NO JENIS PEKERJAAN VOLUME BOBOT% OPNAME% PROGRES% A PEKERJAAN PERSIAPAN 1 PENGUKURAN DAN BOUPLANG 82,5 M1 0,697% 100% 0,697% 2 DIREKSI KETT/BEDENG 24 M2 3,509% 100% 3,509%
JUMLAH 4,206% 4,206%
B PEKERJAAN PONDASI 1 GALIAN TANAH 16,5 M3 0,360% 100% 0,360% 2 PASANG PONDASI BATUKALI 12,6 M3 2,976% 100% 2,976% 3 COR SLOOF 2,8 M3 2,204% 100% 2,204% 4 URUGAN TANAH KEMBALI 6 M3 0,101% 100% 0,101%
JUMLAH 5,641% 5,641%
C PEKERJAAN DINDING 1 PASANG DINDING HEBEL 311 M2 10,144% 90% 9,129% 2 COR KOLOM 125 M1 5,202% 90% 4,681% 3 COR RING BALOK 72 M1 2,996% 100% 2,996% 4 COR PILAR/KOLOM UTAMA+BALOK 3,8 M3 3,846% 100% 3,846% 5 PLESTER DINDING 622 M2 10,494% 95% 9,969% 6 ACIAN DINDING 622 M2 6,646% 95% 6,313% 7 PASANG LOSTER 700 M2 0,212% 100% 0,212% 8 PASANG PINTU UTAMA 3 UNIT 3,205% 65% 2,083% 9 PASANG JENDELA 8 UNIT 2,699% 65% 1,754% 10 PINTU KM/WC 4 UNIT 1,349% 50% 0,674% 11 PINTU R.ALAT DAN GUDANG 2 UNIT 1,124% 65% 0,730% 12 CAT DINDING 616 M2 3,778% JUMLAH 51,695% 42,331% D PEKERJAAN ATAP 1 PASANG ATAP /BAJA RINGAN 185 M2 15,815% 65% 10,279% 2 PASANG LIST PLANG 78 M1 0,614% 3 CAT LIST PLANG 24,45 M2 0,192% JUMLAH 16,621% 10,279% E PEKERJAAN PLAPOND 1 PASANG PLAPOND GYPSUM/HOLLOW 140 M2 5,039% 2 PASANG LIST PLAPOND 143,20 M1 0,886% 3 CAT PLAPOND 197,47 M2 1,555% JUMLAH 7,480% F PEKERJAAN LANTAI 1 PASANG KERAMIK LANTAI 40x40 120 M2 4,570% 2 PASANG KERAMIK LANTAI KM/WC 20x20 26,25 M1 0,915% 3 PASANG KERAMIK DINDING 20x25 25,60 M2 1,007% JUMLAH 6,492% G PEKERJAAN SAMITASI 1 PASANG CLOSET JONGKOK 4 UNIT 0,337% 2 PASANG PIPA 4’’ 17 M1 0,325% 3 PASANG PIPA 3’’ 14 M1 0,236% 4 PASANG PIPA 1/2’’ 34 M1 0,344% 5 PASANG FLOUR DRAIN 4 UNIT 0,112% 6 PASANG KRAN AIR 6 UNIT 0,168% 7 SEPTIC TANK 1 UNIT 4,464% 65% 2,901% JUMLAH 5,986% 2,901% RAB PEKERJAAN MASJID
PERIODE TGL : 12 JUNI 2023
NO JENIS PEKERJAAN VOLUME BOBOT% OPNAME% PROGRES% H PEKERJAAN ELECTRICAL 1 PASANG KWH METER 1 UNIT 0,405% 2 PASANG TITIK LAMPU 26 TITIK 0,935% 3 PASANG STOP KONTAK 4 TITIK 0,143% 4 PASANG SAKLAR 11 TITIK 0,396% JUMLAH 1,879% JUMLAH TOTAL 55,511%