LOKASI :
MENARA SUAR PULAU SELARU, KAB. KEPULAUAN
TANIMBAR - PROPINSI MALUKU
A PEKERJAAN PERSIAPAN
1 PEMBERSIHAN AWAL LS 1,00 8.000.000,00 8.000.000,00
2 MOBILISASI & DEMOBILISASI ALAT/BAHAN LS 1,00 79.724.000,00 79.724.000,00
3 PEMASANGAN BOWPLANK LS 1,00 6.000.000,00 6.000.000,00
4 PEMBERSIHAN AKHIR LS 1,00 4.400.000,00 4.400.000,00
5 GUDANG, DIREKSI KEET & KANTOR LS 1,00 18.300.000,00 18.300.000,00
6 PAPAN NAMA PROYEK LS 1,00 1.000.000,00 1.000.000,00
7 ADMINISTRASI, DOKUMENTASI, P3K LS 1,00 4.000.000,00 4.000.000,00
8 PENGADAAN AIR KERJA LS 1,00 4.010.000,00 4.010.000,00
5 125.434.000,00
B PEKERJAAN PAGAR KELILING
1 GALIAN TANAH M3 165,37 134.981,25 22.321.579,35
2 URUGAN TANAH KEMBALI M3 41,34 307.481,25 12.711.889,84
3 PASANGAN PONDASI BATU KARANG ad, 1 : 4 M3 147,65 1.820.257,38 268.761.001,42
4 SLOF BETON 20 X 20 ( 115KG/M3 ) M3 11,81 7.306.477,33 86.304.110,27
5 KOLOM BETON 25 X 25 ( 135KG/M3 ) M3 10,63 9.050.635,62 96.163.003,42
6 BALOK BETON 15 X 20 ( 150KG/M3 ) M3 8,86 9.503.221,71 84.189.041,12
7 PAS BATU BATA M2 275,15 274.892,98 75.636.803,79
8 PLESTERAN ad, 1 : 5 M2 872,42 368.035,65 321.081.661,77
9 ACIAN M2 872,42 64.432,34 56.212.065,33
10 PEKERJAAN KEPALA PAGAR / LIST PAGAR LS 1,00 5.000.000,00 5.000.000,00
11 PINTU PAGAR BESI TERPASANG LS 1,00 30.000.000,00 30.000.000,00
12 PENGECATAN TEMBOK ( SETARA CAT DULUX ) M2 872,42 50.080,20 43.690.968,08
1.102.072.124,40
HARGA SATUAN PEKERJAAN TANAH SNI DT 91 -0006-2013
Mengurug kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian
CATATAN Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Bukling factor pasir = 20 %
2
Memasang 1 m bekisting untuk sloof Rp 270.011,38
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Kayu kelas III m3 0,0450 Rp 2.030.000,00 Rp 91.350,00
Paku 5 Cm – 12 Cm Kg 0,3000 Rp 20.625,00 Rp 6.187,50
Minyak bekisting Liter 0,1000 Rp 64.750,00 Rp 6.475,00
Tenaga kerja Pekerja OH 0,5200 Rp 150.000,00 Rp 78.000,00
Tukang kayu OH 0,2600 Rp 165.000,00 Rp 42.900,00
Kepala tukang OH 0,0260 Rp 185.000,00 Rp 4.810,00
Mandor OH 0,0260 Rp 195.000,00 Rp 5.070,00
Jumlah Rp 234.792,50
Overhead dan Profit 15 % Rp 35.218,88
2
Memasang 1 m bekisting untuk lantai Rp 626.576,78
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Kayu kelas III m3 0,0400 Rp 2.030.000,00 Rp 81.200,00
Paku 5 cm – 12 cm Kg 0,4000 Rp 20.625,00 Rp 8.250,00
Minyak bekisting Liter 0,2000 Rp 64.750,00 Rp 12.950,00
Kayu Kelas II Balok m3 0,0150 Rp 2.918.125,00 Rp 43.771,88
Plywood 9 mm Lbr 0,3500 Rp 236.250,00 Rp 82.687,50
Dolken Kayu Ø 8 - 10/400
Rp 150.000,00
Cm Batang 6,0000 Rp 25.000,00
Tenaga kerja Pekerja OH 0,6600 Rp 150.000,00 Rp 99.000,00
Tukang kayu OH 0,3300 Rp 165.000,00 Rp 54.450,00
Kepala tukang OH 0,0330 Rp 185.000,00 Rp 6.105,00
Mandor OH 0,0330 Rp 195.000,00 Rp 6.435,00
