Anda di halaman 1dari 3

BOQ (BILL OF QUANTITY)

Nama Proyek : Food Pavillion


Lokasi Proyek : Theme Park Kota Baru Parahyangan

TIME SCHEDULE
NO URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME
START FINISH

A FOODCOURT LAKESIDE
I PEKERJAAN PERSIAPAN
1 Shop Drawing ls 1.00
2 Pas.Bouwplank ls 1.00
3 Pengadaan Air dan Listrik Kerja ls 1.00
4 Kebersihan lapangan ls 1.00
5 Keamanan site ls 1.00

Sub Total

II PEK. GALIAN dan URUGAN


1 Galian Pilecap, 16 titik Galian Blast Material m³ 2.52 5/15/2022 5/29/2022
2 Galian Tiebeam Galian Blast Material m³ 12.42 5/15/2022 5/29/2022
3 Urugan kembali Blast Material m³ 1.48 6/13/2022 6/15/2022
4 Buang Tanah Bekas Blast Material m³ 2.90 5/29/2022 5/5/2022
5 Lantai Kerja di bawah pondasi pile cap t= 5cm m³ 0.18 5/29/2022 6/5/2022
6 Lantai Kerja di bawah Tie beam cap t= 5cm m³ 1.24 5/29/2022 6/5/2022
7 Lantai Kerja di bawah Lantai t= 5cm m³ 2.15 6/29/2022 5/29/2022

Sub Total

III PEK. PONDASI


1 Pemotongan tiang pancang/borepile (termasuk buang potongan tiang pancang) titik 14.00 5/15/2022 5/22/2022
2 Beton Pile cap 50x50x50, 16 titik 50x50x50 m³ 2.10 6/12/2022 6/12/2022
3 Beton Tiebeam 20x40 20x40 m³ 9.94 6/12/2022 6/12/2022
4 Beton Pendestal 30x20x42, 16 titik 30x20x42 m³ 0.42 6/19/2022 6/25/2022
5 Finish + Grouting Pedestal, 16 titik Finish Aci + Grouting titik 16.00 6/26/2022 7/3/2022
6 Beton Slab t=120mm t=120mm m³ 5.16 6/19/2022 6/25/2022

Sub Total

IV PEK. STRUKTUR BAJA


1 Kolom K1, IWF 200x100x5,5x8 IWF 200x100x5,5x8 kg 1,156.18 6/19/2022 7/24/2022
2 Rafter R1, IWF 200x100x5,5x8 IWF 200x100x5,5x9 kg 1,347.87 6/19/2022 7/24/2022
3 Kolom Pipa SCH 40 Ø3", t=5mm IWF 200x100x5,5x8 kg 118.65 6/19/2022 7/24/2022
4 Gording CNP 125x50c20x3,2 CNP 125x50x20x3,2 kg 1,166.66 6/19/2022 7/24/2022
5 Bracing ROD Ø12 ROD Ø12 kg 137.44 6/19/2022 7/24/2022
6 Trekstang ROD Ø12 ROD Ø12 kg 78.03 6/19/2022 7/24/2022
7 Base Plat, t.10mm Plat Baja 25x15 t.10mm kg 46.14 6/19/2022 7/24/2022
8 Plat sambungan 10mm Plat Baja t.10mm kg 150.98 6/19/2022 7/24/2022
9 Cat syncromate, 1lapis Ex. Kansai kg 4,201.94 6/19/2022 7/24/2022
10 Cat Finish, 2lapis Ex. Seiv kg 4,201.94 6/19/2022 7/24/2022
11 Anchor bolt 4 M12 L25 pcs 56.00 6/19/2022 7/24/2022
12 Baut M16 HTB A325 pcs 353.00 6/19/2022 7/24/2022

Sub Total

V PEKERJAAN PENUTUP ATAP FOODCOURT

Atap Metal Corrugated Colorbond


1 Penutup Atap Kliplock Optima t=0,45mm BMT m² 282.28 7/17/2022 8/1/2022
G550 ex. Lysaght

Woodplank (motif kayu) ex


2 Lisplank + Rangka Hollow m¹ 27.30 7/17/2022 8/1/2022
Kalsiplank
3 Talang Air Hujan + Dudukan Rangka Hollow m¹ 27.30 7/17/2022 8/1/2022
4 Flashing Zinc-Alume m¹ 23.58 7/17/2022 8/1/2022

