PEKERJAAN PEMELIHARAAN PERIODIK (SFO)

REKONSTRUKSI PERKERASAN DAN MARKA JALAN


PADA JALAN TOL
JAKARTA - BOGOR - CIAWI
TAHUN 2020

LAPORAN MINGGUAN KE - 39 ADDENDUM FINAL


PERIODE TANGGAL
1 :
07 DESEMBER – 14 DESEMBER 2020

PT MULTI PHI BETA PT PERKASA


ADIGUNA SEMBADA

KONTRAK : No. 05/KONTRAK-JAGO/III/2020 KONTRAK : No. 04/KONTRAK-JAGO/III/2020

TANGGAL: 20 Maret 2020 TANGGAL: 19 Maret 2020

NO SPMK : 42.01/DIR III/EXT/JMTM/III/2020 NO SPMK : 41/DIR III/EXT/JMTM/III/2020

TANGGAL : 21 MARET 2020 TANGGAL : 20 MARET 2020


PT. PERKASA ADIGUNA SEMBADA

LAPORAN PROGRES MINGGUAN K : 39


E
Periode PEKERJAAN : 07 Desember - 14 Desember 2020

: PEMELIHARAAN PERIODIK (SFO),REKONSTRUKSI PERKERASAN DAN MARKA JALAN


PADA JALAN TOL JAKARTA - BOGOR - CIAWI TAHUN 2020

A. STATUS DAN DATA


1 Minggu ke : 39 Dari 39
2 Periode : 07 Desember - 14 Desember 2020

PEMELIHARAAN PERIODIK (SFO),REKONSTRUKSI PERKERASAN DAN MARKA JALAN PADA JALAN TOL JAKARTA - BOGOR - CIAWI TAHUIN
3 Paket / Jalur :
2020

4 Kontraktor Pelaksana : PT. Perkasa Adiguna Sembada

5 Nomor : 04/KONTRAK-JAGO/III/2020

6 Tanggal Kontrak : 19 MARET 2020

7 Nomor SHO : 02/KONTRAK-JAGO/SHO/III/2020


8 Tanggal SHO : 20 MARET 2020
9 Nomor SPMK : 4/DIR III /EXT/JMTM/III/2020
10 Tanggal SPMK : 20 MARET 2020
11 Waktu Masa Pelaksanaan : 270 Hari kalender
12 Masa Pemeliharaan : 365 Hari kalender
13 Konsultan Pengawas : PT MULTI PHI BETA

14 Uang Muka :
B.KONTRAK

Pelaksanaan (
No URAIAN Tanggal Terbit Nilai ( Rp ) Hari Kalender Catatan
)

1 Kontrak Awal 19-Mar-19 108,106,090,000 270

2 Kontrak Addendum 1 25 Juli 2020 47,483,353,000 270

3 Kontrak Addendum 2 23-Oct-20 44,572,305,000 270

C . PROGRES FISIK

No URAIAN Rencana Realisasi Deviasi Catatan


1 Sampai Minggu Lalu 99.528 99.580 0.052
2 Minggu ini 0.473 -0.347 -0.819 lebih Cepat

3 Kumulatif Sampai Minggu Ini 100.000 100.000 0.000 lebih Cepat

4 Sisa s/d Minggu ini 0.000 0.000 0.000 lebih Cepat


5 Rencana Minggu Depan 0.473 0.000
Kumulatif Rencana s/d
6 100.473 100.000 -0.473
Minggu Depan

D . PROGRES WAKTU
Sisa
No Uraian Pelaksanaan ( Hari kalender ) Berjalan ( Hari Kalender ) ( Hari Kalender Catatan
)

1 Kumulatif Waktu ( Hari ) 270 270 0


2 Prosentase ( % ) 100 100.00 0.00
E . PROGRES PEMBAYARAN
NILAI KONTRAK ( Rp ) 108,106,090,000
NILAI ADDENDUM 1 ( Rp ) 47,483,353,000
NILAI ADDENDUM 2 ( Rp ) 44,572,305,000
Pembayaran
Sisa
No Uraian Saat ini Kumulatif Catatan
Rp Rp % Rp %

