Anda di halaman 1dari 1

ACTION PLAN CW04B

UPGRADING DAN KOLAM RETENSI


CEK DAM RINJANI
Waktu TTD Kontrak Jangka Waktu Pelaksaan
FINISH
START (Hari)
21-Jun-21 420 1-Aug-22
Tanggal Waktu
No ACTION PLAN Sat Vol Tanggal Selesai
Mulai (Hari)
Pekerjaan Persiapan
1 Monday, June 21, 2021 Mobilisasi dan Demobilisasi Peralatan (Direksi Kit) Ls 1 14 Monday, July 25, 2022
2 Monday, July 25, 2022 Kesehatan dan keselamatan kerja (K3) & Penanganan Covid-19 Ls 1 35 Monday, August 29, 2022
3 Monday, June 21, 2021 Cabut 1 Tunggul Pohon Tanaman Keras Ø ≥ 15 cm dan membuang btg.
s 12,980 28 Monday, July 26, 2021
4 Monday, June 21, 2021 Uitset Trase Tanggul m' 23,600 21 Monday, July 26, 2021
5 Monday, June 21, 2021 Pengadaan dan Pemasangan Patok bh 474 21 Monday, July 26, 2021
6 Monday, June 21, 2021 Pembuatan Jalan (Sirtu) m2 2,880 14 Monday, July 26, 2021
7 Monday, May 30, 2022 Pemeliharaan Jalan m3 1,920 28 Monday, June 27, 2022
Pekerjaan Timbunan dan Pekerjaan Structure UP STREAM
8 ### Galian Tanah (alat) m3 423,874 112 ###
9 ### Transport Buangan hasil galian m3 422,663 224 Monday, April 11, 2022
10 ### Timbunan Tanggul dipadatkan m3 28,183 84 ###
11 ### U Ditch 60x60 ( 374 Unit ) m 448 28 ###
12 ### Bore Pile diameter 300mm m 2,880 84 ###
13 ### Pemasangan Geotextille Woven m2 4,734 112 ###
14 ### Timbunan Kembali Back Fill m3 1,025 28 ###
15 ### Beton K250 m3 21,900 252 Monday, May 23, 2022
16 ### Beton K-125 Lean Concrete m3 2,087 84 ###
17 ### Urugan Pasir m3 5,936 84 ###
18 ### Pembesian kg 1,569,858 224 Monday, April 25, 2022
19 ### Bekisting m2 6,197 112 ###
20 ### Water Stop m' 1,712 56 ###
21 ### Douwel Bar besi Polos Ø 25 Bh 224 112 ###
22 ### Wheep Hole Unit 837 112 ###
Normali Sungai Bagian hilir (Down Stream)
23 ### Dredging m3 17,360 112 Monday, March 14, 2022
24 ### Transport Buangan hasil galian m3 17,360 112 Monday, March 14, 2022
25 ### Timbunan Kembali Back Fill m3 186 7 ###
26 ### Bore Pile diameter 250mm m 9,920 84 ###
27 ### Beton K250 m3 2,147 168 Monday, July 11, 2022
28 ### Beton K-125 Lean Concrete m3 310 28 ###
29 ### Urugan Pasir m3 310 28 ###
30 ### Pasangan Batu m3 1,823 56 Monday, May 9, 2022
31 ### Plesteran 1 Pc : 4 Psr. m2 820 56 ###
32 ### Pembesian kg 171,725 84 Monday, April 4, 2022
33 ### Bekisting m2 1,737 84 Monday, April 11, 2022
34 ### Water Stop m' 1,067 56 ###
35 ### Douwel Bar besi Polos Ø 25 Bh 180 56 ###
36 ### Wheep Hole Unit 877 56 ###
Pekerjaan Lain-lain
37 Monday, June 21, 2021 Soil Investigations m' 390 56 Monday, August 16, 2021
38 Monday, June 21, 2021 Foto Dokumentasi Ls 1 91 Monday, July 18, 2022
39 Monday, June 21, 2021 Percetakan Gambar Ls 350 21 Monday, July 18, 2022

Anda mungkin juga menyukai