : 3, 1/2 batu 3,508,852.05 28.840 m2 0.74 - - -
3 Plesteran 1 : 3 tebal 15 mm 1,944,383.53 29.760 m2 0.41 - - -
4 Plesteran 1 : 5, tebal 15 mm 12,490,441.00 197.800 m2 2.65 - - -
5 Plesteran 1 : 2 tebal 15 mm (dak Beton) 1,955,742.16 28.500 m2 0.41
6 Acian 12,060,658.50 226.300 m2 2.56
43,604,414.89 9.25
V. PEKERJAAN LANTAI DAN KERAMIK
1 Pek. Rabat Beton T. 6 cm 405,492.40 0.470 m3 0.09 - - -
2 Pek. Lantai Kerja T. 6 cm 2,398,444.41 2.780 m3 0.51 - - -
3 Pek. Lantai Acak 8,365,475.36 25.300 m3 1.77 - - -
4 Lantai Keramik 40 x 40 cm Setara Asia Tile 3,040,491.30 21.000 m2 0.64 - - -
14,209,903.47 3.01
VI. PEKERJAAN KUSEN, ASSESORIES
1 Pek. Kusen Pintu dan Jendela 1 (PJ1) 6,464,086.20 0.360 M3 1.37 - - -
2 Pek. Daun Pintu 2,112,323.40 1.720 M2 0.45 - - -
3 Pek. Daun Jendela 396,256.74 0.510 M2 0.08 - - -
4 Pek. Kaca T. 5 mm 1,745,522.65 7.940 M2 0.37 - - -
5 Pek. Kunci Pintu 643,995.00 2.000 Bh 0.14 - - -
6 Pek. Ensel Pintu 549,408.75 6.000 Bh 0.12 - - -
7 Pek. Ensel Jendela 185,515.00 4.000 Bh 0.04 - - -
8 Grendel Jendela 60,000.00 4.000 Bh 0.01 - - -
9 Hak Angin 139,260.00 4.000 Bh 0.03 - - -
10 Pek. Pintu Besi Hollow 4/6 & 2/4 4,550,000.00 6.500 M2 0.96 - - -
16,846,367.74 3.57
VII. PEKERJAAN RANGKA DAN PLAFOND
1 Rangka plafond hollow 2x4 + 4x4 4,660,652.70 30.060 m2 0.99 - - -
2 Plafond gypsum 120 x 240 x 9 mm 1,564,451.66 30.060 m2 0.33 - - -
3 List plafond lebar 5 cm 1,302,171.75 49.500 m2 0.28 - - -
7,527,276.11 1.60
VIII PEKERJAAN INSTALASI LISTRIK
1 Instalasi Penerangan 770,000.00 4.000 titik 0.16 - - -
2 Instalasi Stop Kontak 940,665.00 4.000 titik 0.20 - - -
3 Lampu SL. 23 watt Philips Sumpit 180,000.00 4.000 bh 0.04 - - -
4 Mcb 40,000.00 1.000 bh 0.01 - - -
5 Saklar seri setara panasonic 70,000.00 2.000 bh 0.01 - - -
6 Saklar Tunggal setara panasonic 60,000.00 2.000 bh 0.01 - - -
7 Stop kontak setara panasonic 80,000.00 2.000 bh 0.02 - - -
2,140,665.00 0.45
IX. PEKERJAAN FINISHING
1 Cat tembok Kw.1 4,456,123.54 88.150 m2 0.95 - - -
2 Cat plafond Metrolite 715,090.82 33.760 m2 0.15 - - -
3 Cat Kayu 326,552.58 6.890 m2 0.07 - - -
4 Cat Finishing Batu Alam Clear Dop 1,518,000.00 25.300 m2 0.32 - - -
5 Cat Anti Bocor Dak Beton 1,920,000.00 32.000 m2 0.41 - - -
6 Pek. Pipa Pembuangan Air Hujan 4" 1,943,350.75 17.000 M' 0.41 - - -
7 Pek. Pemasangan Floor Drain 4" 137,995.00 2.000 Bh 0.03 - - -
11,017,112.69 2.34
X. PEKERJAAN SCULPTURE
1 - Pekerjaan Bonkahan BATU Artifisial 93,000,000.00 1.000 ls 19.72 - - -
- Pekrjaan Batu bentuk Akar dan batang kayu Artifisial -
2 - Pekerjaan Tengkorak dan Tanduk Rusa Artifisia 164,000,000.00 4.000 ls 34.78 - - -
257,000,000.00 54.50
471,529,588 100
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
471,529,588
REKAPITULASI TOTAL

KEMENTRIAN : KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN


UNIT KERJA : BALAI BESAR KONSERVASI SUMBER DAYA ALAM SUL-SEL
PEKERJAAN #REF!
LOKASI : KABUPATEN TAKALAR
TAHUN ANGGARAN : 2018

PEKERJAAN : I. PEMBANGUNAN SUMUR DALAM

NO URAIAN PEKERJAAN JUMLAH


I 2 3

I PEKERJAAN PENDAHULUAN Rp 2,034,672.75

II PEKERJAAN RESERVOIR BETON Rp 34,102,970.53

III PEKERJAAN SUMUR DALAM Rp 116,285,213.00

JUMLAH TOTAL ………………………………. Rp 152,422,856.29


PPN 10 % ………………………………. Rp 15,242,285.63
JUMLAH TOTAL ………………………………. Rp 167,665,141.92
DIBULATKAN ………………………………. Rp 167,665,141.92

Terbilang :
( Seratus Enam Puluh Tujuh Juta Enam Ratus Enam Puluh Lima Ribu Seratus Empat Puluh Satu Koma Sembilan Ratus
Delapan Belas Rupiah )

0
0

0
0
REKAPITULASI TOTAL

KEMENTRIAN : KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN


UNIT KERJA : BALAI BESAR KONSERVASI SUMBER DAYA ALAM SUL-SEL
PEKERJAAN #REF!
LOKASI : KABUPATEN TAKALAR
TAHUN ANGGARAN : 2018

PEKERJAAN : I. PEMBANGUNAN SUMUR DALAM


KODE HARGA SATUAN JUMLAH SATUAN
NO URAIAN PEKERJAAN VOL. SAT.
ANALISA (Rp) (Rp)
1 2 3 4 5 6 7

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi #REF! 4.000 M2 16,775.00 67,100.00
2 Pengukuran dan Pemasangan Bouwplank #REF! 6.500 M' 302,703.50 1,967,572.75
JUMLAH I ….. 2,034,672.75
II PEKERJAAN RESERVOIR BETON
1 Pek. Galian Tanah A.2.3.1.1. 3.460 M3 95,287.50 329,694.75
2 Pek. Pasir Urug A.2.3.1.11 0.670 M3 163,075.00 109,260.25
3 Pek. Batu Kosong A.3.2.1.9 1.330 M3 415,750.50 552,948.17
4 Pondasi Batu Kali 1 :4 A.3.2.1.2 2.990 M3 810,606.50 2,423,713.44
5 Pek. Pasir Urug A.2.3.1.11 0.750 M3 163,075.00 122,306.25
6 Pek. Sloof Beton 20/30
Beton Struktur K.250 A.4.1.1.7 0.590 M3 1,128,214.53 665,646.58
Pembesian Besi Polos A.4.1.1.17 86.730 Kg 16,394.40 1,421,886.31
Bekisting A.4.1.1.21 5.880 M2 192,027.00 1,129,118.76
6 Pek. Plat Lantai T. 20 cm
Beton Struktur K.250 A.4.1.1.7 1.000 M3 1,128,214.53 1,128,214.53
Pembesian Besi Polos A.4.1.1.17 120.000 Kg 16,394.40 1,967,328.00
Bekisting A.4.1.1.24 8.300 M2 192,027.00 1,593,824.10
7 Pek. Dinding Beton t. 15 cm
Beton Struktur K.250 A.4.1.1.7 1.690 M3 1,128,214.53 1,906,682.56
Pembesian Besi Polos A.4.1.1.17 372.940 Kg 16,394.40 6,114,127.54
Bekisting A.4.1.1.25 10.120 M2 417,653.50 4,226,653.42
8 Pek. Plat Beton (atap)
Beton Struktur K.250 A.4.1.1.7 0.870 M3 1,128,214.53 981,546.64
Pembesian Besi Polos A.4.1.1.17 104.400 Kg 16,394.40 1,711,575.36
Bekisting A.4.1.1.24 7.220 M2 516,653.50 3,730,238.27
9 Pek. Plesteran Beton 1 : 2 Sisi dalam A.4.4.2.2 6.250 M2 68,622.53 428,890.83
10 Pek. Acian Semen Dalam A.4.4.2.27 6.250 M2 53,295.00 333,093.75
11 Pek. Acian Semen Luar A.4.4.2.27 18.020 M2 53,295.00 960,375.90
12 Pek. Plesteran Beton 1 : 3 A.4.4.2.3 18.020 M2 65,335.47 1,177,345.13
13 Pek. Penutup Dari Besi Siku dan Plat Baja - 0.360 M2 350,000.00 126,000.00
14 Pek. Water Profing - 17.500 M2 55,000.00 962,500.00
JUMLAH II …. 34,102,970.53
III PEKERJAAN SUMUR DALAM
1 Ijin Pertambangan - 1.000 ls 5,000,000.00 5,000,000.00
2 Penyiapan Alat/Perlengkapan Boring - 1.000 ls 2,700,000.00 2,700,000.00
3 Pengeboran Lubang Sumur Ø 4"(kedalaman 100 m') - 100.000 M' 450,000.00 45,000,000.00
4 Pipa Casing (PVC AW) Ø 6" A.5,1.1.32a 25.000 M' 176,684.75 4,417,118.75
5 Pipa Screen (PVC AW) Ø 4" A.5,1.1.32 50.000 M' 114,314.75 5,715,737.50
6 Pipa Isap pvc Ø 2"(dari Pompa Naik Sampai Ke Ground) A.5,1.1.29 110.000 M' 42,644.25 4,690,867.50
7 Pompa Submersible Pump + Accessories & Panel - 1.000 Unit 31,000,000.00 31,000,000.00
8 Panel Pompa Lengkap + Instalasi - 1.000 Unit 2,700,000.00 2,700,000.00
9 Kabel NYFGAN 4x16mm Waterproof Cable - 1.000 ls 900,000.00 900,000.00
10 Kabel NYFGAN 3x2,5mm Waterproof Cable - 1.000 ls 650,000.00 650,000.00
11 Skun Cabel Set Q =2,5 lt/dtk, H =125, P =>3kw - 1.000 ls 1,800,000.00 1,800,000.00
12 Pek. Stop Kran 2" - 1.000 Unit 150,000.00 150,000.00
13 Pek. Flange Pipe - 1.000 Unit 750,000.00 750,000.00
14 Pek. Beton K. 100 A.4.1.1.4 0.449 M3 862,749.79 387,719.75
15 Pemasangan Penutup Sumur Bor +Bak Kontrol - 1.000 ls 1,800,000.00 1,800,000.00
16 Pek. Gravel Pack - 100.000 M' 65,000.00 6,500,000.00
17 Pek. Pipa Supply PVC AW Ǿ2" A.5,1.1.29 4.000 M' 42,644.25 170,577.00
18 Pek. Pipa Supply PVC AW Ǿ1" A.5,1.1.28 9.000 M' 28,132.50 253,192.50
19 Pek. Pencucian (Penyemprotan ) Lubang Bor - 1.000 ls 1,000,000.00 1,000,000.00
20 Test & Commisioning (Pengujian Pompa ( Debit) - 1.000 ls 700,000.00 700,000.00
JUMLAH III ….. 116,285,213.00
REKAPITULASI TOTAL

KEMENTRIAN : KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN


UNIT KERJA : BALAI BESAR KONSERVASI SUMBER DAYA ALAM SUL-SEL
PEKERJAAN #REF!
LOKASI : KABUPATEN TAKALAR
TAHUN ANGGARAN: 2018

PEKERJAAN : S.PEMBANGUNAN KAMAR MANDI


NO. KETERANGAN JUMLAH HARGA
(1) (2) (3)
I. PEKERJAAN PENDAHULUAN Rp 1,512,010.50
II. PEKERJAAN TANAH, PASIR & PONDASI Rp 20,120,232.37
III. PEKERJAAN BETON Rp 52,012,178.46
IV. PEKERJAAN PASANGAN DAN PLESTERAN Rp 42,792,546.77
V. PEKERJAAN LANTAI DAN KERAMIK Rp 14,932,313.99
VI. PEKERJAAN KUSEN, ASSESORIES Rp 13,364,422.71
VII. PEKERJAAN RANGKA DAN PLAFOND Rp 23,643,876.78
VIII PEKERJAAN SANITAIR Rp 14,563,116.80
IX. PEKERJAAN INSTALASI LISTRIK Rp 3,297,998.75
X. PEKERJAAN FINISHING Rp 9,049,184.89
REAL COST …………………………………………… Rp 195,287,882.02
PPN 10% ……………………………………………… Rp 19,528,788.20
J U M L A H ……………………………………… Rp 214,816,670.23
DIBULATKAN ……………………………………… Rp 214,816,670.23

Terbilang :
( Dua Ratus Empat Belas Juta Delapan Ratus Enam Belas Ribu Enam Ratus Tujuh Puluh Koma Dua Ratus Dua Puluh Tujuh
Rupiah )

0
0

0
0
RENCANA ANGGARAN BIAYA (RAB)

