Kontraktor Pelaksana
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific
DINAS PENDIDIKAN
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas
PT. Dinamika Sarana Inov

TGL BULAN NOVEMBER BULAN DESEMBER

1 30
2 1 MULAI 31
3 2 32
4 3 33
5 4 34
6 5 35 M5
7 6 36
8 7 M1 37
9 8 38
10 9 39
11 10 40
12 11 41
13 12 42 M6
14 13 43
15 14 M2 44
16 15 45
17 16 46
18 17 47
19 18 48
20 19 49 M7
21 20 50
22 21 M3 51
23 22 52
24 23 53
25 24 54
26 25 55
27 26 56 M8
28 27 57
29 28 M4 58
30 29 59
31 60 M9
DAFTAR HARI KALENDER
Kontraktor Pelaksana
CV. Kharisma Scientific Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
Lokasi : KOTA BOGOR
Konsultan Pengawas Tahun Anggaran : 2021
PT. Dinamika Sarana Inovasi Nilai Pekerjaan Rp345,660,086.00

BULAN JANUARI MINGGU PERIODE MINGGUAN

1 : 2 November S/D 8 November 2021


2 : 9 November S/D 15 November 2021
3 :16 November S/D 22 November 2021
4 23 November S/D 29 November 2021
5 30 November S/D 6 Desember 2021
6 07 Desember S/D 13 Desember 2021
7 14 Desember S/D 20 Desember 2021
8 21 Desember S/D 27 Desember 2021
9 28 Desember S/D 31 Desember 2021
KET.

7 1 7 : 1 (SATU)
7 2 14 : 2 (DUA)
7 3 21 : 3 (TIGA)
7 4 28 : 4 (EMPAT)
7 5 35 : 5 (LIMA)
7 6 42 : 6 (ENAM)
WAKTU PELAKSANAAN 60 (ENAM PULUH) HARI KALENDER

7 7 49 : 7 (TUJUH)
7 8 56 : 8 (DELAPAN)
7 9 60 : 9 (SEMBILAN)
7 10 70 : 1 (SATU)
7 11 77 : 1 (SATU)
7 12 84 : 1 (SATU)
7 13 91 : 1 (SATU)
7 14 98 : 1 (SATU)
15 0

12.8571429
JADWAL WAKTU PELAKSANAAN

BOBOT WAKTU PELAKSANAAN 60 HARI KALENDER


NO URAIAN PEKERJAAN
% 1 2 3 4 5 6 7 8 9 KET

100
I 2.741 0.305 0.305 0.305 0.305 0.305 0.305 0.305 0.305 0.305 90
PEKERJAAN PERSIAPAN
80
II 2.926 2.926 2.926 2.926
PEKERJAAN PASANGAN 11.703 70
III 0.451 0.451 0.451 60
PEKERJAAN KUSEN DAN KAYU 1.352
50
IV 1.330 1.33 1.330 40
PEKERJAAN INSTALASI LISTRIK 3.991
30
V 17.662 17.662 17.662 17.662
PEKERJAAN ATAP DAN DINDING 70.650 20
VI 2.391 2.391 2.391 2.391 10
PEKERJAAN PENGECATAN DAN PENYELESAIAN 9.562
0
JUMLAH 100.000
Progres Rencana Kerja Per Minggu 0.305 0.305 0.305 3.230 20.893 25.065 25.065 22.139 2.695
Akumulasi Progres Rencana Kerja Per Minggu - 0.305 0.609 0.914 4.144 25.037 50.101 75.166 97.305 100.000
Realisasi Kerja Per Minggu - 1.065 0.183 0.111 35.853 7.473 20.453 32.222
Akumulasi Realisasi Kerja Per Minggu - - 1.065 1.248 1.360 37.213 44.551 65.727 100.000
LAPORAN PEKERJAAN
REHABILITASI SMPN 3 KOTA BOGOR

NO
URAIAN PEKERJAAN VOLUME SATUAN

1 PEKERJAAN PERSIAPAN
1 papan nama proyek 1.00 ls
2 Pek. Bongkaran ( atap plafond ) 1.00 ls
3 Rencana K3 1.00 ls
4 Pek. Listrik dan air kerja 1.00 ls
5 Pembersihan lokasi 1.00 ls

2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2
2 pas. Keramik 30x30 set. Mulia 27.40 m2
3 pek. Ring balok 15x30 cm 3.51 m3
4 pek. Ring balok 17x16 cm 1.17 m3
5 pek. Ban-banan berikut waterproof 16.80 m1
6 pek. Plesteran dan acian bekas ban-banan 6.72 m2

3 PEKERJAAN KUSEN DAN KAYU


1 pek. Konsol dan kayu 4.00 unit
2 pek. Kusen jendela kayu type J3 4.00 unit

4 PEKERJAAN INSTALASI LISTRIK


1 perbaikan instalasi listrik 1.00 ls
2 pas. Saklar ganda 6.00 bh
3 pas. Stop kontak 5.00 bh
4 pas. Lampu SL 18 watt 27.00 bh

5 PEKERJAAN ATAP DAN PLAFOND


1 pas. Rangka atap baja ringan 539.65 m2
2 pas. Kembali penutup atap genteng pelentong 285.95 m2
3 pas. Penutup atap genteng pelentong kecil (baru) 253.70 m2
4 pas. Nok atap genteng pelentong kecil 43.00 m1
5 pas. Plafond PVC 460.34 m2
6 pas. Rangka hollow 460.34 m2
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1
8 pek. Talang air PVC U-15 43.00 m1

6 PEKERJAAN PENGECATAN DAN PENYELESAIAN


1 pek. pengecatan Dinding TOA 2x 586.63 m2
2 pek. Pengecatan dinding batu alam 121.19 m2
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2
4 pek. Cat bekas ban-banan 6.72 m2
TAMBAHAN PEKERJAAN
1 pek. Talang air 43.00 m1
pek. Ban-banan berikut waterproof 16.8 m1
pek. Plesteran dan acian bekas ban-banan 6.72 m2
pek. Cat bekas ban-banan lama 6.72 m2

RINCIAN PEKERJAAN TAMBAH KURANG


No. URAIAN
PEKERJAAN
PE SESUAI KONTRAK
Vol.

I Pekerjaan Tambah
1 Pek. Balok Beton 30/1
2 Pek. Balok Beton 15/1
3 pas. Kemba 283.02
4 pek. Penge 80
5 pekerjaan talang air
6 pekerjaan ban-banan b
7 pekerjaan plesteran d
8 pekerjaan cat bekas b
9 pekerjaan instalasi kabe
10 pekerjaan 12
11 pek. Penge 10
12 pek. Bongk 5
II Pekerjaan Kurang
2 pas. Kerami 108.99
1 pek. Konso 12
2 pek. Kusen 6
1 pas. Rangka 566.05
3 pas. Penutu 283.02
4 pas. Nok a 45
5 pas. Plafo 499.61
6 pas. Rangk 499.61
7 pek. penge 478.76
HARGA SATUAN JUMLAH HARGA
BOBOT
(Rp) (Rp)

182,500.00 182,500.00 0.06


1,500,000.00 1,500,000.00 0.48
5,180,000.00 5,180,000.00 1.66
1,250,000.00 1,250,000.00 0.40
500,000.00 500,000.00 0.16
8,612,500.00 2.76

89,800.00 743,544.00 0.24


264,000.00 7,233,600.00 2.32
6,458,257.74 22,668,484.67 7.27
7,354,764.89 8,605,074.92 2.76
- 0.00
95,374.40 640,915.97 0.21
39,250,703.59 12.79

250,000.00 1,000,000.00 0.32


850,000.00 3,400,000.00 1.09
4,400,000.00 1.41

200,000.00 200,000.00 0.06


62,100.00 372,600.00 0.12
59,800.00 299,000.00 0.10
180,450.00 4,872,150.00 1.56
5,743,750.00 1.84

150,100.00 81,001,465.00 25.98


14,100.00 4,031,895.00 1.29
88,700.00 22,503,190.00 7.22
31,380.00 1,349,340.00 0.43
150,000.00 69,051,000.00 22.15
76,700.00 35,308,078.00 11.32
89,300.00 7,679,800.00 2.46
114,600.00 4,927,800.00 1.58
220,924,768.00 72.44

