PROGRESS MINGGUAN
PROGRESS PROGRESS
NO URAIAN PEKERJAAN BOBOT SELURUH KETERANGAN
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
100.00% 65.11%
Jaring Wijanarko, S.T., M.T. Nobertus Sutino, S.T. Juni Yonatan, S.T.
NIP. 19770528 200312 1 005 NIP. 1977602 201101 1 003 NIP. 19880602 201502 1 003
Menyetujui,
Pejabat Pembuat Komitmen
Tangga 2 (Lurus)
a Plat Tangga
Beton Ready Mix K-225 2.00 M3 0.09% 0% 100% 100% 0.09%
Tulangan 420.41 Kg 0.23% 40% 60% 100% 0.23%
Bekisting Lantai Plat Tangga 18.77 M2 0.23% 0% 100% 100% 0.23%
Plesteran Plat Tangga 16.66 M2 0.04% 0% 0% 0% 0.00%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
b Plat Bordes
Beton Ready Mix K-225 0.43 M3 0.02% 0% 100% 100% 0.02%
Tulangan 94.10 Kg 0.05% 40% 60% 100% 0.05%
Bekisting Lantai Plat Bordes 4.30 M2 0.05% 0% 100% 100% 0.05%
Plesteran Plat Bordes 3.60 M2 0.01% 0% 0% 0% 0.00%
c Anak Tangga
Beton Ready Mix K-225 1.92 M3 0.08% 0% 100% 100% 0.08%
Tulangan 25.73 Kg 0.01% 40% 60% 100% 0.01%
Wiremesh M6 Anak Tangga 1183.28 Kg 0.63% 0% 100% 100% 0.63%
Bekisting Anak Tangga 6.38 M2 0.08% 0% 100% 100% 0.08%
Keramik Uk. 30x30 cm 17.96 M2 0.13% 0% 0% 0% 0.00%
2.85% 2.54%
C STRUKTUR LANTAI II
1 Balok Beton Bertulang Uk. 15 x 30 cm
Beton Ready Mix K-225 2.83 M3 0.12% 100% 0% 100% 0.12%
Tulangan 369.93 Kg 0.20% 100% 0% 100% 0.20%
Bekisting Balok 47.10 M2 0.34% 100% 0% 100% 0.34%
2 Balok Beton Bertulang Uk. 20 x 40 cm
Beton Ready Mix K-225 19.65 M3 0.86% 100% 0% 100% 0.86%
Tulangan 3679.36 Kg 2.03% 100% 0% 100% 2.03%
Bekisting Balok 245.60 M2 1.79% 100% 0% 100% 1.79%
Plesteran Balok Luar 39.00 M2 0.10% 100% 0% 100% 0.10%
3 Balok Beton Bertulang Uk. 25 x 50 cm
Beton Ready Mix K-225 6.60 M3 0.29% 100% 0% 100% 0.29%
Tulangan 1187.71 Kg 0.66% 100% 0% 100% 0.66%
Bekisting Balok 66.00 M2 0.48% 100% 0% 100% 0.48%
Plesteran Balok Luar 5.63 M2 0.01% 100% 0% 100% 0.01%
4 Plat Lantai Elevasi + 3.00
Beton Ready Mix K-225 36.15 M3 1.59% 80% 20% 100% 1.59%
Wiremesh 2 x M6 2155.14 Kg 1.15% 85% 15% 100% 1.15%
Plastik Cor 301.28 m2 0.05% 80% 20% 100% 0.05%
Bekisting Lantai 301.28 M2 2.35% 80% 20% 100% 2.35%
5 Kolom Beton Bertulang Uk. 10 x 10 cm
Beton Ready Mix K-225 0.10 M3 0.00% 0% 0% 0% 0.00%
Tulangan 19.02 Kg 0.01% 40% 20% 60% 0.01%
Bekisting Kolom 3.96 M2 0.03% 0% 60% 60% 0.02%
6 Kolom Beton Bertulang Uk. 20 x 20 cm
Beton Ready Mix K-225 0.53 M3 0.02% 0% 100% 100% 0.02%
