REKAPITULASI

PROGRESS MINGGUAN

PEKERJAAN : RENOVASI ASRAMA MAHASISWA KALBAR DI BANDUNG


MINGGU KE : 8 (Delapan)
PERIODE TANGGAL : 17-Dec-23 s.d. 23-Dec-23
TAHUN ANGGARAN : 2022

PROGRESS PROGRESS
NO URAIAN PEKERJAAN BOBOT SELURUH KETERANGAN
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8

I. PEKERJAAN PERSIAPAN 0.94% 11.33% 55.90% 67.23% 0.63%


II. SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA 0.48% 9.68% 54.00% 63.68% 0.30%
III. PEKERJAAN PONDASI 5.96% 32.49% 67.51% 100.00% 5.96%
IV. PEKERJAAN STRUKTUR BETON BERTULANG 40.17% 2.80% 95.66% 98.47% 39.55%
V. PEKERJAAN ATAP 5.58% 0.00% 67.10% 67.10% 3.75%
VI. PEKERJAAN LANTAI, DINDING DAN PLAFOND 20.83% 0.00% 63.98% 63.98% 13.33%
VII. PEKERJAAN PINTU,JENDELA DAN VENTILASI 6.82% 0.00% 0.00% 0.00% 0.00%
VIII. PEKERJAAN PENGECATAN 2.83% 0.00% 0.00% 0.00% 0.00%
IX. PEKERJAAN ELEKTRIKAL 3.63% 0.00% 12.56% 12.56% 0.46%
X. PEKERJAAN PLUMBING 3.11% 0.00% 36.40% 36.40% 1.13%
XI. PEKERJAAN INTERIOR & EKSTERIOR 4.65% 0.00% 0.00% 0.00% 0.00%
XII. PEKERJAAN HALAMAN 4.99% 0.00% 0.00% 0.00% 0.00%

100.00% 65.11%

PROGRESS TERCAPAI MINGGU INI 65.11%


PROGRESS TERCAPAI S.D. MINGGU LALU 50.41%
PENAMBAHAN PROGRESS MINGGU INI 14.70%
RENCANA KEMAJUAN KOMULATIF S.D. MINGGU INI 80.80%
DEVIASI -15.69%

Bandung, 20 Desember 2023


Diperiksa Oleh, Dibuat Oleh,
Konsultan Pengawas Kontraktor Pelaksana
PT. GUMILANG SAJATI CV. MAKMUR PERMATA LESTARI

Nurlita Hidayah, S.T., IAI. Iman Sulaiman, S.T.


Team Leader Site Manager

Menyetujui, Diperiksa Oleh,


Pejabat Pelaksana Teknis Kegiatan Tim Teknis

Jaring Wijanarko, S.T., M.T. Nobertus Sutino, S.T. Juni Yonatan, S.T.
NIP. 19770528 200312 1 005 NIP. 1977602 201101 1 003 NIP. 19880602 201502 1 003

Menyetujui,
Pejabat Pembuat Komitmen

Isfandiar, S.T., M.T.


NIP. 19800612 201101 1 003
PROGRESS MINGGUAN
PEKERJAAN : RENOVASI ASRAMA MAHASISWA KALBAR DI BANDUNG
MINGGU KE : 8 (Delapan)
PERIODE TANGGAL : 17-Dec-23 s.d. 23-Dec-23
TAHUN ANGGARAN : 2022

