JADWAL WAKTU PELAKSANAAN

PEKERJAAN : MESS KARYAWAN GROUP LEADER


LOKASI PEKERJAAN : SITE SMU - MANJALUTUNG, KAB. TANA TIDUNG KALIMANTAN UTARA
TAHUN ANGGARAN : 2022/ 2023

PELAKSANAAN PEKERJAAN
BULAN KE - I BULAN KE - II
BOBOT MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8
NO. URAIAN PEKERJAAN SPK
(%)
25/12/22 01/01/23 08/01/23 15/01/23 24/01/23 31/01/23 07/02/23 14/02/23
sd. sd. sd. sd. sd. sd. sd. sd.
31/12/22 07/01/23 14/01/23 23/01/23 30/01/23 06/02/23 13/02/23 22/02/23

I. PEKERJAAN PERSIAPAN 14,826 6,739 7,268 0,819

II. PEKERJAAN PENDAHULUAN 10,767 2,692 3,768 4,307

III. PEKERJAAN PONDASI DAN STRUKTUR 3,336 0,584 2,752

IV. PEKERJAAN RANGKA DINDING 28,223 9,408 9,408 9,408

12 Oktober 2022
V. PEKERJAAN LANTAI DAN DINDING KERAMIK 5,742 1,723 4,020

VI. PEKERJAAN ATAP 13,889 0,926 2,546 10,417

VII. PEKERJAAN PLAFOND GYPSUM RANGKA HOLLOW 11,334 5,667 5,667

VIII. PEKERJAAN SANITAIR 2,831 2,831

IX. PEKERJAAN INSTALASI LISTRIK 4,166 1,250 1,458 1,458

X. PEKERJAAN PENGECATAN 4,528 2,264 2,264

XI. PEKERJAAN LAIN-LAIN 0,357 0,357

100,00 Waktu Pelaksanaan Pekerjaan = 60 (Enam Puluh) Hari Kalender

BOBOT RENCANA 6,739 9,960 4,352 17,393 13,677 30,761 9,389 7,729

KUMULATIF BOBOT RENCANA 6,739 16,699 21,051 38,444 52,121 82,882 92,271 100,000