PROYEK : MNC LIDO CITY

LOKASI : PEDESTRIAN

No Pekerjaan Sat Vol Start

1 Pedestrian Jalan B Ektention, STA 0+175-0+275 ( Entrench )


A Pekerjaan Persiapan
1 Pembersihan Lokasi Ls 1 12/21/2020
2 `Bongkar Kontainer Ls 1 12/21/2020

B Pekerjaan Tanah
1 Galian Tanah + Disposal Area -1 m3 2750 12/22/2020
2 Galian Tanah + Disposal Area -2 m3 2750 1/1/2021

C Perkerasan Jalan
1 Galian RCP m1 20 12/29/2020
2 Pasang RCP Dia 600 mm (Jalur Kael ) m1 20 12/30/2020
3 Gelar Limes Stone m2 420 12/31/2020
4 Gelar ase Course m2 420 1/2/2021

D Pekerjaan Cor Lantai Kerja


1 Area - 1 m2 360 1/2/2021
1.1 Pemadatan Sirtu 10 cm 1/2/2021
1.2 Pasang Plastik Cor 1/4/2021
1.3 Pasang Wiremesh M-5 1/4/2021
1.4 Instal Bekistig 1/5/2021
1.5 Beton Mutu K-250 1/7/2021

2 Area - 2 m2 360 1/7/2021


1.1 Pemadatan Sirtu 10 cm 1/7/2021
1.2 Pasang Plastik Cor 1/9/2021
1.3 Pasang Wiremesh M-5 1/9/2021
1.4 Instal Bekistig 1/10/2021
1.5 Beton Mutu K-250 1/12/2021

Area Perkerasa m2 420 1/13/2021


1.1 Beton Mutu K-250 1/13/2021

E Pekerjaan Saluran
1 Area - 1 m1 48 1/8/2021
1.1 Galian Saluran 1/8/2021
1.2 Pasangan Batu Kali 1:4 1/9/2021
1.3 U-Ditch 30 1/12/2021
1.4 Fiish Plaster + aci 1/13/2021

2 Area - 2 m1 48 1/13/2021
1.1 Galian Saluran 1/13/2021
1.2 Pasangan Batu Kali 1:4 1/14/2021
1.3 U-Ditch 30 1/17/2021
1.4 Fiish Plaster + aci 1/18/2021

F Pekerjaan Pasangan
1 Pasangan Granit + Andesit, Area -1 m2 360 1/8/2021
2 Pasangan Granit + Andesit, Area -2 m2 368 1/13/2021

Note
1 Lokasi Pemuaga Taah Galia elum Di Ketahui
2 Peyediaan 1 Operator Exca+ BBM
3 Peyediaan Operasional 3 Dump Truck
- Estimasi Target Perolehan Buangan1 DT @ Hari = 125 m3 @ Hari ( Cuaca Bagus
Target Desemer 2020
Finish
Hari 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5

12/22/2020 1 Hari
12/22/2020 1 Hari

12/29/2020 7 Hari
1/7/2021 6 Hari

12/30/2020 1 Hari
12/30/2020 0 Hari
1/1/2021 1 Hari
1/3/2021 1 Hari

1/7/2021 6 Hari
1/4/2021 2 Hari
1/4/2021 0 Hari
1/5/2021 1 Hari
1/6/2021 1 Hari
1/7/2021 0 Hari

1/12/2021 6 Hari
1/9/2021 2 Hari
1/9/2021 0 Hari
1/10/2021 1 Hari
1/11/2021 1 Hari
1/12/2021 0 Hari

1/14/2021 1 Hari
1/14/2021 1 Hari

1/15/2021 8 Hari
1/9/2021 1 Hari
1/12/2021 3 Hari
1/13/2021 1 Hari
1/15/2021 2 Hari

1/20/2021 8 Hari
1/14/2021 1 Hari
1/17/2021 3 Hari
1/18/2021 1 Hari
1/20/2021 2 Hari

1/24/2021 16 Hari
1/29/2021 16 Hari

= 125 m3 @ Hari ( Cuaca Bagus )


Jauari 2021
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Keterangan
30 31
QUANTITY SHEET
JALUR PEDESTRIAN
(Drawing : Shop Drawing Entrench Pedestrian Jalan B, ROW 50)

No. DESCRIPTION Unit Calculation Total

A. Jalan B (Entrench)
Area Width Thick
1 Wiremesh m-5 (2,100* 5,400 mm) Lbr 120.00
1.1 Pedestrian Shareway 1 Lbr 752.75 : 8.17 93.00
1.2 Pedestrian Shareway 2 Lbr 216.95 : 8.17 27.00

2 Plastik Cor m2 969.70


2.1 Area Pasangan Granit + Andesit Shareway 1 m2 752.75 752.75
2.2 Area Pasangan Granit + Andesit Shareway 2 m2 216.95 216.95

3 Beton Mutu K-250 m3 67.88


3.1 Pedestrian Shareway 1 m3 752.75 x 0.07 52.69
3.2 Pedestrian Shareway 2 m3 216.95 x 0.07 15.19

4 Beton Mutu K-125 m3 53.20


4.1 Lantai Kerja Perkerasan Jalan Akses Masuk m3 760.00 x 0.07 53.20
(Area Movieland dan Area Entrance)

5 Pipa RCP Dia 60 cm m1 1.00 x 20.00 20.00


5.1 Area Perkerasan Jalan (Jalur KaBel ) m1 1.00 x 20.00 20.00

6 U-Ditch 30, Pedestrian m1 144.00


6.1 Area Shareway 1 m1 1.00 x 97.00 97.00
6.2 Area Shareway 2 m1 1.00 x 47.00 47.00

7 Pasangan Batu Kali 1:4, Pedestrian m3 1.00 x 0.23 x 144.00 32.40


7.1 Semen Zak 161.00 x 32.40 : 40.00 130.41
7.2 Pasir m3 0.52 x 32.40 16.85
7.3 Batu Kali m3 1.20 x 32.40 38.88

8 Screed 1 : 5 Pasangan Granit + Andesit + Pedestrian m3 0.05 x 752.75 37.64


8.1 Semen Zak 520.00 x 37.64 : 40.00 489.29
8.2 Pasir m3 0.75 x 37.64 x 1.30 21.71

9 Perkerasan Jalan (Area MovieLand + Area Entrance) m2 1.00 x 760.00 760.00


9.1 Limes Stone 40 cm m3 1.00 x 760.00 x 0.40 304.00
9.2 Base Course stone 20 cm m3 1.00 x 760.00 x 0.20 152.00