SOAL LAPORAN PELAKSANAAN PRAKTIKUM

1. Input data pekerjaan :

NO Nama Pekerjaan Durasi NO Nama Pekerjaan Durasi


Rangka Atap Baja R.
1 Pekerjaan Persiapan 11 days 33 10 days
Adm
2 Pembersihan Lapangan 6 days 34 Pekerjaan Atap 26 days
3 Bouwplank 2 days 35 Asbes Gelombang 10 days
4 Direksi Keet & Gudang 3 days 36 Genteng 4 days
5 Pekerjaan Tanah 25 days 37 Pekerjaan Plafon 320 days
6 Galian Tanah 10 days 38 Plafond Pabrik 320 days
7 Urugan Tanah Kembali 2 days 39 Plafond R. Adm 10 days
8 Urugan Pasir 2 days 40 Pekerjaan Kusen 80 days
9 Pekerjaan Beton 92 days 41 Kusen 80 days
10 Lantai Kerja 3 days 42 Daun Pintu dan Jendela 10 days
11 Beton Foot Plat 5 days 43 Kaca 5 mm 10 days
12 Beton Sloof 3 days 44 Pekerjaan Listrik -
13 Beton Kolom Lt. 1 7 days 45 Box Sekring/MCB 3 days
14 Beton Kolom Praktis Lt. 1 5 days 46 Titik Lampu dan Saklar 4 days
15 Beton Balok & Plat Lt. 2 14 days 47 Instalasi Listrik 10 days
16 Beton Kolom Lt. 2 6 days 48 Pekerjaan Plumbing 328 days
17 Beton Kolom Praktis Lt. 2 3 days 49 Talang 10 days
18 Beton Ringbalk 7 days 50 Instalasi AC 3 days
19 Beton Rabat 3 days 51 Pekerjaan Sanitasi 91 days
20 Beton Tangga 28 days 52 Instalasi Air Bersih 10 days
21 Pekerjaan Pasangan 75 days 53 Instalasi Air Kotor 20 days
22 Pasangan Batu Kali 1:3 7 days 54 Septictank dan Peresapan 14 days
23 Pasangan Batu Bata 1:2 15 days 55 Wastafel dan Closet 5 days
24 Pasangan Batu Bata 1:4 30 days 56 Sumur dan Bak Tandon 21 days
25 Plesteran 20 days 57 Pekerjaan Cat 298 days
26 Pasangan Keramik Lantai 20 days 58 Cat Kayu/Besi 14 days
Pasangan Keramik
27 5 days 59 Cat Tembok 25 days
Tangga
Pasangan Keramik
28 20 days 60 Pekerjaan Lain - Lain 333 days
KM/WC
29 Pekerjaan Besi/Baja 59 days 61 Hydran 5 days
30 Kolom Baja 30 days 62 Penangkal Petir 3 days
31 Konsol Baja Pabrik 10 days 63 Finishing 5 days
32 Rangka Atap Baja Pabrik 25 days
2. Tentukannlah hubungan antar pekerjaan sesuai daftar berikut ini :

No.Pek Predecessor No.Pek Predecessor No.Pekerjaa Predecessor


n

1 22 6 43 42

2 23 12 44

3 2 24 23 45 25

4 2,3 25 24 46 38,39,47

5 26 8 47 45

6 3 27 26 48

7 11,2 28 26 49 35

8 7 29 50 46

9 30 12 51

10 6 31 32 52 26,28

11 10 32 30 53 49,52

12 11 33 18 54 4,6

13 12 34 55 52,53,56

14 12,13,23 35 31,32 56 6,52

15 13,14 36 33 57

16 15 37 58 38,39,43

17 15,16,20 38 35 59 27,52

28 16,17 39 25,36 60

19 61 40 61 25,52

20 13 41 23,24 62 35

21 42 41 63 5,19,50,56,59,52
3. Menghubungkan antar pekerjaan non standar dan menggunakan Lag time dan Lead time