Jumlah Rp 544.849,38
Overhead dan Profit 15 % Rp 81.727,41
2
Rp
Memasang 1 m dinding batako ukuran (8 x 10 x 20) cm tebal 1/2 bata, campuran spesi 1 PC : 4 PP 274.892,98
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Batako Buah 30,0000 Rp 3.875,00 Rp 116.250,00
Semen Portland Kg 11,5000 Rp 1.762,50 Rp 20.268,75
Pasir Pasang m3 0,0430 Rp 842.875,00 Rp 36.243,63
Tenaga kerja Pekerja OH 0,3000 Rp 150.000,00 Rp 45.000,00
Tukang batu OH 0,1000 Rp 165.000,00 Rp 16.500,00
Kepala tukang OH 0,0100 Rp 185.000,00 Rp 1.850,00
Mandor OH 0,0150 Rp 195.000,00 Rp 2.925,00
Jumlah Rp 239.037,38
Overhead dan Profit 15 % Rp 35.855,61
Memasang 1 m2 dinding batako ukuran (8 x 10 x 20) cm tebal 1/2 bata, campuran spesi 1 PC : 5 PP
Rp 273.142,68
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Batako Buah 30,0000 Rp 3.875,00 Rp 116.250,00
Semen Portland Kg 9,6800 Rp 1.762,50 Rp 17.061,00
Pasir Pasang m3 0,0450 Rp 842.875,00 Rp 37.929,38
Tenaga kerja Pekerja OH 0,3000 Rp 150.000,00 Rp 45.000,00
Tukang batu OH 0,1000 Rp 165.000,00 Rp 16.500,00
Kepala tukang OH 0,0100 Rp 185.000,00 Rp 1.850,00
Mandor OH 0,0150 Rp 195.000,00 Rp 2.925,00
Jumlah Rp 237.515,38
Overhead dan Profit 15 % Rp 35.627,31
Membuat dan memasang 1 m2 pintu dan jendela kaca, kayu kelas I Rp 1.285.872,50
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Papan kayu m3 0,0240 Rp 8.125.000,00 Rp 195.000,00
Kaca Rayben 5 mm m2 1,1000 Rp 306.250,00 Rp 336.875,00
Lem kayu Kg 0,3000 Rp 60.250,00 Rp 18.075,00
Tenaga kerja Pekerja OH 0,8000 Rp 150.000,00 Rp 120.000,00
Tukang kayu OH 2,4000 Rp 165.000,00 Rp 396.000,00
Kepala tukang OH 0,2400 Rp 185.000,00 Rp 44.400,00
Mandor OH 0,0400 Rp 195.000,00 Rp 7.800,00
Jumlah Rp 1.118.150,00
Overhead dan Profit 15 % Rp 167.722,50
2
6.5 Memasang 1 m Lantai tripleks ukuran (120 x 240) cm, tebal 18 mm Rp 191.705,00
Harga Satuan
Jml Harga
Kebutuhan Satuan Indeks Bahan
Bahan Tripleks 18 mm Lembar 0,3750 Rp 350.000,00 Rp 131.250,00
Paku tripleks Kg 0,0300 Rp 37.500,00 Rp 1.125,00
Tenaga kerja Pekerja OH 0,1000 Rp 150.000,00 Rp 15.000,00
Tukang kayu OH 0,1000 Rp 165.000,00 Rp 16.500,00
Kepala tukang OH 0,0100 Rp 185.000,00 Rp 1.850,00
Mandor OH 0,0050 Rp 195.000,00 Rp 975,00
Jumlah Rp 166.700,00
Overhead dan Profit 15 % Rp 25.005,00
2
6.5 Memasang 1 m langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm Rp 86.587,81
Harga Satuan
Jml Harga
Kebutuhan Satuan Indeks Bahan
Bahan Tripleks Lembar 0,3750 Rp 106.250,00 Rp 39.843,75
Paku tripleks Kg 0,0300 Rp 37.500,00 Rp 1.125,00
Tenaga kerja Pekerja OH 0,1000 Rp 150.000,00 Rp 15.000,00
Tukang kayu OH 0,1000 Rp 165.000,00 Rp 16.500,00
Kepala tukang OH 0,0100 Rp 185.000,00 Rp 1.850,00
Mandor OH 0,0050 Rp 195.000,00 Rp 975,00
Jumlah Rp 75.293,75
Overhead dan Profit 15 % Rp 11.294,06