PROGRESS (%) PROGRESS


NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
I. PEKERJAAN PERSIAPAN
1 Pembongkaran Gedung Lama 81.29 m3 0.44% 100% 0% 100% 0.44%
2 Pengukuran & Pembuatan Bouwplank 98.00 m 0.19% 100% 0% 100% 0.19%
3 Pembuatan Direksi Keet, Gudang & Los Kerja 24.00 m2 0.31% 0% 0% 0% 0.00%
4 Pembuatan Papan Nama Proyek 1.00 Ls 0.01% 100% 0% 100% 0.01%
0.94% 0.63%
II. SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA
1 Penyiapan RKK, RKPPL, dan RMLLP 1.00 Ls 0.01% 50% 0% 50% 0.00%
2 Sosialiasi, Promosi dan Pelatihan 1.00 Ls 0.01% 60% 0% 60% 0.00%
3 Alat Pelindung Kerja dan Alat Pelindung Diri 1.00 Ls 0.15% 50% 0% 50% 0.08%
4 Asuransi dan Perizinan 1.00 Ls 0.15% 60% 0% 60% 0.09%
5 Personel Keselamatan Konstruksi 1.00 Ls 0.05% 50% 0% 50% 0.02%
6 Fasilitas Sarana, Prasarana dan Alat Kesehatan 1.00 Ls 0.02% 100% 0% 100% 0.02%
7 Rambu dan Perlengkapan Lalu Lintas yang Diperlukan 1.00 Ls 0.01% 50% 0% 50% 0.00%
8 Konsultasi dengan Ahli Terkait Keselamatan Konstruksi 1.00 Ls 0.08% 100% 0% 100% 0.08%
9 Kegiatan dan Peralatan Terkait dengan Pengendalian 1.00 Ls 0.01% 100% 0% 100% 0.01%
0.48% 0.30%
III. PEKERJAAN PONDASI
1 Galian Tanah 136.78 M3 0.38% 100% 0% 100% 0.38%
2 Urugan Tanah Kembali 101.98 m3 0.21% 100% 0% 100% 0.21%
2 Urugan Pasir bawah poer t = 10 cm 9.12 M3 0.07% 100% 0% 100% 0.07%
3 Lantai Kerja bawah poer t = 5 cm 4.56 M3 0.17% 100% 0% 100% 0.17%
4 Poer Pondasi Beton Bertulang Type P1
Beton Ready Mix K-300 1.01 M3 0.05% 100% 0% 100% 0.05%
Tulangan 247.15 Kg 0.14% 100% 0% 100% 0.14%
Bekisting Pondasi 5.40 M2 0.04% 100% 0% 100% 0.04%
5 Poer Pondasi Beton Bertulang Type P2
Beton Ready Mix K-300 2.40 M3 0.11% 100% 0% 100% 0.11%
Tulangan 509.08 Kg 0.28% 100% 0% 100% 0.28%
Bekisting Pondasi 9.60 M2 0.06% 100% 0% 100% 0.06%
6 Poer Pondasi Beton Bertulang Type P3
Beton Ready Mix K-300 8.75 M3 0.40% 100% 0% 100% 0.40%
Tulangan 1695.16 Kg 0.94% 100% 0% 100% 0.94%
Bekisting Pondasi 28.00 M2 0.19% 100% 0% 100% 0.19%
7 Poer Pondasi Beton Bertulang Type P4
Beton Ready Mix K-300 3.38 M3 0.16% 100% 0% 100% 0.16%
Tulangan 488.62 Kg 0.27% 100% 0% 100% 0.27%
Bekisting Pondasi 9.00 M2 0.06% 100% 0% 100% 0.06%
8 Poer Pondasi Beton Bertulang Type P5
Beton Ready Mix K-300 5.51 M3 0.25% 100% 0% 100% 0.25%
Tulangan 746.19 Kg 0.41% 100% 0% 100% 0.41%
Bekisting Pondasi 12.60 M2 0.08% 100% 0% 100% 0.08%
9 Kolom Pondasi Beton Bertulang Uk. 20 x 20 cm
Beton Ready Mix K-300 0.23 M3 0.01% 100% 0% 100% 0.01%
Tulangan 54.06 Kg 0.03% 100% 0% 100% 0.03%
Bekisting Kolom Pondasi 4.60 M2 0.03% 100% 0% 100% 0.03%
10 Kolom Pondasi Beton Bertulang Uk. 30 x 30 cm
Beton Ready Mix K-300 5.18 M3 0.24% 100% 0% 100% 0.24%
Tulangan 1192.88 Kg 0.66% 100% 0% 100% 0.66%
Bekisting Kolom Pondasi 69.00 M2 0.50% 100% 0% 100% 0.50%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
11 Kolom Pondasi Beton Bertulang Uk. 40 x 40 cm
