SIPIL
RENCANA PENYELESAIAN CHECKLIST TANGGAL HARIAN ( DES 2022 )
NO URAIAN PEKERJAAN
MULAI SELESAI DURASI TENAGA 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
I RESEVOIR
I.a. Area Sisi Dalam & Sekat
- Chiping & Cleanning lantai Zona C & D 06-Dec-22 12-Dec-22 6 6 6 6 6 6 6 6 6
- Potong Besi stek di Zona B,C & D 07-Dec-22 10-Dec-22 3 -
- Repair & Finishing Dinding Zona B,C & D 06-Dec-22 14-Dec-22 8 4 4 4 4 4 4 4 4 4 4
- Waterproffing Zona B,C & D 08-Dec-22 16-Dec-22 8 -
I.b. Area Sisi Luar
- Pengecoran Tanggulan Main Hole 06-Dec-22 10-Dec-22 4 3 3 3 3 3 3
- Cleanning atap dak 11-Dec-22 16-Dec-22 5 4 4 4 4 4 4 4
- Finishing perapihan dinding 16-Dec-22 23-Dec-22 7 6 6 6 6 6 6 6 6 6
II WTP 1
II.a. Area sisi Luar
- Screed lantai cantilever & lorong tengah 10-Dec-22 12-Dec-22 2 3 3 3 3
- Finishing perapihan dinding 13-Dec-22 15-Dec-22 2 3 3 3 3
- Railling Area Walk Way 06-Dec-22 12-Dec-22 6 -
- Rangka Atap Baja & Penutup spandek 13-Dec-22 27-Dec-22 14 -
III WTP 2
III.a. Area Sisi dalam
- Perapihan Dinding atas batas air 09-Dec-22 12-Dec-22 3 4 4 4 4 4
III.b. Area Sisi Luar
- Finishing Perapihan dinding 06-Dec-22 12-Dec-22 6 3 3 3 3 3 3 3 3
- Screed lantai cantilever & lorong tengah 13-Dec-22 16-Dec-22 3 3 3 3 3 3
- Railling Area Walk Way 12-Dec-22 15-Dec-22 3 -
- Rangka Atap Baja & Penutup spandek 16-Dec-22 27-Dec-22 11 -
IV OFFICE BUILDING
- Pemasangan Plafond GRC Teras 07-Dec-22 12-Dec-22 5 4 4 4 4 4 4 4
- Finishing & Perapihan dinding (trmsk Sponeng,Opening & Profil) 08-Dec-22 15-Dec-22 7 3 3 3 3 3 3 3 3 3
- Penyambungan Pipa Pembuangan ke Septitank 09-Dec-22 12-Dec-22 3 2 2 2 2 2
- Pembuatan Septitank 12-Dec-22 16-Dec-22 4 2 2 2 2 2 2
- Pengecoran Teras Belakang & Samping 15-Dec-22 17-Dec-22 2 4 4 4 4
- Pemasangan Sanitasi (Kloset,Wastafel,Zink,Floordrain,Kran) 19-Dec-22 24-Dec-22 5 3 3 3 3 3 3 3
- Test Rendam + Waterproffing Kamar Mandi + Wudlu LT. 2 09-Dec-22 12-Dec-22 3 3 3 3 3 3
- Pemasangan Lantai Keramik Kamar Mandi 13-Dec-22 18-Dec-22 5 3 3 3 3 3 3 3
- Pemasangan & Perapihan Keramik Area Tangga 08-Dec-22 12-Dec-22 4 3 3 3 3 3 3
- Screed / Keramik Selasar teras 20-Dec-22 23-Dec-22 3 4 4 4 4 4
- Finishing & Perapihan Cat Dinding & Plafond 08-Dec-22 15-Dec-22 7 3 3 3 3 3 3 3 3 3
- Pabrikasi & Pemasangan Pintu & Jendela Aluminium + Kaca 19-Dec-22 29-Dec-22 10 -
- Pabrikasi & Pemasangan Kanopi depan pintu masuk 17-Dec-22 29-Dec-22 12 -
- Pemasangan Pipa Saluran Air dari Talang Hujan 20-Dec-22 23-Dec-22 3 2 2 2 2 2
- Penyambungan Pipa dari Tower Air 17-Dec-22 19-Dec-22 2 2 2 2 2
- Pemasangan Bata Parapet 1,2 m 12-Dec-22 16-Dec-22 4 2 2 2 2 2 2
V CHEMICAL BUILDING
- Eksposed bawah dak Lantai 13-Dec-22 17-Dec-22 4 2 2 2 2 2 2
- Perapihan Cat Dinding 15-Dec-22 20-Dec-22 5 2 2 2 2 2 2 2
- Screed lantai selasar teras 20-Dec-22 23-Dec-22 3 2 2 2 2 2
VI POWER HOUSE
- Screed lantai selasar teras 15-Dec-22 17-Dec-22 2 4 4 4 4
- Pembuatan Ramp untuk akses 18-Dec-22 23-Dec-22 5 4 4 4 4 4 4 4
X SCREEWPRESS BUILDING
- Pengecoran Kekurangan Selasar keliling 15-Dec-22 17-Dec-22 2 2 2 2 2
- Screed lantai selasar teras 18-Dec-22 19-Dec-22 1 2 2 2
By Sub-Kont