Sub Total

B PEKERJAAN FOOD PAVILLION


I PEKERJAAN PASANGAN
1 Kolom praktis m¹ 84.00 6/26/2022 7/3/2022
2 Balok Praktis m¹ 40.44 7/3/2022 7/31/2022
3 Pekerjaan pasangan bata Bata Merah ex Garut m² 142.26 7/3/2022 7/31/2022
4 Pekerjaan plester aci dinding Mortar Instan m² 209.73 7/3/2022 7/31/2022
5 Pekerjaan finish kamprot halus m² 12.97 7/3/2022 7/31/2022
BOQ (BILL OF QUANTITY)
Nama Proyek : Food Pavillion
Lokasi Proyek : Theme Park Kota Baru Parahyangan

TIME SCHEDULE
NO URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME
START FINISH

6 Pekerjaan nat dinding m¹ 18.09 7/3/2022 7/31/2022


7 Pekerjaan pemasangan keramik lantai Roman 30x30, Gol.B m² 43.03 7/3/2022 7/31/2022
8 Pekerjaan pemasangan keramik dinding Roman 30x30, Gol.B m² 61.83 7/3/2022 7/31/2022
9 Pekerjaan pemasangan plint lantai Gudang Roman 30x10, Gol.B m¹ 10.92 7/3/2022 7/31/2022

II PEKERJAAN PLAFOND
1 Gypsum t=9mm + Rangka Hollow Galvanis 4x4 dan 2x4 Hollow t=0,3mm m2 43.03 8/1/2022 8/14/2022
2 Gypsum Water Resist t=9mm + Rangka Hollow Galvanis 4x4 dan 2x4 Hollow t=0,3mm m2 27.78 8/1/2022 8/14/2022
3 List alumunium uk. 2 x 1 cm m' 69.95 8/1/2022 8/14/2022

III PEKERJAAN PENGECATAN


1 Pengecatan Dinding Eksterior Weathershield Paint ex Dulux m2 108.45 8/1/2022 8/14/2022
2 Pengecatan Dinding Interior Acrilyc Emulsion Paint ex Dulux m2 101.28 8/1/2022 8/14/2022
3 Pengecatan Plafond ex Dulux Catylac m2 70.81 8/1/2022 8/14/2022

IV PEKERJAAN ATAP
1 Rangka Atap
Rafter R1, IWF 200x100x5,5x8 IWF 200x100x5,5x9 kg 470.40 6/19/2022 7/24/2022
Gording CNP 125x50c20x3,2 CNP 125x50x20x3,2 kg 346.20 6/19/2022 7/24/2022
Trekstang ROD Ø12 ROD Ø12 kg 39.32 6/19/2022 7/24/2022
Base Plat, t.10mm Plat Baja 20x10 t.10mm kg 6.80 6/19/2022 7/24/2022
Plat sambungan 10mm Plat Baja 20x30 t.10mm kg 20.41 6/19/2022 7/24/2022
Cat syncromate, 1lapis Ex. Kansai kg 883.14 6/19/2022 7/24/2022
Cat Finish, 2lapis Ex. Seiv kg 883.14 6/19/2022 7/24/2022
2 Penutup atap Upah Pasang, Material By Owner m2 60.73 6/19/2022 7/24/2022
3 Nok Atap Upah Pasang, Material By Owner m' 33.60 6/19/2022 7/24/2022
Woodplank (motif kayu) ex
4 Lisplank + Rangka Hollow m¹ 31.98 6/19/2022 7/24/2022
Kalsiplank

V PEKERJAAN MEKANIKAL & ELEKTRIKAL


Mekanikal
1 Instalasi air bersih
Pipa PPR Ø25 Ke GV BC m¹ 12.60 7/3/2022 7/31/2022
Gate Valve Ø25 unit 2.00 7/3/2022 7/31/2022
Water Meter Ø25 unit 1.00 7/3/2022 7/31/2022
2 Instalasi air kotor
Pipa PVC Rucika AW Ø50 m¹ 15.75 7/3/2022 7/31/2022
Pipa PVC Rucika AW Ø50 Dari GT ke Manhole m¹ 31.50 7/3/2022 7/31/2022
3 Instalasi air hujan
Pipa PVC Rucika AW 3" m¹ 18.38 7/3/2022 7/31/2022
Pipa PVC Rucika AW 6" m¹ 27.30 7/3/2022 7/31/2022
Pasangan Bata, 1pc:5ps, tutup
4 Bak Kontrol (40x40x50) unit 3.00 7/3/2022 7/31/2022
beton k125
Pasangan Bata, 1pc:5ps, tutup plat
5 Bak Kontrol (60x250x30) unit 1.00 7/3/2022 7/31/2022
bordes
6 Grease Trap GT-30 unit 2.00 7/3/2022 7/31/2022
7 Clean Out unit 2.00 7/3/2022 7/31/2022
8 Roof Drain Ø3" unit 5.00 7/3/2022 7/31/2022