41,500.00 24,345,145.00 7.81


61,400.00 7,441,066.00 2.39
41,500.00 1,070,700.00 0.34
- 0.00
32,856,911.00 10.54
101.79
311,788,632.59

tambah
kurang

AN SESUAI KONTRAK PEKERJAAN TAMBAH


Sat. Harga Sat Jumlah HarBobot Vol. Jumlah Har
(Rp.) ( Rp) (%) ( Rp )

m3 6458257.74 - - 3.51 22668485


m3 7354764.89 - - 1.1696 8602133
m2 14100 3990582 2.93 41313
m2 61400 4912000 63.3289 3888394
m' 43
m' 16.8
m2 6.72
m2 6.72
- -
unit -
unit
unit

m2 264000 28773360 - 0
unit 250000 3000000 - 0
unit 850000 5100000 - 0
m2 150100 84964105 - 0
m2 88700 25103874 0
m1 31380 1412100 - 0
m2 150000 74941500 - 0
m2 76700 38320087 - 0
m2 41500 19868540 0
Jumlah : 35200325
PEKERJAAN KURANG PEKERJAAN SESUAI PELAKSANAAN
Bobot Vol. Jumlah HarBobot Vol. Jumlah HarBobot
(%) ( Rp) (%) (Rp.) (%)

- 0 0 3.51 22668485
- 0 0 1.1696 8602133
0 0 285.95 4031895
- 0 0 143.3289 8800394

0 71.79 18952560 37.2 9820800


0 12 3000000 0 0
0 1 850000 5 4250000
0 26.4 3962640 539.65 81001465
0 29.32 2600684 253.7 22503190
0 2 62760 43 1349340
0 39.27 5890500 460.34 69051000
0 39.27 3012009 460.34 35308078
35.4619 1471669 443.2981 18396871
39802822
RINCIAN PEKERJAAN TAMBAH KURANG

PEKERJAAN : REHABILITASI SMPN 03 KOTA BOGOR


LOKASI : KOTA BOGOR
PEKERJAAN SESUAI KONTRAK PEKERJAAN TAMBAH PEKERJAAN KURANG PEKERJAAN SESUAI PELAKSANAAN
No. URAIAN PEKERJAAN Vol. Sat. Harga Sat Jumlah Harga Bobot Vol. Jumlah Harga Bobot Vol. Jumlah Harga Bobot Vol. Jumlah Harga Bobot
(Rp.) ( Rp) (%) ( Rp ) (%) ( Rp) (%) (Rp.) (%)

1 PEKERJAAN PERSIAPAN
1 papan nama proyek 1.00 ls 182,500.00 182,500.00 0.058 - - - - - - 1.00 182,500.00 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 1,500,000.00 1,500,000.00 0.477 - - - - - - 1.00 1,500,000.00 0.477
3 rencana K3 1.00 ls 5,180,000.00 5,180,000.00 1.648 - - - - - - 1.00 5,180,000.00 1.648
4 pek. Listrik dan air kerja 1.00 ls 1,250,000.00 1,250,000.00 0.398 - - - - - - 1.00 1,250,000.00 0.398
5 pembersihan lokasi 1.00 ls 500,000.00 500,000.00 0.159 - - - - - - 1.00 500,000.00 0.159
8,612,500.00 2.740 - - - - 8,612,500.00 2.740
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 89,800.00 743,544.00 0.237 - - - - - - 8.28 743,544.00 0.237
2 pas. Keramik 30x30 set. Mulia 108.99 m2 264,000.00 28,773,360.00 9.153 - - - 104.91 27,695,028.47 8.810 4.08 1,078,331.53 0.343
3 Pek. Balok Beton 30/15 cm m3 6,458,257.74 - - 3.48 22,474,736.94 7.149 - - - 3.48 22,474,736.94 7.149
4 Pek. Balok Beton 16/17 cm m3 7,354,764.89 - - 1.17 8,605,074.92 2.737 - - - 1.17 8,605,074.92 2.737
5 pekerjaan ban-banan m' 39,300.00 - - 16.80 660,240.00 0.210 - - - 16.80 660,240.00 0.210
6 pekerjaan plesteran dan acian bekas ban-banan m2 89,800.00 - - 6.72 603,456.00 0.192 - - - 6.72 603,456.00 0.192
29,516,904.00 9.389 32,343,507.86 10.289 27,695,028.47 8.810 34,165,383.39 10.868
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Konsol dan kayu 12.00 unit 250,000.00 3,000,000.00 0.954 - - - 12.00 3,000,000.00 0.954 - - -
2 pek. Kusen jendela kayu type J3 6.00 unit 850,000.00 5,100,000.00 1.622 - - - 1.00 850,000.00 0.270 5.00 4,250,000.00 1.352
8,100,000.00 2.577 - - 3,850,000.00 1.225 4,250,000.00 1.352
4 PEKERJAAN INSTALASI LISTRIK
1 perbaikan instalasi listrik 1.00 ls 200,000.00 200,000.00 0.064 - - - - - - 1.00 200,000.00 0.064
1 Pas. instalasi listrik titik 184,800.00 - - 27.00 4,989,600.00 1.587 - - - 27.00 4,989,600.00 1.587
2 pas. Saklar ganda 6.00 bh 62,100.00 372,600.00 0.119 - - - - - - 6.00 372,600.00 0.119
3 pas. Stop kontak 5.00 bh 59,800.00 299,000.00 0.095 - - - - - - 5.00 299,000.00 0.095
4 pas. Lampu SL 18 watt 27.00 bh 180,450.00 4,872,150.00 1.550 - - - - - - 27.00 4,872,150.00 1.550
5,743,750.00 1.827 4,989,600.00 1.587 - - 10,733,350.00 3.414
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 566.05 m2 150,100.00 84,964,105.00 27.028 - - - 26.40 3,962,640.00 1.261 539.65 81,001,465.00 25.767
2 pas. Kembali penutup atap genteng pelentong 283.02 m2 14,100.00 3,990,582.00 1.269 - - - 37.92 534,672.00 0.170 245.10 3,455,910.00 1.099
3 pas. Penutup atap genteng pelentong kecil (baru) 283.02 m2 88,700.00 25,103,874.00 7.986 - - - 29.32 2,600,684.00 0.827 253.70 22,503,190.00 7.158
4 pas. Nok atap genteng pelentong kecil 45.00 m1 31,380.00 1,412,100.00 0.449 - - - 2.00 62,760.00 0.020 43.00 1,349,340.00 0.429
5 pas. Plafond PVC 499.61 m2 150,000.00 74,941,500.00 23.839 - - - 39.27 5,890,500.00 1.874 460.34 69,051,000.00 21.966
6 pas. Rangka hollow 499.61 m2 76,700.00 38,320,087.00 12.190 - - - 39.27 3,012,009.00 0.958 460.34 35,308,078.00 11.232
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 89,300.00 7,679,800.00 2.443 - - - - - - 86.00 7,679,800.00 2.443
8 pekerjaan talang air Seng BJLS lebar 20 cm m1 109,600.00 - - 43.00 4,712,800.00 1.499 - - - 43.00 4,712,800.00 1.499
236,412,048.00 75.204 4,712,800.00 1.499 16,063,265.00 5.110 225,061,583.00 71.593
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 478.76 m2 41,500.00 19,868,540.00 6.320 - - - 35.46 1,471,668.85 0.468 443.30 18,396,871.15 5.852
2 pek. Pengecatan dinding batu alam 80.00 m2 61,400.00 4,912,000.00 1.563 63.33 3,888,394.46 1.237 - - - 143.33 8,800,394.46 2.799
3 pek. Pengecatan lisplank GRC TOA 3x 28.80 m2 41,500.00 1,195,200.00 0.380 - - - - - - 28.80 1,195,200.00 0.380
4 pekerjaan cat bekas ban-banan lama m2 41,500.00 - - 6.72 278,880.00 0.089 - - - 6.72 278,880.00 0.089
5 pek. Pengecatan kusen jendela m2 41,500.00 - - 65.80 2,730,700.00 0.869 - - - 65.80 2,730,700.00 0.869
6 pek. Water profing m2 54,000.00 - - 2.52 136,080.00 0.043 - - - 2.52 136,080.00 0.043
25,975,740.00 8.263 7,034,054.46 2.238 1,471,668.85 0.468 31,538,125.61 10.032
JUMLAH 314,360,942.00 100.000 49,079,962.32 15.613 49,079,962.32 15.613 314,360,942.00 100.000
PPN 10 % 31,436,094.20 4,907,996.23 4,907,996.23 31,436,094.20
JUMLAH TOTAL 345,797,036.20 53,987,958.55 53,987,958.55 345,797,036.20
DIBULATKAN 345,797,000.00 53,987,900.00 53,987,900.00 345,797,000.00

Mengetahui: Mengetahui: Konsultan Pengawas Kontraktor Pelaksana


Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan PT. Dinamika Sarana Inovasi CV. Kharisma Scientific

Junenti Kolbert Nadeak, S.T, M.E Firmansyah, ST H. Ruslan Abdul Gaffar, S.T.
NIP. 19780620 200501 1 005 NIP. 197610292006041012 Direktur Direktur.
VOL

-
-

3.476
1.170
16.800
6.720
531.050
245.100
285.950
43.000
289.41 170 459.26
294.55 170 464.40