Beton Ready Mix K-300 0.92 M3 0.04% 100% 0% 100% 0.04%
Tulangan 212.08 Kg 0.12% 100% 0% 100% 0.12%
Bekisting Kolom Pondasi 9.20 M2 0.07% 100% 0% 100% 0.07%
5.96% 5.96%
IV. PEKERJAAN STRUKTUR BETON BERTULANG
A STRUKTUR LANTAI I
1 Sloof Beton Bertulang Uk. 15 x 30 cm
Beton Ready Mix K-225 4.79 M3 0.21% 100% 0% 100% 0.21%
Tulangan 410.52 Kg 0.23% 100% 0% 100% 0.23%
Bekisting Sloof Bertulang 410.52 M2 2.22% 100% 0% 100% 2.22%
2 Sloof Beton Bertulang Uk. 20 x 40 cm
Beton Ready Mix K-225 22.32 M3 0.98% 100% 0% 100% 0.98%
Tulangan 4073.57 Kg 2.25% 100% 0% 100% 2.25%
Bekisting Sloof Bertulang 279.00 M2 1.51% 100% 0% 100% 1.51%
Plesteran Sloof Luar 39.00 M2 0.10% 100% 0% 100% 0.10%
3 Dinding Penahan Tanah
Beton Ready Mix K-225 4.70 M3 0.21% 0% 100% 100% 0.21%
Tulangan 450.49 Kg 0.25% 0% 100% 100% 0.25%
Bekisting 62.67 m3 0.34% 0% 100% 100% 0.34%
4 Plat Lantai
Beton Ready Mix K-225 39.15 M3 1.72% 100% 0% 100% 1.72%
Wiremesh 2 x M6 2357.76 Kg 1.26% 100% 0% 100% 1.26%
Urugan Pasir Bawah Lantai 32.63 m3 0.24% 100% 0% 100% 0.24%
Urugan Tanah Bawah Lantai 176.33 m3 0.95% 100% 0% 100% 0.95%
5 Kolom Beton Bertulang Uk. 10 x 10 cm
Beton Ready Mix K-225 0.34 M3 0.01% 0% 0% 0% 0.00%
Tulangan 65.66 Kg 0.04% 70% 0% 70% 0.03%
Bekisting Kolom Bertulang 6.82 M2 0.05% 100% 0% 100% 0.05%
6 Kolom Beton Bertulang Uk. 20 x 20 cm
Beton Ready Mix K-225 1.98 M3 0.09% 50% 50% 100% 0.09%
Tulangan 283.98 Kg 0.16% 100% 0% 100% 0.16%
Bekisting Kolom Bertulang 39.68 M2 0.29% 100% 0% 100% 0.29%
Plesteran Kolom 29.76 M2 0.07% 50% 50% 100% 0.07%
7 Kolom Beton Bertulang Uk. 30 x 30 cm
Beton Ready Mix K-225 14.79 M3 0.65% 100% 0% 100% 0.65%
Tulangan 2174.55 Kg 1.20% 100% 0% 100% 1.20%
Bekisting Kolom Bertulang 197.16 M2 1.42% 100% 0% 100% 1.42%
Plesteran Kolom 164.30 M2 0.40% 100% 0% 100% 0.40%
8 Kolom Beton Bertulang Uk. 40 x 40 cm
Beton Ready Mix K-225 1.49 M3 0.07% 100% 0% 100% 0.07%
Tulangan 221.94 Kg 0.12% 100% 0% 100% 0.12%
Bekisting Kolom Bertulang 14.88 M2 0.11% 100% 0% 100% 0.11%
Plesteran Kolom 13.02 M2 0.03% 100% 0% 100% 0.03%
17.16% 17.13%
B STRUKTUR TANGGA
Tangga 1 (U)
a Plat Tangga
Beton Ready Mix K-225 1.35 M3 0.06% 0% 100% 100% 0.06%
Tulangan 282.31 Kg 0.16% 40% 60% 100% 0.16%
Bekisting Lantai Plat Tangga 13.05 M2 0.16% 0% 100% 100% 0.16%
Plesteran Plat Tangga 11.25 M2 0.03% 0% 0% 0% 0.00%
b Plat Bordes
Beton Ready Mix K-225 0.52 M3 0.02% 0% 100% 100% 0.02%
Tulangan 112.66 Kg 0.06% 40% 60% 100% 0.06%
Bekisting Lantai Plat Bordes 5.24 M2 0.06% 0% 100% 100% 0.06%
Plesteran Plat Bordes 4.35 M2 0.01% 0% 0% 0% 0.00%
c Anak Tangga
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
Beton Ready Mix K-225 1.37 M3 0.06% 0% 100% 100% 0.06%
Tulangan 23.28 Kg 0.01% 40% 60% 100% 0.01%
Wiremesh M6 Anak Tangga 764.71 Kg 0.41% 0% 100% 100% 0.41%
Bekisting Anak Tangga 4.56 M2 0.06% 0% 100% 100% 0.06%
Keramik Uk. 30x30 cm 12.83 M2 0.09% 0% 0% 0% 0.00%

