JADWAL WAKTU PELAKSANAAN & KURVA S (TIME SCHEDULE

PAKET : PEKERJAAN STRUKTUR, ARSITEKTUR DAN PLUMBING


PROYEK : PEMBANGUNAN HOTEL SANTIKA
LOKASI : JL.TUANKU NAN RENCEH BUKITTINGGI - SUMATERA BARAT

JANG
TAHU
NO URAIAN PEKERJAAN BOBOT DURASI BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
(MINGGU) PER 15-Jan 21-Jan 28-Jan 04-Feb 11-Feb 18-Feb 25-Feb 04-Mar 11-Mar 18-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr 29-Apr 06-Mei 13-Mei 20-Mei 27-Mei 03-Jun 10-Jun 17-Jun 24-Jun
MINGGU s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
20-Jan 27-Jan 03-Feb 10-Feb 17-Feb 24-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Apr 14-Apr 21-Apr 28-Apr 05-Mei 12-Mei 19-Mei 26-Mei 02-Jun 09-Jun 16-Jun 23-Jun 30-Jun

1 PEKERJAAN PERSIAPAN 2,616 46 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057
2 PEKERJAAN STRUKTUR
I PEKERJAAN STRUTTING 3,196 5 0,639 0,639 0,639 0,639 0,639 0,639
II PEKERJAAN GALIAN, PILE CAP & TIE BEAM 7,809 10 0,781 0,781 0,781 0,781 0,781 0,781 0,781 0,781 0,781 0,781 0,781
III PEKERJAAN STRUKTUR ATAS
A PEKERJAAN LANTAI LG2 4,723 7 0,675 0,675 0,675 0,675 0,675 0,675 0,675 0,675
B PEKERJAAN LANTAI LG-1 DAN LG-1 MEZANIN 5,336 6 0,889 0,889 0,889 0,889 0,889 0,889 0,889
C PEKERJAAN LANTAI SATU 4,762 6 0,794 0,794 0,794 0,794 0,794 0,794 0,794
D PEKERJAAN LANTAI MEZANIN 3,306 6 0,551 0,551 0,551 0,551 0,551
E PEKERJAAN LANTAI DUA 2,342 5 0,468
F PEKERJAAN LANTAI TIGA 2,339 5 0,468
G PEKERJAAN LANTAI EMPAT 2,346 5 0,469
H PEKERJAAN LANTAI LIMA 2,337 5 0,467
I PEKERJAAN LANTAI ENAM 2,289 5 0,458

Libur Hari Raya Idul Fitri


J PEKERJAAN LANTAI TUJUH 2,303 5 0,461
K PEKERJAAN LANTAI ATAP, R.TANGGA & R. MESIN 2,681 4 0,670
L PEKERJAAN FRAME DROP OFF 0,391 5 0,078
M PEKERJAAN CANOPY OUT DOOR RESTO 0,235 5 0,047
N PEKERJAAN CANOPY LOADING BAY 0,106 4 0,026
IV PEKERJAAN BANGUNAN PENUNJANG
A PEKERJAAN BANGUNAN POWER HOUSE 0,911 8 0,114 0,114 0,114 0,114 0,114 0,114 0,114 0,114 0,114
3 PEKERJAAN ARSITEKTUR
I PEKERJAAN FINISHING GEDUNG
A FINISHING LANTAI LG - 2 2,612 6 0,435 0,435 0,435 0,435 0,435 0,435 0,435
B FINISHING LANTAI LG - 1 4,837 5 0,967 0,967
C FINISHING LANTAI - 1 4,188 5 0,838
D FINISHING LANTAI - MEZZANINE 2,716 5 0,543
E FINISHING LANTAI - 2 4,235 5 0,847
F FINISHING LANTAI - 3 4,254 6 0,709
G FINISHING LANTAI - 4 4,273 5 0,855
H FINISHING LANTAI - 5 4,292 5 0,858
I FINISHING LANTAI - 6 4,563 6 0,760
J FINISHING LANTAI - 7 4,678 6 0,780
K FINISHING LANTAI - ATAP 0,725 4 0,181
L FINISHING FASAD 5,080 5 1,016
II PEKERJAAN SARANA LUAR
A PEKERJAAN FINISHING BANGUNAN POWER HOUSE 0,507 7 0,072 0,072 0,072 0,072 0,072 0,072 0,072 0,072
B PEKERJAAN FINISHING BANGUNAN SECURITY 0,109 9 0,012
C PEKERJAAN PERKERASAN JALAN & PARKIR 1,368 8 0,171
D PEKERJAAN FINISHING TIANG BENDERA 0,104 5 0,021
4 PEKERJAAN PLUMBING
A INSTALASI PIPA AIR BERSIH 0,447 20 0,022
B INSTALASI PIPA AIR PANAS 0,281 20 0,014
C INSTALASI PIPA AIR KOTOR, AIR BEKAS & VENT 0,331 13 0,025
D INSTALASI PIPA AIR HUJAN 0,361 8 0,045
E TESTING COMMISSIONING 0,013 6 0,002