-
- - -
-

-
-
4.08458914205
RINCIAN PEKERJAAN TAMBAH KURANG

PEKERJAAN : REHABILITASI SMPN 03 KOTA BOGOR


LOKASI : KOTA BOGOR
PEKERJAAN SESUAI KONTRAK PEKERJAAN TAMBAH PEKERJAAN KURANG PEKERJAAN SESUAI PELAKSANAAN
No. URAIAN PEKERJAAN Vol. Sat. Harga Sat Jumlah Harga Bobot Vol. Jumlah Harga Bobot Vol. Jumlah Harga Bobot Vol. Jumlah Harga Bobot
(Rp.) ( Rp) (%) ( Rp ) (%) ( Rp) (%) (Rp.) (%)

1 PEKERJAAN PERSIAPAN
1 papan nama proyek 1.00 ls 182,500.00 182,500.00 0.058 - - - - - - 1.00 182,500.00 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 1,500,000.00 1,500,000.00 0.477 - - - - - - 1.00 1,500,000.00 0.477
3 Rencana K3 1.00 ls 5,180,000.00 5,180,000.00 1.648 - - - - - - 1.00 5,180,000.00 1.648
4 pek. Listrik dan air kerja 1.00 ls 1,250,000.00 1,250,000.00 0.398 - - - - - - 1.00 1,250,000.00 0.398
5 pembersihan lokasi 1.00 ls 500,000.00 500,000.00 0.159 - - - - - - 1.00 500,000.00 0.159
8,612,500.00 2.741 - - - - 8,612,500.00 2.741
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 89,800.00 743,544.00 0.237 - - - - - - 8.28 743,544.00 0.237
2 pas. Keramik 30x30 set. Mulia 108.99 m2 264,000.00 28,773,360.00 9.157 - - - 88.20 23,284,329.86 7.410 20.79 5,489,030.14 1.747
3 Pek. Balok Beton 30/15 cm (termasuk Besi & begisting) m3 6,071,057.74 - - 3.48 21,127,280.94 6.723 - - - 3.48 21,127,280.94 6.723
4 Pek. Balok Beton 16/17 cm (termasuk Besi & begisting) m3 6,967,564.89 - - 1.17 8,152,050.92 2.594 - - - 1.17 8,152,050.92 2.594
5 pekerjaan ban-banan m' 39,300.00 - - 16.80 660,240.00 0.210 - - - 16.80 660,240.00 0.210
6 pekerjaan plesteran dan acian bekas ban-banan m2 89,800.00 - - 6.72 603,456.00 0.192 - - - 6.72 603,456.00 0.192
29,516,904.00 9.393 30,543,027.86 9.720 23,284,329.86 7.410 36,775,602.00 11.703
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Konsol dan kayu 12.00 unit 250,000.00 3,000,000.00 0.955 - - - 12.00 3,000,000.00 0.955 - - -
2 pek. Kusen jendela kayu type J3 6.00 unit 850,000.00 5,100,000.00 1.623 - - - 1.00 850,000.00 0.270 5.00 4,250,000.00 1.352
8,100,000.00 2.578 - - 3,850,000.00 1.225 4,250,000.00 1.352
4 PEKERJAAN INSTALASI LISTRIK
1 perbaikan instalasi listrik 1.00 ls 200,000.00 200,000.00 0.064 - - - 1.00 200,000.00 0.064 - - -
1 Pas. instalasi listrik (lengkap asesoris) titik 259,200.00 - - 27.00 6,998,400.00 2.227 - - - 27.00 6,998,400.00 2.227
2 pas. Saklar ganda 6.00 bh 62,100.00 372,600.00 0.119 - - - - - - 6.00 372,600.00 0.119
3 pas. Stop kontak 5.00 bh 59,800.00 299,000.00 0.095 - - - - - - 5.00 299,000.00 0.095
4 pas. Lampu SL 18 watt 27.00 bh 180,450.00 4,872,150.00 1.550 - - - - - - 27.00 4,872,150.00 1.550
5,743,750.00 1.828 6,998,400.00 2.227 200,000.00 0.064 12,542,150.00 3.991
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 566.05 m2 150,100.00 84,964,105.00 27.038 - - - 26.40 3,962,640.00 1.261 539.65 81,001,465.00 25.777
2 pas. Kembali penutup atap genteng pelentong 283.02 m2 14,100.00 3,990,582.00 1.270 - - - 7.07 99,687.00 0.032 275.95 3,890,895.00 1.238
3 pas. Penutup atap genteng pelentong kecil (baru) 283.02 m2 88,700.00 25,103,874.00 7.989 - - - 29.32 2,600,684.00 0.828 253.70 22,503,190.00 7.161
4 pas. Nok atap genteng pelentong kecil 45.00 m1 31,380.00 1,412,100.00 0.449 - - - 2.00 62,760.00 0.020 43.00 1,349,340.00 0.429
5 pas. Plafond PVC 499.61 m2 150,000.00 74,941,500.00 23.849 - - - 39.27 5,890,500.00 1.875 460.34 69,051,000.00 21.974
6 pas. Rangka hollow 499.61 m2 76,700.00 38,320,087.00 12.195 - - - 39.27 3,012,009.00 0.959 460.34 35,308,078.00 11.236
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 89,300.00 7,679,800.00 2.444 - - - - - - 86.00 7,679,800.00 2.444
8 pekerjaan talang PVC m1 68,000.00 - - 18.00 1,224,000.00 0.390 - - - 18.00 1,224,000.00 0.390
236,412,048.00 75.234 1,224,000.00 0.390 15,628,280.00 4.973 222,007,768.00 70.650
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 478.76 m2 41,500.00 19,868,540.00 6.323 - - - 28.74 1,192,710.00 0.380 450.02 18,675,830.00 5.943
2 pek. Pengecatan dinding batu alam 80.00 m2 61,400.00 4,912,000.00 1.563 63.33 3,888,462.00 1.237 - - - 143.33 8,800,462.00 2.801
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 41,500.00 1,070,700.00 0.341 - - - - - - 25.80 1,070,700.00 0.341
4 pek. Pengecatan kusen jendela m2 41,500.00 - - 32.90 1,365,350.00 0.434 - - - 32.90 1,365,350.00 0.434
5 pek. Water profing ban banan m2 54,000.00 - - 2.52 136,080.00 0.043 - - - 2.52 136,080.00 0.043
25,851,240.00 8.227 5,389,892.00 1.715 1,192,710.00 0.380 30,048,422.00 9.562
JUMLAH 314,236,442.00 100.000 44,155,319.86 14.052 44,155,319.86 14.052 314,236,442.00 100.000
PPN 10 % 31,423,644.20 4,415,531.99 4,415,531.99 31,423,644.20
JUMLAH TOTAL 345,660,086.20 48,570,851.84 48,570,851.84 345,660,086.20
DIBULATKAN 345,660,000.00 48,570,800.00 48,570,800.00 345,660,000.00
-
Mengetahui:
Dinas Pendidikan Kota Bogor Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas Kontraktor Pelaksana
Kepala Bidang Bidang Sarana dan Prasana Dinas Pendidikan Kota Bogor PT. Dinamika Sarana Inovasi CV. Kharisma Scientific
Selaku Pejabat Pembuat Komimen

Junenti Kolbert Nadeak, S.T, M.E Firmansyah, ST H. Ruslan Abdul Gaffar, S.T. Dwi Kuncoro
NIP. 19780620 200501 1 005 NIP. 197610292006041012 Direktur Direktur.
PIHAK PERTAMA PIHAK KEDUA
Dinas Pendidikan Kota Bogor Kontraktor Pelaksana
Kepala Bidang Bidang Sarana dan Prasana CV. Kharisma Scientific
Selaku Pejabat Pembuat Komimen

Junenti Kolbert Nadeak, S.T, M.E Dwi Kuncoro


NIP. 19780620 200501 1 005 Direktur.