Tangga 2 (Lurus)
a Plat Tangga
Beton Ready Mix K-225 2.00 M3 0.09% 0% 100% 100% 0.09%
Tulangan 420.41 Kg 0.23% 40% 60% 100% 0.23%
Bekisting Lantai Plat Tangga 18.77 M2 0.23% 0% 100% 100% 0.23%
Plesteran Plat Tangga 16.66 M2 0.04% 0% 0% 0% 0.00%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
b Plat Bordes
Beton Ready Mix K-225 0.43 M3 0.02% 0% 100% 100% 0.02%
Tulangan 94.10 Kg 0.05% 40% 60% 100% 0.05%
Bekisting Lantai Plat Bordes 4.30 M2 0.05% 0% 100% 100% 0.05%
Plesteran Plat Bordes 3.60 M2 0.01% 0% 0% 0% 0.00%
c Anak Tangga
Beton Ready Mix K-225 1.92 M3 0.08% 0% 100% 100% 0.08%
Tulangan 25.73 Kg 0.01% 40% 60% 100% 0.01%
Wiremesh M6 Anak Tangga 1183.28 Kg 0.63% 0% 100% 100% 0.63%
Bekisting Anak Tangga 6.38 M2 0.08% 0% 100% 100% 0.08%
Keramik Uk. 30x30 cm 17.96 M2 0.13% 0% 0% 0% 0.00%
2.85% 2.54%
C STRUKTUR LANTAI II
1 Balok Beton Bertulang Uk. 15 x 30 cm
Beton Ready Mix K-225 2.83 M3 0.12% 100% 0% 100% 0.12%
Tulangan 369.93 Kg 0.20% 100% 0% 100% 0.20%
Bekisting Balok 47.10 M2 0.34% 100% 0% 100% 0.34%
2 Balok Beton Bertulang Uk. 20 x 40 cm
Beton Ready Mix K-225 19.65 M3 0.86% 100% 0% 100% 0.86%
Tulangan 3679.36 Kg 2.03% 100% 0% 100% 2.03%
Bekisting Balok 245.60 M2 1.79% 100% 0% 100% 1.79%
Plesteran Balok Luar 39.00 M2 0.10% 100% 0% 100% 0.10%
3 Balok Beton Bertulang Uk. 25 x 50 cm
Beton Ready Mix K-225 6.60 M3 0.29% 100% 0% 100% 0.29%
Tulangan 1187.71 Kg 0.66% 100% 0% 100% 0.66%
Bekisting Balok 66.00 M2 0.48% 100% 0% 100% 0.48%
Plesteran Balok Luar 5.63 M2 0.01% 100% 0% 100% 0.01%
4 Plat Lantai Elevasi + 3.00
Beton Ready Mix K-225 36.15 M3 1.59% 80% 20% 100% 1.59%
Wiremesh 2 x M6 2155.14 Kg 1.15% 85% 15% 100% 1.15%
Plastik Cor 301.28 m2 0.05% 80% 20% 100% 0.05%
Bekisting Lantai 301.28 M2 2.35% 80% 20% 100% 2.35%
5 Kolom Beton Bertulang Uk. 10 x 10 cm
Beton Ready Mix K-225 0.10 M3 0.00% 0% 0% 0% 0.00%
Tulangan 19.02 Kg 0.01% 40% 20% 60% 0.01%
Bekisting Kolom 3.96 M2 0.03% 0% 60% 60% 0.02%
6 Kolom Beton Bertulang Uk. 20 x 20 cm
Beton Ready Mix K-225 0.53 M3 0.02% 0% 100% 100% 0.02%
Tulangan 75.47 Kg 0.04% 80% 20% 100% 0.04%
Bekisting Kolom 10.56 M2 0.08% 0% 100% 100% 0.08%
Plesteran Kolom 7.92 M2 0.02% 0% 100% 100% 0.02%
7 Kolom Beton Bertulang Uk. 30 x 30 cm
Beton Ready Mix K-225 9.21 M3 0.40% 30% 70% 100% 0.40%
Tulangan 1344.99 Kg 0.74% 80% 20% 100% 0.74%
Bekisting Kolom 122.76 M2 0.89% 0% 100% 100% 0.89%
Plesteran Kolom 102.30 M2 0.25% 30% 70% 100% 0.25%
8 Kolom Beton Bertulang Uk. 40 x 40 cm
Beton Ready Mix K-225 1.58 M3 0.07% 0% 100% 100% 0.07%
Tulangan 234.27 Kg 0.13% 40% 60% 100% 0.13%
Bekisting Kolom 15.84 M2 0.11% 0% 100% 100% 0.11%
Plesteran Kolom 13.86 M2 0.03% 0% 100% 100% 0.03%
9 Ring Balok Beton Bertulang Uk. 15 x 30 cm
Beton Ready Mix K-225 7.79 M3 0.34% 0% 100% 100% 0.34%
Tulangan 1019.07 Kg 0.56% 0% 100% 100% 0.56%
Bekisting Ring Balok 129.90 M2 0.95% 0% 100% 100% 0.95%
Plesteran Balok Luar 29.25 M2 0.07% 0% 0% 0% 0.00%
10 Ring Balok Beton Bertulang Uk. 20 x 40 cm
Beton Ready Mix K-225 5.63 M3 0.25% 0% 100% 100% 0.25%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
Tulangan 1055.89 Kg 0.58% 0% 100% 100% 0.58%
Bekisting Ring Balok 70.40 M2 0.51% 0% 100% 100% 0.51%
Plesteran Balok Luar 39.00 M2 0.10% 0% 0% 0% 0.00%
11 Ring Balok Beton Bertulang Uk. 25 x 50 cm
Beton Ready Mix K-225 6.77 M3 0.30% 0% 100% 100% 0.30%
Tulangan 1696.06 Kg 0.94% 0% 100% 100% 0.94%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
Bekisting Ring Balok 84.60 M2 0.62% 0% 100% 100% 0.62%
Plesteran Balok Luar 39.00 M2 0.10% 0% 0% 0% 0.00%
20.17% 19.88%