100,000
Bobot Rencana 0,000 0,000 0,000 0,838 0,838 0,838 0,952 1,626 1,626 1,626 2,265 3,155 3,227 2,446 2,452 2,248 2,248 1,909 1,909 - - - 1,837 2,011
Bobot Rencana Kumulatif 0,000 0,000 0,000 0,838 1,675 2,513 3,465 5,091 6,717 8,344 10,609 13,764 16,991 19,438 21,889 24,137 26,385 28,294 30,204 30,204 30,204 30,204 32,040 34,051
Bobot Realisasi
Bobot Realisasi Kumulatif
Deviasi ( + / - )
Waktu pelaksanaan pekerjaan = 365 hari kalender
ME SCHEDULE)

JANGKA WAKTU PELAKSANAAN


TAHUN 2019 TAHUN 2020 KET
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 PRESTASI
01-Jul 08-Jul 15-Jul 22-Jul 29-Jul 05-Agust 12-Agust 19-Agust 26-Agust 02-Sep 09-Sep 16-Sep 23-Sep 30-Sep 07-Okt 14-Okt 21-Okt 28-Okt 04-Nop 11-Nop 18-Nop 25-Nop 02-Des 09-Des 16-Des 23-Des 30-Des 06-Jan %
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
07-Jul 14-Jul 21-Jul 28-Jul 04-Agust 11-Agust 18-Agust 25-Agust 01-Sep 08-Sep 15-Sep 22-Sep 29-Sep 06-Okt 13-Okt 20-Okt 27-Okt 03-Nop 10-Nop 17-Nop 24-Nop 01-Des 08-Des 15-Des 22-Des 29-Des 05-Jan 14-Jan

0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 0,057 100

0,551 0,551 KURVA S


0,468 0,468 0,468 0,468 0,468
0,468 0,468 0,468 0,468 0,468
0,469 0,469 0,469 0,469 0,469
0,467 0,467 0,467 0,467 0,467
0,458 0,458 0,458 0,458 0,458
0,461 0,461 0,461 0,461 0,461
0,670 0,670 0,670 0,670
0,078 0,078 0,078 0,078 0,078
0,047 0,047 0,047 0,047 0,047
0,026 0,026 0,026 0,026

50

0,967 0,967 0,967 0,967


0,838 0,838 0,838 0,838 0,838
0,543 0,543 0,543 0,543 0,543
0,847 0,847 0,847 0,847 0,847
0,709 0,709 0,709 0,709 0,709 0,709
0,855 0,855 0,855 0,855 0,855
0,858 0,858 0,858 0,858 0,858
0,760 0,760 0,760 0,760 0,760 0,760
0,780 0,780 0,780 0,780 0,780 0,780
0,181 0,181 0,181 0,181
1,016 1,016 1,016 1,016 1,016

0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012 0,012


0,171 0,171 0,171 0,171 0,171 0,171 0,171 0,171
0,021 0,021 0,021 0,021 0,021

0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022 0,022
0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014 0,014
0,025 0,025 0,025 0,025 0,025 0,025 0,025 0,025 0,025 0,025 0,025 0,025 0,025
0,045 0,045 0,045 0,045 0,045 0,045 0,045 0,045
0,002 0,002 0,002 0,002 0,002 0,002 0

2,044 2,044 2,330 2,798 1,867 1,942 2,411 1,573 1,953 2,420 2,586 2,195 2,690 2,698 3,089 4,357 3,741 4,108 3,923 3,086 2,605 2,015 1,345 1,581 1,327 1,075 1,075 1,073
36,095 38,139 40,469 43,267 45,134 47,075 49,486 51,059 53,012 55,432 58,018 60,213 62,903 65,601 68,689 73,046 76,787 80,895 84,818 87,904 90,508 92,524 93,869 95,450 96,777 97,852 98,927 100,000