345797000
VOL

-
-

3.476
1.170
16.800
6.720
531.050
245.100 10.00
285.950
43.000
289.41 170 459.26
294.55 170 464.40

(25.000)

-
- - -
-

-
1

Cat Batu alam : CAT BATU ALAM DALAM KELAS :


panjang taman tinggi 6.084
Depan R2 49.364
43 - 10.95 = 32.05 x 1.86 59.613 43.28
panjang tinggi 5.913
R3 49.253
Belakang atas 2.7 x 1 = 2.7 43.34
bawah 33.5 x 0.9 = 30.15 32.85 5.913
R4 49.253
panjang tinggi 43.34
lorong 15.12 x 1.9 = 28.728 28.728 147.87
67.87
Cat Batu alam : 121.191
2 RAB 80
Selisish
Cat Dinding dalam kelas : CAT BATU ALAM DALAM KELAS : 591.17
panjang tinggi V. Jendela 5.64
R1 R2 47.878
29.5 x 3.9 = 115.05 - 21.13 93.92 42.238 23.52
panjang tinggi V. Jendela 5.76 41.116
R2 R3 47.7432
29.48 x 3.9 = 114.972 - 22.95 44.144 41.9832
panjang tinggi V. Jendela 5.8425
R3 R4 47.7077
29.54 x 3.9 = 115.206 - 22.16 45.3028 41.8652
panjang tinggi V. Jendela 143.3289 23.61
R4
29.54 x 3.9 = 115.206 - 22.27 45.2283 63.3289 41.173
panjang tinggi V. Jendela
R5
29.54 x 3.9 = 115.206 - 22.06 93.146
panjang tinggi V. Jendela
Lorong
14 x 2 = 28 - 28 23.61
349.7411 41.173
V. Jendela V. Batu alam
total V.jendela = 127.54 + 92.463 = 220.003

Cat dinding luar depan belakang :

80.4 x 3.9 = 313.56 - 220.003 93.557

Total V. Cat dinding 443.2981


RAB 478.76
Selisih 35.4619

3
Volume atap. lebar panjang Perkiraan Drajat kemiringan 30: Volume 427.23 43
Belakang 6.65 x 43 = 285.95 243.98 43
depan 5.9 x 43 = 253.7 539.65 537 dedy 426.63 43
total V. Atap 539.65 RAB 566.05 179.76 43
RAB 566.05 selisih -26.4
selisih 26.4
4
#VALUE!
Pas. Genteng lama 6.65 x 43 285.95 #VALUE!
RAB 283.02
Selisih 2.93 7 Pekerjaan tambahan
5
Pas. Genteng baru 5.9 x 43 253.7 1.Penambahan Pekerjaan Ringbalk.
RAB 283.02 - depan :
Selisih 29.32 Panjang 43
lebar 0.17 439 43
6
tinggi 0.16 220 43
Pas. Plafon PVC dan rangka hollo : volume 1.1696 m3 439 43
panjang lebar - belakang + tengah/sekat : 200 43
R1
7.85 x 6.9 = 54.165 Panjang 78
panjang lebar lebar 0.15
R2
7.84 x 6.9 = 54.096 tinggi 0,0,3
panjang lebar volume 3.51 m3 442.04 43
R3
7.87 x 6.9 = 54.303 Total volume 4.6796 m3 230 43
panjang lebar 2. pek. Pasangan talang air 43 berikut vertical 442.04 43
R4
7.87 x 6.9 = 54.303 3. pek. Ban-banan baru 16.8 m' 190 43
panjang lebar 4. pek. Plester bekas ban-banan lama
R5
7.87 x 6.9 = 54.303 0,5x8,4x2= 8,4 m2
panjang lebar 5. pasangan instalasi listrik kabelnya
Lorong
2.8 x 6.9 = 19.32 6. kekurangan pengecatan.
panjang lebar 7. pas. Genteng baru
depan
43 x 1.7 = 73.1
panjang lebar
belakang
43 x 2.25 = 96.75
460.34
RAB 499.61 ambil dari pek.konsol,kusen jendala dan pas. Kramik
Selisih 39.27 pas.plafon.

0
11.18 12.34
11.77 29.346
41.686 0.972
42.658

10.53 13.08
11.63 29.543
42.623 1.17
43.793

10.53 13.08
11.63 29.543
42.623 1.17
43.793

18370.89
10491.14
18345.09
7729.68
54936.8
549.368

18877
9460
18877
8600
55814
558.14

19007.72 442.04 43 19007.72


9890 220 43 9460
19007.72 442.04 43 19007.72
8170 200 43 8600
56075.44 56075.44
560.7544 560.7544
Kode Paket
Nama Paket Rehabilitasi SMPN 03
Nama Peserta CV. Kharisma Scientific
NO Jenis Barang/Jasa Satuan Unit Volume Harga Satuan Total sebelum Pajak Pajak (%)
1 Papan Nama Proyek BH 1,00 182,500 Rp 182,500.00 0.058 10%
2 Pek. Bongkaran Atap Plafond Paket 1.00 1,500,000 Rp 1,500,000.00 0.477 10%
3 Pengarahan K3 Org 5.00 15,000 Rp 75,000.00 0.024 10%
4 Spanduk K3 Lbr 1.00 115,000 Rp 115,000.00 0.037 10%
5 Jaring Pengaman SET 1.00 500,000 Rp 500,000.00 0.159 10%
6 Tali Keselamatan SET 1.00 300,000 Rp 300,000.00 0.095 10%
7 Topi Helm Safety bh 5.00 60,000 Rp 300,000.00 0.095 10%
8 Pelindung Pernafasan Bh 5.00 7,500 Rp 37,500.00 0.012 10%
9 Sarung Tangan Psg 5.00 7,500 Rp 37,500.00 0.012 10%
10 Sepatu Safety psg 5.00 150,000 Rp 750,000.00 0.239 10%
11 Rompi Safety Bh 5.00 65,000 Rp 325,000.00 0.103 10%
12 Jas Hujan Proyek bh 5.00 50,000 Rp 250,000.00 0.080 10%
13 Bpjs k3 ls 1.00 700,000 Rp 700,000.00 0.223 10%
14 Peralatan K3 set 1.00 250,000 Rp 250,000.00 0.080 10%
15 APAR 4.5 BH 1.00 700,000 Rp 700,000.00 0.223 10%
16 Hand Sinitizer LT 3.00 250,000 Rp 750,000.00 0.239 10%
17 Masker Medis BOX 6.00 15,000 Rp 90,000.00 0.029 1.648 10%
18 Pek Listrik dan Air paket 1.00 1,250,000 Rp 1,250,000.00 0.398 10%
19 pembersihan lokasi paket 1.00 500,000 Rp 500,000.00 0.159 10%
20 Pas.Plesteran, acian Opening kusein M2 8.28 89,800 Rp 743,544.00 0.237 10%
21 pas Keramik30x30 set mulya m2 108.99 264,000 Rp 28,773,360.00 9.157 10%
22 Pek Konsol Kayu unit 12.00 250,000 Rp 3,000,000.00 0.955 10%
23 Pek kusein Jendela Kayu tipe J3 unit 6.00 850,000 Rp 5,100,000.00 1.623 10%
24 Pek Instalasi Listrik lS 1.00 200,000 Rp 200,000.00 0.064 10%
25 Pas saklar Ganda Bh 6.00 62,100 Rp 372,600.00 0.119 10%
26 Pas Stop Kontak Bh 5.00 59,800 Rp 299,000.00 0.095 10%
27 Pas Lampu Sl 18 watt bh 27.00 180,450 Rp 4,872,150.00 1.550 10%
28 Pas Rangka Atap Baja Ringan m2 566.05 150,100 Rp 84,964,105.00 27.038 10%
29 Pas Kembali Penutup atap genteng plentong m2 283.02 14,100 Rp 3,990,582.00 1.270 10%
30 Pas Penutup Atap Genteng Plentong kecil Baru m2 283.02 88,700 Rp 25,103,874.00 7.989 10%
31 Pas Nok Atap Genteng Plentong Kecil m1 45.00 31,380 Rp 1,412,100.00 0.449 10%
32 Pas Plafond Pvc m2 499.61 150,000 Rp 74,941,500.00 23.849 10%
33 Pas Rangka Hollow m2 499.61 76,700 Rp 38,320,087.00 12.195 10%
34 Pas Listplank Tumpang Sari GRC 20+15 cm m1 86.00 89,300 Rp 7,679,800.00 2.444 10%
35 Pek.Pengecatan Dinding Toa 2x m2 478.76 41,500 Rp 19,868,540.00 6.323 10%
36 Pek.Pengecatan Batu Alam m3 80.00 61,400 Rp 4,912,000.00 1.563 10%
37 Pas Pengecatan Listplank GRC Toa 3x m2 25.80 41,500 Rp 1,070,700.00 0.341 10%
Total Rp 314,236,442.00 100.00
Total setelah Pajak Keterangan
Rp 200,750.00
Rp 1,650,000.00
Rp 82,500.00 Rencana K3
Rp 126,500.00 Rencana K3
Rp 550,000.00 Rencana K3
Rp 330,000.00 Rencana K3
Rp 330,000.00 Rencana K3
Rp 41,250.00 Rencana K3
Rp 41,250.00 Rencana K3
Rp 825,000.00 Rencana K3
Rp 357,500.00 Rencana K3
Rp 275,000.00 Rencana K3
Rp 770,000.00 Rencana K3
Rp 275,000.00 Rencana K3
Rp 770,000.00 Rencana K3
Rp 825,000.00 Prokes Covid 19
Rp 99,000.00 Prokes Covid 19
Rp 1,375,000.00
Rp 550,000.00
Rp 817,898.40
Rp 31,650,696.00
Rp 3,300,000.00
Rp 5,610,000.00
Rp 220,000.00
Rp 409,860.00
Rp 328,900.00
Rp 5,359,365.00
Rp 93,460,515.50
Rp 4,389,640.20
Rp 27,614,261.40
Rp 1,553,310.00
Rp 82,435,650.00
Rp 42,152,095.70
Rp 8,447,780.00
Rp 21,855,394.00
Rp 5,403,200.00
Rp 1,177,770.00
Rp 345,660,086.20
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 20 Bogor
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu : 1 (SATU)
PT. Dinamika Sarana Inovasi Periode : 2 November S/D 8 November 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Bobot Progress Bobot
Vol. Vol. Vol. Progress % Bobot %
% % % %
1 PEKERJAAN PERSIAPAN
1 papan nama proyek 1.00 ls 0.058 - 0% - - 0% - - 0% -
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 - 0% - - 0% - - 0% -
3 rencana K3 1.00 ls 1.648 - 0% - - 0% - - 0% -
4 pek. Listrik dan air kerja 1.00 ls 0.398 - 0% - - 0% - - 0% -
5 pembersihan lokasi 1.00 ls 0.159 - 0% - - 0% - - 0% -
2.741 0.000 0.000 0.000
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 - 0% - - 0% - - 0% -
2 pas. Keramik 30x30 set. Mulia 108.99 m2 9.157 - 0% - - 0% - - 0% -
9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Konsol dan kayu 12.00 unit 0.955 - 0% - - 0% - - 0% -
2 pek. Kusen jendela kayu type J3 6.00 unit 1.623 - 0% - - 0% - - 0% -
2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK
1 perbaikan instalasi listrik 1.00 ls 0.064 - 0% - - 0% - - 0% -
2 pas. Saklar ganda 6.00 bh 0.119 - 0% - - 0% - - 0% -
3 pas. Stop kontak 5.00 bh 0.095 - 0% - - 0% - - 0% -
4 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - - 0% - - 0% -
1.828 - - -
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 566.05 m2 27.038 - 0% - - 0% - - 0% -
2 pas. Kembali penutup atap genteng pelentong 283.02 m2 1.270 - 0% - - 0% - - 0% -
3 pas. Penutup atap genteng pelentong kecil (baru) 283.02 m2 7.989 - 0% - - 0% - - 0% -
4 pas. Nok atap genteng pelentong kecil 45.00 m1 0.449 - 0% - - 0% - - 0% -
5 pas. Plafond PVC 499.61 m2 23.849 - 0% - - 0% - - 0% -
6 pas. Rangka hollow 499.61 m2 12.195 - 0% - - 0% - - 0% -
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 - 0% - - 0% - - 0% -
75.234 - - -
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 478.76 m2 6.323 - 0% - - 0% - - 0% -
2 pek. Pengecatan dinding batu alam 80.00 m2 1.563 - 0% - - 0% - - 0% -
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - - 0% - - 0% -
8.227 - - -
100.000
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 20 Bogor
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 1
PT. Dinamika Sarana Inovasi Periode : 2 November S/D 8 November 2021