KEMENTRIAN : KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN


UNIT KERJA : BALAI BESAR KONSERVASI SUMBER DAYA ALAM SUL-SEL
PEKERJAAN #REF!
LOKASI : KABUPATEN TAKALAR
TAHUN ANGGARAN: 2018
PEKERJAAN : S.PEMBANGUNAN KAMAR MANDI
KODE
NO. URAIAN PEKERJAAN VOLUME SAT. HARGA JUMLAH JUMLAH SATUAN
ANALISA
1 2 3 4 5 6 7
I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi #REF! 36.00 m2 16,775.00 603,900.00
2 Pengukuran dan Pemasangan Bouwplank #REF! 3.00 m' 302,703.50 908,110.50
SUB TOTAL I. …………… 1,512,010.50
II. PEKERJAAN TANAH, PASIR & PONDASI
1 Galian tanah A.2.3.1.1 36.57 m3 77,687.50 2,841,031.88
2 Urugan kembali A.2.3.1.9. 9.14 m3 56,375.00 515,267.50
3 Pasir urug
- Bawah pondasi garis A.2.3.1.11 1.10 m3 163,075.00 179,382.50
- Bawah Lantai A.2.3.1.11 7.85 m3 163,075.00 1,280,138.75
4 pekerjaan Timbunan Tanah A.2.3.1.11 10.46 m3 130,075.00 1,360,584.50
5 Pas. batu kosong A.3.2.1.9. 8.13 m3 415,750.50 3,380,051.57
6 Pondasi batu gunung 1 PC : 4 Psr A.3.2.1.2. 11.51 m3 810,606.50 9,330,080.82
7 Pondasi Trasram 1 : 3 A.4.4.1.8. 10.14 m2 121,666.16 1,233,694.86
SUB TOTAL II. ……… 20,120,232.37
III. PEKERJAAN BETON
1 Sloof - 20/25
- Beton Struktur K.250 A.4.1.1.7 2.33 m3 1,128,214.53 2,628,739.87
- Besi Polos A.4.1.1.17 274.94 kg 16,394.40 4,507,476.34
- Bekisting 3 x pakai A.4.1.1.21 11.65 m2 192,027.00 2,237,114.55
2 Kolom - 12/12
- Beton Struktur K.250 A.4.1.1.7 1.37 m3 1,128,214.53 1,545,653.91
- Besi Polos A.4.1.1.17 273.60 kg 16,394.40 4,485,507.84
- Bekisting 2 x pakai A.4.1.1.22 7.61 m2 384,653.50 2,927,213.14
3 Kolom - 15/30
- Beton Struktur K.250 A.4.1.1.7 1.37 m3 1,128,214.53 1,545,653.91
- Besi Polos A.4.1.1.17 171.00 kg 16,394.40 2,803,442.40
- Bekisting 2 x pakai A.4.1.1.22 7.25 m2 384,653.50 2,788,737.88
4 Kolom Beton K2 - 15/40
- Beton Struktur K.250 A.4.1.1.7 0.61 m3 1,128,214.53 688,210.87
- Besi Polos A.4.1.1.17 80.66 kg 16,394.40 1,322,372.30
- Bekisting 2 x pakai A.4.1.1.22 4.46 m2 384,653.50 1,715,554.61
5 Balok Plat 15/25
- Beton Struktur K.250 A.4.1.1.7 0.86 m3 1,128,214.53 970,264.50
- Besi Polos A.4.1.1.17 175.23 kg 16,394.40 2,872,790.71
- Bekisting 2 x pakai A.4.1.1.23 7.47 m2 345,744.00 2,582,707.68
6 Pek. Plat t. 12 cm
- Beton Struktur K.250 A.4.1.1.7 1.37 m3 1,128,214.53 1,545,653.91
- Besi Polos A.4.1.1.17 137.16 kg 16,394.40 2,248,655.90
- Bekisting 2 x pakai A.4.1.1.23 5.49 m2 345,744.00 1,898,134.56
7 Balok Ringbalk 12/20
- Beton Struktur K.250 A.4.1.1.7 1.10 m3 1,128,214.53 1,241,035.99
- Besi Polos A.4.1.1.17 177.79 kg 16,394.40 2,914,760.38
- Bekisting 2 x pakai A.4.1.1.23 7.34 m2 345,744.00 2,537,760.96
8 Pek. Kanopi Beton 12/40
- Beton Struktur K.250 A.4.1.1.7 0.62 m3 1,128,214.53 699,493.01
- Besi Polos A.4.1.1.17 71.30 kg 16,394.40 1,168,920.72
- Bekisting 2 x pakai A.4.1.1.23 3.53 m2 345,744.00 1,220,476.32
9 Pek. Plat Meja Wastafel
- Beton Struktur K.250 A.4.1.1.7 0.18 m3 1,128,214.53 203,078.62
- Besi Polos A.4.1.1.17 20.70 kg 16,394.40 339,364.08
- Bekisting 2 x pakai A.4.1.1.23 1.08 m2 345,744.00 373,403.52
SUB TOTAL III. ……… 52,012,178.46
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. batu bata 1 : 5, 1/2 batu A.4.4.1.9 118.62 m2 117,738.50 13,966,140.87
2 Plesteran 1 : 3 tebal 15 mm A.4.4.2.3 10.14 m2 65,335.47 662,501.65
3 Plesteran 1 : 5, tebal 15 mm A.4.4.2.5 237.23 m2 63,146.82 14,980,320.11
4 Acian A.4.4.2.27 247.37 m2 53,295.00 13,183,584.15
SUB TOTAL IV. ……… 42,792,546.77
V. PEKERJAAN LANTAI DAN KERAMIK
1 Pek. Rabat Beton K. 100 T. 6 cm A.4.1.1.4 1.09 m3 862,749.79 940,397.27
2 Pek. Lantai Kerja K. 100 T. 6 cm A.4.1.1.4 1.92 m3 862,749.79 1,656,479.59
3 Pek. Lantai Keramik 40 x 40 cm A.4.4.3.4 22.97 m2 144,785.30 3,325,718.34
4 Pek. Keramik 25x25 cm km&meja wastafel A.4.4.3.4 11.11 m2 198,651.20 2,207,014.83
5 Pek. Keramik 25x40 t.1,2 M km&rg.wastafel A.4.4.3.4a 34.68 m2 196,156.40 6,802,703.95
SUB TOTAL V ……… 14,932,313.99
VI. PEKERJAAN KUSEN, ASSESORIES
1 Pek. Kusen Pintu dan Jendela A.4.6.1.1 0.14 M3 17,955,795.00 2,513,811.30
2 Pek. Daun Pintu Kayu Kls. I A.4.6.1.5 2.94 M2 1,228,095.00 3,610,599.30
3 Pek. Kaca A.4.6.2.17 2.45 M2 219,839.13 538,605.86
4 Pek. Kunci Pintu A.4.6.2.2 1.00 Bh 321,997.50 321,997.50
5 Pek. Grendel Pintu Panjang 20 Cm - 2.00 Bh 65,000.00 130,000.00
6 Pek. Engsel Pintu A.4.6.2.5 6.00 Bh 91,568.13 549,408.75
7 Kusen Almunium & Pintu Almunium Spanrell - 6.00 Unit 950,000.00 5,700,000.00
SUB TOTAL VI ………… 13,364,422.71
VII. PEKERJAAN RANGKA DAN PLAFOND
1 Rangka Atap Baja Ringan A.4.2.1.20 52.50 m2 190,823.93 10,018,256.33
2 Atap Spandek Warna A.4.5.1.7 52.50 m2 83,490.00 4,383,225.00
3 Rangka plafond hollow 2x4 + 4x4 A.4.2.1.20 44.63 m2 155,045.00 6,919,658.35
4 Plafond Klasiboard 120 x 240 x 9 mm A.4.5.1.7 44.63 m2 52,044.30 2,322,737.11
SUB TOTAL VIII……… 23,643,876.78
VIII PEKERJAAN SANITAIR
1 Pek. Septictank - 1.00 Unit 1,500,000.00 1,500,000.00
2 Pipa PVC 3/4 A.5.1.1.26 29.40 m' 23,138.50 680,271.90
3 Pipa PVC Disposal 4" A.5.1.1.26 28.50 m' 114,314.75 3,257,970.38
4 Pipa Air Kotor PVC 3" A.5.1.1.26 10.00 m' 89,366.75 893,667.50
5 Pipa Air Kotor PVC 1,5" A.5.1.1.26 9.90 m' 29,724.75 294,275.03
6 Pek. Kloset jongkok A.5,1.1.2 4.00 Bh 609,268.00 2,437,072.00
7 Pek. Wastafel Lengkap A.5,1.1.5 3.00 bh 861,850.00 2,585,550.00
8 Pek. Urinoir Lengkap A.5,1.1.4 2.00 bh 834,075.00 1,668,150.00
9 Stop kran PVC dia. 1/2" Toto H. Bahan 9.00 bh 41,635.00 374,715.00
10 Kran air Wastafel dia. 1/2" Toto A.5.1.1.19 3.00 bh 41,635.00 124,905.00
11 Kran air dia. 1/2" Toto A.5.1.1.19 4.00 bh 151,635.00 606,540.00
12 Cermin 60 cm x 100 cm - 2.00 Set 70,000.00 140,000.00
SUB TOTAL IX………... 14,563,116.80
IX. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Penerangan dihitung 9.00 titik 192,500.00 1,732,500.00
2 Instalasi Stop Kontak dihitung 3.00 titik 235,166.25 705,498.75
3 Lampu SL. 23 watt Philips Sumpit H. Bahan 9.00 bh 45,000.00 405,000.00
4 Mcb H. Bahan 1.00 bh 50,000.00 50,000.00
5 Saklar seri setara panasonic H. Bahan 1.00 bh 35,000.00 35,000.00
6 Saklar Tunggal setara panasonic H. Bahan 7.00 bh 30,000.00 210,000.00
7 Stop kontak setara panasonic H. Bahan 3.00 bh 40,000.00 120,000.00
8 MCB 1.00 bh 40,000.00 40,000.00
SUB TOTAL X….. ……. 3,297,998.75
X. PEKERJAAN FINISHING
1 Cat tembok A.4.7.1.10 247.37 m2 21,181.60 5,239,692.39
2 Cat plafond A.4.7.1.10a 47.73 m2 21,181.60 1,010,997.77
3 Cat Kayu + Lisplank A.4.7.1.14 38.20 m2 47,395.15 1,810,494.73
4 Cat Waterproofing dak & kanopi - 15.20 m2 65,000.00 988,000.00
SUB TOTAL XI……….. 9,049,184.89
REKAPITULASI TOTAL

KEMENTRIAN : KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN


UNIT KERJA : BALAI BESAR KONSERVASI SUMBER DAYA ALAM SUL-SEL
PEKERJAAN #REF!
LOKASI : KABUPATEN TAKALAR
T . ANGGARAN : 2018

PEKERJAAN : C.PEMBANGUNAN GEDUNG LOKET KARCIS, POS JAGA DAN SCULPTURE


NO. KETERANGAN JUMLAH HARGA
(1) (2) (3)
I. PEKERJAAN PENDAHULUAN Rp 4,303,442.00
II. PEKERJAAN TANAH, PASIR & PONDASI Rp 26,522,855.90
III. PEKERJAAN BETON Rp 88,357,550.37
IV. PEKERJAAN PASANGAN DAN PLESTERAN Rp 43,604,414.89
V. PEKERJAAN LANTAI DAN KERAMIK Rp 14,209,903.47
VI. PEKERJAAN KUSEN, ASSESORIES Rp 16,846,367.74
VII PEKERJAAN RANGKA DAN PLAFOND Rp 7,527,276.11
VIII PEKERJAAN INSTALASI LISTRIK Rp 2,140,665.00
IX PEKERJAAN FINISHING Rp 11,017,112.69
X PEKERJAAN SCULPTURE Rp 257,000,000.00
REAL COST ………………………………………… Rp 471,529,588.18
PPN 10% …………………………………………… Rp 47,152,958.82
J U M L A H …………………………………… Rp 518,682,546.99
DIBULATKAN ………………………………… Rp 518,682,546.99

Terbilang : ###
( Lima Ratus Delapan Belas Juta Enam Ratus Delapan Puluh Dua Ribu Lima Ratus Empat Puluh Enam Koma Sembilan
Ratus Sembilan Puluh Lima Rupiah )

0
0

0
0
RENCANA ANGGARAN BIAYA (RAB)

KEMENTRIAN : KEMENTERIAN LINGKUNGAN HIDUP DAN KEHUTANAN


UNIT KERJA : BALAI BESAR KONSERVASI SUMBER DAYA ALAM SUL-SEL
PEKERJAAN #REF!
LOKASI : KABUPATEN TAKALAR
T . ANGGARAN : 2018