V. PEKERJAAN ATAP
A ATAP SPANDEK
1 Rangka Atap Baja Ringan 484.93 M2 2.62% 0% 85% 85% 2.22%
2 Atap Spandek 484.93 m2 1.73% 0% 85% 85% 1.47%
3 Nok / Bubungan Atap Spandek 41.44 m 0.11% 0% 50% 50% 0.06%
4 Listplank 107.30 m 0.29% 0% 0% 0% 0.00%
4.74% 3.75%
B ATAP DAK BELAKANG
1 Beton Ready Mix K-225 6.16 m3 0.27% 0% 0% 0% 0.00%
2 Tulangan 314.98 Kg 0.17% 0% 0% 0% 0.00%
3 Bekisting Lantai 51.30 m2 0.40% 0% 0% 0% 0.00%
0.84% 0.00%

VI. PEKERJAAN LANTAI, DINDING DAN PLAFOND


VI.A Lantai 1
1 PEKERJAAN DINDING
a. Dinding Bata Ringan 322.19 m2 1.99% 0% 90% 90% 1.79%
b. Dinding Rooster 75.00 m3 0.69% 0% 40% 40% 0.28%
c. Acian Dinding 768.60 m2 0.79% 0% 60% 60% 0.47%
d. Keramik Dinding WC 20x40cm 48.00 m2 0.40% 0% 60% 60% 0.24%
2 PEKERJAAN LANTAI
a. Granite 40x40 cm Polished 192.89 m2 1.38% 0% 80% 80% 1.11%
b. Granite 40x40 cm Unpolished 137.97 m2 0.90% 0% 60% 60% 0.54%
c. Keramik 20x20cm 7.84 m2 0.06% 0% 60% 60% 0.03%
3 PEKERJAAN PLAFOND
a. Rangka Plafond Metal Hollow 344.02 m2 1.27% 0% 100% 100% 1.27%
b. Plafond Gypsum 247.76 m2 0.41% 0% 60% 60% 0.25%
c. Plafond GRC 96.26 m2 0.16% 0% 0% 0% 0.00%
8.05% 5.97%
VI.B Lantai 2
1 PEKERJAAN DINDING
a. Dinding Bata Ringan 669.37 m2 4.12% 0% 90% 90% 3.71%
b. Dinding Rooster 20.40 m2 0.19% 0% 40% 40% 0.08%
c. Acian Dinding 1270.80 m2 1.30% 0% 60% 60% 0.78%
d. Keramik Dinding WC 20x40cm 64.00 m2 0.53% 0% 60% 60% 0.32%
2 PEKERJAAN LANTAI
a. Granite 40x40 cm Polished 176.90 m2 1.27% 0% 60% 60% 0.76%
b. Granite 40x40 cm Unpolished 166.06 m2 1.08% 0% 60% 60% 0.65%
c. Keramik 20x20cm 15.68 m2 0.11% 0% 60% 60% 0.07%
3 PEKERJAAN PLAFOND
a. Rangka Plafond Metal Hollow 358.64 m2 1.33% 0% 60% 60% 0.80%
b. Plafond Gypsum 192.58 m2 0.32% 0% 60% 60% 0.19%
c. Plafond GRC 166.06 m2 0.28% 0% 0% 0% 0.00%
10.53% 7.35%
VI.C Railing Tangga
Tangga 1 (U)
1 Besi Hollow 40x40mm 86.10 m 0.80% 0% 0% 0% 0.00%
2 Kawat Harmonika Kecil 20.32 m2 0.09% 0% 0% 0% 0.00%
3 Pengelasan 720.00 Cm 0.11% 0% 0% 0% 0.00%
Tangga 2 (Lurus)
1 Besi Hollow 40x40mm 63.60 m 0.59% 0% 0% 0% 0.00%
2 Kawat Harmonika Kecil 11.14 m2 0.05% 0% 0% 0% 0.00%
3 Pengelasan 324.00 Cm 0.05% 0% 0% 0% 0.00%
Railing Pagar
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
1 Besi Hollow 40x40mm 51.00 m 0.47% 0% 0% 0% 0.00%
2 Kawat Harmonika Kecil 10.50 m2 0.05% 0% 0% 0% 0.00%
3 Pengelasan 228.00 Cm 0.04% 0% 0% 0% 0.00%
2.25% 0.00%

VII. PEKERJAAN PINTU,JENDELA DAN VENTILASI


VII.A Lantai 1
1 Pintu, Jendela dan Ventilasi (PJV.1)
a. Kusen Alumunium Putih 169.92 m 0.62% 0% 0% 0% 0.00%
b. Daun Pintu panel + fin. HPL (70 x 210 cm) 20.16 m2 0.47% 0% 0% 0% 0.00%
c. Engsel Pintu 36.00 Bh 0.10% 0% 0% 0% 0.00%
d. Handle + Kunci Pintu 12.00 Bh 0.09% 0% 0% 0% 0.00%
e. Ventilasi Alumunium 6.05 m2 0.09% 0% 0% 0% 0.00%
f. Kaca Tebal 5mm 5.04 m2 0.04% 0% 0% 0% 0.00%
g. Engsel Casement Jendela 24.00 Set 0.11% 0% 0% 0% 0.00%
h. Rambuncis Aluminium 24.00 Unit 0.02% 0% 0% 0% 0.00%
i. Jendela Kaca Hidup, Rangka Alumunium 24.00 Unit 0.56% 0% 0% 0% 0.00%
2 Pintu dan Ventilasi (PV.2)
a. Kusen Alumunium Putih 6.48 m 0.02% 0% 0% 0% 0.00%
b. Daun Pintu panel kayu klas I 1 (70 x 210 cm) 1.47 m2 0.03% 0% 0% 0% 0.00%
c. Engsel Pintu 3.00 Bh 0.01% 0% 0% 0% 0.00%
d. Handle + Kunci Pintu 1.00 Bh 0.01% 0% 0% 0% 0.00%
e. Slot Pintu 1.00 Bh 0.00% 0% 0% 0% 0.00%
f. Ventilasi Alumunium 0.56 m2 0.01% 0% 0% 0% 0.00%
g. Kaca Tebal 5mm 1.40 m2 0.01% 0% 0% 0% 0.00%
4 Jendela dan Ventilasi (JV.1)
a. Kusen Alumunium Putih 10.80 m 0.04% 0% 0% 0% 0.00%
b. Jendela Kaca Hidup, Rangka Alumunium 4.00 Unit 0.09% 0% 0% 0% 0.00%
c. Kaca Tebal 5mm 0.84 m2 0.01% 0% 0% 0% 0.00%
d. Engsel Casement Jendela 4.00 Set 0.02% 0% 0% 0% 0.00%
e. Rambuncis Aluminium 4.00 Unit 0.00% 0% 0% 0% 0.00%
5 Ventilasi (V.1)
a. Kusen Alumunium Putih 5.08 m 0.02% 0% 0% 0% 0.00%
b. Kaca Tebal 5mm 0.74 m2 0.01% 0% 0% 0% 0.00%
6 Pintu Alumunium Toilet + ACC 4.00 Unit 0.12% 0% 0% 0% 0.00%
7 Pintu Dorong Besi
a. Daun Pintu panel kayu klas I 1 (70 x 210 cm) 7.56 m2 0.22% 0% 0% 0% 0.00%
b. Rel Pintu Dorong 1.00 Set 0.03% 0% 0% 0% 0.00%
2.76% 0.00%
VII.B Lantai 2
1 Pintu, Jendela dan Ventilasi (PJV.1)
a. Kusen Alumunium Putih 283.20 m 1.04% 0% 0% 0% 0.00%
b. Daun Pintu panel + fin. HPL (70 x 210 cm) 33.60 m2 0.78% 0% 0% 0% 0.00%
c. Engsel Pintu 60.00 Bh 0.17% 0% 0% 0% 0.00%
d. Handle + Kunci Pintu 20.00 Bh 0.14% 0% 0% 0% 0.00%
e. Ventilasi Alumunium 10.08 m2 0.16% 0% 0% 0% 0.00%
f. Kaca Tebal 5mm 8.40 m2 0.07% 0% 0% 0% 0.00%
g. Engsel Casement Jendela 40.00 Set 0.19% 0% 0% 0% 0.00%
h. Rambuncis Aluminium 40.00 Unit 0.03% 0% 0% 0% 0.00%
i. Jendela Kaca Hidup, Rangka Alumunium 40.00 Unit 0.93% 0% 0% 0% 0.00%
2 Jendela dan Ventilasi (JV.1)
a. Kusen Alumunium Putih 21.60 m 0.08% 0% 0% 0% 0.00%
b. Jendela Kaca Hidup, Rangka Alumunium 8.00 Unit 0.19% 0% 0% 0% 0.00%
c. Kaca Tebal 5mm 1.68 m2 0.01% 0% 0% 0% 0.00%
d. Engsel Casement Jendela 8.00 Set 0.04% 0% 0% 0% 0.00%
e. Rambuncis Aluminium 8.00 Unit 0.01% 0% 0% 0% 0.00%
3 Pintu Alumunium Toilet + ACC 8.00 Unit 0.25% 0% 0% 0% 0.00%
4.07% 0.00%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8