PRESTASI FISIK PEKERJAAN


BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 - - -


2 PEKERJAAN PASANGAN 9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU 2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK 1.828 - - -
5 PEKERJAAN ATAP DAN DINDING 75.234 - - -
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN 8.227 - - -
JUMLAH 100.000 - - -

PROGRESS RENCANA 0.305 WAKTU YANG TELAH DIPERGUNAKAN 7 HARI KERJA


PROGRESS REALISASI - SISA WAKTU PELAKSANAAN 53 HARI KERJA
DEVIASI ( +/- ) - 0.305 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 08 November 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi
Yogi Ponco S.
Pelaksana Pengawas
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu : 2 (DUA)
PT. Dinamika Sarana Inovasi Periode : 9 November S/D 15 November 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Bobot Progress Bobot
Vol. Vol. Vol. Progress % Bobot %
% % % %
1 PEKERJAAN PERSIAPAN
1 papan nama proyek 1.00 ls 0.058 - 0% - 1.00 100% 0.058 1.00 100% 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 - 0% - 0.30 30% 0.143 0.30 30% 0.143
3 rencana K3 1.00 ls 1.648 - 0% - 0.50 50% 0.824 0.50 50% 0.824
4 pek. Listrik dan air kerja 1.00 ls 0.398 - 0% - 0.10 10% 0.040 0.10 10% 0.040
5 pembersihan lokasi 1.00 ls 0.159 - 0% - - 0% - - 0% -
2.741 0.000 1.065 1.065
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 - 0% - - 0% - - 0% -
2 pas. Keramik 30x30 set. Mulia 108.99 m2 9.157 - 0% - - 0% - - 0% -
9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Konsol dan kayu 12.00 unit 0.955 - 0% - - 0% - - 0% -
2 pek. Kusen jendela kayu type J3 6.00 unit 1.623 - 0% - - 0% - - 0% -
2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK
1 perbaikan instalasi listrik 1.00 ls 0.064 - 0% - - 0% - - 0% -
2 pas. Saklar ganda 6.00 bh 0.119 - 0% - - 0% - - 0% -
3 pas. Stop kontak 5.00 bh 0.095 - 0% - - 0% - - 0% -
4 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - - 0% - - 0% -
1.828 - - -
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 566.05 m2 27.038 - 0% - - 0% - - 0% -
2 pas. Kembali penutup atap genteng pelentong 283.02 m2 1.270 - 0% - - 0% - - 0% -
3 pas. Penutup atap genteng pelentong kecil (baru) 283.02 m2 7.989 - 0% - - 0% - - 0% -
4 pas. Nok atap genteng pelentong kecil 45.00 m1 0.449 - 0% - - 0% - - 0% -
5 pas. Plafond PVC 499.61 m2 23.849 - 0% - - 0% - - 0% -
6 pas. Rangka hollow 499.61 m2 12.195 - 0% - - 0% - - 0% -
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 - 0% - - 0% - - 0% -
75.234 - - -
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 478.76 m2 6.323 - 0% - - 0% - - 0% -
2 pek. Pengecatan dinding batu alam 80.00 m2 1.563 - 0% - - 0% - - 0% -
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - - 0% - - 0% -
8.227 - - -
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 2
PT. Dinamika Sarana Inovasi Periode : 9 November S/D 15 November 2021

PRESTASI FISIK PEKERJAAN


BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 - 1.065 1.065


2 PEKERJAAN PASANGAN 9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU 2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK 1.828 - - -
5 PEKERJAAN ATAP DAN DINDING 75.234 - - -
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN 8.227 - - -
JUMLAH 100.000 - 1.065 1.065

PROGRESS RENCANA 0.609 WAKTU YANG TELAH DIPERGUNAKAN 14 HARI KERJA


PROGRESS REALISASI 1.065 SISA WAKTU PELAKSANAAN 46 HARI KERJA
DEVIASI ( +/- ) 0.456 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 15 November 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi

Yogi Ponco S.
Pelaksana Pengawas
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 3
PT. Dinamika Sarana Inovasi Periode :16 November S/D 22 November 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Progress Bobot
Vol. 3.00 Vol. Vol. Progress % Bobot %
% % %
1 PEKERJAAN PERSIAPAN :16 November S/D 22 November 2021
1 papan nama proyek 1.00 ls 0.058 1.00 100% 0.058 - 0% - 1.00 100% 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 0.30 30% 0.143 0.30 30% 0.143 0.60 60% 0.286
3 rencana K3 1.00 ls 1.648 0.50 50% 0.824 - 0% - 0.50 50% 0.824
4 pek. Listrik dan air kerja 1.00 ls 0.398 0.10 10% 0.040 0.10 10% 0.040 0.20 20% 0.080
5 pembersihan lokasi 1.00 ls 0.159 - 0% - - 0% - - 0% -
2.741 1.065 0.183 1.248
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 - 0% - - 0% - - 0% -
2 pas. Keramik 30x30 set. Mulia 27.40 m2 9.157 - 0% - - 0% - - 0% -
9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Konsol dan kayu 3.00 unit 0.955 - 0% - - 0% - - 0% -
2 pek. Kusen jendela kayu type J3 4.00 unit 1.623 - 0% - - 0% - - 0% -
2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK
1 perbaikan instalasi listrik 1.00 ls 0.064 - 0% - - 0% - - 0% -
2 pas. Saklar ganda 6.00 bh 0.119 - 0% - - 0% - - 0% -
3 pas. Stop kontak 5.00 bh 0.095 - 0% - - 0% - - 0% -
4 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - - 0% - - 0% -
1.828 - - -
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 531.05 m2 27.038 - 0% - - 0% - - 0% -
2 pas. Kembali penutup atap genteng pelentong 285.95 m2 1.270 - 0% - - 0% - - 0% -
3 pas. Penutup atap genteng pelentong kecil (baru) 245.10 m2 7.989 - 0% - - 0% - - 0% -
4 pas. Nok atap genteng pelentong kecil 43.00 m1 0.449 - 0% - - 0% - - 0% -
5 pas. Plafond PVC 499.61 m2 23.849 - 0% - - 0% - - 0% -
6 pas. Rangka hollow 499.61 m2 12.195 - 0% - - 0% - - 0% -
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 - 0% - - 0% - - 0% -
75.234 - - -
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 478.76 m2 6.323 - 0% - - 0% - - 0% -
2 pek. Pengecatan dinding batu alam 80.00 m2 1.563 - 0% - - 0% - - 0% -
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - - 0% - - 0% -
8.227 - - -
100.000
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 3
PT. Dinamika Sarana Inovasi Periode :16 November S/D 22 November 2021