Elektrikal
1 Instalasi penerangan, stop kontak, saklar ttk 74.00 8/1/2022 8/14/2022
2 Down Light LED 13 Watt ex. Phillips bh 40.00 8/1/2022 8/14/2022
3 Down Light LED 13 Watt c/w Battery ex. Phillips bh 5.00 8/1/2022 8/14/2022
4 TL LED 4x8 Watt Recessed Mounted 600x600 ex. Phillips bh 4.00 8/1/2022 8/14/2022

5 TL LED 4x8 Watt Recessed Mounted 600x600 c/w Battery 1 tube ex. Phillips bh 1.00 8/1/2022 8/14/2022

6 Stop Kontak ex. Legrand bh 14.00 8/1/2022 8/14/2022


7 Outlet Data ex. Legrand bh 2.00 8/1/2022 8/14/2022
8 Outlet Telp ex. Legrand bh 1.00 8/1/2022 8/14/2022
9 Saklar Tunggal ex. Legrand bh 1.00 8/1/2022 8/14/2022
BOQ (BILL OF QUANTITY)
Nama Proyek : Food Pavillion
Lokasi Proyek : Theme Park Kota Baru Parahyangan

TIME SCHEDULE
NO URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME
START FINISH

10 Saklar Seri ex. Legrand bh 2.00 8/1/2022 8/14/2022


11 Saklar 6 gang ex. Legrand bh 2.00 8/1/2022 8/14/2022
12 Axial Fan ex. Cooger, Vantex bh 1.00 8/1/2022 8/14/2022
13 Wall Mounted ex. Cooger, Vantex bh 1.00 8/1/2022 8/14/2022
14 Kwh Meter bh 1.00 8/1/2022 8/14/2022
15 MCB Box Panel bh 1.00 8/1/2022 8/14/2022

VI PEKERJAAN SANITARY
1 Kitchen Sink Royal SB-9 bh 2.00 7/3/2022 7/31/2022
2 Sink Tap Toto T 30 AR13V7N bh 2.00 7/3/2022 7/31/2022
3 Floor Drain Toto TX 1 N bh 2.00 7/3/2022 7/31/2022

VII PEKERJAAN MEJA BETON


1 Bekisting Multiplek Multiplek 9mm m2 13.65 7/3/2022 7/31/2022
2 Pembesian D13 D13, Ø10 kg 155.75 7/3/2022 7/31/2022
3 Cor beton meja beton m3 1.12 7/3/2022 7/31/2022
4 Pasangan bata dibawah meja beton Bata Merah m2 4.03 7/3/2022 7/31/2022
5 Finish Acian meja beton m2 17.01 7/3/2022 7/31/2022
6 Pekerjaan pemasangan keramik meja beton Roman 30x30, Gol.B m2 13.65 7/3/2022 7/31/2022

VIII PEKERJAAN PINTU dan JENDELA


Kusen Alum ex. YKK Fility +
1 Pintu Gudang unit 1.00 8/1/2022 8/14/2022
Daun Pintu Alumunium Fility
Kusen Alum ex. YKK Fility +
2 Pintu Kitchen unit 1.00 8/1/2022 8/14/2022
Daun Pintu Alumunium Fility
Kusen Alum ex. YKK Nexsta
3 Jendela Sliding atas bawah unit 2.00 8/1/2022 8/14/2022
Sliding + Kaca 6mm
4 Jendela Kaca Mati Frameless Kaca 8mm frameless unit 3.00 8/1/2022 8/14/2022
Kusen Kayu Kamper finish
5 unit 1.00 8/1/2022 8/14/2022
Jendela Bulat melamic + Kaca 6mm

Anda mungkin juga menyukai