VIII. PEKERJAAN PENGECATAN


1 Cat Tembok Weathershield ex Dulux 506.15 m2 0.82% 0% 0% 0% 0.00%
2 Cat Tembok Interior ex Dulux 1237.20 m2 1.42% 0% 0% 0% 0.00%
3 Cat Meni Besi 321.12 m2 0.55% 0% 0% 0% 0.00%
4 Cat Meni Kayu 24.00 m2 0.04% 0% 0% 0% 0.00%
2.83% 0.00%

IX. PEKERJAAN ELEKTRIKAL


IX.A Lantai 1
1 Instalasi Titik Lampu dan Stop Kontak 68.00 Titik 0.52% 0% 40% 40% 0.21%
2 Lampu Downlight 16watt + Fitting 45.00 Bh 0.21% 0% 0% 0% 0.00%
3 Lampu Downlight 12 watt + Fitting 7.00 Bh 0.03% 0% 0% 0% 0.00%
4 Lampu LED Strip 16.00 m 0.02% 0% 0% 0% 0.00%
5 Saklar Tunggal 20.00 Bh 0.03% 0% 0% 0% 0.00%
6 Saklar Ganda 5.00 Bh 0.01% 0% 0% 0% 0.00%
7 Saklar Triple 15.00 Bh 0.02% 0% 0% 0% 0.00%
8 Stop Kontak 15.00 Bh 0.02% 0% 0% 0% 0.00%
9 MCB 6 A 3.00 Bh 0.00% 0% 0% 0% 0.00%
10 MCB Box 3.00 Bh 0.02% 0% 0% 0% 0.00%
11 Box Panel 1.00 Bh 0.15% 0% 0% 0% 0.00%
1.05% 0.21%
IX.B Lantai 2
1 Instalasi Titik Lampu dan Stop Kontak 80.00 Titik 0.62% 0% 40% 40% 0.25%
2 Lampu Downlight 16watt + Fitting 51.00 Bh 0.24% 0% 0% 0% 0.00%
3 Lampu Downlight 12 watt + Fitting 8.00 Bh 0.03% 0% 0% 0% 0.00%
4 Lampu LED Strip 18.00 m 0.03% 0% 0% 0% 0.00%
5 Saklar Tunggal 33.00 Bh 0.05% 0% 0% 0% 0.00%
6 Saklar Ganda 3.00 Bh 0.00% 0% 0% 0% 0.00%
7 Stop Kontak 20.00 Bh 0.03% 0% 0% 0% 0.00%
8 MCB 6 A 3.00 Bh 0.00% 0% 0% 0% 0.00%
9 MCB Box 3.00 Bh 0.02% 0% 0% 0% 0.00%
10 Box Panel 1.00 Bh 0.15% 0% 0% 0% 0.00%
11 Lampu Sorot 50watt 2.00 Bh 0.06% 0% 0% 0% 0.00%
11 Instalasi Penangkal Petir
- Head Penangkal Petir Non-Radioaktif 6.00 Unit 0.93% 0% 0% 0% 0.00%
- Down Conductor NYY 1x70 mm 29.00 M 0.09% 0% 0% 0% 0.00%
Dudukan Tiang, Tiang Penangkal Petir (5 meter) dan Material
- 6.00 Unit 0.19% 0% 0% 0% 0.00%
Bantu
- Grounding Sistem, Bak Kontrol, dan Instalasi 1.00 Unit 0.15% 0% 0% 0% 0.00%
2.59% 0.25%

