3 III JALAN AKSES (FLEXIBEL PAVEMENT) 35,030 17,850 17,267 17,181 1,622 0,583
5 V BANGUNAN PELENGKAP DAN AREA BUNDARAN 17,140 13,204 14,619 3,936 -1,492 -1,415
7 VII UTILITAS DAN DRAINASE 11,500 10,814 10,337 0,685 0,477 0,477
LINGKUP BARU
PEKERJAAN PENYAMBUNGAN LISTRIK DAN SUPLAI
1 I 0,589 0,000 0,001 0,589 0,002 -0,001
AIR KE TAMAN SEGARA KERTI
PEKERJAAN PEMUGARAN PURA / PELINGGIH
2 II 0,418 0,000 0,000 0,418 0,000 0,000
BATU ARCA DESA ADAT KEPAON
3 III PEKERJAAN REKLAMASI PADA AREA PERAIRAN 2,023 0,899 0,040 1,124 0,865 0,859
TOTAL BOBOT 73,499 48,550 47,887 24,948 1,643 0,663
Ir. Wahju Iswandy, ST, MT, IPM. A.A. Gde Ngurah Cakradwipayana,ST.
Team Leader T.A. Struktur
EVALUASI PROGRESS PEKERJAAN SIPIL M59
volume bobot
target mulai target penyelesaian
deviasi bobot BOBOT prosentase deviasi bobot deviasi bobot Status progress
no item volume add volume volume satuan bobot add berdasarkan berdasarkan time
progress s/d progress RENCANA S/D progress thd progress thd progress thd thd add II
II kontrak diprogress II time schedule schedule
add II submit MINGGU INI pekerjaan bobot add II rencana
I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1,000 1,000 0,811 0,189 Ls 0,224 0,181 0,186 81% 0,042 -0,005 on going M1 M82
2 Pekerjaan persiapan dan fasilitas sementara 1,000 1,000 1,000 0,000 Ls 0,033 0,033 0,033 100% 0,000 0,000 completed
Pekerjaan penyelengaraan keamanan dan kesehatan kerja serta
3 1,000 1,000 M82
keselamatan konstruksi dan protokol kesehatan 0,981 0,019 Ls 0,241 0,237 0,234 98% 0,005 0,003 on going M1
4 Survey dan Penyelidikan Tanah 1,000 1,000 1,000 0,000 Ls 0,126 0,126 0,126 100% 0,000 0,000 completed
5 Pekerjaan Detailed Engineering Design 1,000 1,000 1,000 0,000 Ls 0,903 0,903 0,903 100% 0,000 0,000 completed
6 Pekerjaan Dokumentasi dan Laporan 1,000 1,000 0,889 0,111 Ls 0,022 0,020 0,018 89% 0,002 0,001 on going M1 M82
7 Pekerjaan pembersihan area mangrove 1,000 1,000 0,000 1,000 Ls 0,130 0,000 0,000 0% 0,130 0,000 on going M67 M67
TOTAL I 1,678 1,499 1,500
e. Lapis Perkerasan AC-BC 463,435 508,342 463,435 0,000 0,416 0,416 0,416 100% 0,000 0,000 completed
f. Lapis Perkerasan AC-WC 307,146 338,895 0,000 307,146 0,279 0,000 0,000 0% 0,279 0,000 on going M73 M73
a. Lapis Pondasi Agregat 1026,988 1282,524 1026,988 0,000 0,272 0,272 0,272 100% 0,000 0,000 completed
b. Lapis Resap Pengikat 4450,281 3109,148 4363,750 86,531 0,020 0,020 0,020 98% 0,000 0,000 on going M55 M78
c. Lapis Perekat 1369,317 6218,296 663,172 706,145 0,041 0,020 0,020 48% 0,021 0,000 on going M61 M78
d. Lapis Perkerasan AC-Base 618,384 625,716 521,390 96,993 0,439 0,370 0,370 84% 0,069 0,000 on going M66 M78
e. Lapis Perkerasan AC-BC 455,572 536,328 358,290 97,282 0,388 0,305 0,305 79% 0,083 0,000 on going M61 M78