No.Pek Predecessor No.Pek Predecessor No.Pek Predecessor

1 22 6 43 42SS

2 23 12 44

3 2FS+2 days 24 23 45 25

4 2;3SS 25 24 46 38;39;47

5 26 8 47 45

6 3 27 26 48

7 11;12 28 26 49 35

8 7FS+1 day 29 50 46

9 30 12SS-3 days 51

10 6 31 32SS+5 days 52 26;28

11 10FF 32 30SS+5 days 53 49;52

12 11FS+4 days 33 18 54 4;6

13 12SS+4 days 34 55 52;53;56

14 12;13;23 35 31;32FS+10 days 56 6;52

15 13;14 36 33SS+7 days 57

16 15 37 58 38;39;43

17 15;16;20 38 35 59 27;55

28 16;17 39 25;36 60

19 61SS+5 days 40 61 25;52

20 13FF 41 23;24SS-7 days 62 35

21 42 41SS 63 5;19;50;56;59;62
4. Mengisi data untuk RESOURCES SHEET dan GANTT CHART :

Cost
Resource Material Max. Std. Ovt. Base
No Type Initials Group /Us Accrue At
Name Label Units Rate Rate Calendar
e

1 Mandor Work Mcat 5 2000 1000 Prorated Standard

2 K T Batu Work KTB 5 1750 750 Prorated Standard

3 T Batu Work TB 20 1500 500 Prorated Standard

4 Pekerja Work P 50 1500 500 Prorated Standard

5 K T Kayu Work KTK 5 1750 750 Prorated Standard

6 T Kayu Work TK 10 1500 500 Prorated Standard

7 K T Besi Work KTBs 5 1750 750 Prorated Standard

8 T Besi Work TBs 10 1500 500 Prorated Standard

9 K T Cat Work KTC 10 1750 750 Prorated Standard

10 T Cat Work TC 10 1500 500 Start Standard

11 Pasir Urug Material m3 PU 30000 Start

12 Beton Material m3 B 300000 Start

Batu
13 Material m3 BB 175000 Start
Belah

14 Semen Material Sak S 25000 Start

15 Kapur Material m3 Kpr 75000 Start

Pasir
16 Material m3 PPs 150000 Start
Pasang

17 Batu Bata Material Bh BBt 500 Start

18 Tegel Material Bh Tgl 15000 Start

19 Besi Material m3 Bs 125000 Start

20 Mur Baut Material Kg Mbaut 15000 Start

21 Asbes Material Bh Asbes 2000 Start

22 Sekrup Material Bh Skrp 500 Start


23 Genteng Material Bh Gt 2000 Start

24 Eternit Material Bh E 4000 Start

Kayu
25 Material m3 KKpr 100000 Start
Kamper

26 Paku Material Kg Pk 5000 Start

27 Kayu Jati Material m3 KJ 200000 Start

28 Angkur Material Bh Ang 5000 Start

29 Teakwood Material Bh Twoo 10000 Start

30 Kaca Material m2 Kc 25000 Start

31 Lis Kayu Material m1 LK 10000 Start

32 Seng Material Bh Seng 25000 Start

33 AC Material Bh AC 250000 Start

34 Cat Meni Material Kg Cmen 20000 Start

35 Cat Kilap Material Ltr Ckilap 20000 Start

Minyak
36 Material Ltr Mcat 5000 Start
Cat

37 Plamir Material Kg Plamir 10000 Start

38 Amplas Material Bh Amp 5000 Start

Cat
39 Material Kg CTbk 25000 Start
Tembok

40 Sub Kon B Work SKB 1 100000 25000 End Standard

41 Sub Kon C Work SKC 1 100000 25000 End Standard

42 Sub Kon A Work SKA 1 100000 25000 End Standard

43 Sub Kon D Work SKD 1 100000 25000 End Standard

5. Tetapkan hari libur nasional pada jadwal proyek pada latihan 4 : 25 Desember 2018
6. Simpanlah file latihan 5 dengan BASELINE, masukkan kemajuan pekerjaan dengan data
sementara sbb :

Kemajuan
No. Task Name
Pekerjaan

1 Pekerjaan Persiapan

2 Pembersihan Lapangan 100%

3 Bouwplank 100%

4 Direksi Keet & Gudang 100%

5 Pekerjaan Tanah

6 Galian Tanah 25%

7 Urugan Tanah Kembali 100%

8 Urugan Pasir 100%

7. Buatlah laporan proyek (DASHBOARDS, RESOURCES, COSTS, IN PROGRESS) ?