X. PEKERJAAN PLUMBING
X.A Lantai 1
1 Instalasi Air Bersih + Pipa AW 1 1/2" + Acc 60.80 m 0.11% 30% 10% 40% 0.04%
2 Instalasi Air Kotor + Pipa AW 3" + Acc 13.00 m 0.04% 20% 20% 40% 0.02%
3 Instalasi Air Buangan + Pipa AW 4" + Acc 13.00 m 0.09% 20% 20% 40% 0.04%
4 Kloset Jongkok 4.00 Unit 0.11% 0% 0% 0% 0.00%
5 Kloset Duduk 2.00 Unit 0.22% 0% 0% 0% 0.00%
6 Wastafel + Dudukan 2.00 Unit 0.13% 0% 0% 0% 0.00%
7 Kran Air 3/4" 8.00 Unit 0.03% 0% 0% 0% 0.00%
8 Floordrain Stainless 6.00 Unit 0.01% 0% 0% 0% 0.00%
9 Kaca Cermin 0.55 m2 0.02% 0% 0% 0% 0.00%
10 Bak Mandi PVC 120 Liter 6.00 Unit 0.09% 0% 0% 0% 0.00%
12 Septic Tank 1 (Buis Beton + Pemasangan) 4.00 Unit 0.06% 0% 0% 0% 0.00%
13 Pekerjaan Septic Tank
a. Galian Tanah 11.25 m3 0.03% 100% 0% 100% 0.03%
b. Beton K-175 4.50 m3 0.19% 100% 0% 100% 0.19%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
c. Tulangan 706.93 Kg 0.39% 100% 0% 100% 0.39%
d. Bekisting 36.00 m2 0.19% 100% 0% 100% 0.19%
1.71% 0.90%
X.B Lantai 2
1 Instalasi Air Bersih + Pipa AW 1 1/2" + Acc 48.00 m 0.09% 30% 10% 40% 0.03%
2 Instalasi Air Kotor + Pipa AW 3" + Acc 48.00 m 0.15% 20% 20% 40% 0.06%
3 Instalasi Air Buangan + Pipa AW 4" + Acc 48.00 m 0.35% 20% 20% 40% 0.14%
4 Kloset Jongkok 7.00 Unit 0.19% 0% 0% 0% 0.00%
5 Kloset Duduk 1.00 Unit 0.11% 0% 0% 0% 0.00%
6 Wastafel + Dudukan 2.00 Unit 0.13% 0% 0% 0% 0.00%
7 Kran Air 3/4" 10.00 Unit 0.03% 0% 0% 0% 0.00%
8 Floordrain Stainless 8.00 Unit 0.01% 0% 0% 0% 0.00%
9 Kaca Cermin 0.55 m2 0.02% 0% 0% 0% 0.00%
10 Bak Mandi PVC 120 Liter 7.00 Unit 0.11% 0% 0% 0% 0.00%
11 Pompa Air 2.00 Unit 0.03% 0% 0% 0% 0.00%
12 Tanki Air Kap. 2000 Liter 3.00 Unit 0.19% 0% 0% 0% 0.00%
1.40% 0.23%

XI. PEKERJAAN INTERIOR & EKSTERIOR


1 Alumunium Composite Panel + Rangka + Pemasangan 101.70 m2 2.35% 0% 0% 0% 0.00%
2 CNC Cutting Plat + Rangka + Pemasangan
- Motif Melayu 7.52 m2 0.23% 0% 0% 0% 0.00%
- Motif Pucuk Rebung 31.76 m2 0.98% 0% 0% 0% 0.00%
- Motif Enggang Gading 0.72 m2 0.02% 0% 0% 0% 0.00%
- Motif Batik Dayak 16.45 m2 0.51% 0% 0% 0% 0.00%
3 Box Acrylic + Pencahayaan : Logo Pemprov Kalbar 1.00 Unit 0.09% 0% 0% 0% 0.00%
4 Huruf Timbul Stainless Tinggi 20cm
Tulisan "ASRAMA MAHASISWA KALIMANTAN BARAT" 30.00 Huruf 0.46% 0% 0% 0% 0.00%
4.65% 0.00%

XII. PEKERJAAN HALAMAN


1 Pekerjaan Pagar Depan
a. Galian Tanah 0.65 m3 0.00% 0% 0% 0% 0.00%
b. Bekisting 18.72 m2 0.10% 0% 0% 0% 0.00%
c. Pembesian 150.84 Kg 0.08% 0% 0% 0% 0.00%
d. Beton K-175 1.58 m3 0.07% 0% 0% 0% 0.00%
e. Dinding HB10 4.50 m2 0.03% 0% 0% 0% 0.00%
f. Plesteran 14.76 m2 0.04% 0% 0% 0% 0.00%
g. CNC Cutting Plat Motif Pucuk Rebung 13.50 m2 0.42% 0% 0% 0% 0.00%
h. Pengecatan 14.76 m2 0.03% 0% 0% 0% 0.00%