PEKERJAAN : C.PEMBANGUNAN GEDUNG LOKET KARCIS, POS JAGA DAN SCULPTURE


KODE
NO. URAIAN PEKERJAAN VOLUME SAT. HARGA JUMLAH JUMLAH SATUAN
ANALISA
1 2 3 4 5 6 7
I. PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi A.2.2.1.9. 40.00 m2 16,775.00 671,000.00
2 Pengukuran dan Pemasangan Bouwplank A.2.3.1.1. 12.00 m' 302,703.50 3,632,442.00
SUB TOTAL I. …………… 4,303,442.00
II. PEKERJAAN TANAH, PASIR & PONDASI
1 Galian tanah A.2.3.1.1 17.20 m3 77,687.50 1,336,225.00
2 Urugan kembali A.2.3.1.9. 5.73 m3 56,375.00 323,028.75
3 Pasir urug
- Bawah pondasi garis A.2.3.1.11 1.20 m3 163,075.00 195,690.00
- Bawah Lantai A.2.3.1.11 3.60 m3 163,075.00 587,070.00
4 pekerjaan Timbunan Tanah A.2.3.1.11 7.20 m3 130,075.00 936,540.00
5 Pas. batu kosong A.3.2.1.9. 7.61 m3 415,750.50 3,163,861.31
6 Pondasi batu gunung 1 PC : 4 Psr A.3.2.1.2. 21.00 m3 810,606.50 17,022,736.50
7 Pondasi Trasram 1 : 3 A.4.4.1.8. 24.31 m2 121,666.16 2,957,704.35
SUB TOTAL II. ……… 26,522,855.90
III. PEKERJAAN BETON
1 Pekerjaan Pondasi Poer 80x90
- Beton Struktur K.250 A.4.1.1.7 2.16 m3 1,111,121.70 2,400,022.87
- Besi Polos A.4.1.1.17 129.60 kg 16,394.40 2,124,714.24
- Bekisting 2 x pakai A.4.1.1.21 5.40 m2 181,027.00 977,545.80
2 Pekerjaan Stek Kolom 20/30
- Beton Struktur K.250 A.4.1.1.7 0.78 m3 1,111,121.70 866,674.92
- Besi Polos A.4.1.1.17 46.80 kg 16,394.40 767,257.92
- Bekisting 2 x pakai A.4.1.1.21 1.79 m2 384,653.50 688,529.77
3 Sloof Beton - 20/30
- Beton Struktur K.250 A.4.1.1.7 1.95 m3 1,111,121.70 2,166,687.31
- Besi Polos A.4.1.1.17 349.83 kg 16,394.40 5,735,252.95
- Bekisting 2 x pakai A.4.1.1.21 13.01 m2 181,027.00 2,355,161.27
4 Kolom - 12/12
- Beton Struktur K.250 A.4.1.1.7 0.40 m3 1,111,121.70 444,448.68
- Besi Polos A.4.1.1.17 103.32 kg 16,394.40 1,693,869.41
- Bekisting 2 x pakai A.4.1.1.22 3.33 m2 384,653.50 1,280,896.16
5 Kolom Beton K1 - 20/30
- Beton Struktur K.250 A.4.1.1.7 2.28 m3 1,111,121.70 2,533,357.47
- Besi Polos A.4.1.1.17 457.30 kg 16,394.40 7,497,159.12
- Bekisting 2 x pakai A.4.1.1.22 18.99 m2 384,653.50 7,304,569.97
6 Balok Beton 20/30 Bawah
- Beton Struktur K.250 A.4.1.1.7 0.37 m3 1,111,121.70 411,115.03
- Besi Polos A.4.1.1.17 81.84 kg 16,394.40 1,341,717.70
- Bekisting 2 x pakai A.4.1.1.22 2.23 m2 397,853.50 887,213.30
7 Balok Beton 20/30
- Beton Struktur K.250 A.4.1.1.7 2.10 m3 1,111,121.70 2,333,355.57
- Besi Polos A.4.1.1.17 462.00 kg 16,394.40 7,574,212.80
- Bekisting A.4.1.1.23 26.61 m2 397,853.50 10,586,881.64
8 Balok Ringbalk 15/20
- Beton Struktur K.250 A.4.1.1.7 0.18 m3 1,111,121.70 200,001.91
- Besi Polos A.4.1.1.17 33.01 kg 16,394.40 541,179.14
- Bekisting A.4.1.1.23 2.46 m2 397,853.50 978,719.61
9 Pek. Plat Beton T. 12 cm
- Beton Struktur K.250 A.4.1.1.7 3.39 m3 1,111,121.70 3,766,702.56
- Besi Polos A.4.1.1.17 389.30 kg 16,394.40 6,382,339.92
- Bekisting A.4.1.1.23 28.10 m2 516,653.50 14,517,963.35
SUB TOTAL III. ……… 88,357,550.37
IV. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pas. batu bata 1 : 5, 1/2 batu A.4.4.1.9 98.90 m2 117,738.50 11,644,337.65
2 Pas. batu bata 1 : 3, 1/2 batu A.4.4.1.8 28.84 m2 121,666.16 3,508,852.05
3 Plesteran 1 : 3 tebal 15 mm A.4.4.2.3 29.76 m2 65,335.47 1,944,383.53
4 Plesteran 1 : 5, tebal 15 mm A.4.4.2.5 197.80 m2 63,146.82 12,490,441.00
5 Plesteran 1 : 2 tebal 15 mm (dak Beton) A.4.4.2.5 28.50 m2 68,622.53 1,955,742.16
6 Acian A.4.4.2.27 226.30 m2 53,295.00 12,060,658.50
SUB TOTAL IV. ……… 43,604,414.89
V. PEKERJAAN LANTAI DAN KERAMIK
1 Pek. Rabat Beton T. 6 cm A.4.1.1.4 0.47 m3 862,749.79 405,492.40
2 Pek. Lantai Kerja T. 6 cm A.4.1.1.4 2.78 m3 862,749.79 2,398,444.41
3 Pek. Lantai Acak - 25.30 m3 330,651.20 8,365,475.36
4 Lantai Keramik 40 x 40 cm Setara Asia Tile A.4.4.3.4 21.00 m2 144,785.30 3,040,491.30
SUB TOTAL V ……… 14,209,903.47
VI. PEKERJAAN KUSEN, ASSESORIES
1 Pek. Kusen Pintu dan Jendela 1 (PJ1) A.4.6.1.1 0.36 M3 17,955,795.00 6,464,086.20
2 Pek. Daun Pintu A.4.6.1.5 1.72 M2 1,228,095.00 2,112,323.40
3 Pek. Daun Jendela A.4.6.1.6 0.51 M2 776,974.00 396,256.74
4 Pek. Kaca T. 5 mm A.4.6.2.17 7.94 M2 219,839.13 1,745,522.65
5 Pek. Kunci Pintu A.4.6.2.2 2.00 Bh 321,997.50 643,995.00
6 Pek. Ensel Pintu A.4.6.2.5 6.00 Bh 91,568.13 549,408.75
7 Pek. Ensel Jendela A.4.6.2.56 4.00 Bh 46,378.75 185,515.00
8 Grendel Jendela - 4.00 Bh 15,000.00 60,000.00
9 Hak Angin A.4.6.2.16 4.00 Bh 34,815.00 139,260.00
10 Pek. Pintu Besi Hollow 4/6 & 2/4 - 6.50 M2 700,000.00 4,550,000.00
SUB TOTAL VI ………… 16,846,367.74
VII PEKERJAAN RANGKA DAN PLAFOND
1 Rangka plafond hollow 2x4 + 4x4 A.4.2.1.20 30.06 m2 155,045.00 4,660,652.70
2 Plafond gypsum 120 x 240 x 9 mm A.4.5.1.7 30.06 m2 52,044.30 1,564,451.66
3 List plafond lebar 5 cm A.4.5.1.9 49.50 m' 26,306.50 1,302,171.75
SUB TOTAL VII……… 7,527,276.11
VIII PEKERJAAN INSTALASI LISTRIK
1 Instalasi Penerangan dihitung 4.00 titik 192,500.00 770,000.00
2 Instalasi Stop Kontak dihitung 4.00 titik 235,166.25 940,665.00
3 Lampu SL. 23 watt Philips Sumpit H. Bahan 4.00 bh 45,000.00 180,000.00
5 Mcb H. Bahan 1.00 bh 40,000.00 40,000.00
6 Saklar seri setara panasonic H. Bahan 2.00 bh 35,000.00 70,000.00
7 Saklar Tunggal setara panasonic H. Bahan 2.00 bh 30,000.00 60,000.00
8 Stop kontak setara panasonic H. Bahan 2.00 bh 40,000.00 80,000.00
SUB TOTAL VIII ……. 2,140,665.00
IX PEKERJAAN FINISHING
1 Cat tembok Kw.1 A.4.7.1.10 88.15 m2 50,551.60 4,456,123.54
2 Cat plafond Metrolite A.4.7.1.10a 33.76 m2 21,181.60 715,090.82
3 Cat Kayu A.4.7.1.4 6.89 m2 47,395.15 326,552.58
4 Cat Finishing Batu Alam Clear Dop - 25.30 m2 60,000.00 1,518,000.00
5 Cat Anti Bocor Dak Beton - 32.00 m2 60,000.00 1,920,000.00
6 Pek. Pipa Pembuangan Air Hujan 4" A.5,1.1.32 17.00 M' 114,314.75 1,943,350.75
7 Pek. Pemasangan Floor Drain 4" A.5,1.1.14 2.00 Bh 68,997.50 137,995.00
SUB TOTAL IX……… 11,017,112.69
X PEKERJAAN SCULPTURE
1 - Pekerjaan Bonkahan BATU Artifisial - 1.00 ls 93,000,000.00 93,000,000.00
- Pekrjaan Batu bentuk Akar dan batang kayu Artifisial
2 - Pekerjaan Tengkorak dan Tanduk Rusa Artifisial. 4.00 ls 41,000,000.00 164,000,000.00
SUB TOTAL X……… 257,000,000.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2017

KODE KOEFISIEN SAT. URAIAN HARGA SATUAN JUMLAH HARGA


NO
ANALISA (Rp) (Rp)

I A.2.2.1 HARGA SATUAN PERSIAPAN


1 A.2.3.1.1. M' Mengukuran dan Pemasangan Bouwplank
a. Bahan
0.120 m3 Kayu bAlok 5/7 @ Rp 2,000,000.00 Rp 240,000.00
0.020 kg Paku @ Rp 18,000.00 Rp 360.00
0.007 m3 Kayu Papan 3/20 @ Rp 2,000,000.00 Rp 14,000.00
jumlah a……… Rp 254,360.00
b. Tenaga
0.100 Oh Pekerja @ Rp 90,000.00 Rp 9,000.00
0.100 Oh Tukang Kayu @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,200.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah a……… Rp 20,825.00
jumlah a + b …. Rp 275,185.00
b. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 275,185.00 Rp 27,518.50
jumlah total….. Rp 302,703.50
2 A.2.2.1.9. M2 Pembersihan Lapangan dan Peralatan
a. Tenaga
0.100 Oh Pekerja @ Rp 90,000.00 Rp 9,000.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah a……… Rp 15,250.00
b. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 15,250.00 Rp 1,525.00
jumlah total….. Rp 16,775.00
3 A.2.2.1.14. M3 Pembongkaran Dinding Tembok Batu Bata
a. Tenaga
6.667 Oh Pekerja @ Rp 90,000.00 Rp 600,030.00
0.333 Oh Mandor @ Rp 125,000.00 Rp 41,625.00
jumlah a……… Rp 641,655.00
b. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 641,655.00 Rp 64,165.50
jumlah total….. Rp 705,820.50
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
1 A.2.3.1.1. Menggali 1 M3 tanah biasa sedalam 1 m
a. Tenaga
0.750 Oh Pekerja @ Rp 90,000.00 Rp 67,500.00
0.025 Oh Mandor @ Rp 125,000.00 Rp 3,125.00
jumlah a……… Rp 70,625.00
b. Overhead & Profit
0.10 % 10 % x jumlah a @ Rp 70,625.00 Rp 7,062.50
jumlah total….. Rp 77,687.50
2 A.2.3.1.2. Menggali 1 M3 tanah biasa sedalam 2 m
a. Tenaga
0.900 Oh Pekerja @ Rp 90,000.00 Rp 81,000.00
0.045 Oh Mandor @ Rp 125,000.00 Rp 5,625.00
jumlah a……… Rp 86,625.00
b. Overhead & Profit
0.10 % 10 % x jumlah a @ Rp 86,625.00 Rp 8,662.50
jumlah total….. Rp 95,287.50
3 A.2.3.1.9 Mengurug kembali 1 M3 galian Tanah
a. Tenaga
0.500 Oh Pekerja @ Rp 90,000.00 Rp 45,000.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah a……… Rp 51,250.00
b. Overhead & Profit
0.10 % 10 % x jumlah a @ Rp 51,250.00 Rp 5,125.00
jumlah total….. Rp 56,375.00
4 A.2.3.1.11 Mengurug 1 M3 pasir urug
a. Bahan
1.200 M3 Pasir urug @ Rp 100,000.00 Rp 120,000.00
jumlah a……… Rp 120,000.00
b. Tenaga
0.300 Oh Pekerja @ Rp 90,000.00 Rp 27,000.00
0.010 Oh Mandor @ Rp 125,000.00 Rp 1,250.00
jumlah b……… Rp 28,250.00
jumlah a + b …. Rp 148,250.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 148,250.00 Rp 14,825.00
jumlah total….. Rp 163,075.00
5 A.2.3.1.11 Mengurug 1 M3 Tanah Timbunan
a. Bahan
1.200 M3 Tanah timbunan @ Rp 75,000.00 Rp 90,000.00
jumlah a……… Rp 90,000.00
b. Tenaga
0.300 Oh Pekerja @ Rp 90,000.00 Rp 27,000.00
0.010 Oh Mandor @ Rp 125,000.00 Rp 1,250.00
jumlah b……… Rp 28,250.00
jumlah a + b …. Rp 118,250.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 118,250.00 Rp 11,825.00
jumlah total….. Rp 130,075.00