1 MC 1 2,963,345,390.70 2,963,345,390.70 2.74 105,142,744,609 97.259


2 MC 2 5,397,404,534.45 8,360,749,925.15 7.73 99,745,340,075 92.27
3 MC 3 4,801,548,825.85 13,162,298,751.00 12.18 94,943,791,249 87.82
4 MC4 4,532,170,356.93 17,694,469,107.93 37.26 90,411,620,892 83.63
5 MC 5 6,581,458,227.29 24,275,927,335 51.13 23,207,425,665 48.87
6 MC 6 4,758,733,896.92 29,034,661,232 61.15 18,448,691,768 38.85
7 MC 7 6,942,783,451.00 35,977,444,683.14 75.77 11,505,908,317 24.23
8 MC 8 4,550,975,911.36 40,528,420,594.50 90.93 4,043,884,406 9.07

F . URAIAN PEKERJAAN MINGGU INI


No Uraian Kegiatan Rencana Progres ( % )

A Pemeliharaan Periodik (SFO)


BAB 1 Umum
1 Laboratorium 0.009
2 Mobilisasi dan Demobilisasi 0.016
3 Kendaraan Operasional Satgas 2 (dua) Kendaraan / bulan 0.009
4 Kantor Operasional Lapangan 0.005
5 Pasang Spanduk Pemberitahuan -
6 Pasang Selebaran -
7 Asbuilt Drawing 0.034
8 Pengamanan dan Pengaturan Lalu lintas Tipe A -
9 Pengamanan dan Pengaturan Lalu lintas Tipe B 0.005
10 Pergerakan Peralatan Pengaspalan -
11 Pergerakan Peralatan Scrapping -
12 Kelengkapan SMK3 Type A 0.005
BAB 3 Pembongkaran -
13 Bongkar Perkerasan Jalan Aspal (Cold Milling Machine / Road Cutter) -
BAB 9 Perkerasan -
14 Bitumen Lapis Pengikat (Tack Coat) -
15 Asphalt Concrete Wearing Course -
16 Semen Aspal (Asphalt Cement) -
BAB 12 Pekerjaan Lain lain -
17 Marka Jalan, Sementara (0.016)
18 Patching Type 1 (Permanen) 0.181
19 Patching Type 3 (Asphalticplug), tebal = 5 cm -
20 Pengadaan Aspal Instan (Cold Mix) kemasan 25 kg -
21 Perbaikan Expansion Joint Aspal (Asphaltic Plug Joint) 0.112
Asphaltic Joint Filler (Sealant) -
B Rekonstruksi Perkerasan Jalan -
BAB 1 Umum -
1 Laboratorium 0.013
2 Mobilisasi dan Demobilisasi 0.036
3 Kendaraan Operasional Satgas 2 (dua) Kendaraan / bulan (0.005)
4 Kantor Operasional Lapangan 0.006
5 Pasang Spanduk Pemberitahuan -
Pasang Spanduk Pemberitahuan (Harga Timpang) 0.001
6 Asbuilt Drawing 0.031
7 Pengamanan dan Pengaturan Lalu lintas Tipe A (0.001)
8 Rekayasa Lalu Lintas ( Contra Flow ) Pekerjaan Rekonstruksi (0.022)
Kelengkapan SMK3 Type A 0.009
BAB 3 Pembongkaran -
9 Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) -
Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) (Harga Timpang) -
10 Bongkar Perkerasan Jalan Beton (Excavator Hidrolic/Jack Hammer) (0.046)
11 Bongkar Lapis Pondasi Aggregat Kelas A -
BAB 4 Pekerjaan Tanah -
12 Galian Biasa Untuk Dibuang -
BAB 6 Drainase -
13 Pipa Berlubang Banyak Untuk Pekerjaan Drainase Bawah Permukaan -
14 Pengeboran Pipa Horizontal Sub Drain (0.015)
new Pipa Vertikal 12" -
15 Pengeboran Horizontal Vertical Drain dia. 12" -
16 Pengeboran Vertical Drain -
Geotextile Non Woven -
Geotextile Non Woven -
BAB 7 Sub Grade -
17 Penyiapan Tanah Dasar -
BAB 8 Lapis pondasi Aggregat -
18 Lapis Pondasi Agregat Kelas A -
BAB 9 Perkerasan -
19 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 hari, single wire mesh dia. 10 mm # 15 mm, t = 30 cm -
New Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 hari, Double wire mesh dia. 10 mm # 15 mm, t = 30 cm -
20 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3 hari, single wire mesh dia. 10 mm # 15 mm, t = 30 cm (0.023)
21 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3 hari, tanpa wire mash, t = 30 cm (0.032)
22 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 7 hari, single wire mesh dia. 10 mm # 15 mm, t = 30 cm -
23 Perkerasan Beton fs 45 umur 28 hari, t = 30 cm -
New Beton Fs-45 umur 1 Hari (Levelling) -
24 Bor Dowel -
24 Bor Tie Bar -
new Bor Shear Conector -
new Baja Tulangan Ulir (Pelat Injak) -
BAB 12 Pekerjaan lain lain -
1 Marka Jalan, Sementara -
2 Marka Jalan, Sementara -
BAB 1 Umum -
1 Laboratorium 0.004
2 Kelengkapan SMK3 Type B 0.002
BAB 12 Pekerjaan lain lain -
1 Marka Jalan Tipe (t=3mm) Thermoplastic Putih 0.001
2 Marka Jalan Tipe (t=3mm) Thermoplastic Kuning 0.040
BAB 1 Umum -
1 Pengamanan dan Pengaturan lalu lintas 0.002
2 Laboratorium 0.001
3 Kelengkapan SMK3 Type B 0.001
BAB 12 Pekerjaan lain lain -
1 Penghapusan Marka Thermoplastik 0.032
2 Marka Jalan Tipe (t=3mm) Thermoplastic Kuning 0.076