6.8 Memasang 1 m2 langit-langit akustik ukuran (60 x 120) cm + rangka alluminium Rp 293.674,06
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Besi Holom 3 x 4 m’ 3,6000 Rp 18.750,00 Rp 67.500,00
Kawat diameter 4 mm Kg 0,1500 Rp 50.000,00 Rp 7.500,00
Ramset Buah 1,0500 Rp 15.625,00 Rp 16.406,25
Tenaga kerja Pekerja OH 0,3000 Rp 150.000,00 Rp 45.000,00
Tukang besi OH 0,6000 Rp 165.000,00 Rp 99.000,00
Kepala tukang OH 0,1000 Rp 185.000,00 Rp 18.500,00
Mandor OH 0,0075 Rp 195.000,00 Rp 1.462,50
Jumlah Rp 255.368,75
Overhead dan Profit 15 % Rp 38.305,31
6.3a Memasang 1 m2 konstruksi baja ringan (bersertifikat dan bergaransi sepuluh tahun) Rp 411.938,91
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Main truss C-75-75 m' 2,8000 Rp 40.000,00 Rp 112.000,00
Roof bottom/reng R-33-
Rp 95.625,00
0.45 m' 5,1000 Rp 18.750,00
Self drilling screw dia 6 x
Rp 31.250,00
20 mm (Truss Screw) Bh 25,0000 Rp 1.250,00
Self drilling screw dia 4 x
16 mm (Roof Batten Rp 32.812,50
Screw) Bh 35,0000 Rp 937,50
Dinabold dia 12 x 120
Rp 4.375,00
mm Bh 1,0000 Rp 4.375,00
Alat bantu (bor listrik,
Rp 10.381,25
gurinda potong) Ls 1,0000 Rp 10.381,25
Tenaga kerja Pekerja OH 0,2470 Rp 150.000,00 Rp 37.050,00
Tukang besi OH 0,1760 Rp 165.000,00 Rp 29.040,00
Kepala tukang OH 0,0176 Rp 185.000,00 Rp 3.256,00
Mandor OH 0,0124 Rp 195.000,00 Rp 2.418,00
Jumlah Rp 358.207,75
Overhead dan Profit 15 % Rp 53.731,16
1 m² Mengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup Rp 90.335,38
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan Cat Meni Kg 0,2000 Rp 50.000,00 Rp 10.000,00
Plamir Kg 0,1500 Rp 16.250,00 Rp 2.437,50
Cat Dasar Kg 0,1700 Rp 25.000,00 Rp 4.250,00
Cat Kayu glotek Kg 0,3500 Rp 93.750,00 Rp 32.812,50
Tenaga Pekerja Oh 0,0700 Rp 150.000,00 Rp 10.500,00
Tukang Cat Oh 0,1050 Rp 165.000,00 Rp 17.325,00
Kepala tukang Oh 0,0040 Rp 185.000,00 Rp 740,00
Mandor Oh 0,0025 Rp 195.000,00 Rp 487,50
Jumlah Rp 78.552,50
Overhead dan Profit 15 % Rp 11.782,88
1 m² Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) Rp 50.080,20
Harga Satuan
Kebutuhan Satuan Indeks Jumlah Harga
Bahan
Bahan
Cat Dasar Kg 0,1000 Rp 25.000,00 Rp 2.500,00
Cat Tembok Dulux Kg 0,2600 Rp 100.000,00 Rp 26.000,00
Tenaga Pekerja Oh 0,0200 Rp 150.000,00 Rp 3.000,00
Tukang Cat Oh 0,0630 Rp 165.000,00 Rp 10.395,00
Kepala tukang Oh 0,0063 Rp 185.000,00 Rp 1.165,50
Mandor Oh 0,0025 Rp 195.000,00 Rp 487,50
Jumlah Rp 43.548,00
Overhead dan Profit 15 % Rp 6.532,20
PEKERJAAN PONDASI
Berat Besi/M² Beton Besi Beton Beton K225 Bakesting Siram dan Bongkar Jumlah Harga
5 M²
Netto 100 Kg 2.681.656,25 2.182.515,77 1.291.694,38 690.000,00 6.845.866,40
Netto 150 Kg 4.022.484,38 2.182.515,77 1.291.694,38 690.000,00 8.186.694,52
Netto 140 Kg 3.754.318,75 2.182.515,77 1.291.694,38 690.000,00 7.918.528,90