PRESTASI FISIK PEKERJAAN

BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 1.065 0.183 1.248


2 PEKERJAAN PASANGAN 9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU 2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK 1.828 - - -
5 PEKERJAAN ATAP 75.234 - - -
6 PEKERJAAN PENG 8.227 - - -
JUMLAH 100.000 1.065 0.183 1.248

PROGRESS RENCANA 0.914 WAKTU YANG TELAH DIPERGUNAKAN 21 HARI KERJA


PROGRESS REALISASI 1.248 SISA WAKTU PELAKSANAAN 39 HARI KERJA
DEVIASI ( +/- ) 0.335 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 22 November 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi
Yogi Ponco S.
Pelaksana Pengawas
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 4
PT. Dinamika Sarana Inovasi Periode 23 November S/D 29 November 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Progress Bobot
Vol. 3.00 Vol. Vol. Progress % Bobot %
% % %
1 PEKERJAAN PERSIAPAN :16 November S/D 22 November 2021
1 papan nama proyek 1.00 ls 0.058 1.00 100% 0.058 - 0% - 1.00 100% 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 0.60 60% 0.286 0.15 15% 0.072 0.75 75% 0.358
3 rencana K3 1.00 ls 1.648 0.50 50% 0.824 - 0% - 0.50 50% 0.824
4 pek. Listrik dan air kerja 1.00 ls 0.398 0.20 20% 0.080 0.10 10% 0.040 0.30 30% 0.119
5 pembersihan lokasi 1.00 ls 0.159 - 0% - - 0% - - 0% -
2.741 1.248 0.111 1.360
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 - 0% - - 0% - - 0% -
2 pas. Keramik 30x30 set. Mulia 27.40 m2 9.157 - 0% - - 0% - - 0% -
9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Konsol dan kayu 3.00 unit 0.955 - 0% - - 0% - - 0% -
2 pek. Kusen jendela kayu type J3 4.00 unit 1.623 - 0% - - 0% - - 0% -
2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK
1 perbaikan instalasi listrik 1.00 ls 0.064 - 0% - - 0% - - 0% -
2 pas. Saklar ganda 6.00 bh 0.119 - 0% - - 0% - - 0% -
3 pas. Stop kontak 5.00 bh 0.095 - 0% - - 0% - - 0% -
4 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - - 0% - - 0% -
1.828 - - -
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 531.05 m2 27.038 - 0% - - 0% - - 0% -
2 pas. Kembali penutup atap genteng pelentong 285.95 m2 1.270 - 0% - - 0% - - 0% -
3 pas. Penutup atap genteng pelentong kecil (baru) 245.10 m2 7.989 - 0% - - 0% - - 0% -
4 pas. Nok atap genteng pelentong kecil 43.00 m1 0.449 - 0% - - 0% - - 0% -
5 pas. Plafond PVC 499.61 m2 23.849 - 0% - - 0% - - 0% -
6 pas. Rangka hollow 499.61 m2 12.195 - 0% - - 0% - - 0% -
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 - 0% - - 0% - - 0% -
75.234 - - -
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 478.76 m2 6.323 - 0% - - 0% - - 0% -
2 pek. Pengecatan dinding batu alam 80.00 m2 1.563 - 0% - - 0% - - 0% -
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - - 0% - - 0% -
8.227 - - -
100.000
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 4
PT. Dinamika Sarana Inovasi Periode 23 November S/D 29 November 2021

PRESTASI FISIK PEKERJAAN

BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 1.248 0.111 1.360


2 PEKERJAAN PASANGAN 9.393 - - -
3 PEKERJAAN KUSEN DAN KAYU 2.578 - - -
4 PEKERJAAN INSTALASI LISTRIK 1.828 - - -
5 PEKERJAAN ATAP 75.234 - - -
6 PEKERJAAN PENG 8.227 - - -
JUMLAH 100.000 1.248 0.111 1.360

PROGRESS RENCANA 4.144 WAKTU YANG TELAH DIPERGUNAKAN 28 HARI KERJA


PROGRESS REALISASI 1.360 SISA WAKTU PELAKSANAAN 32 HARI KERJA
DEVIASI ( +/- ) - 2.784 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 29 November 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi
Yogi Ponco S.
Pelaksana Pengawas
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 5
PT. Dinamika Sarana Inovasi Periode 30 November S/D 6 Desember 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Progress Bobot
Vol. 3.00 Vol. Vol. Progress % Bobot %
% % %
1 PEKERJAAN PERSIAPAN
1 papan nama proyek 1.00 ls 0.058 1.00 100% 0.058 - 0% - 1.00 100% 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 0.75 75% 0.358 0.25 25% 0.119 1.00 100% 0.477
3 rencana K3 1.00 ls 1.648 1.00 50% 1.648 - 0% - 0.50 50% 0.824
4 pek. Listrik dan air kerja 1.00 ls 0.398 0.30 30% 0.119 0.05 5% 0.020 0.35 35% 0.139
5 pembersihan lokasi 1.00 ls 0.159 0.35 35% 0.056 - 0% - - 0% -
2.741 2.240 0.139 1.499
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 - 0% - - 0% - - 0% -
2 pas. Keramik 30x30 set. Mulia 20.79 m2 1.747 - 0% - - 0% - - 0% -
3 pek. Ring balok 15x30 cm (termasuk besi & begisting) 3.48 m3 6.723 - 0% - 3.48 100% 6.723 3.48 100% 6.723
4 pek. Ring balok 17x16 cm (termasuk besi & begisting) 1.17 m3 2.594 - 0% - 1.17 100% 2.594 1.17 100% 2.594
5 pekerjaan ban-banan 16.80 m1 0.210 - 0% - - 0% - - 0% -
6 pekerjaan plesteran dan acian bekas ban-banan 6.72 m2 0.192 - 0% - - 0% - - 0% -
11.703 5.515 9.318 9.318
3 PEKERJAAN KUSEN DAN KAYU
2 pek. Kusen jendela kayu type J3 5.00 unit 1.352 - 0% - - 0% - - 0% -
1.352 - - -
4 PEKERJAAN INSTALASI LISTRIK
2 Pas. instalasi listrik (lengkap asesoris) 27.00 titik 2.227 - 0% - - 0% - - -
3 pas. Saklar ganda 6.00 bh 0.119 - 0% - - 0% - - 0% -
4 pas. Stop kontak 5.00 bh 0.095 - 0% - - 0% - - 0% -
5 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - - 0% - - 0% -
3.991 - - -
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 539.65 m2 25.777 - 0% - 539.65 100% 25.777 539.65 100% 25.777
2 pas. Kembali penutup atap genteng pelentong 275.95 m2 1.238 - 0% - 137.98 50% 0.619 137.98 50% 0.619
3 pas. Penutup atap genteng pelentong kecil (baru) 253.70 m2 7.161 - 0% - - 0% - - 0% -
4 pas. Nok atap genteng pelentong kecil 43.00 m1 0.429 - 0% - - 0% - - 0% -
5 pas. Plafond PVC 460.34 m2 21.974 - 0% - - 0% - - 0% -
6 pas. Rangka hollow 460.34 m2 11.236 - 0% - - 0% - - 0% -
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 - 0% - - 0% - - 0% -
8 pekerjaan talang PVC 18.00 m1 0.390 - 0% - - 0% - - 0% -
70.650 - 26.396 26.396
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 450.02 m2 5.943 - 0% - - 0% - - 0% -
2 pek. Pengecatan dinding batu alam 143.33 m2 2.801 - 0% - - 0% - - 0% -
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - - 0% - - 0% -
4 pek. Pengecatan kusen jendela 32.90 m2 0.434 - 0% - - 0% - - 0% -
5 pek. Water profing ban banan 2.52 m2 0.043 - 0% - - 0% - - 0% -
9.562 - - -
100.000 7.75 35.85 37.213
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 5
PT. Dinamika Sarana Inovasi Periode 30 November S/D 6 Desember 2021