6 SNI.610.1 Pemadatan Tanah 1 m3 Tanah (per 20 cm)


a. Tenaga
0.500 Oh Pekerja @ Rp 90,000.00 Rp 45,000.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah a……… Rp 51,250.00
b. Peralatan
0.021 Jam Stamper @ Rp 50,000.00 Rp 1,050.00
jumlah b……… Rp 1,050.00
jumlah a + b …. Rp 52,300.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 52,300.00 Rp 5,230.00
jumlah total….. Rp 56,480.00
III A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.2 Memasang 1 M3 pondasi batu gunung, campuran 1PC : 4PP
a. Bahan
1.200 M3 Batu gunung @ Rp 180,000.00 Rp 216,000.00
163.000 Kg Semen Portland @ Rp 1,380.00 Rp 224,940.00
0.520 M3 Pasir pasang @ Rp 130,000.00 Rp 67,600.00
jumlah a……… Rp 508,540.00
b. Tenaga
1.500 Oh Pekerja @ Rp 90,000.00 Rp 135,000.00
0.750 Oh Tukang batu @ Rp 100,000.00 Rp 75,000.00
0.075 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 9,000.00
0.075 Oh Mandor @ Rp 125,000.00 Rp 9,375.00
jumlah b……… Rp 228,375.00
jumlah a + b …. Rp 736,915.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 736,915.00 Rp 73,691.50
jumlah total….. Rp 810,606.50
2 A.3.2.1.9 Memasang 1 M3 batu kosong (aanstamping)
a. Bahan
1.200 M3 Batu gunung @ Rp 180,000.00 Rp 216,000.00
0.432 M3 Pasir urug @ Rp 100,000.00 Rp 43,200.00
jumlah a……… Rp 259,200.00
b. Tenaga
0.780 Oh Pekerja @ Rp 90,000.00 Rp 70,200.00
0.390 Oh Tukang batu @ Rp 100,000.00 Rp 39,000.00
0.039 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 4,680.00
0.039 Oh Mandor @ Rp 125,000.00 Rp 4,875.00
jumlah b……… Rp 118,755.00
jumlah a + b …. Rp 377,955.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 377,955.00 Rp 37,795.50
jumlah total….. Rp 415,750.50
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON
1 A.4.1.1.4 Membuat 1 M3 Lantai Kerja beton mutu f'c=7,4 Mpa (K100), slump (12 ± 2) cm, w/c=0,87
a. Bahan
230.000 Kg Semen Portland @ Rp 1,380.00 Rp 317,400.00
893.000 Kg Pasir beton @ Rp 128.57 Rp 114,814.29
1,027.000 Kg split/chipping 2-3 cm @ Rp 203.70 Rp 209,203.70
200.000 liter Air @ Rp 25.00 Rp 5,000.00
jumlah a……… Rp 646,417.99
b. Tenaga
1.200 Oh Pekerja @ Rp 90,000.00 Rp 108,000.00
0.200 Oh Tukang batu @ Rp 100,000.00 Rp 20,000.00
0.020 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 2,400.00
0.060 Oh Mandor @ Rp 125,000.00 Rp 7,500.00
jumlah b……… Rp 137,900.00
jumlah a + b …. Rp 784,317.99
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 784,317.99 Rp 78,431.80
jumlah total….. Rp 862,749.79
2 A.4.1.1.7 Membuat 1 M3 beton mutu f'c=24,0 Mpa (K 225), slump (12 ± 2) cm, w/c=0,58
a. Bahan
371.000 Kg Semen Portland @ Rp 1,380.00 Rp 511,980.00
698.0000 Kg Pasir beton (Kg) @ Rp 128.57 Rp 89,742.86
1,047.000 Kg split/chipping 2-3 cm(Kg) @ Rp 203.70 Rp 213,277.78
215.000 Ltr Air @ Rp 25.00 Rp 5,375.00
jumlah a……… Rp 820,375.63
b. Tenaga
1.650 Oh Pekerja @ Rp 90,000.00 Rp 148,500.00
0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00
0.028 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 3,360.00
0.083 Oh Mandor @ Rp 125,000.00 Rp 10,375.00
jumlah b……… Rp 189,735.00
jumlah a + b …. Rp 1,010,110.63
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 1,010,110.63 Rp 101,011.06
jumlah total….. Rp 1,111,121.70
3 A.4.1.1.8 Membuat 1 M3 beton mutu f'c=19,3 Mpa (K 250), slump (12 ± 2) cm, w/c=0,56
a. Bahan
384.000 Kg Semen Portland @ Rp 1,380.00 Rp 529,920.00
692.000 Kg Pasir beton (Kg) @ Rp 128.57 Rp 88,971.43
1,039.000 Kg split/chipping 1-2 cm(Kg) @ Rp 203.70 Rp 211,648.15
215.000 liter Air @ Rp 25.00 Rp 5,375.00
jumlah a……… Rp 835,914.58
b. Tenaga
1.650 Oh Pekerja @ Rp 90,000.00 Rp 148,500.00
0.275 Oh Tukang batu @ Rp 100,000.00 Rp 27,500.00
0.028 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 3,360.00
0.083 Oh Mandor @ Rp 125,000.00 Rp 10,375.00
jumlah b……… Rp 189,735.00
jumlah a + b …. Rp 1,025,649.58
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 1,025,649.58 Rp 102,564.96
jumlah total….. Rp 1,128,214.53
4 A.4.1.1.17 Menegrjakan Pembesian 10 Kg dengan besi polos atau ulir
a. Bahan
10.500 Kg Besi beton polos @ Rp 12,500.00 Rp 131,250.00
0.150 Kg Kawat beton @ Rp 21,000.00 Rp 3,150.00
jumlah a……… Rp 134,400.00
b. Tenaga
0.070 Oh Pekerja @ Rp 90,000.00 Rp 6,300.00
0.070 Oh Tukang besi @ Rp 100,000.00 Rp 7,000.00
0.007 Oh Kepala Tukang Besi @ Rp 120,000.00 Rp 840.00
0.004 Oh Mandor @ Rp 125,000.00 Rp 500.00
jumlah b……… Rp 14,640.00
jumlah a + b …. Rp 149,040.00
c. Overhead & Profit
0.10 % 15 % x jumlah a + b @ Rp 149,040.00 Rp 14,904.00
jumlah total….. Rp 163,944.00
Untuk Pembesian Polos 1 Kg….. Rp 16,394.40
5 A.4.1.1.20 Memasang 1 M2 bekisting untuk pondasi
a. Bahan
0.040 M3 Kayu klas III (papan) @ Rp 2,000,000.00 Rp 80,000.00
0.300 Kg Paku biasa 2" - 5" @ Rp 18,000.00 Rp 5,400.00
jumlah a……… Rp 85,400.00
b. Tenaga
0.520 Oh Pekerja @ Rp 90,000.00 Rp 46,800.00
0.260 Oh Tukang kayu @ Rp 100,000.00 Rp 26,000.00
0.026 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 3,120.00
0.026 Oh Mandor @ Rp 125,000.00 Rp 3,250.00
jumlah b……… Rp 79,170.00
jumlah a + b …. Rp 164,570.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 164,570.00 Rp 16,457.00
jumlah total….. Rp 181,027.00
6 A.4.1.1.21 Memasang 1 M2 bekisting untuk sloof
a. Bahan
0.045 M3 Kayu klas III (papan) @ Rp 2,000,000.00 Rp 90,000.00
0.300 Kg Paku biasa 2" - 5" @ Rp 18,000.00 Rp 5,400.00
jumlah a……… Rp 95,400.00
b. Tenaga
0.520 Oh Pekerja @ Rp 90,000.00 Rp 46,800.00
0.260 Oh Tukang Kayu @ Rp 100,000.00 Rp 26,000.00
0.026 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 3,120.00
0.026 Oh Mandor @ Rp 125,000.00 Rp 3,250.00
jumlah b……… Rp 79,170.00
jumlah a + b …. Rp 174,570.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 174,570.00 Rp 17,457.00
jumlah total….. Rp 192,027.00
7 A.4.1.1.22 Memasang 1 M2 bekisting untuk kolom
a. Bahan
0.040 M3 Kayu klas III (papan) @ Rp 2,000,000.00 Rp 80,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp 18,000.00 Rp 7,200.00
0.015 M3 Kayu klas II (balok) @ Rp 4,000,000.00 Rp 60,000.00
0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 120,000.00 Rp 42,000.00
2.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 60,000.00
jumlah a……… Rp 249,200.00
b. Tenaga
0.660 Oh Pekerja @ Rp 90,000.00 Rp 59,400.00
0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00
0.033 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 3,960.00
0.033 Oh Mandor @ Rp 125,000.00 Rp 4,125.00
jumlah b……… Rp 100,485.00
jumlah a + b …. Rp 349,685.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 349,685.00 Rp 34,968.50
jumlah total….. Rp 384,653.50
8 A.4.1.1.23 Memasang 1 M2 bekisting untuk balok
a. Bahan
0.040 M3 Kayu klas III (papan) @ Rp 2,000,000.00 Rp 80,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp 18,000.00 Rp 7,200.00
0.018 M3 Kayu klas II (balok) @ Rp 4,000,000.00 Rp 72,000.00
0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 120,000.00 Rp 42,000.00
2.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 60,000.00
jumlah a……… Rp 261,200.00
b. Tenaga
0.660 Oh Pekerja @ Rp 90,000.00 Rp 59,400.00
0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00
0.033 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 3,960.00
0.033 Oh Mandor @ Rp 125,000.00 Rp 4,125.00
jumlah b……… Rp 100,485.00
jumlah a + b …. Rp 361,685.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 361,685.00 Rp 36,168.50
jumlah total….. Rp 397,853.50
9 A.4.1.1.24 Memasang 1 M2 bekisting untuk lantai
a. Bahan
0.040 M3 Kayu klas III (papan) @ Rp 2,000,000.00 Rp 80,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp 18,000.00 Rp 7,200.00
0.015 M3 Kayu klas II (balok) @ Rp 4,000,000.00 Rp 60,000.00
0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 120,000.00 Rp 42,000.00
6.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 180,000.00
jumlah a……… Rp 369,200.00
b. Tenaga
0.660 Oh Pekerja @ Rp 90,000.00 Rp 59,400.00
0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00
0.033 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 3,960.00
0.033 Oh Mandor @ Rp 125,000.00 Rp 4,125.00
jumlah b……… Rp 100,485.00
jumlah a + b …. Rp 469,685.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 469,685.00 Rp 46,968.50
jumlah total….. Rp 516,653.50
10 A.4.1.1.25 Memasang 1 M2 bekisting untuk dinding
a. Bahan
0.030 M3 Kayu klas III (papan) @ Rp 2,000,000.00 Rp 60,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp 18,000.00 Rp 7,200.00
0.020 M3 Kayu klas II (balok) @ Rp 4,000,000.00 Rp 80,000.00
0.350 Lbr Multipleks 1.22 x 2.44 x 9 mm @ Rp 120,000.00 Rp 42,000.00
3.000 Btg Dolken kayu Ø8-10/400 cm @ Rp 30,000.00 Rp 90,000.00
jumlah a……… Rp 279,200.00
b. Tenaga
0.660 Oh Pekerja @ Rp 90,000.00 Rp 59,400.00
0.330 Oh Tukang kayu @ Rp 100,000.00 Rp 33,000.00
0.033 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 3,960.00
0.033 Oh Mandor @ Rp 125,000.00 Rp 4,125.00
jumlah b……… Rp 100,485.00
jumlah a + b …. Rp 379,685.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 379,685.00 Rp 37,968.50
jumlah total….. Rp 417,653.50
V A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 A.4.4.1.2 Memasang1 M2 dinding bata merah uk. (5x11x22) cm tebal 1 bt. camp. 1PC : 4PP
a. Bahan
140.000 Bh Batu merah @ Rp 650.00 Rp 91,000.00
26.500 Kg Semen Portland @ Rp 1,380.00 Rp 36,570.00
0.093 M3 Pasir pasang @ Rp 130,000.00 Rp 12,090.00
jumlah a……… Rp 139,660.00
b. Tenaga
0.600 Oh Pekerja @ Rp 90,000.00 Rp 54,000.00
0.200 Oh Tukang batu @ Rp 100,000.00 Rp 20,000.00
0.020 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 2,400.00
0.030 Oh Mandor @ Rp 125,000.00 Rp 3,750.00
jumlah b……… Rp 80,150.00
jumlah a + b …. Rp 219,810.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 219,810.00 Rp 21,981.00
jumlah total….. Rp 241,791.00
2 A.4.4.1.8 Memasang1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 3PP
a. Bahan
70.000 Bh Batu merah @ Rp 650.00 Rp 45,500.00
14.370 Kg Semen Portland @ Rp 1,380.00 Rp 19,830.60
0.040 M3 Pasir pasang @ Rp 130,000.00 Rp 5,200.00
jumlah a……… Rp 70,530.60
b. Tenaga
0.300 Oh Pekerja @ Rp 90,000.00 Rp 27,000.00
0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,200.00
0.015 Oh Mandor @ Rp 125,000.00 Rp 1,875.00
jumlah b……… Rp 40,075.00
jumlah a + b …. Rp 110,605.60
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 110,605.60 Rp 11,060.56
jumlah total….. Rp 121,666.16
3 A.4.4.1.9 Memasang 1 M2 dinding bata merah uk. (5x11x22) cm tebal 1/2 bt. camp. 1PC : 4PP
a. Bahan
70.000 Bh Batu merah @ Rp 650.00 Rp 45,500.00
11.500 Kg Semen Portland @ Rp 1,380.00 Rp 15,870.00
0.043 M3 Pasir pasang @ Rp 130,000.00 Rp 5,590.00
jumlah a……… Rp 66,960.00
b. Tenaga
0.300 Oh Pekerja @ Rp 90,000.00 Rp 27,000.00
0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,200.00
0.015 Oh Mandor @ Rp 125,000.00 Rp 1,875.00
jumlah b……… Rp 40,075.00
jumlah a + b …. Rp 107,035.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 107,035.00 Rp 10,703.50
jumlah total….. Rp 117,738.50
VI A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.2 Memasang 1 M2 plesteran 1PC : 2PP, tebal 15 mm
a. Bahan
10.224 Kg Semen Portland @ Rp 1,380.00 Rp 14,109.12
0.020 M3 Pasir pasang @ Rp 130,000.00 Rp 2,600.00
jumlah a……… Rp 16,709.12
b. Tenaga
0.300 Oh Pekerja @ Rp 90,000.00 Rp 27,000.00
0.150 Oh Tukang batu @ Rp 100,000.00 Rp 15,000.00
0.015 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,800.00
0.015 Oh Mandor @ Rp 125,000.00 Rp 1,875.00
jumlah b……… Rp 45,675.00
jumlah a + b …. Rp 62,384.12
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 62,384.12 Rp 6,238.41
jumlah total….. Rp 68,622.53
2 A.4.4.2.3 Memasang 1 M2 plesteran 1PC : 3PP, tebal 15 mm
a. Bahan
7.776 Kg Semen Portland @ Rp 1,380.00 Rp 10,730.88
0.023 M3 Pasir pasang @ Rp 130,000.00 Rp 2,990.00
jumlah a……… Rp 13,720.88
b. Tenaga
0.300 Oh Pekerja @ Rp 90,000.00 Rp 27,000.00
0.150 Oh Tukang batu @ Rp 100,000.00 Rp 15,000.00
0.015 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,800.00
0.015 Oh Mandor @ Rp 125,000.00 Rp 1,875.00
jumlah b……… Rp 45,675.00
jumlah a + b …. Rp 59,395.88
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 59,395.88 Rp 5,939.59
jumlah total….. Rp 65,335.47
3 A.4.4.2.4 Memasang 1 M2 plesteran 1PC : 4PP, tebal 15 mm
a. Bahan
6.240 Kg Semen Portland @ Rp 1,380.00 Rp 8,611.20
0.024 M3 Pasir pasang @ Rp 130,000.00 Rp 3,120.00
jumlah a……… Rp 11,731.20
b. Tenaga
0.300 Oh Pekerja @ Rp 90,000.00 Rp 27,000.00
0.150 Oh Tukang batu @ Rp 100,000.00 Rp 15,000.00
0.015 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,800.00
0.015 Oh Mandor @ Rp 125,000.00 Rp 1,875.00
jumlah b……… Rp 45,675.00
jumlah a + b …. Rp 57,406.20
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 57,406.20 Rp 5,740.62
jumlah total….. Rp 63,146.82
4 A.4.4.2.27 Memasang 1 M2 acian
a. Bahan
3.250 Kg Semen Portland @ Rp 1,380.00 Rp 4,485.00
jumlah a……… Rp 4,485.00
b. Tenaga
0.200 Oh Pekerja @ Rp 90,000.00 Rp 18,000.00
0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,200.00
0.010 Oh Mandor @ Rp 125,000.00 Rp 1,250.00
jumlah b……… Rp 30,450.00
jumlah a + b …. Rp 48,450.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 48,450.00 Rp 4,845.00
jumlah total….. Rp 53,295.00
VII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING
1 A.4.4.3.28 Memasang 1 M2 lantai Keramik (40 x 40) cm
a. Bahan
6.630 Bh Keramik @ Rp 11,000.00 Rp 72,930.00
9.800 Kg Semen Portland @ Rp 1,380.00 Rp 13,524.00
0.045 M3 Pasir pasang @ Rp 130,000.00 Rp 5,850.00
0.063 Kg Semen warna @ Rp 18,000.00 Rp 1,134.00
jumlah a……… Rp 93,438.00
b. Tenaga
0.250 Oh Pekerja @ Rp 90,000.00 Rp 22,500.00
0.125 Oh Tukang batu @ Rp 100,000.00 Rp 12,500.00