Netto 165 Kg 4.424.732,81 2.182.515,77 1.291.694,38 690.000,00 8.588.942,96
Netto 180 Kg 4.826.981,25 2.182.515,77 1.291.694,38 690.000,00 8.991.191,40
Netto 181 Kg 4.853.797,81 2.182.515,77 1.291.694,38 690.000,00 9.018.007,96
PEKERJAAN SLOOF
Berat Besi/M² Beton Besi Beton Beton K225 Bakesting Siram dan Bongkar Jumlah Harga
5 M²
Netto 115 Kg 3.083.904,69 2.182.515,77 1.350.056,88 690.000,00 7.306.477,33
Netto 120 Kg 3.217.987,50 2.182.515,77 1.350.056,88 690.000,00 7.440.560,15
Netto 140 Kg 3.754.318,75 2.182.515,77 1.350.056,88 690.000,00 7.976.891,40
Netto 165 Kg 4.424.732,81 2.182.515,77 1.350.056,88 690.000,00 8.647.305,46
Netto 200 Kg 5.363.312,50 2.182.515,77 1.350.056,88 690.000,00 9.585.885,15
Netto 265 Kg 7.106.389,06 2.182.515,77 1.350.056,88 690.000,00 11.328.961,71
PEKERJAAN KOLOM
Berat Besi/M² Beton Besi Beton Beton K225 Bakesting Siram dan Bongkar Jumlah Harga
5 M²
Netto 100 Kg 2.681.656,25 2.182.515,77 2.557.883,91 690.000,00 8.112.055,93
Netto 135 Kg 3.620.235,94 2.182.515,77 2.557.883,91 690.000,00 9.050.635,62
Netto 170 Kg 4.558.815,63 2.182.515,77 2.557.883,91 690.000,00 9.989.215,30
Netto 230 Kg 6.167.809,38 2.182.515,77 2.557.883,91 690.000,00 11.598.209,05
Netto 217 Kg 5.819.194,06 2.182.515,77 2.557.883,91 690.000,00 11.249.593,74
Netto 300 Kg 8.044.968,75 2.182.515,77 2.557.883,91 690.000,00 13.475.368,43
Netto 385 Kg 10.324.376,56 2.182.515,77 2.557.883,91 690.000,00 15.754.776,24
PEKERJAAN BALOK
Berat Besi/M² Beton Besi Beton Beton K225 Bakesting Siram dan Bongkar Jumlah Harga
5 M²
Netto 130 Kg 3.486.153,13 2.182.515,77 2.608.221,56 690.000,00 8.966.890,46
Netto 85 Kg 2.279.407,81 2.182.515,77 2.608.221,56 690.000,00 7.760.145,15
Netto 150 Kg 4.022.484,38 2.182.515,77 2.608.221,56 690.000,00 9.503.221,71
Netto 236 Kg 6.328.708,75 2.182.515,77 2.608.221,56 690.000,00 11.809.446,08
Netto 244 Kg 6.543.241,25 2.182.515,77 2.608.221,56 690.000,00 12.023.978,58
Netto 230 Kg 6.167.809,38 2.182.515,77 2.608.221,56 690.000,00 11.648.546,71
PEKERJAAN LANTAI/LISPLANK
Berat Besi/M² Beton Besi Beton Beton K225 Bakesting Siram dan Bongkar Jumlah Harga
5 M²
Netto 100 Kg 2.681.656,25 2.182.515,77 3.132.883,91 690.000,00 8.687.055,93
Netto 75 Kg 2.011.242,19 2.182.515,77 3.132.883,91 690.000,00 8.016.641,87
Netto 175 Kg 4.692.898,44 2.182.515,77 3.132.883,91 690.000,00 10.698.298,12
Netto 200 Kg 5.363.312,50 2.182.515,77 3.132.883,91 690.000,00 11.368.712,18
- 2.182.515,77 3.132.883,91 690.000,00 6.005.399,68
- 2.182.515,77 3.132.883,91 690.000,00 6.005.399,68
PEKERJAAN DINDING
Berat Besi/M² Beton Besi Beton Beton K225 Bakesting Siram dan Bongkar Jumlah Harga
5 M²
Netto 75 Kg 2.011.242,19 2.182.515,77 2.670.961,25 690.000,00 7.554.719,21
Netto 120 Kg 3.217.987,50 2.182.515,77 2.670.961,25 690.000,00 8.761.464,52