PRESTASI FISIK PEKERJAAN

BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 1.360 0.139 1.499


2 PEKERJAAN PASANGAN 11.703 - 9.318 9.318
3 PEKERJAAN KUSEN DAN KAYU 1.352 - - -
4 PEKERJAAN INSTALASI LISTRIK 3.991 - - -
5 PEKERJAAN ATAP DAN DINDING 70.650 - 26.396 26.396
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN 9.562 - - -
JUMLAH 100.000 1.360 35.853 37.213

PROGRESS RENCANA 25.037 WAKTU YANG TELAH DIPERGUNAKAN 35 HARI KERJA


PROGRESS REALISASI 37.213 SISA WAKTU PELAKSANAAN 25 HARI KERJA
DEVIASI ( +/- ) 12.176 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 06 Desember 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi
Yogi Ponco S.
Pelaksana Pengawas
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 6
PT. Dinamika Sarana Inovasi Periode 07 Desember S/D 13 Desember 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Progress Bobot
Vol. 3.00 Vol. Vol. Progress % Bobot %
% % %
1 PEKERJAAN PERSIAPAN :16 November S/D 22 November 2021
1 papan nama proyek 1.00 ls 0.058 1.00 100% 0.058 - 0% - 1.00 100% 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 0.75 100% 0.477 - 0% - 1.00 100% 0.477
3 rencana K3 1.00 ls 1.648 1.00 50% 0.824 0.10 10% 0.165 0.60 60% 0.989
4 pek. Listrik dan air kerja 1.00 ls 0.398 0.30 35% 0.139 0.10 10% 0.040 0.45 45% 0.179
5 pembersihan lokasi 1.00 ls 0.159 0.35 0% - - 0% - - 0% -
2.741 1.499 0.205 1.703
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 - 0% - 3.31 40% 0.095 3.31 40% 0.095
2 pas. Keramik 30x30 set. Mulia 20.79 m2 1.747 - 0% - - 0% - - 0% -
3 pek. Ring balok 15x30 cm (termasuk besi & begisting) 3.48 m3 6.723 3.48 100% 6.723 - 0% - 3.48 100% 6.723
4 pek. Ring balok 17x16 cm (termasuk besi & begisting) 1.17 m3 2.594 1.17 100% 2.594 - 0% - 1.17 100% 2.594
5 pekerjaan ban-banan 16.80 m1 0.210 - 0% - - 0% - - 0% -
6 pekerjaan plesteran dan acian bekas ban-banan 6.72 m2 0.192 - 0% - - 0% - - 0% -
11.703 9.318 0.095 9.412
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Kusen jendela kayu type J3 5.00 unit 1.352 - 0% - 0.50 10% 0.135 0.50 10% 0.135
1.352 - 0.135 0.135
4 PEKERJAAN INSTALASI LISTRIK
1 Pas. instalasi listrik (lengkap asesoris) 27.00 titik 2.227 - 0% - - 0% - - 0% -
2 pas. Saklar ganda 6.00 bh 0.119 - 0% - - 0% - - 0% -
3 pas. Stop kontak 5.00 bh 0.095 - 0% - - 0% - - 0% -
4 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - - 0% - - 0% -
3.991 - - -
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 539.65 m2 25.777 539.65 100% 25.777 - 0% - 539.65 100% 25.777
2 pas. Kembali penutup atap genteng pelentong 275.95 m2 1.238 137.98 50% 0.619 137.98 50% 0.619 275.95 100% 1.238
3 pas. Penutup atap genteng pelentong kecil (baru) 253.70 m2 7.161 - 0% - 25.37 10% 0.716 25.37 10% 0.716
4 pas. Nok atap genteng pelentong kecil 43.00 m1 0.429 - 0% - - 0% - - 0% -
5 pas. Plafond PVC 460.34 m2 21.974 - 0% - 46.03 10% 2.197 46.03 10% 2.197
6 pas. Rangka hollow 460.34 m2 11.236 - 0% - 138.10 30% 3.371 138.10 30% 3.371
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 - 0% - - 0% - - 0% -
8 pekerjaan talang PVC 18.00 m1 0.390 - 0% - - 0% - - 0% -
70.650 26.396 6.903 33.300
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 450.02 m2 5.943 - 0% - - 0% - - 0% -
2 pek. Pengecatan dinding batu alam 143.33 m2 2.801 - 0% - - 0% - - 0% -
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - - 0% - - 0% -
4 pek. Pengecatan kusen jendela 32.90 m2 0.434 - 0% - - 0% - - 0% -
5 pek. Water profing ban banan 2.52 m2 0.043 - 0% - - 0% - - 0% -
9.562 - - -
100.000 44.551
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 6
PT. Dinamika Sarana Inovasi Periode 07 Desember S/D 13 Desember 2021

PRESTASI FISIK PEKERJAAN

BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 1.499 0.205 1.703


2 PEKERJAAN PASANGAN 11.703 9.318 0.095 9.412
3 PEKERJAAN KUSEN DAN KAYU 1.352 - 0.135 0.135
4 PEKERJAAN INSTALASI LISTRIK 3.991 - 0.135 -
5 PEKERJAAN ATAP DAN DINDING 70.650 26.396 6.903 33.300
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN 9.562 - - -
JUMLAH 100.000 37.213 7.473 44.551

PROGRESS RENCANA 50.101 WAKTU YANG TELAH DIPERGUNAKAN 42 HARI KERJA


PROGRESS REALISASI 44.551 SISA WAKTU PELAKSANAAN 18 HARI KERJA
DEVIASI ( +/- ) - 5.551 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 13 Desember 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi
Yogi Ponco S.
Pelaksana Pengawas
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 7
PT. Dinamika Sarana Inovasi Periode 14 Desember S/D 20 Desember 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Progress Bobot
Vol. 3.00 Vol. Vol. Progress % Bobot %
% % %
1 PEKERJAAN PERSIAPAN :16 November S/D 22 November 2021
1 papan nama proyek 1.00 ls 0.058 1.00 100% 0.058 - 0% - 1.00 100% 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 1.00 100% 0.477 - 0% - 1.00 100% 0.477
3 rencana K3 1.00 ls 1.648 0.60 60% 0.989 0.15 15% 0.247 0.75 75% 1.236
4 pek. Listrik dan air kerja 1.00 ls 0.398 0.45 45% 0.179 0.15 15% 0.060 0.60 60% 0.239
5 pembersihan lokasi 1.00 ls 0.159 - 0% - - 0% - - 0% -
2.741 1.703 0.307 2.010
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 3.31 40% 0.095 3.31 40% 0.095 6.62 80% 0.189
2 pas. Keramik 30x30 set. Mulia 20.79 m2 1.747 - 0% - - 0% - - 0% -
3 pek. Ring balok 15x30 cm (termasuk besi & begisting) 3.48 m3 6.723 3.48 100% 6.723 - 0% - 3.48 100% 6.723
4 pek. Ring balok 17x16 cm (termasuk besi & begisting) 1.17 m3 2.594 1.17 100% 2.594 - 0% - 1.17 100% 2.594
5 pekerjaan ban-banan 16.80 m1 0.210 - 0% - - 0% - - 0% -
6 pekerjaan plesteran dan acian bekas ban-banan 6.72 m2 0.192 - 0% - - 0% - - 0% -
11.703 9.412 0.095 9.507
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Kusen jendela kayu type J3 5.00 unit 1.352 0.50 10% 0.135 3.50 70% 0.947 4.00 80% 1.082
1.352 0.135 0.947 1.082
4 PEKERJAAN INSTALASI LISTRIK
1 Pas. instalasi listrik (lengkap asesoris) 27.00 titik 2.227 - 0% - 20.25 75% 1.670 20.25 75% 1.670
2 pas. Saklar ganda 6.00 bh 0.119 - 0% - - 0% - - 0% -
3 pas. Stop kontak 5.00 bh 0.095 - 0% - - 0% - - 0% -
4 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - - 0% - - 0% -
3.991 - 1.670 1.670
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 539.65 m2 25.777 539.65 100% 25.777 - 0% - 539.65 100% 25.777
2 pas. Kembali penutup atap genteng pelentong 275.95 m2 1.238 275.95 100% 1.238 - 0% - 275.95 100% 1.238
3 pas. Penutup atap genteng pelentong kecil (baru) 253.70 m2 7.161 25.37 10% 0.716 228.33 90% 6.445 253.70 100% 7.161
4 pas. Nok atap genteng pelentong kecil 43.00 m1 0.429 - 0% - 43.00 100% 0.429 43.00 100% 0.429
5 pas. Plafond PVC 460.34 m2 21.974 46.03 10% 2.197 138.10 30% 6.592 184.14 40% 8.790
6 pas. Rangka hollow 460.34 m2 11.236 138.10 30% 3.371 92.07 20% 2.247 230.17 50% 5.618
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 - 0% - 86.00 100% 2.444 86.00 100% 2.444
8 pekerjaan talang PVC 18.00 m1 0.390 - 0% - - 0% - - 0% -
70.650 33.300 18.158 51.458
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 450.02 m2 5.943 - 0% - - 0% - - 0% -
2 pek. Pengecatan dinding batu alam 143.33 m2 2.801 - 0% - - 0% - - 0% -
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - - 0% - - 0% -
4 pek. Pengecatan kusen jendela 32.90 m2 0.434 - 0% - - 0% - - 0% -
5 pek. Water profing ban banan 2.52 m2 0.043 - 0% - - 0% - - 0% -
9.562 - - -
100.000 65.727
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 7
PT. Dinamika Sarana Inovasi Periode 14 Desember S/D 20 Desember 2021