0.013 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,560.00
0.013 Oh Mandor @ Rp 125,000.00 Rp 1,625.00
jumlah b……… Rp 38,185.00
jumlah a + b …. Rp 131,623.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 131,623.00 Rp 13,162.30
jumlah total….. Rp 144,785.30
2 A.4.4.3.9 Memasang 1 M2 lantai Granito (60x60) cm
a. Bahan
2.770 Bh Granit 60 x 60 Cm @ Rp 80,000.00 Rp 221,600.00
9.600 Kg Semen Portland @ Rp 1,380.00 Rp 13,248.00
0.045 M3 Pasir pasang @ Rp 130,000.00 Rp 5,850.00
1.500 Kg Semen warna @ Rp 18,000.00 Rp 27,000.00
jumlah a……… Rp 267,698.00
b. Tenaga
0.240 Oh Pekerja @ Rp 90,000.00 Rp 21,600.00
0.120 Oh Tukang batu @ Rp 100,000.00 Rp 12,000.00
0.012 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,440.00
0.012 Oh Mandor @ Rp 125,000.00 Rp 1,500.00
jumlah b……… Rp 36,540.00
jumlah a + b …. Rp 304,238.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 304,238.00 Rp 30,423.80
jumlah total….. Rp 334,661.80
3 A.4.4.3.9a Memasang 1 M2 lantai Niro Granito (30x60) cm
a. Bahan
5.550 Bh Niro Granito 30 x 60 Cm @ Rp 40,000.00 Rp 222,000.00
9.600 Kg Semen Portland @ Rp 1,380.00 Rp 13,248.00
0.045 M3 Pasir pasang @ Rp 130,000.00 Rp 5,850.00
1.500 Kg Semen warna @ Rp 18,000.00 Rp 27,000.00
jumlah a……… Rp 268,098.00
b. Tenaga
0.240 Oh Pekerja @ Rp 90,000.00 Rp 21,600.00
0.120 Oh Tukang batu @ Rp 100,000.00 Rp 12,000.00
0.012 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,440.00
0.013 Oh Mandor @ Rp 125,000.00 Rp 1,625.00
jumlah b……… Rp 36,665.00
jumlah a + b …. Rp 304,763.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 304,763.00 Rp 30,476.30
jumlah total….. Rp 335,239.30
4 A.4.4.3.6a Memasang 1 M2 lantai keramik ukuran (25x25) cm
a. Bahan
20.000 Bh Tegel keramik 25 x 25 cm (kasar) @ Rp 4,500.00 Rp 90,000.00
10.400 Kg Semen Portland @ Rp 1,380.00 Rp 14,352.00
0.045 M3 Pasir pasang @ Rp 130,000.00 Rp 5,850.00
1.620 Kg Semen warna @ Rp 18,000.00 Rp 29,160.00
jumlah a……… Rp 139,362.00
b. Tenaga
0.270 Oh Pekerja @ Rp 90,000.00 Rp 24,300.00
0.135 Oh Tukang batu @ Rp 100,000.00 Rp 13,500.00
0.014 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,680.00
0.014 Oh Mandor @ Rp 125,000.00 Rp 1,750.00
jumlah b……… Rp 41,230.00
jumlah a + b …. Rp 180,592.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 180,592.00 Rp 18,059.20
jumlah total….. Rp 198,651.20
5 A.4.4.3.6b Memasang 1 M2 dinding keramik ukuran (25/40) cm
a. Bahan
10.000 Bh Tegel keramik 25 x 40 cm ( warna ) @ Rp 8,700.00 Rp 87,000.00
9.300 Kg Semen Portland @ Rp 1,380.00 Rp 12,834.00
0.018 M3 Pasir pasang @ Rp 130,000.00 Rp 2,340.00
1.940 Kg Semen warna @ Rp 18,000.00 Rp 34,920.00
jumlah a……… Rp 137,094.00
b. Tenaga
0.270 Oh Pekerja @ Rp 90,000.00 Rp 24,300.00
0.135 Oh Tukang batu @ Rp 100,000.00 Rp 13,500.00
0.014 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,680.00
0.014 Oh Mandor @ Rp 125,000.00 Rp 1,750.00
jumlah b……… Rp 41,230.00
jumlah a + b …. Rp 178,324.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 178,324.00 Rp 17,832.40
jumlah total….. Rp 196,156.40
6 Memasang 1 M2 Batu Acak
a. Bahan
1.050 M2 Batu Acak @ Rp 200,000.00 Rp 210,000.00
10.400 Kg Semen Portland @ Rp 1,380.00 Rp 14,352.00
0.045 M3 Pasir pasang @ Rp 130,000.00 Rp 5,850.00
1.620 Kg Semen warna @ Rp 18,000.00 Rp 29,160.00
jumlah a……… Rp 259,362.00
b. Tenaga
0.270 Oh Pekerja @ Rp 90,000.00 Rp 24,300.00
0.135 Oh Tukang batu @ Rp 100,000.00 Rp 13,500.00
0.014 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,680.00
0.014 Oh Mandor @ Rp 125,000.00 Rp 1,750.00
jumlah b……… Rp 41,230.00
jumlah a + b …. Rp 300,592.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 300,592.00 Rp 30,059.20
jumlah total….. Rp 330,651.20
VIII A.4.5.1 PEKERJAAN LANGIT - LANGIT/PLAFOND
1 A.4.5.1.21 Memasang 1 M2 Rangka Hollow Almunium 1 x 40 x 40 Modul 60/60 cm
a. Bahan
4.000 M Hollow Almunium 4 x 4 @ Rp 8,500.00 Rp 34,000.00
(100 x rangka ) ls (Assesoris, Perkauatan, dll) @ Rp 34,000.00 Rp 34,000.00
jumlah a……… Rp 68,000.00
b. Tenaga
0.350 Oh Pekerja @ Rp 90,000.00 Rp 31,500.00
0.350 Oh Tukang Besi @ Rp 100,000.00 Rp 35,000.00
0.035 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 4,200.00
0.018 Oh Mandor @ Rp 125,000.00 Rp 2,250.00
jumlah b……… Rp 72,950.00
jumlah a + b …. Rp 140,950.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 140,950.00 Rp 14,095.00
jumlah total….. Rp 155,045.00
2 A.4.5.1.7 Memasang 1 M2 langit-langit Gypsumboard board ukuran (120x240) mm, tebal 9 mm
a. Bahan
0.364 Lbr Gypsumboard ex jayaboard t. 9 mm @ Rp 70,000.00 Rp 25,480.00
0.110 Kg Srews/sekrup Gypsum @ Rp 70,000.00 Rp 7,700.00
jumlah a……… Rp 33,180.00
b. Tenaga
0.100 Oh Pekerja @ Rp 90,000.00 Rp 9,000.00
0.050 Oh Tukang Kayu @ Rp 100,000.00 Rp 5,000.00
0.005 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 600.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah b……… Rp 15,225.00
jumlah a + b …. Rp 48,405.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 48,405.00 Rp 4,840.50
jumlah total….. Rp 53,245.50
3 A.4.5.1.7a Memasang 1 M2 langit-langit Kalsiboar ukuran (120x240) mm, tebal 4 mm
a. Bahan
0.364 Lbr Calsyboard 4 mm @ Rp 67,000.00 Rp 24,388.00
0.110 Bh Srews/sekrup @ Rp 70,000.00 Rp 7,700.00
jumlah a……… Rp 32,088.00
b. Tenaga
0.100 Oh Pekerja @ Rp 90,000.00 Rp 9,000.00
0.050 Oh Tukang Kayu @ Rp 100,000.00 Rp 5,000.00
0.005 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 600.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah b……… Rp 15,225.00
jumlah a + b …. Rp 47,313.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 47,313.00 Rp 4,731.30
jumlah total….. Rp 52,044.30
4 A.4.4.5.1.9 Memasang 1 M' list Plafond Gypsum Kecil
a. Bahan
1.050 M' List Gypsum l. 10 cm @ Rp 12,000.00 Rp 12,600.00
6.000 Bh Srews/sekrup @ Rp 140.00 Rp 840.00
jumlah a……… Rp 13,440.00
b. Tenaga
0.050 Oh Pekerja @ Rp 90,000.00 Rp 4,500.00
0.050 Oh Tukang kayu @ Rp 100,000.00 Rp 5,000.00
0.005 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 600.00
0.003 Oh Mandor @ Rp 125,000.00 Rp 375.00
jumlah b……… Rp 10,475.00
jumlah a + b …. Rp 23,915.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 23,915.00 Rp 2,391.50
jumlah total….. Rp 26,306.50
5 A.4.4.5.1.9 Memasang 1 M' list Plafond Gypsum Besar
a. Bahan
1.050 M' List Gypsum 25 cm @ Rp 25,000.00 Rp 26,250.00
6.000 Bh Srews/sekrup @ Rp 140.00 Rp 840.00
jumlah a……… Rp 27,090.00
b. Tenaga
0.050 Oh Pekerja @ Rp 90,000.00 Rp 4,500.00
0.050 Oh Tukang kayu @ Rp 100,000.00 Rp 5,000.00
0.005 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 600.00
0.003 Oh Mandor @ Rp 125,000.00 Rp 375.00
jumlah b……… Rp 10,475.00
jumlah a + b …. Rp 37,565.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 37,565.00 Rp 3,756.50
jumlah total….. Rp 41,321.50
6 A.4.4.5.1.9a Memasang 1 M2 Dinding Gypsum ukuran (120x240) mm, tebal 9 mm + rangka Metal Stud
a. Bahan
2.200 M' Metal Stud @ Rp 18,500.00 Rp 40,700.00
2.200 M' Metal Track @ Rp 18,500.00 Rp 40,700.00
0.780 Lbr Gipsumboard t. 9. mm @ Rp 70,000.00 Rp 54,600.00
0.600 Kg UB 888/400 Compoud @ Rp 6,500.00 Rp 3,900.00
0.100 Roll Isolasi Gypsun @ Rp 37,500.00 Rp 3,750.00
11.500 Bh Srews/sekrup @ Rp 140.00 Rp 1,610.00
2.000 Lbr Kertas Amplas @ Rp 4,000.00 Rp 8,000.00
jumlah a……… Rp 153,260.00
b. Tenaga
0.250 Oh Pekerja @ Rp 90,000.00 Rp 22,500.00
0.150 Oh Tukang Kayu @ Rp 100,000.00 Rp 15,000.00
0.150 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 18,000.00
0.015 Oh Mandor @ Rp 125,000.00 Rp 1,875.00
jumlah b……… Rp 57,375.00
jumlah a + b …. Rp 210,635.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 210,635.00 Rp 21,063.50
jumlah total….. Rp 231,698.50
IX A.4.5.2 PEKERJAAN SATUAN PEKERJAAAN PENUTUP ATAP
1 A.4.2.1.22 Memasang 1 m2 Atap Jurai Rangka Atap Baja Ringan Canai Dingin Profil C.75
a. Bahan
4.050 kg Baja Ringan Profil C. 0,75,075 @ Rp 7,000.00 Rp 28,350.00
1.013 kg Reng Baja Ringan U 0,40.0,48 @ Rp 7,000.00 Rp 7,087.50
jumlah a……… Rp 35,437.50
b. Tenaga
0.5069 Oh Pekerja @ Rp 90,000.00 Rp 45,624.00
0.7604 Oh Tukang Besi @ Rp 100,000.00 Rp 76,040.00
0.0760 Oh Kepala Tukang @ Rp 120,000.00 Rp 9,124.80
0.0380 Oh Mandor @ Rp 125,000.00 Rp 4,750.00
jumlah b……… Rp 135,538.80
C. Peralatan
0.10 % Peralatan @ Rp 25,000.00 Rp 2,500.00
jumlah c……… Rp 2,500.00
jumlah a + b + c …. Rp 173,476.30
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 173,476.30 Rp 17,347.63
jumlah total….. Rp 190,823.93
2 A.4.5.2.33 Memasang 1 m2 Atap Multi Roof - atap jurai
a. Bahan
2.000 M2 Multi Roof KW.1 @ Rp 90,000.00 Rp 180,000.00
0.050 Kg Sekrup Atap @ Rp 85,000.00 Rp 4,250.00
jumlah a……… Rp 184,250.00
b. Tenaga
0.200 Oh Pekerja @ Rp 90,000.00 Rp 18,000.00
0.100 Oh Tukang kayu @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,200.00
0.001 Oh Mandor @ Rp 125,000.00 Rp 125.00
jumlah b……… Rp 29,325.00
jumlah a + b …. Rp 213,575.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 213,575.00 Rp 21,357.50
jumlah total….. Rp 234,932.50
3 A.4.5.2.37 Memasang 1m' Nok Genteng Metal
a. Bahan
1.100 M' Nok Multi Roof (Nok Ratu) @ Rp 40,000.00 Rp 44,000.00
0.025 Kg Sekrup Atap @ Rp 85,000.00 Rp 2,125.00
jumlah a……… Rp 46,125.00
b. Tenaga
0.250 Oh Pekerja @ Rp 90,000.00 Rp 22,500.00
0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00
0.015 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,800.00
0.013 Oh Mandor @ Rp 125,000.00 Rp 1,625.00
jumlah b……… Rp 40,925.00
jumlah a + b …. Rp 87,050.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 87,050.00 Rp 8,705.00
jumlah total….. Rp 95,755.00
4 A.4.5.2.43 Memasang 1m2 Almunium Foil
a. Bahan
1.050 M2 Almunium Foil @ Rp 15,000.00 Rp 15,750.00
jumlah a……… Rp 15,750.00
b. Tenaga
0.150 Oh Pekerja @ Rp 90,000.00 Rp 13,500.00
0.050 Oh Tukang kayu @ Rp 100,000.00 Rp 5,000.00
0.005 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 600.00
0.008 Oh Mandor @ Rp 125,000.00 Rp 1,000.00
jumlah b……… Rp 20,100.00
jumlah a + b …. Rp 35,850.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 35,850.00 Rp 3,585.00
jumlah total….. Rp 39,435.00
5 A.4.5.2.43 Memasang 1m2 Atap Spandek
a. Bahan
1.050 M2 Atap spandek @ Rp 43,000.00 Rp 45,150.00
0.020 Kg Sekrup @ Rp 85,000.00 Rp 1,700.00
jumlah a……… Rp 45,150.00
b. Tenaga
0.150 Oh Pekerja @ Rp 90,000.00 Rp 13,500.00
0.075 Oh Tukang kayu @ Rp 100,000.00 Rp 7,500.00
0.075 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 9,000.00
0.006 Oh Mandor @ Rp 125,000.00 Rp 750.00
jumlah b……… Rp 30,750.00
jumlah a + b …. Rp 75,900.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 75,900.00 Rp 7,590.00
jumlah total….. Rp 83,490.00
6 dihitung Memasang 1 m' Lisplank Ukuran 1 x 0.8/20 cm, woodplank
a. Bahan
1.100 M' Woodplank T. 8 @ Rp 23,000.00 Rp 25,300.00
0.050 Kg Paku sekrup 2" - 3" @ Rp 85,000.00 Rp 4,250.00
jumlah a……… Rp 29,550.00
b. Tenaga
0.100 Oh Pekerja @ Rp 90,000.00 Rp 9,000.00
0.120 Oh Tukang kayu @ Rp 100,000.00 Rp 12,000.00
0.012 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,440.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah b……… Rp 28,690.00
jumlah a + b …. Rp 58,240.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 58,240.00 Rp 5,824.00
jumlah total….. Rp 64,064.00
X A.5.1.1 PEKERJAAN SATUAN PEKERJAAN SANITASI
1 A.5,1.1.1 Memasang 1 Buah Kloset Duduk/Monoblok
a. Bahan
1.000 M2 Kloset Duduk @ Rp 2,400,000.00 Rp 2,400,000.00
0.060 Set Perlengkapan @ Rp 144,000.00 Rp 8,640.00
jumlah a……… Rp 2,408,640.00
b. Tenaga
2.100 Oh Pekerja @ Rp 90,000.00 Rp 189,000.00
0.960 Oh Tukang Batu @ Rp 100,000.00 Rp 96,000.00
0.001 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 120.00
0.16000 Oh Mandor @ Rp 125,000.00 Rp 20,000.00
jumlah b……… Rp 305,120.00
jumlah a + b …. Rp 2,713,760.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 2,713,760.00 Rp 271,376.00
jumlah total….. Rp 2,985,136.00
2 A.5,1.1.2 Memasang 1 Bh kloset Jongkok
a. Bahan
1.000 Bh Closet Jongkok @ Rp 250,000.00 Rp 250,000.00
7.00 Bh Batu Merah @ Rp 650.00 Rp 4,550.00
6.00 Kg Semen Portland @ Rp 1,380.00 Rp 8,280.00
0.01 Kg Pasir Pasangan @ Rp 130,000.00 Rp 1,300.00
jumlah a……… Rp 264,130.00
b. Tenaga
1.000 Oh Pekerja @ Rp 90,000.00 Rp 90,000.00
1.500 Oh Tukang batu @ Rp 100,000.00 Rp 150,000.00
0.300 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 36,000.00
0.110 Oh Mandor @ Rp 125,000.00 Rp 13,750.00
jumlah b……… Rp 289,750.00
jumlah a + b …. Rp 553,880.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 553,880.00 Rp 55,388.00
jumlah total….. Rp 609,268.00
3 A.5,1.1.4 Memasang 1 Bh Urinoir
a. Bahan
1.000 Bh Urinoir @ Rp 550,000.00 Rp 550,000.00
jumlah a……… Rp 550,000.00
b. Tenaga
1.000 Oh Pekerja @ Rp 90,000.00 Rp 90,000.00
1.000 Oh Tukang batu @ Rp 100,000.00 Rp 100,000.00
0.100 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 12,000.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah b……… Rp 208,250.00
jumlah a + b …. Rp 758,250.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 758,250.00 Rp 75,825.00
jumlah total….. Rp 834,075.00
4 A.5,1.1.5 Memasang 1 Bh wastafel
a. Bahan
1.000 Bh Wastafel keramik @ Rp 500,000.00 Rp 500,000.00
jumlah a……… Rp 500,000.00
b. Tenaga
1.200 Oh Pekerja @ Rp 90,000.00 Rp 108,000.00
1.450 Oh Tukang batu @ Rp 100,000.00 Rp 145,000.00
0.150 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 18,000.00
0.100 Oh Mandor @ Rp 125,000.00 Rp 12,500.00
jumlah b……… Rp 283,500.00
jumlah a + b …. Rp 783,500.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 783,500.00 Rp 78,350.00
jumlah total….. Rp 861,850.00
5 A.5,1.1.12 Memasang 1 Bh Bak Cuci Piring Stainlessteel
a. Bahan
