RENCANA ANGGARAN PELAKSANAAN

NAMA : WTP - KIK


PROYEK : JALAN LINGKUNGAN
VOLUME : 2059,8 M2
JENIS : HOTMIX LASTON 4 CM

HARGA
JUMLAH BOBOT
NO URAIAN VOLUME SATUAN SATUAN
( Rp ) ( Rp ) (%)
A B C D E F=CXE G

1 PEK. BASE COURSE


1.1 LIMESTONE 527,43 M3 160.000 84.388.800
1.2 GALIAN TANAH 682,65 M3 65.000 44.372.250
1.3 PEMBUANGAN TANAH 682,65 M3 30.000 20.479.500
1.4 ANYAMAN BAMBU 2.059,75 M2 12.000 24.717.000
SUB TOTAL 1 173.957.550 36,78%
2 PEK. HOTMIX (LASTON T4CM)
2.1 BAHAN
2.1.1 HRS 165,00 TON 1.450.000 239.250.000
2.1.2 BATU PECAH TERSARING (LPA) 2/3 16,00 M3 360.000 5.760.000
2.1.3 BATU PECAH TERSARING (LPA) 5/7 25,75 M3 360.000 9.268.875
SUB TOTAL 2.1 245.010.000 51,80%
2.2 ALAT
2.2.1 ALAT BANTU (SET @3ALAT) 2,00 SET 250.000 500.000
2.2.2 MESIN GILAS TANDEM ROLLER 2,00 HARI 1.600.000 3.200.000
2.2.3 KOMPRESOR AIRMAN 2,00 HARI 600.000 1.200.000
2.2.4 MESIN ASPHALT SPRAYER 2,00 HARI 1.500.000 3.000.000
2.2.5 MESIN FINISHER 2,00 HARI 4.000.000 8.000.000
2.2.6 TANKI ASPHLAT DISTRIBUTOR 2,00 HARI 1.500.000 3.000.000
2.2.6 MOBILISASI DAN DEMOBILISAS ALAT 1,00 LS 2.000.000 2.000.000
SUB TOTAL 2.2 20.900.000 4,42%
2.3 UPAH
2.3.1 OPERATOR 15,00 HOK 250.000 3.750.000
2.3.2 PEMBANTU OPERATOR 15,00 HOK 150.000 2.250.000
2.3.3 PEKERJA 236,00 HOK 100.000 23.600.000
2.3.4 TUKANG 29,00 HOK 120.000 3.480.000
SUB TOTAL 2.3 33.080.000 6,99%

JUMLAH RAP 472.947.550 100%


RISK & SERVICE 14.188.427
TOTAL RAP 487.135.977
HARGA PER METER PERSEGI 236.497