Tulangan 75.47 Kg 0.04% 80% 20% 100% 0.04%
Bekisting Kolom 10.56 M2 0.08% 0% 100% 100% 0.08%
Plesteran Kolom 7.92 M2 0.02% 0% 100% 100% 0.02%
7 Kolom Beton Bertulang Uk. 30 x 30 cm
Beton Ready Mix K-225 9.21 M3 0.40% 30% 70% 100% 0.40%
Tulangan 1344.99 Kg 0.74% 80% 20% 100% 0.74%
Bekisting Kolom 122.76 M2 0.89% 0% 100% 100% 0.89%
Plesteran Kolom 102.30 M2 0.25% 30% 70% 100% 0.25%
8 Kolom Beton Bertulang Uk. 40 x 40 cm
Beton Ready Mix K-225 1.58 M3 0.07% 0% 100% 100% 0.07%
Tulangan 234.27 Kg 0.13% 40% 60% 100% 0.13%
Bekisting Kolom 15.84 M2 0.11% 0% 100% 100% 0.11%
Plesteran Kolom 13.86 M2 0.03% 0% 100% 100% 0.03%
9 Ring Balok Beton Bertulang Uk. 15 x 30 cm
Beton Ready Mix K-225 7.79 M3 0.34% 0% 100% 100% 0.34%
Tulangan 1019.07 Kg 0.56% 0% 100% 100% 0.56%
Bekisting Ring Balok 129.90 M2 0.95% 0% 100% 100% 0.95%
Plesteran Balok Luar 29.25 M2 0.07% 0% 0% 0% 0.00%
10 Ring Balok Beton Bertulang Uk. 20 x 40 cm
Beton Ready Mix K-225 5.63 M3 0.25% 0% 100% 100% 0.25%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
Tulangan 1055.89 Kg 0.58% 0% 100% 100% 0.58%
Bekisting Ring Balok 70.40 M2 0.51% 0% 100% 100% 0.51%
Plesteran Balok Luar 39.00 M2 0.10% 0% 0% 0% 0.00%
11 Ring Balok Beton Bertulang Uk. 25 x 50 cm
Beton Ready Mix K-225 6.77 M3 0.30% 0% 100% 100% 0.30%
Tulangan 1696.06 Kg 0.94% 0% 100% 100% 0.94%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
Bekisting Ring Balok 84.60 M2 0.62% 0% 100% 100% 0.62%
Plesteran Balok Luar 39.00 M2 0.10% 0% 0% 0% 0.00%
20.17% 19.88%
V. PEKERJAAN ATAP
A ATAP SPANDEK
1 Rangka Atap Baja Ringan 484.93 M2 2.62% 0% 85% 85% 2.22%
2 Atap Spandek 484.93 m2 1.73% 0% 85% 85% 1.47%
3 Nok / Bubungan Atap Spandek 41.44 m 0.11% 0% 50% 50% 0.06%
4 Listplank 107.30 m 0.29% 0% 0% 0% 0.00%
4.74% 3.75%
B ATAP DAK BELAKANG
1 Beton Ready Mix K-225 6.16 m3 0.27% 0% 0% 0% 0.00%
2 Tulangan 314.98 Kg 0.17% 0% 0% 0% 0.00%
3 Bekisting Lantai 51.30 m2 0.40% 0% 0% 0% 0.00%
0.84% 0.00%
X. PEKERJAAN PLUMBING
X.A Lantai 1
1 Instalasi Air Bersih + Pipa AW 1 1/2" + Acc 60.80 m 0.11% 30% 10% 40% 0.04%
2 Instalasi Air Kotor + Pipa AW 3" + Acc 13.00 m 0.04% 20% 20% 40% 0.02%
3 Instalasi Air Buangan + Pipa AW 4" + Acc 13.00 m 0.09% 20% 20% 40% 0.04%
4 Kloset Jongkok 4.00 Unit 0.11% 0% 0% 0% 0.00%
5 Kloset Duduk 2.00 Unit 0.22% 0% 0% 0% 0.00%
6 Wastafel + Dudukan 2.00 Unit 0.13% 0% 0% 0% 0.00%
7 Kran Air 3/4" 8.00 Unit 0.03% 0% 0% 0% 0.00%