0.473

G . PERMASALAHAN DAN SOLUSI

No Permasalahan Solusi

Perbaikan diusahakan siang malam supaya temuan


1 Temuan pra PHO segera dipercepat proses pelaksanaanya supaya pada saat PHO bisa segera close
ketidaksempurnaan bisa segera tuntas

PT .Perkasa segera menyiapkan persyaratan PHO dan


2 Segera diajukan permohonan PHO supaya PHO bisa dilaksanakan sebelum tanggal 24 Desember 2020
administrasi lainnya
H . URAIAN KEADAAN CUACA MINGGU INI
Kondisi Cuaca
No HARI / TANGGAL KETERANGAN WAKTU HUJAN
Cerah Berawan Hujan
1 Senin 7-Dec-20 V
2 Selasa 8-Dec-20 V
3 Rabu 9-Dec-20 V
4 Kamis 10-Dec-20 V
5 Jum'at 11-Dec-20 V
6 Sabtu 12-Dec-20 V
7 Minggu 13-Dec-20 V

I . URAIAN KEADAAN ALAT SCRAPPING FILLING MINGGU INI z

No HARI / TANGGAL Jenis Jumlah Kondisi Alat Keterangan

1 Senin 7-Dec-20

2 Selasa 8-Dec-20

3 Rabu 9-Dec-20

4 Kamis 10-Dec-20

5 Jum'at 11-Dec-20

6 Sabtu 12-Dec-20

7 Minggu 13-Dec-20
J . URAIAN KEADAAN ALAT REKONSTRUKSI MINGGU INI

No HARI / TANGGAL Jenis Jumlah Kondisi Alat Keterangan

1 Senin 7-Dec-20

2 Selasa 8-Dec-20

3 Rabu 9-Dec-20

4 Kamis 10-Dec-20

5 Jumat 11-Dec-20

6 Sabtu 12-Dec-20

7 Minggu 13-Dec-20

K . URAIAN PEKERJAAN MINGGU DEPAN


No Uraian Kegiatan Rencana Progres ( % ) Keterangan

A Pemeliharaan Periodik (SFO)