1.000 Bh Bak Cuci Piring @ Rp 450,000.00 Rp 450,000.00
jumlah a……… Rp 450,000.00
b. Tenaga
1.200 Oh Pekerja @ Rp 90,000.00 Rp 108,000.00
1.450 Oh Tukang batu @ Rp 100,000.00 Rp 145,000.00
0.150 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 18,000.00
0.100 Oh Mandor @ Rp 125,000.00 Rp 12,500.00
jumlah b……… Rp 283,500.00
jumlah a + b …. Rp 733,500.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 733,500.00 Rp 73,350.00
jumlah total….. Rp 806,850.00
6 A.5,1.1.14 Memasang 1 Bh Floor Drain
a. Bahan
1.000 Bh Floor Drain @ Rp 50,000.00 Rp 50,000.00
jumlah a……… Rp 50,000.00
b. Tenaga
0.010 Oh Pekerja @ Rp 90,000.00 Rp 900.00
0.100 Oh Tukang batu @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang Batu @ Rp 120,000.00 Rp 1,200.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah b……… Rp 12,725.00
jumlah a + b …. Rp 62,725.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 62,725.00 Rp 6,272.50
jumlah total….. Rp 68,997.50
7 A.5,1.1.19 Memasang 1 Bh kran diameter 3/4" atau 1/2"
a. Bahan
1.000 Bh Kran air biasa 1/2" - 3/4" @ Rp 125,000.00 Rp 125,000.00
0.025 Bh Seal tape @ Rp 5,000.00 Rp 125.00
jumlah a……… Rp 125,125.00
b. Tenaga
0.010 Oh Pekerja @ Rp 90,000.00 Rp 900.00
0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 1,200.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah b……… Rp 12,725.00
jumlah a + b …. Rp 137,850.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 137,850.00 Rp 13,785.00
jumlah total….. Rp 151,635.00
8 A.5,1.1.19a Memasang 1 Bh Shower Tray
a. Bahan
1.000 Bh Shower Tray + Acc @ Rp 185,000.00 Rp 185,000.00
0.025 Bh Seal tape @ Rp 5,000.00 Rp 125.00
jumlah a……… Rp 185,125.00
b. Tenaga
0.010 Oh Pekerja @ Rp 90,000.00 Rp 900.00
0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 1,200.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah b……… Rp 12,725.00
jumlah a + b …. Rp 197,850.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 197,850.00 Rp 19,785.00
jumlah total….. Rp 217,635.00
9 A.5,1.1.19b Memasang 1 Bh Stop kran
a. Bahan
1.000 Bh Stop Kran @ Rp 25,000.00 Rp 25,000.00
0.025 Bh Seal tape @ Rp 5,000.00 Rp 125.00
jumlah a……… Rp 25,125.00
b. Tenaga
0.010 Oh Pekerja @ Rp 90,000.00 Rp 900.00
0.100 Oh Tukang pipa @ Rp 100,000.00 Rp 10,000.00
0.010 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 1,200.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah b……… Rp 12,725.00
jumlah a + b …. Rp 37,850.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 37,850.00 Rp 3,785.00
jumlah total….. Rp 41,635.00
10 A.5,1.1.26 Memasang 1 M' pipa PVC tipe AW diameter 3/4"
a. Bahan
1.200 M' Pipa PVC AW 3/4'' @ Rp 7,000.00 Rp 8,400.00
35 % Perlengkapan 2,940.00 Rp 2,450.00
jumlah a……… Rp 10,850.00
b. Tenaga
0.036 Oh Pekerja @ Rp 90,000.00 Rp 3,240.00
0.060 Oh Tukang pipa @ Rp 100,000.00 Rp 6,000.00
0.006 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 720.00
0.002 Oh Mandor @ Rp 125,000.00 Rp 225.00
jumlah b……… Rp 10,185.00
jumlah a + b …. Rp 21,035.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 21,035.00 Rp 2,103.50
jumlah total….. Rp 23,138.50
11 A.5,1.1.27 Memasang 1 M' pipa PVC tipe AW diameter 1"
a. Bahan
1.200 M' Pipa PVC AW 1'' @ Rp 9,500.00 Rp 11,400.00
0.350 % Perlengkapan 11,400.00 Rp 3,990.00
jumlah a……… Rp 15,390.00
b. Tenaga
0.036 Oh Pekerja @ Rp 90,000.00 Rp 3,240.00
0.060 Oh Tukang pipa @ Rp 100,000.00 Rp 6,000.00
0.006 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 720.00
0.002 Oh Mandor @ Rp 125,000.00 Rp 225.00
jumlah b……… Rp 10,185.00
jumlah a + b …. Rp 25,575.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 25,575.00 Rp 2,557.50
jumlah total….. Rp 28,132.50
12 A.5,1.1.28 Memasang 1 M' pipa PVC tipe AW diameter 1,1/2"
a. Bahan
1.200 M' Pipa PVC AW 1.1/2'' @ Rp 12,500.00 Rp 15,000.00
0.35 % Perlengkapan 5,250.00 Rp 1,837.50
jumlah a……… Rp 16,837.50
b. Tenaga
0.036 Oh Pekerja @ Rp 90,000.00 Rp 3,240.00
0.060 Oh Tukang pipa @ Rp 100,000.00 Rp 6,000.00
0.006 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 720.00
0.002 Oh Mandor @ Rp 125,000.00 Rp 225.00
jumlah b……… Rp 10,185.00
jumlah a + b …. Rp 27,022.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 27,022.50 Rp 2,702.25
jumlah total….. Rp 29,724.75
13 A.5,1.1.29 Memasang 1 M' pipa PVC tipe AW diameter 2"
a. Bahan
1.200 M' Pipa PVC AW 2'' @ Rp 14,500.00 Rp 17,400.00
0 % Perlengkapan 17,400.00 Rp 6,090.00
jumlah a……… Rp 23,490.00
b. Tenaga
0.054 Oh Pekerja @ Rp 90,000.00 Rp 4,860.00
0.090 Oh Tukang pipa @ Rp 100,000.00 Rp 9,000.00
0.009 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 1,080.00
0.003 Oh Mandor @ Rp 125,000.00 Rp 337.50
jumlah b……… Rp 15,277.50
jumlah a + b …. Rp 38,767.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 38,767.50 Rp 3,876.75
jumlah total….. Rp 42,644.25
14 A.5,1.1.31 Memasang 1 M' pipa PVC tipe AW diameter 3"
a. Bahan
1.200 M' Pipa PVC AW 3'' @ Rp 36,000.00 Rp 43,200.00
0.35 % Perlengkapan 43,200.00 Rp 15,120.00
jumlah a……… Rp 58,320.00
b. Tenaga
0.081 Oh Pekerja @ Rp 90,000.00 Rp 7,290.00
0.135 Oh Tukang pipa @ Rp 100,000.00 Rp 13,500.00
0.014 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 1,620.00
0.004 Oh Mandor @ Rp 125,000.00 Rp 512.50
jumlah b……… Rp 22,922.50
jumlah a + b …. Rp 81,242.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 81,242.50 Rp 8,124.25
jumlah total….. Rp 89,366.75
15 A.5,1.1.32 Memasang 1 M' pipa PVC tipe AW diameter 4"
a. Bahan
1.200 M' Pipa PVC AW 4'' @ Rp 50,000.00 Rp 60,000.00
0.35 % Perlengkapan 60,000.00 Rp 21,000.00
jumlah a……… Rp 81,000.00
b. Tenaga
0.081 Oh Pekerja @ Rp 90,000.00 Rp 7,290.00
0.135 Oh Tukang pipa @ Rp 100,000.00 Rp 13,500.00
0.014 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 1,620.00
0.004 Oh Mandor @ Rp 125,000.00 Rp 512.50
jumlah b……… Rp 22,922.50
jumlah a + b …. Rp 103,922.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 103,922.50 Rp 10,392.25
jumlah total….. Rp 114,314.75
16 A.5,1.1.32 Memasang 1 M' pipa PVC tipe AW diameter 6"
a. Bahan
1.200 M' Pipa PVC AW 6'' @ Rp 85,000.00 Rp 102,000.00
0.35 % Perlengkapan 102,000.00 Rp 35,700.00
jumlah a……… Rp 137,700.00
b. Tenaga
0.081 Oh Pekerja @ Rp 90,000.00 Rp 7,290.00
0.135 Oh Tukang pipa @ Rp 100,000.00 Rp 13,500.00
0.014 Oh Kepala Tukang pipa @ Rp 120,000.00 Rp 1,620.00
0.004 Oh Mandor @ Rp 125,000.00 Rp 512.50
jumlah b……… Rp 22,922.50
jumlah a + b …. Rp 160,622.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 160,622.50 Rp 16,062.25
jumlah total….. Rp 176,684.75
XI A.4.2.1 PEKERJAAN BESI DAN ALUMINIUM
1 A.4.2.1.11 Mengerjakan 1 M' Kusen Aluminium
a. Bahan
1.100 M' Kusen Aluminium Warna 4" x 1 3/4" @ Rp 110,000.00 Rp 121,000.00
2.000 Bh Sektrup Fixer @ Rp 250.00 Rp 500.00
0.060 Tube Sealent @ Rp 65,000.00 Rp 3,900.00
jumlah a……… Rp 125,400.00
b. Tenaga
0.043 Oh Pekerja @ Rp 90,000.00 Rp 3,870.00
0.043 Oh Tukang besi @ Rp 100,000.00 Rp 4,300.00
0.0043 Oh Kepala Tukang Besi @ Rp 120,000.00 Rp 516.00
0.0021 Oh Mandor @ Rp 125,000.00 Rp 262.50
jumlah b……… Rp 8,948.50
jumlah a + b …. Rp 134,348.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 134,348.50 Rp 13,434.85
jumlah total….. Rp 147,783.35
2 A.4.2.1.13 Mengerjakan 1 M2 Pintu Kaca Rangka Aluminium
a. Bahan
4.400 M' Bingkai Pintu Aluminium Warna 4" @ Rp 120,000.00 Rp 528,000.00
4.500 M' Profil Kaca @ Rp 35,000.00 Rp 157,500.00
0.270 Tube Sealent @ Rp 65,000.00 Rp 17,550.00
jumlah a……… Rp 703,050.00
b. Tenaga
0.085 Oh Pekerja @ Rp 90,000.00 Rp 7,650.00
0.085 Oh Tukang besi @ Rp 100,000.00 Rp 8,500.00
0.090 Oh Kepala Tukang Besi @ Rp 120,000.00 Rp 10,800.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah b……… Rp 33,200.00
jumlah a + b …. Rp 736,250.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 736,250.00 Rp 73,625.00
jumlah total….. Rp 809,875.00
3 A.4.2.1.13a Mengerjakan 1 M2 Jendela Kaca Rangka Aluminium
a. Bahan
4.400 M' Bingkai Jendela Aluminium @ Rp 105,000.00 Rp 462,000.00
4.500 M' Profil Kaca @ Rp 35,000.00 Rp 157,500.00
0.270 Tube Sealent @ Rp 65,000.00 Rp 17,550.00
jumlah a……… Rp 637,050.00
b. Tenaga
0.085 Oh Pekerja @ Rp 90,000.00 Rp 7,650.00
0.085 Oh Tukang besi @ Rp 100,000.00 Rp 8,500.00
0.090 Oh Kepala Tukang Besi @ Rp 120,000.00 Rp 10,800.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah b……… Rp 33,200.00
jumlah a + b …. Rp 670,250.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 670,250.00 Rp 67,025.00
jumlah total….. Rp 737,275.00
XII A.4.6.1 PEKERJAAN SATUAN PEKERJAAAN KAYU
1 A.4.6.1.1 1 M3 Pembuatan dan Pemasangan kusen Pintu Kls I
a. Bahan
1.100 Kg Balok Kayu @ Rp 12,000,000.00 Rp 13,200,000.00
1.250 Kg Paku 10 cm @ Rp 18,000.00 Rp 22,500.00
1.000 Kg Lem @ Rp 75,200.00 Rp 75,200.00
jumlah a……… Rp 13,297,700.00
b. Tenaga
7.000 Oh Pekerja @ Rp 90,000.00 Rp 630,000.00
21.000 Oh Tukang kayu @ Rp 100,000.00 Rp 2,100,000.00
2.100 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 252,000.00
0.350 Oh Mandor @ Rp 125,000.00 Rp 43,750.00
jumlah b……… Rp 3,025,750.00
jumlah a + b …. Rp 16,323,450.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 16,323,450.00 Rp 1,632,345.00
jumlah total….. Rp 17,955,795.00
2 A.4.6.1.5 1 M2 Membuat daun pintu Panel kayu Kelas I
a. Bahan
0.040 Kg Papan Kayu @ Rp 15,000,000.00 Rp 600,000.00
0.500 Kg Paku 10 cm @ Rp 18,000.00 Rp 9,000.00
1.000 Kg Lem @ Rp 75,200.00 Rp 75,200.00
jumlah a……… Rp 684,200.00
b. Tenaga
1.000 Oh Pekerja @ Rp 90,000.00 Rp 90,000.00
3.000 Oh Tukang kayu @ Rp 100,000.00 Rp 300,000.00
0.300 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 36,000.00
0.050 Oh Mandor @ Rp 125,000.00 Rp 6,250.00
jumlah b……… Rp 432,250.00
jumlah a + b …. Rp 1,116,450.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 1,116,450.00 Rp 111,645.00
jumlah total….. Rp 1,228,095.00
3 A.4.6.1.6 1 M2 Membuat daun Jendela Kaca
a. Bahan
0.024 M3 Papan Kayu @ Rp 15,000,000.00 Rp 360,000.00
0.030 Kg Lem Kayu @ Rp 18,000.00 Rp 540.00
jumlah a……… Rp 360,540.00
b. Tenaga
0.800 Oh Pekerja @ Rp 90,000.00 Rp 72,000.00
2.400 Oh Tukang kayu @ Rp 100,000.00 Rp 240,000.00
0.240 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 28,800.00
0.040 Oh Mandor @ Rp 125,000.00 Rp 5,000.00
jumlah b……… Rp 345,800.00
jumlah a + b …. Rp 706,340.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 706,340.00 Rp 70,634.00
jumlah total….. Rp 776,974.00
XIII A.4.6.2 PEKERJAAN KUNCI DAN KACA
1 A.4.6.2.2 Memasang 1 Bh kunci tanam Biasa
a. Bahan
1.000 Bh Kunci @ Rp 240,000.00 Rp 240,000.00
jumlah a……… Rp 240,000.00
b. Tenaga
0.010 Oh Pekerja @ Rp 90,000.00 Rp 900.00
0.500 Oh Tukang kayu @ Rp 100,000.00 Rp 50,000.00
0.010 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,200.00
0.005 Oh Mandor @ Rp 125,000.00 Rp 625.00
jumlah b……… Rp 52,725.00
jumlah a + b …. Rp 292,725.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 292,725.00 Rp 29,272.50
jumlah total….. Rp 321,997.50
2 A.4.6.2.5 Memasang 1 Bh engsel pintu
a. Bahan
1.000 Bh Engsel pintu 4" Fino @ Rp 65,000.00 Rp 65,000.00
jumlah a……… Rp 65,000.00
b. Tenaga
0.015 Oh Pekerja @ Rp 90,000.00 Rp 1,350.00
0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00
0.015 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,800.00
0.0008 Oh Mandor @ Rp 125,000.00 Rp 93.75
jumlah b……… Rp 18,243.75
jumlah a + b …. Rp 83,243.75
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 83,243.75 Rp 8,324.38
jumlah total….. Rp 91,568.13
3 A.4.6.2.56 Memasang 1 Bh engsel Jendela
a. Bahan
1.000 Bh Engsel Jendela @ Rp 30,000.00 Rp 30,000.00
jumlah a……… Rp 30,000.00
b. Tenaga
0.0100 Oh Pekerja @ Rp 90,000.00 Rp 900.00
0.1000 Oh Tukang kayu @ Rp 100,000.00 Rp 10,000.00
0.0100 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,200.00
0.0005 Oh Mandor @ Rp 125,000.00 Rp 62.50
jumlah c……… Rp 12,162.50
jumlah a + c …. Rp 42,162.50
jumlah b + c …. Rp 42,162.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 42,162.50 Rp 4,216.25
jumlah total….. Rp 46,378.75
4 A.4.6.2.16 Memasang 1 Bh Kait Angin
a. Bahan
1.000 Bh Kait Angin @ Rp 12,500.00 Rp 12,500.00
jumlah a……… Rp 12,500.00
b. Tenaga
0.0150 Oh Pekerja @ Rp 90,000.00 Rp 1,350.00
0.1500 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00
0.0150 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,800.00
0.0080 Oh Mandor @ Rp 125,000.00 Rp 1,000.00
jumlah b……… Rp 19,150.00
jumlah a + b …. Rp 31,650.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 31,650.00 Rp 3,165.00
jumlah total….. Rp 34,815.00
5 A.4.6.2.10 Memasang 1 Bh door closer
a. Bahan
1.000 Bh Door closer/espanyolet @ Rp 265,000.00 Rp 265,000.00
jumlah a……… Rp 265,000.00
b. Tenaga
0.050 Oh Pekerja @ Rp 90,000.00 Rp 4,500.00
0.500 Oh Tukang kayu @ Rp 100,000.00 Rp 50,000.00
0.050 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 6,000.00
0.0025 Oh Mandor @ Rp 125,000.00 Rp 312.50
jumlah b……… Rp 60,812.50
jumlah a + b …. Rp 325,812.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 325,812.50 Rp 32,581.25
jumlah total….. Rp 358,393.75
6 A.4.6.2.17 Memasang 1 M2 kaca Bening, tebal 5 mm
a. Bahan
1.100 M2 Kaca Bening 5mm @ Rp 165,100.00 Rp 181,610.00
jumlah a……… Rp 181,610.00
b. Tenaga
0.015 Oh Pekerja @ Rp 90,000.00 Rp 1,350.00
0.150 Oh Tukang kayu @ Rp 100,000.00 Rp 15,000.00
0.015 Oh Kepala Tukang Kayu @ Rp 120,000.00 Rp 1,800.00
0.00075 Oh Mandor @ Rp 125,000.00 Rp 93.75
jumlah b……… Rp 18,243.75
jumlah a + b …. Rp 199,853.75
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 199,853.75 Rp 19,985.38
jumlah total….. Rp 219,839.13
XIV A. 4.7. 1 HARGA SATUAN PEKERJAAN PENGECATAN
1 A.4.7.1.4 Mengecat 1 M2 bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup

0.200 Kg Cat meni @ Rp 12,500.00 Rp 2,500.00


0.150 Kg Dempul @ Rp 26,300.00 Rp 3,945.00
0.170 Kg Cat dasar @ Rp 45,000.00 Rp 7,650.00
0.260 Kg Cat kayu @ Rp 72,400.00 Rp 18,824.00
0.010 Bh Kuas @ Rp 8,500.00 Rp 85.00
0.030 Kg Pengencer @ Rp 35,000.00 Rp 1,050.00
0.200 Lbr Amplas @ Rp 4,000.00 Rp 800.00
jumlah a……… Rp 34,854.00
b. Tenaga
0.070 Oh Pekerja @ Rp 90,000.00 Rp 6,300.00
0.009 Oh Tukang cat @ Rp 100,000.00 Rp 900.00
0.006 Oh Kepala Tukang Cat @ Rp 120,000.00 Rp 720.00
0.0025 Oh Mandor @ Rp 125,000.00 Rp 312.50
jumlah b……… Rp 8,232.50
jumlah a + b …. Rp 43,086.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 43,086.50 Rp 4,308.65
jumlah total….. Rp 47,395.15
2 A.4.7.1.10 Mengecat 1 M2 tembok baru (1 lapis plamir, 1 lapis cat dasar, dan 2 lapis cat penutup), (Interior)
a. Bahan
0.100 Kg Plamur tembok @ Rp 10,250.00 Rp 1,025.00
0.100 Kg Cat dasar @ Rp 45,000.00 Rp 4,500.00
0.260 Kg Cat tembok Kw. 1 (Interior) @ Rp 92,000.00 Rp 23,920.00
jumlah a……… Rp 29,445.00
b. Tenaga
0.020 Oh Pekerja @ Rp 90,000.00 Rp 1,800.00
0.063 Oh Tukang cat @ Rp 100,000.00 Rp 6,300.00
0.0063 Oh Kepala Tukang Cat @ Rp 120,000.00 Rp 756.00
0.0030 Oh Mandor @ Rp 125,000.00 Rp 375.00
jumlah b……… Rp 9,231.00
jumlah a + b …. Rp 38,676.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 38,676.00 Rp 3,867.60
jumlah total….. Rp 42,543.60
3 A.4.7.1.10a Mengecat 1 M2 tembok baru (1 lapis plamir, 1 lapis cat dasar, dan 2 lapis cat penutup), (Eksterior)
a. Bahan
0.100 Kg Plamur tembok @ Rp 10,250.00 Rp 1,025.00
0.100 Kg Cat dasar @ Rp 45,000.00 Rp 4,500.00
0.260 Kg Cat tembok Kw. 1 (Exterior) @ Rp 120,000.00 Rp 31,200.00
jumlah a……… Rp 36,725.00
b. Tenaga
0.020 Oh Pekerja @ Rp 90,000.00 Rp 1,800.00
0.063 Oh Tukang cat @ Rp 100,000.00 Rp 6,300.00
0.0063 Oh Kepala Tukang Cat @ Rp 120,000.00 Rp 756.00
0.0030 Oh Mandor @ Rp 125,000.00 Rp 375.00
jumlah b……… Rp 9,231.00
jumlah a + b …. Rp 45,956.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 45,956.00 Rp 4,595.60
jumlah total….. Rp 50,551.60
4 A.4.7.1.10b Mengecat 1 M2 tembok baru (1 lapis cat dasar, dan 2 lapis cat penutup)
a. Bahan
0.100 Kg Cat dasar @ Rp 60,000.00 Rp 6,000.00
0.260 Kg Cat Aquaproof @ Rp 60,000.00 Rp 15,600.00
jumlah a……… Rp 21,600.00
b. Tenaga
0.020 Oh Pekerja @ Rp 90,000.00 Rp 1,800.00
0.063 Oh Tukang cat @ Rp 100,000.00 Rp 6,300.00
0.0063 Oh Kepala Tukang Cat @ Rp 120,000.00 Rp 756.00
0.0030 Oh Mandor @ Rp 125,000.00 Rp 375.00
jumlah b……… Rp 9,231.00
jumlah a + b …. Rp 30,831.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 30,831.00 Rp 3,083.10
jumlah total….. Rp 33,914.10

