SCHEDULE PENGECORAN

PROYEK LIKUPANG ECO FAMILY HOTEL

Periode : 13 Juni 2022 s/d 18 Juni 2022

HARI / TANGGAL
NO MUTU BETON KUBIKASI SENIN SELASA RABU KAMIS JUM'AT SABTU JUMLAH KETERANGAN
13 14 15 16 17 18
1 Beton K250 m3 0
2 Beton K300 m3 54 29 71 70 36 23 283
3 Beton K400 m3 0
4 Beton K450 m3 0

Keterangan
Senin - pool deck kolam renang Kamis - Dinding planter selasar depan reception
- Pondasi tapak lagon - Pondasi tapak lagon
Disetujui Oleh - Pondasi selasar depan reception - Tangga akses gedung ke standing damkar Dibuat Oleh
- Lantai pedestrian samping standing damkar - Lantai dan baok looding dock

Selasa - Gater reception Jum'at - Pool deck play kid


- Pondasi selasar depan reception - Jalan damkar depan reception
- Dinding beton samping pedestrian - Lantai ramp area selasar reception

Project Manager Rabu - Pool deck water play Sabtu - Pondasi tapak lagon Site Manager
- Gater reception - Bench area reception
- Resto seafood - Atap trend