- 2.182.515,77 2.670.961,25 690.000,00 5.543.477,02
- 2.182.515,77 2.670.961,25 690.000,00 5.543.477,02
- 2.182.515,77 2.670.961,25 690.000,00 5.543.477,02
- 2.182.515,77 2.670.961,25 690.000,00 5.543.477,02
PEKERJAAN TANGGA
Berat Besi Besi Beton Beton K225 Bakesting Siram dan Bongkar Jumlah Harga
5 M²
Netto 100 Kg 2.681.656,25 2.182.515,77 2.422.543,28 690.000,00 7.976.715,30
Netto 125 Kg 3.352.070,31 2.182.515,77 2.422.543,28 690.000,00 8.647.129,37
- 2.182.515,77 2.422.543,28 690.000,00 5.295.059,05
- 2.182.515,77 2.422.543,28 690.000,00 5.295.059,05
- 2.182.515,77 2.422.543,28 690.000,00 5.295.059,05
- 2.182.515,77 2.422.543,28 690.000,00 5.295.059,05
DAFTAR HARGA SATUAN UPAH KERJA
Harga Satuan
NO Uraian Satuan
( Rp )
1 Pekerja OH 150.000,00
2 Tukang Gali Oh 165.000,00
3 Tukang Cat Oh 165.000,00
4 Tukang OH 165.000,00
5 Tukang Batu OH 165.000,00
6 Tukang Batu/Pipa OH 165.000,00
7 Tukang Besi OH 165.000,00
8 Tukang Kayu OH 165.000,00
9 Kepala Tukang OH 185.000,00
10 Tukang Las OH 165.000,00
11 Mandor OH 195.000,00
Harga Satuan
NO Uraian Satuan
( Rp )
0 Air liter 250,00
1 Ampelas lembar 7.500,00
2 Atap Genteng Beton m2 225.000,00
3 Balok Kayu Klas I m3 8.375.000,00
4 Bambu Ø 7 - 10 / 600 Cm btg 37.500,00
5 Batako/ tela Uk. 8 x 10 x 20 cm bh 3.875,00
6 Batu Belah m3 400.000,00
7 Batu Belah 15/20 m3 400.000,00
8 Batu Belah 5/7 m3 350.000,00
9 Batu Kerikil/Koral m3 687.500,00
10 Batu Kerikil/Koral (KG) kg 509,26
11 Batu koral 3/4 m3 687.500,00
12 Batu koral 2/3 m3 687.500,00
13 BBM ltr 10.000,00
14 Besi Angkur Ø=8 mm kg 20.500,00
15 Besi Baja IWF kg 34.375,00
16 Besi Beton kg 19.375,00
17 Besi Beton Ulir kg 23.750,00
18 Cat Tembok ( DULUXE ) kg 100.000,00
19 Cat Dasar kg 25.000,00
20 Cat Kayu Glotek kg 93.750,00
21 Cat Meni kg 50.000,00
22 Dempul jadi kg 50.000,00
23 Dolken Kayu Ø 8 - 10/400 Cm btg 25.000,00
24 Engsel Jendela unilon psng 40.000,00
25 Engsel Pintu unilon standar psng 58.375,00
26 Floor Drain stainless bh 93.750,00
27 Main truss C-75-75 m' 40.000,00
28 Roof bottom/reng R-33-0.45 m' 18.750,00
29 Self drilling screw dia 6 x 20 mm (Truss Screw) Bh 1.250,00
30 Self drilling screw dia 4 x 16 mm (Roof Batten Screw) Bh 937,50
31 Dinabold dia 12 x 120 mm Bh 4.375,00
32 Kaca Rayben 5 mm m2 306.250,00
33 Kait Angin bh 22.500,00
34 Kapur Sirih kg 18.750,00
35 Kaso 5 / 7 ( Albasiah ) m3 3.312.500,00
36 Kawat Beton kg 37.500,00
37 Kayu Kelas I Balok m3 7.739.375,00
38 Kayu Kelas II m3 2.918.125,00
39 Kayu Kelas II Balok m3 2.918.125,00
40 Kayu Kelas III m3 2.030.000,00
41 Kayu Kelas III (Papan) m3 2.030.000,00
42 Kayu Papan m3 7.739.375,00
43 Kayu Papan 3 / 20 Borneo m3 2.918.125,00
44 Kayu Terentang m3 2.918.125,00
45 Kloset Duduk bh 1.875.000,00
46 Kran Air 3/4" KIT bh 62.500,00
47 Kunci Tanam Biasa bh 218.750,00