BAB 1 Umum
1 Laboratorium 0.009
2 Mobilisasi dan Demobilisasi 0.016
3 Kendaraan Operasional Satgas 2 (dua) Kendaraan/bulan 0.009
4 Kantor Operasional Lapangan 0.005
5 Pasang Spanduk Pemberitahuan -
6 Pasang Selebaran -
7 Asbuilt Drawing 0.034
8 Pengamanan dan Pengaturan Lalu Lintas, Tipe A -
9 Pengamanan dan Pengaturan Lalu Lintas, Tipe B 0.005
10 Pergerakan Peralatan Pengaspalan -
11 Pergerakan Peralatan Scrapping -
12 Kelengkapan SMK3 Type A 0.005
BAB 3 Pembongkaran -
13 Bongkar Perkerasan Jalan Aspal (Cold Milling Machine/Road Cutter) -
BAB 9 Perkerasan -
14 Bitumen Lapis Pengikat (Tack Coat) -
15 Asphalt Concrete Wearing Course -
16 Semen Aspal (Asphalt Cement) -
BAB 12 Pekerjaan Lain lain -
17 Marka Jalan, Sementara (0.016)
18 Patching Type 1 (Permanen) 0.181
19 Patching Type 3 (Asphalticplug), tebal = 5 cm -
20 Pengadaan Aspal Instan (Cold Mix) kemasan 25 kg -
21 Perbaikan Expansion Joint Aspal (Asphaltic Plug Joint) 0.112
21 Asphaltic Joint Filler (Sealant) -
B Rekonstruksi Perkerasan Jalan -
BAB 1 Umum -
1 Laboratorium 0.013
2 Mobilisasi dan Demobilisasi 0.036
3 Kendaraan Operasional Satgas 2 (dua) Kendaraan / bulan (0.005)
4 Kantor Operasional Lapangan 0.006
5 Pasang Spanduk Pemberitahuan -
Pasang Spanduk Pemberitahuan (Harga Timpang) 0.001
6 Asbuilt Drawing 0.031
7 Pengamanan dan Pengaturan Lalu lintas Tipe A (0.001)
8 Rekayasa Lalu Lintas ( Contra Flow ) Pekerjaan Rekonstruksi (0.022)
Kelengkapan SMK3 Type A 0.009
BAB 3 Pembongkaran -
9 Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) -
Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) (Harga Timpang) -
10 Bongkar Perkerasan Jalan Beton (Excavator Hidrolic/Jack Hammer) (0.046)
11 Bongkar Lapis Pondasi Aggregat Kelas A -
BAB 4 Pekerjaan Tanah -
12 Galian Biasa Untuk Dibuang -
BAB 6 Drainase -
13 Pipa Berlubang Banyak Untuk Pekerjaan Drainase Bawah Permukaan -
14 Pengeboran Pipa Horizontal Sub Drain (0.015)
New Pipa Vertikal 12" -
15 Pengeboran Horizontal Vertical Drain dia. 12" -
16 Pengeboran Vertical Drain -
17 Geotextile Non Woven -
Geotextile Non Woven -
BAB 7 Sub Grade -
18 Penyiapan Tanah Dasar -
BAB 8 Lapis pondasi Aggregat -
19 Lapis Pondasi Agregat Kelas A -
BAB 9 Perkerasan -
20 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 hari, single wire mesh dia. 10 mm # 15 mm, t = 30 cm -
Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 hari, Double wire mesh dia. 10 mm # 15 mm, t = 30 cm -
21 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3 hari, single wire mesh dia. 10 mm # 15 mm, t = 30 cm (0.023)
22 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3 hari, tanpa wire mash, t = 30 cm (0.032)
23 Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 7 hari, single wire mesh dia. 10 mm # 15 mm, t = 30 cm -
24 Perkerasan Beton fs 45 umur 28 hari, t = 30 cm -
Beton Fs-45 umur 1 hari (Levelling) -
25 Bor Dowel -
26 Bor Tie Bar -
New Bor Shear Conector -
New Baja Tulangan Ulir (Pelat Injak) -
BAB 12 Pekerjaan lain lain -
27 Marka Jalan, Sementara -
28 Marka Jalan, Sementara -
BAB1 UMUM -
29 Laboratorium 0.004
30 Kelengkapan SMK3 Type B 0.002
BAB 12 Pekerjaan lain lain -
31 Marka Jalan Tipe A & B ( Warna Putih ) 0.001
32 Marka Jalan Tipe A & B ( Warna Kuning ) 0.040
BAB1 UMUM -
33 Pengamanan dan Pengaturan lalu lintas 0.002
34 Laboratorium 0.001
35 Kelengkapan SMK3 Type B 0.001
BAB 12 Pekerjaan lain lain -
36 Penghapusan Marka Thermoplastik 0.032
37 Marka Jalan Tipe (t=3mm) Thermoplastic Kuning 0.076

0.473
PT. PERKASA ADIGUNA SEMBADA

PROGRES MINGGU KE 39 ADDENDUM FINAL


PEKERJAAN PEMELIHARAAN PERIODIK (SFO), REKONSTRUKSI PERKERASAN DAN MARKA JALAN
PADA JALAN TOL JAKARTA - BOGOR - CIAWI TAHUN 2020