2 Pembuatan Pintu Pagar


a. Rel Pintu Dorong 2.00 Set 0.19% 0% 0% 0% 0.00%
b. Rangka Besi Hollow 40x40 mm 9.60 m2 0.30% 0% 0% 0% 0.00%
c. CNC Cutting Plat Corak Insang 6.40 m2 0.20% 0% 0% 0% 0.00%
d. Kunci Pintu Besi 2.00 Set 0.03% 0% 0% 0% 0.00%

3 Pekerjaan Saluran Keliling


a. Galian Tanah 15.15 m3 0.04% 0% 0% 0% 0.00%
b. Bekisting 40.40 m2 0.22% 0% 0% 0% 0.00%
c. Wiremesh M-5 150.59 Kg 0.08% 0% 0% 0% 0.00%
d. Beton K-175 7.07 m3 0.29% 0% 0% 0% 0.00%

4. Pekerjaan Lantai Halaman & Lapangan Bulu Tangkis


Ramp Jalan
a. Bekisting 1.13 m2 0.01% 0% 0% 0% 0.00%
b. Urugan Pasir 0.70 m3 0.01% 0% 0% 0% 0.00%
PROGRESS (%) PROGRESS
NO. NAMA PEKERJAAN VOLUME BOBOT SELURUH
s.d. MG. LALU MG. INI s.d. MG. INI PEKERJAAN
1 2 3 4 5 6 7 8
c. Plastik Cor 2.25 m2 0.00% 0% 0% 0% 0.00%
d. Beton K-175 1.40 m2 0.06% 0% 0% 0% 0.00%
Paving Stone
a. Bekisting 22.80 m2 0.12% 0% 0% 0% 0.00%
b. Beton K-175 1.71 m3 0.07% 0% 0% 0% 0.00%
c. Paving Stone K-300 210.49 m2 2.27% 0% 0% 0% 0.00%
d. Pengecatan 210.49 m2 0.36% 0% 0% 0% 0.00%
4.99% 0.00%

100% 65.11%
TIME SCHEDULE

KEGIATAN : REHABILITASI, RENOVASI, DAN UBAHSUAI BANGUNAN GEDUNG WAKTU PELAKSANAAN hari
LOKASI : BANDUNG
TAHUN ANGGARAN : 2022

PERIODE

BULAN I BULAN II

Bobot Dalam Mg-1 Mg-2 Mg-3 Mg-4 Mg-5 Mg-6 Mg-7 Mg-8 Mg-9
NO. URAIAN PEKERJAAN
(%)
31-Oct-23 6-Nov-23 13-Nov-23 20-Nov-23 27-Nov-23 4-Dec-23 11-Dec-23 18-Dec-23 25-Dec-23 Skala
Curva
s.d. s.d. s.d. s.d. s.d. s.d. s.d. s.d. s.d.

5-Nov-23 12-Nov-23 19-Nov-23 26-Nov-23 3-Dec-23 10-Dec-23 17-Dec-23 24-Dec-23 31-Dec-23


1 2 3 4 5 6 7 8 9 10 11 12

100

I. PEKERJAAN PERSIAPAN 1.05 0.94


90

II. SISTEM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA 0.42 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
80
III. PEKERJAAN PONDASI 4.87 2.98 2.98

70
IV. PEKERJAAN STRUKTUR BETON BERTULANG 36.77 8.58 8.58 10.41 2.83 9.77

V. PEKERJAAN ATAP 9.52 5.58 60

VI. PEKERJAAN LANTAI, DINDING DAN PLAFOND 25.80 8.05 7.53 7.97 -2.72
50

VII. PEKERJAAN PINTU,JENDELA DAN VENTILASI 6.00 3.41 3.41


40
VIII. PEKERJAAN PENGECATAN 2.09 1.42 1.42
30
IX. PEKERJAAN ELEKTRIKAL 2.16 1.82 1.82

20
X. PEKERJAAN PLUMBING 2.43 0.31 1.40 1.40

XI. PEKERJAAN INTERIOR & EKSTERIOR 5.11 4.65 10

XII. PEKERJAAN HALAMAN 3.77 4.99 0

100.00

RENCANA KEMAJUAN PERMINGGU 0.99 3.03 3.03 8.63 8.94 18.51 17.05 20.61 19.20

RENCANA KOMULATIF SAMPAI MINGGU KE 0 0.99 4.03 7.06 15.69 24.63 43.14 60.19 80.80 100.00

REALISASI KEMAJUAN PERMINGGU 0.14 3.17 3.51 9.18 8.09 12.20 14.12 14.70

REALISASI KOMULATIF SAMPAI MINGGU KE - 0.14 3.31 6.82 16.00 24.08 36.29 50.41 65.11

DEVIASI PEKERJAAN (0.85) (0.72) (0.24) 0.31 (0.55) (6.86) (9.79) (15.69)

Anda mungkin juga menyukai