SCHEDULE PEKERJAAN

PROYEK PEMBANGUNAN GUDANG CURAH KERING DI PELABUHAN BANTEN

DURASI DESEMBER 2022 JANUARI 2023 FEBRUARI 2023 MARET 2023


No. URAIAN PEKERJAAN START FINISH 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
(HARI)
PEKERJAAN PRE ENGINEERED BUILDING (PEB) 16/12/2022 28/02/2023 74
PEKERJAAN ERECTION 16/12/2022 19/02/2023 65
1 Pemasangan Angkur
2 Onsite Material PEB 16/12/2022
3 Bongkar Matrial 18/12/2022 21/12/2022 3
4 Rakit Matrial 20/12/2022 03/01/2023 14
5 Erexsion Kolom Depan 28/12/2022 20/01/2023 23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
6 Erexsion Kolom Belakang 24/12/2022 10/02/2023 48 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
7 Pemasangan Rafter 01/01/2023 16/02/2023 46 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
8 Perkutan Rafter 02/01/2023 17/02/2023 46 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
9 Pemasangan Gording 02/01/2023 17/02/2023 46 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
10 Pemasangan Ikatan Angin 01/12/2023 18/02/2023 -286
11 Pemasangan Trestang 03/01/2023 18/02/2023 46
12 Rangka Talang + Talang 29/01/2023 19/02/2023 21

PEKERJAAN WALL AND ROOF SHEETING 10/01/2023 28/02/2023 49


13 Onsite material UPVC 10/01/2023
14 Persetujuan Material Talang 25/01/2023
15 Persetujuan Gambar Talang 25/01/2023 26/01/2023 1
16 Persetujuan Gambar Atap dan Dinding UPVC 26/01/2023 27/01/2023 1
17 Produksi Material Talang FRP 25/01/2023 09/02/2023 15
18 Pas. Talang + Pipa Air 02/02/2023 14/02/2023 12
19 Pemasangan Atap UPVC Segmen 1 03/02/2023 06/02/2023 3
20 Pemasangan Atap UPVC Segmen 2 07/02/2023 10/02/2023 3
21 Pemasangan Atap UPVC Segmen 3 11/02/2023 14/02/2023 3
22 Pemasangan Atap UPVC Segmen 4 15/02/2023 18/02/2023 3
23 Pemasangan Dinding Samping Kom.1 26/02/2023 01/03/2023 3
24 Pemasangan Dinding Samping Kom.6 18/02/2023 20/02/2023 2
25 Pemasangan Dinding Depan 01/02/2023 22/02/2023 21
26 Pemasangan Dinding Belakang 13/02/2023 28/02/2023 15

MEKANIKAL ELEKTRIKAL
MECHHANICAL WORKS
Pekerjaan Pemadam Kebakaran
1 Pembongkaran Paving Exksisting
2 Pekerjaan Galian Pipa
3 Timbunan dan Perapihan Kembali
4 Pemasangan Pipa Hydrant Utama
5 Pemasangan Pipa Hydrant Cabang
6 Pemasangan Pilar Hydraft
7 Pemasangan Hydrant Box
8 Fire Extinguisher
9 Partial Testcomm

Pekerjaan HVAC
1 Factory Visit
2 Pengadaan Exhaust Fan
3 Instalasi Exhasut Fan
4 Terminasi
5 Partial Testcomm

ELECTRICAL WORKS
Panel Listrik
1 Factory Visit
2 Pengadaan Panel Listrik
3 Pabrikasi dan Pemasangan Supoort
4 Instalasi Panel Listrik
5 Partial Testcomm

Pekerjaan Kabel
1 Pekerjaan Galian Kabel
2 Timbunan dan Perapihan Kembali
3 Pabrikasi dan Pemasangan Support
4 Pemasangan Cable Tray
5 Instalasi Kabel
6 Megger Test
7 Partial Testcomm

Pekerjaan Lighting
1 Lighting Indoor
2 Terminasi
3 Pabrikasi dan Pemasangan Support
4 Pemasangan Lampu
5 Partial Testcomm

Penangkal Petir
1 Approval Material
2 Terminasi
3 Pemasangan Air Teminal dan kelengkapan
4 Sistem Pentanahan

Pekerjaan Elektronik
1 Approval Material
2 Terminasi
3 Megger Test
4 Pemasangan Fire Alarm dan Kelengkapan
5 Pemasangan Sound System dan Kelengkapan
6 Test dan Commisioning

catatan : Item dengan review warna merah perlu evaluasi ulang