KONTRAK AWAL ADDENDUM FINAL PROGRES PEKERJAAN SISA

Mata S/D MINGGU INI S/D MINGGU INI


Uraian Pekerjaan Satuan
Pembayaran Bobot Bobot
Volume Volume
(%) (%)
BOBOT BOBOT
KUANTITAS KUANTITAS
(%) (%)
A PEKERJAAN PEMELIHARAAN PERIODIK (SFO)
Bab 1 Umum
1.20(1) Laboratorium lump sump 1.00 0.139 1.000 0.339 1.000 0.339 - -
1.20(2) Mobilisasi dan Demobilisasi lump sump 1.00 0.107 1.000 0.263 1.000 0.263 - -
1.20.(3)b Kendaraan Operasional Satgas 2 (dua) Kendaraan / bulan bulan 10.00 0.179 6.500 0.285 6.500 0.285 - -
1.20.(3).c Kantor Operasional Lapangan bulan 10.00 0.128 9.000 0.281 9.000 0.281 - -
1.19(3)a Pasang Spanduk Pemberitahuan set 4.00 0.008 2.000 0.010 2.000 0.010 - -
1.19(3)b Pasang Selebaran lembar 500.00 0.007 75.000 0.003 75.000 0.003 - -
1.35 Asbuilt Drawing lump sump 1.00 0.044 1.000 0.107 1.000 0.107 - -
SK. 1.02(1) Pengamanan dan Pengaturan Lalu lintas Tipe A tim - hari 248.00 0.632 24.000 0.150 24.000 0.150 - -
SK. 1.02(2) Pengamanan dan Pengaturan Lalu lintas Tipe B tim - hari 125.0000 0.1935 111.402 0.421 111.402 0.421 - -
SK. 1.03(1) Pergerakan Peralatan Pengaspalan kali 248.00 3.053 24.000 0.722 24.000 0.722 - -
SK. 1.03(2) Pergerakan Peralatan Scrapping kali 248.00 1.388 24.000 0.328 24.000 0.328 - -
SK. 10 Kelengkapan SMK3 Type A lump sump 1.00 0.076 1.000 0.186 1.000 0.186 - -
SUB TOTAL BAB 1 5.955 3.09 3.094 0.000
Bab 3 Pembongkaran
3.01.(3)a Bongkar Perkerasan Jalan Aspal (Cold Milling Machine / Road Cutter m3 7,843.13 3.472 1060.845 1.148 1,060.845 1.148 - -
SUB TOTAL BAB 3 3.472 1.148 1.148 0.000
Bab 9 Perkerasan
9.05 Bitumen Lapis Pengikat (Tack Coat) ltr 73,912.80 0.978 6929.644 0.224 6,929.644 0.224 - -
9.07(3) Asphalt Concrete Wearing Course ton 22,498.20 17.032 2227.963 4.122 2,227.963 4.122 - -
9.07(4) Semen Aspal (Asphalt Cement) ton 1,385.27 11.939 134.670 2.837 134.670 2.837 - -
SUB TOTAL BAB 9 29.948 7.18 7.183 0.000
KONTRAK AWAL ADDENDUM FINAL PROGRES PEKERJAAN SISA