48 Lem Kayu kg 60.250,00
49 Meni ( Read Lead ) A kg 59.375,00
50 Meni ( Read Lead ) B kg 54.375,00
51 Meni Besi Lt 72.750,00
52 Minyak Bekisting Liter 64.750,00
53 Minyak Cat kg 27.500,00
Harga Satuan
NO Uraian Satuan
( Rp )
54 Nok Genteng Beton m' 105.000,00
55 Paku 1 Cm - 2,5 Cm kg 28.750,00
56 Paku 3 Cm kg 28.750,00
57 Paku 5 Cm – 12 Cm kg 20.625,00
58 Paku Hak Panjang 5 Cm kg 40.000,00
59 Paku Skrup kg 43.750,00
60 Paku Skrup 1 Cm – 2,5 Cm bh 43.750,00
61 Paku Skrup 10 Cm kg 62.500,00
62 Paku Skrup 3.5" bh 1.500,00
63 Paku Skrup 5 Cm kg 37.500,00
64 Paku Tripleks kg 37.500,00
65 Papan Kayu m3 8.125.000,00
66 Papan Kayu Borneo Tebal 3Cm m3 3.750.000,00
67 Papan Kayu Kelas II m3 3.750.000,00
68 Papan Kayu Kelas II Atau III m3 3.750.000,00
69 Pasir Beton m3 842.875,00
70 Pasir Beton ( Kg ) kg 491,07
71 Pasir Pasang m3 842.875,00
72 Pasir Urug m3 437.500,00
73 Pelitur ltr 68.750,00
74 Pelitur Jadi ltr 81.250,00
75 Perancah Kayu m3 2.500.000,00
76 Pipa PVC Ø 1/2" m' 10.937,50
77 Pipa PVC Tipe Aw Ø ¾" m' 14.000,00
78 Pipa PVC Tipe Aw Ø 1" m' 17.375,00
79 Pipa PVC Tipe Aw Ø 1½" m' 28.343,75
80 Pipa PVC Tipe Aw Ø 2" m' 59.000,00
81 Pipa Besi Ø 2,5" m' 72.500,00
82 Plamir kg 16.250,00
83 Plywood 4 mm lembar 121.250,00
84 Plywood 9 mm lembar 236.250,00
85 Ramset bh 15.625,00
86 Sealant tube 52.500,00
87 Semen Portland kg 1.762,50
88 Semen Warna kg 12.500,00
89 Seng Gelombang 3" X 6" Bjls 28 lembar 109.375,00
70 Seng Gelombang 3"-5" lembar 87.500,00
90 Seng Gelombang Bjls 32 lembar 112.500,00
91 Sirtu m3 187.500,00
92 Tripleks lembar 106.250,00
Tripleks 18 mm lembar 350.000,00
93 Ubin keramik (20 x 20) cm bh 3.750,00
94 Ubin Granit (60 x 60) cm bh 62.500,00
95 Panel MCB Bh 68.750,00
96 Ttik Instalasi Ttk 306.250,00
97 Stop Kontak Bh 37.500,00
98 Saklar Tunggal Bh 37.500,00
99 Saklar Ganda Bh 43.750,00
100 Lampu Philips 18 Watt Bh 83.750,00
101 Lampu Tl Bambu 40 Watt Bh 250.000,00
102 Lampu down light Bh 281.250,00
104 Lis Gipsun profil M' 50.000,00
102 Grendel jendela Bh 45.000,00
103 Exausfan Bh 500.000,00
104 Kloset Duduk Warna Standard TOTO C 240 Lengkap Bh 1.875.000,00
103 Wastafellengkap acessories Bh 1.062.500,00
104 Septictank Unit 10.000.000,00
105 Saluran Air ( Got ) M' 343.750,00
Harga Satuan
NO Uraian Satuan
( Rp )
106 Griil penutup Saluran / Got bahan stainless M' 218.750,00
107 Solar Ltr 8.750,00
108 Minyak Pelumas Ltr 43.750,00
109 Sewa Alat Las Jam 31.250,00
110 Logo dan huruf papan nama bahan stailess Unit 7.500.000,00
111 PASANG ORNAMEN BATU ALAM M2 375.000,00
113 Lisplank Bahan GRC 0,9 x 30 x 300 cm Lbr 125.000,00
114 Gypsum Board Lbr 150.000,00
115 Kalsibor 10 mm Lbr 276.000,00
116 Paper HPL Terpasang + Upah M2 160.000,00
117 Kawat 4 mm Kg 50.000,00
118 Besi holow 3 x 4 M' 18.750,00
119 Atap Alumunium Spandek M2 325.000,00