8 Floordrain Stainless 6.00 Unit 0.01% 0% 0% 0% 0.00%
9 Kaca Cermin 0.55 m2 0.02% 0% 0% 0% 0.00%
10 Bak Mandi PVC 120 Liter 6.00 Unit 0.09% 0% 0% 0% 0.00%
12 Septic Tank 1 (Buis Beton + Pemasangan) 4.00 Unit 0.06% 0% 0% 0% 0.00%
13 Pekerjaan Septic Tank
a. Galian Tanah 11.25 m3 0.03% 100% 0% 100% 0.03%
b. Beton K-175 4.50 m3 0.19% 100% 0% 100% 0.19%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
c. Tulangan 706.93 Kg 0.39% 100% 0% 100% 0.39%
d. Bekisting 36.00 m2 0.19% 100% 0% 100% 0.19%
1.71% 0.90%
X.B Lantai 2
1 Instalasi Air Bersih + Pipa AW 1 1/2" + Acc 48.00 m 0.09% 30% 10% 40% 0.03%
2 Instalasi Air Kotor + Pipa AW 3" + Acc 48.00 m 0.15% 20% 20% 40% 0.06%
3 Instalasi Air Buangan + Pipa AW 4" + Acc 48.00 m 0.35% 20% 20% 40% 0.14%
4 Kloset Jongkok 7.00 Unit 0.19% 0% 0% 0% 0.00%
5 Kloset Duduk 1.00 Unit 0.11% 0% 0% 0% 0.00%
6 Wastafel + Dudukan 2.00 Unit 0.13% 0% 0% 0% 0.00%
7 Kran Air 3/4" 10.00 Unit 0.03% 0% 0% 0% 0.00%
8 Floordrain Stainless 8.00 Unit 0.01% 0% 0% 0% 0.00%
9 Kaca Cermin 0.55 m2 0.02% 0% 0% 0% 0.00%
10 Bak Mandi PVC 120 Liter 7.00 Unit 0.11% 0% 0% 0% 0.00%
11 Pompa Air 2.00 Unit 0.03% 0% 0% 0% 0.00%
12 Tanki Air Kap. 2000 Liter 3.00 Unit 0.19% 0% 0% 0% 0.00%
1.40% 0.23%
100% 65.11%
TIME SCHEDULE
KEGIATAN : REHABILITASI, RENOVASI, DAN UBAHSUAI BANGUNAN GEDUNG WAKTU PELAKSANAAN hari
LOKASI : BANDUNG
TAHUN ANGGARAN : 2022
PERIODE
BULAN I BULAN II
Bobot Dalam Mg-1 Mg-2 Mg-3 Mg-4 Mg-5 Mg-6 Mg-7 Mg-8 Mg-9
NO. URAIAN PEKERJAAN
(%)
31-Oct-23 6-Nov-23 13-Nov-23 20-Nov-23 27-Nov-23 4-Dec-23 11-Dec-23 18-Dec-23 25-Dec-23 Skala
Curva
s.d. s.d. s.d. s.d. s.d. s.d. s.d. s.d. s.d.
100
II. SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA 0.42 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
80
III. PEKERJAAN PONDASI 4.87 2.98 2.98
70
IV. PEKERJAAN STRUKTUR BETON BERTULANG 36.77 8.58 8.58 10.41 2.83 9.77
VI. PEKERJAAN LANTAI, DINDING DAN PLAFOND 25.80 8.05 7.53 7.97 -2.72
50
20
X. PEKERJAAN PLUMBING 2.43 0.31 1.40 1.40
100.00
RENCANA KEMAJUAN PERMINGGU 0.99 3.03 3.03 8.63 8.94 18.51 17.05 20.61 19.20
RENCANA KOMULATIF SAMPAI MINGGU KE 0 0.99 4.03 7.06 15.69 24.63 43.14 60.19 80.80 100.00
REALISASI KEMAJUAN PERMINGGU 0.14 3.17 3.51 9.18 8.09 12.20 14.12 14.70
REALISASI KOMULATIF SAMPAI MINGGU KE - 0.14 3.31 6.82 16.00 24.08 36.29 50.41 65.11
DEVIASI PEKERJAAN (0.85) (0.72) (0.24) 0.31 (0.55) (6.86) (9.79) (15.69)