LAPORAN KEMAJUAN PEKERJAAN (LKP) MINGGU (V) KELIMA

PERIODE 2 S/D 8 FEBRUARII 2020


PEKERJAAN RENOVASI GEDUNG 17
PT. SATU DUA TIGA KONTRAKTOR PT. SATU
KONS. PENGAWAS CV. DUA

WAKTU PELAKSANAAN
BULAN BULAN I/JANUARI BULAN II/FEBRUARI BULAN III/MARET BULAN IV/APRIL BULAN V/MEI
No. URAIAN BOBOT SKALA
MINGGU M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20
TANGGAL 5 S/D 11/1 12 S/D 18/1 19 S/D 25/1 26/1 SD 1/2 2 S/D 8/2 9 S/D 15/2 16 S/D 22/2 23 SD 29/2 1 S/D 7/3 8 S/D 14/3 15 S/D 21/3 22 SD 28/3 29/3 S/D 4/4 5 S/D 11/4 12 S/D 18/4 19 SD 25/4 26/4 S/D 2/5 3 S/D 9/5 10 S/D 16/5 17 SD 23/5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
I PEKERJAAN PENDAHULUAN 0,630 RENCANA 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 0,031 100
REALISASI 0,252 0,066 0,017 0,017 0,017
II PEKERJAAN BONGKARAN 0,333 RENCANA 0,167 0,167
REALISASI 0,167 0,167
III PEKERJAAN PONDASI DAN URUGAN 8,149 RENCANA 1,630 1,630 1,630 1,630 1,630
REALISASI 2,714 1,56 1,84
IV PEKERJAAN BETON 13,088 RENCANA 1,190 1,190 1,190 1,190 1,190 1,190 1,190 1,190 1,190 1,190 1,190
REALISASI 0,38 1,52
V PEKERJAAN PASANGAN 14,497 RENCANA 1,450 1,450 1,450 1,450 1,450 1,450 1,450 1,450 1,450 1,450
REALISASI
VI PEKERJAAN LANTAI 11,283 RENCANA 1,612 1,612 1,612 1,612 1,612 1,612 1,612
REALISASI
VII PEKERJAAN PLAFOND/ATAP 22,720 RENCANA 4,544 4,544 4,544 4,544 4,544 50
REALISASI
VIII KUSEN, PINTU DAN JENDELA 21,434 RENCANA 7,145 7,145 7,145
REALISASI
IX PEKERJAAN INSTALASI LISTRIK 2,399 RENCANA 1,199 1,199
REALISASI
X PEKERJAAN SANITASI 1,165 RENCANA 0,582 0,582
REALISASI
XI PEKERJAAN PENGECATAN 3,349 RENCANA 1,116 1,116 1,116
REALISASI
XII PEKERJAAN LAIN-LAIN 0,954 RENCANA 0,954
REALISASI 0

RENCANA MINGGUAN 100,000 0,198 0,198 1,661 2,851 2,851 4,301 4,301 2,671 7,215 7,215 8,827 8,827 8,827 4,283 3,093 1,643 8,788 10,074 10,074 2,102
RENCANA KOMULATIF MINGGUAN 0 0,198 0,396 2,057 4,909 7,760 12,061 16,361 19,033 26,248 33,463 42,289 51,116 59,943 64,226 67,319 68,962 77,750 87,824 97,898 100,000
REALISASI MINGGUAN 8,720 0,232 2,731 1,958 3,380
REALISASI KOMULATIF MINGGUAN 0 0,418 0,651 3,382 5,340 8,720
DEVIASI 0,220 0,255 1,325 0,432 0,961

KETERANGAN
RENCANA