5 A.4.7.1.10a Mengecat 1 M2 tembok baru (1 lapis plamir, 1 lapis cat dasar, dan 2 lapis cat penutup), (Eksterior)
a. Bahan
0.100 Kg Plamur tembok @ Rp 10,250.00 Rp 1,025.00
0.100 Kg Cat dasar @ Rp 25,000.00 Rp 2,500.00
0.260 Kg Cat tembok Kw. 1 (Exterior) @ Rp 25,000.00 Rp 6,500.00
jumlah a……… Rp 10,025.00
b. Tenaga
0.020 Oh Pekerja @ Rp 90,000.00 Rp 1,800.00
0.063 Oh Tukang cat @ Rp 100,000.00 Rp 6,300.00
0.0063 Oh Kepala Tukang Cat @ Rp 120,000.00 Rp 756.00
0.0030 Oh Mandor @ Rp 125,000.00 Rp 375.00
jumlah b……… Rp 9,231.00
jumlah a + b …. Rp 19,256.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 19,256.00 Rp 1,925.60
jumlah total….. Rp 21,181.60
XV HARGA SATUAN PEKERJAAN LISTRIK
1 dihitung Mengerjakan 1 Titik Instalasi Listrik
a. Bahan
5.000 M' Kabel NYM (2 x 2,5) mm @ Rp 14,000.00 Rp 70,000.00
5.000 M' Pipa Listrik PVC @ Rp 4,500.00 Rp 22,500.00
1.000 ls Bahan Laiinya @ Rp 15,000.00 Rp 15,000.00
jumlah a……… Rp 107,500.00
b. Tenaga
0.050 Oh Tukang Listrik @ Rp 100,000.00 Rp 5,000.00
0.500 Oh Kepala Tukang Listrik @ Rp 125,000.00 Rp 62,500.00
jumlah b……… Rp 67,500.00
jumlah a + b …. Rp 175,000.00
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 175,000.00 Rp 17,500.00
jumlah total….. Rp 192,500.00
2 dihitung Mengerjakan 1 Titik Instalasi Daya Stop Kontak
a. Bahan
6.870 M' Kabel NYM (3 x2,5) mm @ Rp 17,000.00 Rp 116,790.00
0.333 Roll Solatif Kabel @ Rp 7,500.00 Rp 2,497.50
1.500 Btg Pipa Kabel @ Rp 18,000.00 Rp 27,000.00
jumlah a……… Rp 146,287.50
b. Tenaga
0.050 Oh Tukang Listrik @ Rp 100,000.00 Rp 5,000.00
0.500 Oh Kepala Tukang Listrik @ Rp 125,000.00 Rp 62,500.00
jumlah b……… Rp 67,500.00
jumlah a + b …. Rp 213,787.50
c. Overhead & Profit
0.10 % 10 % x jumlah a + b @ Rp 213,787.50 Rp 21,378.75
jumlah total….. Rp 235,166.25
DAFTAR HARGA BAHAN DAN UPAH
TAHUN ANGGARAN 2017

NO URAIAN SAT HARGA


I. HARGA BAHAN
A BAHAN BATU, PASIR, CIPPING DAN BATU MERAH
1 Batu gunung M3 Rp 180,000.00
2 Pasir pasang M3 Rp 130,000.00
3 Pasir beton M3 Rp 180,000.00
4 Pasir beton (Kg) Kg Rp 128.57
5 Pasir urug M3 Rp 100,000.00
6 Sirtu M3 Rp 150,000.00
7 split/chipping 2-3 cm M3 Rp 275,000.00
8 split/chipping 2-3 cm(Kg) Kg Rp 203.70
9 Tanah Timbunan M3 Rp 75,000.00
10 Batu merah Bh Rp 650.00
11 Air Ltr Rp 25.00
12 Stamper Jam Rp 50,000.00
B BAHAN SEMEN
1 Semen PC 50kg (zak) Zak Rp 69,000.00
2 Semen Portland Kg Rp 1,380.00
3 Semen warna Kg Rp 18,000.00
C BAHAN BESI DAN ALMUNIUM
1 Besi beton polos Kg Rp 12,500.00
2 Kawat beton Kg Rp 21,000.00
3 Paku Biasa Kg Rp 18,000.00
4 Srews/sekrup Gypsum Kg Rp 70,000.00
5 Srews/sekrup Gypsum Bh Rp 140.00
6 Srews/sekrup Atap Kg Rp 85,000.00
7 Hollow Almunium 4 x 4 M Rp 8,500.00
8 Paku sekrup '2"-3" Lisplank Kg Rp 150,000.00
9 Sekrup Kusen Almunium Bh Rp 250.00
D BAHAN PLAPON DAN PARTISI
1 Trikpleks 1.22 x 2.44 x 9 mm Lbr Rp 120,000.00
2 Trikpleks 1.22 x 2.44 x 4 mm Lbr Rp 65,000.00
3 Gypsumboard ex jayaboard t. 9 mm Lbr Rp 70,000.00
4 Selica Board 4 mm Lbr Rp 67,000.00
5 List Gypsum Sedang 10 cm M' Rp 12,000.00
6 List Gypsum Besar lebar 25 cm M' Rp 25,000.00
E BAHAN KERAMIK
1 Lantai keramik 25/25 cm (Warna) Setara Kia Bh Rp 4,500.00
2 Dinding keramik 25/40 cm ( warna ) Setara Kia Bh Rp 8,700.00
3 Plint Keramik Km/Wc 8/25 Cm setara Kia Bh Rp 5,500.00
4 Keramik 40/40 Bh Rp 11,000.00
5 Lantai Niro Granito 60/60 GN 708 sevilla Bh Rp 80,000.00
6 Lantai Tangga Niro Granito 30/60 Cm GN 708 sevilla Bh Rp 40,000.00
Batu Acak M2 Rp 200,000.00
NO URAIAN SAT HARGA
F BAHAN ATAP
1 Multi Roof T. 0,35 mm (2 susun 4 daun) Multi roof Lbr Rp 90,000.00
2 Atap spandek Zincalume M2 Rp 43,000.00
3 Nok Multi Roof (nok ratu) M' Rp 40,000.00
4 Almunium Foil INSFOIL 920 DS (125 x 60M) M2 Rp 15,000.00
5 Baja Ringan Profil C 0,75.0,75 Kg Rp 7,000.00
6 Reng Baja Ringan 0,4.0,48 Kg Rp 7,000.00
G BAHAN KAYU
1 Kayu klas I (balok gergaji somil) M3 Rp 12,000,000.00
2 Kayu klas I (papan gergaji somil) M3 Rp 15,000,000.00
3 Kayu klas II (balok) M3 Rp 4,000,000.00
4 Kayu klas II (papan) M3 Rp 4,000,000.00
5 Kayu klas III (balok) M3 Rp 2,000,000.00
6 Kayu klas III (papan) M3 Rp 2,000,000.00
7 Dolken kayu Ø8-10/400 cm Btg Rp 30,000.00
8 Woodplank T. 8 x 300 x 4000 mm M' Rp 23,000.00
9 Bambu, Uk. Besar Btg Rp 30,000.00
H BAHAN SENG/ALUMINIUM
1 Kusen Aluminium 4"x1 3/4" - Warna Coklat M' Rp 110,000.00
2 Bingkai Pintu Aluminium 4" - Warna Coklat M' Rp 120,000.00
3 Bingkai Jendela Aluminium 2" - Warna Coklat M' Rp 105,000.00
4 Profil Kaca M' Rp 35,000.00
5 Metal Stud 76/3.35 M' Rp 18,500.00
6 Metal Track 76/3.35 M' Rp 18,500.00
7 Pintu Almunium Alumnium Spanrell (Lenkap + Pasang) Set Rp 850,000.00
I BAHAN KUNCI, ENGSEL, GRENDEL DAN HAK ANGIN
1 Kunci tanam silinder Fino - DC FN OAO1-07 Bh Rp 240,000.00
2 Engsel Pintu Fino - SEL-FB08 4x3x3mm 4BB Bh Rp 65,000.00
3 Engsel Jendela 3" Bh Rp 30,000.00
Kait Angin Bh Rp 12,500.00
4 Grendel Rambuncis - KEND 76 034 Bh Rp 75,000.00
5 Door closer Dorma TS.77 Bh Rp 265,000.00
6 handle Pintu Swing Full Almunium - 21 cm Bh Rp 75,000.00
7 handle Pintu Kayu - Fino Bh Rp 375,000.00
J BAHAN KACA
1 Kaca Cermin Tebal 5 mm M2 Rp 120,000.00
2 Kaca buram 5 mm M2 Rp 135,000.00
3 Kaca bening 5mm M2 Rp 165,100.00
4 Karet List Kaca M' Rp 4,000.00
5 Sealant Tube Rp 65,000.00
K BAHAN CAT
1 Cat No Drop Kg Rp 60,000.00
2 Cat dasar Kg Rp 45,000.00
3 Cat tembok Kw. 1 (Interior Mowilex) Kg Rp 92,000.00
4 Cat tembok Kw. 1 (Exterior Mowilex) Kg Rp 120,000.00
5 Cat tembok Kg Rp 25,000.00
NO URAIAN SAT HARGA
6 Cat tembok Kg Rp 25,000.00
5 Cat dasar Kg Rp 45,000.00
6 Cat kayu Kg Rp 72,400.00
7 Cat meni Kg Rp 12,500.00
8 Plamur tembok Kg Rp 10,250.00
9 Minyak bekisting Ltr Rp 8,000.00
10 Tenner Ltr Rp 35,000.00
11 Dempul Kg Rp 26,300.00
12 Kertas amplas Lbr Rp 4,000.00
13 Kuas Bh Rp 8,500.00
14 UB 888/400 Compoud Kg Rp 6,500.00
15 Isolasi Gypsun Roll Rp 37,500.00
16 Lem Fox Kg Rp 75,200.00
L BAHAN PIPA
1 Pipa PVC AW 2'' setara maspion M' Rp 20,000.00
1 Pipa PVC AW 3/4'' setara maspion M' Rp 7,000.00
2 Pipa PVC AW 1'' setara maspion M' Rp 9,500.00
3 Pipa PVC AW 1,1/2'' setara maspion M' Rp 12,500.00
4 Pipa PVC AW 2'' setara maspion M' Rp 14,500.00
5 Pipa PVC AW 3'' setara maspion M' Rp 36,000.00
6 Pipa PVC AW 4'' setara maspion M' Rp 50,000.00
7 Pipa PVC AW 6'' setara maspion M' Rp 85,000.00
8 Pipa Besi Angin 1" M' Rp 35,000.00
9 Knee Besi 1" M' Rp 23,000.00
L BAHAN SANITASI
1 Closet duduk warna Monoblok 2 tombol setara toto Bh Rp 2,400,000.00
2 Closet jongkok setara toto Bh Rp 250,000.00
3 Wastafel Keramik setara toto lengkap Bh Rp 500,000.00
4 Roof drain Bh Rp 50,000.00
5 Floor drain Stainlees Bh Rp 35,000.00
6 Seal tape Bh Rp 2,700.00
7 Kran air toto 1/2" - 3/4" Bh Rp 125,000.00
8 Kran air toto 1/2" - 3/4" Angsa Bh Rp 120,000.00
9 Kran Shower Bh Rp 60,000.00
10 Shower Tray + Acc setara toto Set Rp 185,000.00
11 Stop kran Bh Rp 25,000.00
12 Washbasin stainless stel Setara Royal - lengkap Bh Rp 450,000.00
13 Waterdrain + Accesoriss Bh Rp 65,000.00
14 Reservoir stainless steel Kap. 1 M3 setara Maspion Bh Rp 4,100,000.00
15 Tempat Sabun Dinding Bh Rp 95,000.00
16 Urinoir Lengkap Bh Rp 550,000.00
17 Mesin Pompa Air Wasser PC 500 EA Bh Rp 4,000,000.00
18 (Lengkap Preasure Tank & Pengabelan)
M BAHAN LISTRIK
1 Kabel NYM (2 x 2,5) mm M' Rp 14,000.00
2 Kabel NYM (3 x 2,5) mm M' Rp 17,000.00
NO URAIAN SAT HARGA
3 Kabel NYM (4 x 6) mm M' Rp 75,000.00
4 Lampu TKI Esential TL LED 2 x 18 Watt Bh Rp 750,000.00
5 Lampu TKI Esential TL LED 1 x 18 Watt Bh Rp 500,000.00
6 Lampu TKI Esential Balk TL 1 x 36 Watt Bh Rp 250,000.00
7 Lampu Down Light 5" 10 Watt LED Bh Rp 225,000.00
7 Lampu Down Light 5" 14 Watt LED Bh Rp 275,000.00
8 Saklar Tunggal Ex Panasonic Bh Rp 30,000.00
9 Saklar Seri 2 Ex Panasonic Bh Rp 35,000.00
10 Saklar Seri 3 Ex Panasonic Bh Rp 40,000.00
11 Stop Kontak 16 Amper ( AC ) Ex Panasonic Bh Rp 40,000.00
12 Stop Kontak 16 Amper (Arde) Ex Panasonic Bh Rp 40,000.00
13 Lampu SL. 23 watt Philips Sumpit Bh Rp 45,000.00
14 Lampu SL. 14 watt Philips Sumpit Bh Rp 60,000.00
15 Donw Light 3" Bh Rp 60,000.00
16 MCB Bh Rp 50,000.00
17 Pipa Listrik 5/8" Btg Rp 18,000.00
18 Pipa Listrik 5/8" M' Rp 4,500.00
19 Solatif Kabel Bh Rp 7,500.00
20 Panel 40 x 60 Lengkap dengan Isi Bh Rp 5,000,000.00
II. HARGA UPAH KERJA
1 Tukang kayu Oh Rp 100,000.00
2 Tukang Pipa Oh Rp 100,000.00
3 Tukang gali Oh Rp 100,000.00
4 Tukang batu Oh Rp 100,000.00
5 Tukang besi Oh Rp 100,000.00
6 Tukang cat Oh Rp 100,000.00
7 Tukang listrik Oh Rp 100,000.00
8 Pembantu Tukang Listrik Oh Rp 100,000.00
9 Kepala Tukang Kayu Oh Rp 120,000.00
10 Kepala Tukang Batu Oh Rp 120,000.00
11 Kepala Tukang Cat Oh Rp 120,000.00
12 Kepala Tukang Listrik Oh Rp 120,000.00
13 Kepala Tukang Pipa Oh Rp 120,000.00
14 Kepala Tukang Besi Oh Rp 120,000.00
15 Mandor Oh Rp 125,000.00
16 Pekerja Oh Rp 90,000.00

Anda mungkin juga menyukai