f. Lapis Perkerasan AC-WC 301,934 357,552 54,999 246,936 0,260 0,047 0,047 18% 0,213 0,000 on going M78 M78
IV PEDESTRIAN
1 Peningkatan Jalan Section A (Lebar 14 m)
1.1 Pekerjaan Struktur 100%
a. Pekerjaan lantai kerja 52,005 159,915 52,005 0,000 0,027 0,027 0,027 100% 0,000 0,000 completed
b. Pekerjaan Pembesian 1447,639 15170,922 1447,639 0,000 0,043 0,043 0,043 100% 0,000 0,000 completed
c. Pekerjaan Bekisting 404,660 607,679 404,660 0,000 0,022 0,022 0,022 100% 0,000 0,000 completed
d. Pekerjaan Planter Box (Dinding Penahan) 5,206 0,000 5,206 0,008 0,000 0,008 0% 0,008 -0,008 on going M56 M58
SUBTOTAL 1 0,100 0,092 0,100
7 Pekerjaan paving block tebal 10 cm K-300 2844,265 2773,092 2778,475 65,790 0,329 0,321 0,303 98% 0,008 0,018 on going
8 Pekerjaan rambu jalan 58,000 50,000 35,000 23,000 0,072 0,043 0,043 59% 0,029 0,000 on going M76 M78
9 Pengecatan marka jalan 2454,811 2695,059 0,000 2454,811 0,201 0,000 0,000 0% 0,201 0,000 on going M76 M78
10 Pos Keamanan 1,000 1,000 0,982 0,018 0,028 0,028 0,028 98% 0,001 0,000 on going
11 Pekerjaan Pagar Pedestrian 1554,000 1546,600 1554,000 0,000 4,372 4,372 4,372 100% 0,000 0,000 completed
12 Pekerjaan Median Jalan 308,192 323,390 219,479 88,713 0,553 0,394 0,311 71% 0,159 0,083 on going M63 M74
4 Pekerjaan pemasangan u ditch Uk. 80x100x120cm 1900,13 406,28 1667,860 232,270 1,079 0,947 0,583 88% 0,132 0,364 on going M58 M71
5 Pekerjaan pemasangan pipa PVC 3" 1428,08696 1460,15 970,504 457,583 0,058 0,039 0,046 68% 0,019 -0,007 on going M57 M71
6 Pekerjaan ducting beton Uk. 80x80x120cm 4546,462 4913 4464,828 81,634 5,278 5,183 5,278 98% 0,095 -0,095 on going M57 M71
7 Pekerjaan drainase outlet 354,106 390,8 303,956 50,150 0,783 0,672 0,444 86% 0,111 0,228 on going M62 M71
TOTAL VII 11,500 10,814 10,337
Pekerjaan Penyambungan Listrik dan Suplai Air Ke Taman
I Segara Kerti
1 Persiapan
1 Pekerjaan Bongkar Pasang Paving Eksisting (RTH) 47,000 47,000 0,000 47,000 0,003 0,001 0% 0,003 -0,001 on going M59 M62
2 Pekerjaan Coring Beton untuk Tapping 12,000 0,000 12,000 0,002 0,000 0% 0,002 0,000 on going M66 M67
3 Pekerjaan Tangga
A Pekerjaan Struktur
1 Pekerjaan Beton Bertulang K - 225 2,421 0,000 2,421 0,004 0,000 0,000 0% 0,004 0,000 on going M71 M74
2 Pekerjaan Timbunan 5,627 0,000 5,627 0,000 0,000 0,000 0% 0,000 0,000 on going M71 M74
B Pekerjaan Finishing
1 Pekerjaan Beton Lantai K - 225 3,730 0,000 3,730 0,003 0,000 0,000 0% 0,003 0,000 on going M73 M75
2 Pekerjaan Pembesian 75,870 0,000 75,870 0,001 0,000 0,000 0% 0,001 0,000 on going M73 M75
3 Pekerjaan Bekisting 9,810 0,000 9,810 0,001 0,000 0,000 0% 0,001 0,000 on going M73 M75
4 Pekerjaan Pengadaan dan Pemasangan Batu Hitam 22,266 0,000 22,266 0,011 0,000 0,000 0% 0,011 0,000 on going M75 M78
Mengetahui,
Dibuat Oleh,