PRESTASI FISIK PEKERJAAN

BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 1.703 0.307 2.010


2 PEKERJAAN PASANGAN 11.703 9.412 0.095 9.507
3 PEKERJAAN KUSEN DAN KAYU 1.352 0.135 0.947 1.082
4 PEKERJAAN INSTALASI LISTRIK 3.991 - 0.947 1.670
5 PEKERJAAN ATAP DAN DINDING 70.650 33.300 18.158 51.458
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN 9.562 - - -
JUMLAH 100.000 44.551 20.453 65.727

PROGRESS RENCANA 75.166 WAKTU YANG TELAH DIPERGUNAKAN 49 HARI KERJA


PROGRESS REALISASI 65.727 SISA WAKTU PELAKSANAAN 11 HARI KERJA
DEVIASI ( +/- ) - 9.439 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 20 Desember 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi
Yogi Ponco S.
Pelaksana Pengawas
REKAPITULASI PROGRESS MINGGUAN
Kontaraktor pelaksaan Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 8
PT. Dinamika Sarana Inovasi Periode 21 Desember S/D 27 Desember 2021

Persentasi s/d Minggu Lalu Persentasi Minggu Ini Prensentasi s/d Minggu Ini
NO. Jenis Pekerjaan Vol. Sat. Bobot %
Progress Progress Bobot
Vol. 3.00 Vol. Vol. Progress % Bobot %
% % %
1 PEKERJAAN PERSIAPAN :16 November S/D 22 November 2021
1 papan nama proyek 1.00 ls 0.058 1.00 100% 0.058 - 0% - 1.00 100% 0.058
2 pek. Bongkaran ( atap plafond ) 1.00 ls 0.477 1.00 100% 0.477 - 0% - 1.00 100% 0.477
3 rencana K3 1.00 ls 1.648 0.75 75% 1.236 0.25 25% 0.412 1.00 100% 1.648
4 pek. Listrik dan air kerja 1.00 ls 0.398 0.60 60% 0.239 0.40 40% 0.159 1.00 100% 0.398
5 pembersihan lokasi 1.00 ls 0.159 - 0% - 1.00 100% 0.159 1.00 100% 0.159
2.741 2.010 0.730 2.741
2 PEKERJAAN PASANGAN
1 pas. Plesteran, acian openingan kusen 8.28 m2 0.237 6.62 80% 0.189 1.66 20% 0.047 8.28 100% 0.237
2 pas. Keramik 30x30 set. Mulia 20.79 m2 1.747 - 0% - 20.79 100% 1.747 20.79 100% 1.747
3 pek. Ring balok 15x30 cm (termasuk besi & begisting) 3.48 m3 6.723 3.48 100% 6.723 - 0% - 3.48 100% 6.723
4 pek. Ring balok 17x16 cm (termasuk besi & begisting) 1.17 m3 2.594 1.17 100% 2.594 - 0% - 1.17 100% 2.594
5 pekerjaan ban-banan 16.80 m1 0.210 - 0% - 16.80 100% 0.210 16.80 100% 0.210
6 pekerjaan plesteran dan acian bekas ban-banan 6.72 m2 0.192 - 0% - 6.72 100% 0.192 6.72 100% 0.192
11.703 9.507 2.196 11.703
3 PEKERJAAN KUSEN DAN KAYU
1 pek. Kusen jendela kayu type J3 5.00 unit 1.352 4.00 80% 1.082 1.00 20% 0.270 5.00 100% 1.352
1.352 1.082 0.270 1.352
4 PEKERJAAN INSTALASI LISTRIK
1 Pas. instalasi listrik (lengkap asesoris) 27.00 titik 2.227 20.25 75% 1.670 6.75 25% 0.557 27.00 100% 2.227
2 pas. Saklar ganda 6.00 bh 0.119 - 0% - 6.00 100% 0.119 6.00 100% 0.119
3 pas. Stop kontak 5.00 bh 0.095 - 0% - 5.00 100% 0.095 5.00 100% 0.095
4 pas. Lampu SL 18 watt 27.00 bh 1.550 - 0% - 27.00 100% 1.550 27.00 100% 1.550
3.991 1.670 2.321 3.991
5 PEKERJAAN ATAP DAN DINDING
1 pas. Rangka atap baja ringan 539.65 m2 25.777 539.65 100% 25.777 - 0% - 539.65 100% 25.777
2 pas. Kembali penutup atap genteng pelentong 275.95 m2 1.238 275.95 100% 1.238 - 0% - 275.95 100% 1.238
3 pas. Penutup atap genteng pelentong kecil (baru) 253.70 m2 7.161 253.70 100% 7.161 - 0% - 253.70 100% 7.161
4 pas. Nok atap genteng pelentong kecil 43.00 m1 0.429 43.00 100% 0.429 - 0% - 43.00 100% 0.429
5 pas. Plafond PVC 460.34 m2 21.974 184.14 40% 8.790 276.20 60% 13.185 460.34 100% 21.974
6 pas. Rangka hollow 460.34 m2 11.236 230.17 50% 5.618 230.17 50% 5.618 460.34 100% 11.236
7 pas. Listplank tumpang sari GRC 20x15 cm 86.00 m1 2.444 86.00 100% 2.444 - 0% - 86.00 100% 2.444
8 pekerjaan talang PVC 18.00 m1 0.390 - 0% - 18.00 100% 0.390 18.00 100% 0.390
70.650 51.458 19.192 70.650
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN
1 pek. pengecatan Dinding TOA 2x 450.02 m2 5.943 - 0% - 450.02 100% 5.943 450.02 100% 5.943
2 pek. Pengecatan dinding batu alam 143.33 m2 2.801 - 0% - 143.33 100% 2.801 143.33 100% 2.801
3 pek. Pengecatan lisplank GRC TOA 3x 25.80 m2 0.341 - 0% - 25.80 100% 0.341 25.80 100% 0.341
4 pek. Pengecatan kusen jendela 32.90 m2 0.434 - 0% - 32.90 100% 0.434 32.90 100% 0.434
5 pek. Water profing ban banan 2.52 m2 0.043 - 0% - 2.52 100% 0.043 2.52 100% 0.043
9.562 - 9.562 9.562
REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN
Kontaraktor pelaksana Nama Pekerjaan : REHABILITASI SMPN 3 KOTA BOGOR
PEMERINTAH DAERAH KOTA BOGOR CV. Kharisma Scientific Lokasi : KOTA BOGOR
DINAS PENDIDIKAN Tahun Anggaran : 2021
Jl. Raya Pajajaran No. 125 Bogor Konsultan Pengawas Minggu 8
PT. Dinamika Sarana Inovasi Periode 21 Desember S/D 27 Desember 2021

PRESTASI FISIK PEKERJAAN

BOBOT
NO URAIAN PEKERJAAN PRESENTASI S/D PRESENTASI PRESENTASI S/D
%
MINGGU LALU MINGGU INI MINGGU INI

1 PEKERJAAN PERSIAPAN 2.741 2.010 0.730 2.741


2 PEKERJAAN PASANGAN 11.703 9.507 2.196 11.703
3 PEKERJAAN KUSEN DAN KAYU 1.352 1.082 0.270 1.352
4 PEKERJAAN INSTALASI LISTRIK 3.991 1.670 0.270 3.991
5 PEKERJAAN ATAP DAN DINDING 70.650 51.458 19.192 70.650
6 PEKERJAAN PENGECATAN DAN PENYELESAIAN 9.562 - 9.562 9.562
JUMLAH 100.000 65.727 32.222 100.000

PROGRESS RENCANA 97.305 WAKTU YANG TELAH DIPERGUNAKAN 60 HARI KERJA


PROGRESS REALISASI 100.000 SISA WAKTU PELAKSANAAN 0 HARI KERJA
DEVIASI ( +/- ) 2.695 WAKTU PELAKSANAAN 60 HARI KERJA

Bogor, 27 Desember 2021

Diketahui Oleh : Dibuat Oleh :


Kontaraktor pelaksana Konsultan Pengawas
CV. Kharisma Scientific PT. Dinamika Sarana Inovasi
Yogi Ponco S.
Pelaksana Pengawas