Mata
Uraian Pekerjaan Satuan S/D MINGGU INI S/D MINGGU INI
Pembayaran Bobot Bobot
Volume Volume
(%) (%)
BOBOT BOBOT
KUANTITAS (%)
KUANTITAS
(%)
Bab 12 Pekerjaan Lain-Lain
12.08 Marka Jalan, Sementara m' 8,740.61 0.231 4439.000 0.287 4,439.000 0.287 - -
12.14.(1) Patching Type 1 (Permanen) m3 1,259.70 7.320 405.463 5.759 405.463 5.759 - -
12.14.(3) Patching Type 3 (Asphalticplug), tebal = 5 cm m2 175.60 0.467 0.000 0.000 - - - -
12.14.(4) Pengadaan Aspal Instan (Cold Mix) kemasan 25 kg zak 7,000.00 1.567 2600.000 1.423 2,600.000 1.423 - -
SK. 3.06.(1) Perbaikan Expansion Joint Aspal (Asphaltic Plug Joint) m' 740.60 1.197 100.350 0.397 100.350 0.397 - -
SK3.03(3) Asphaltic Joint Filler (Sealant) m' 300.00 0.008 0.000 0.000 - - - -
SUB TOTAL BAB 12 10.791 7.86 7.865 0.000
B REKONSTRUKSI PERKERASAN
Bab 1 Umum
1.20(1) Laboratorium lump sump 1.00 0.209 1.000 0.510 1.000 0.510 - -
1.20(2) Mobilisasi dan Demobilisasi lump sump 1.00 0.160 1.000 0.391 1.000 0.391 - -
1.20.(3).b Kendaraan Operasional Satgas 2 (dua) Kendaraan / bulan bulan 9.00 0.161 6.500 0.285 6.500 0.285 - -
1.20.(3).c Kantor Operasional Lapangan bulan 9.00 0.096 9.000 0.234 9.000 0.234 - -
1.19(3).a Pasang Spanduk Pemberitahuan set 4.00 0.008 4.000 0.020 4.000 0.020 - -
Pasang Spanduk Pemberitahuan (Harga Timpang) set 1.000 0.004 1.000 0.004 - -
1.35 Asbuilt Drawing lump sump 1.00 0.038 1.000 0.093 1.000 0.093 - -
SK. 1.02(1) Pengamanan dan Pengaturan Lalu lintas Tipe A tim - hari 459.00 1.330 182.679 1.293 182.679 1.293 - -
Rekayasa Lalu Lintas ( Contra Flow ) Pekerjaan Rekonstruksi 41.000 0.448 41.000 0.448 - -
SK. 10 Kelengkapan SMK3 Type A lump sump 1.00 0.076 1.000 0.186 1.000 0.186 - -
SUB TOTAL BAB 1 2.078 3.46 3.465 0.000
Bab 3 Pembongkaran
3.01.(3).a Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) m3 3,505.75 1.637 3505.750 4.002 3,505.750 4.002 - -
Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) (Harga
97.578 0.101 97.578 0.101 - -
Timpang)
3.01.(3).b Bongkar Perkerasan Jalan Beton (Excavator Hidrolic/Jack Hammer) m3 140.00 0.067 4449.105 5.178 4,449.105 5.178 - -
3.01.(4) Bongkar Lapis Pondasi Aggregat Kelas A m3 9,114.38 1.781 3427.862 1.637 3,427.862 1.637 - -
SUB TOTAL BAB 3 3.485 10.92 10.918 0.000
Bab 4 Pekerjaan Tanah
4.03.(2) Galian Biasa Untuk Dibuang m3 7,291.50 0.972 2082.381 0.678 2,082.381 0.678 - -
SUB TOTAL BAB 4 0.972 0.68 0.678 0.000
KONTRAK AWAL ADDENDUM FINAL PROGRES PEKERJAAN SISA

Mata
Uraian Pekerjaan Satuan S/D MINGGU INI S/D MINGGU INI
Pembayaran Bobot Bobot
Volume Volume
(%) (%)
BOBOT BOBOT
KUANTITAS (%)
KUANTITAS
(%)
Bab 5 Galian Struktur
6.09.(3) Pipa Berlubang Banyak Untuk Pekerjaan Drainase Bawah Permukaa m' 1,572.08 0.433 1927.970 1.299 1,927.970 1.299 - -
SK. 6.(01) Pengeboran Pipa Horizontal Sub Drain m' 1,572.08 0.390 419.440 0.255 419.440 0.255 - -
New Pay Item Pipa vertikal 12" m' 49.600 0.075 49.600 0.075 - -
SK. 6.(01)a Pengeboran Horizontal Vertical Drain dia. 12" m' 40.00 0.114 52.000 0.363 52.000 0.363 - -
Pengeboran Vertical Drain 201.360 0.122 201.360 0.122 - -
6.10 Geotextile Non Woven m2 3,193.92 0.107 3193.920 0.262 3,193.920 0.262 - -
Geotextile Non Woven harga timpang m2 10501.162 0.701 10,501.162 0.701 - -
SUB TOTAL BAB 5 1.045 3.08 3.077 0.000
Bab 7 Sub Grade
7.01 Penyiapan Tanah Dasar m2 36,457.50 0.705 22689.166 1.072 22,689.166 1.072 - -
SUB TOTAL BAB 7 0.705 1.07 1.072 0.000
Bab 8 Lapis Pondasi Agregat
8.01(1) Lapis Pondasi Agregat Kelas A m3 9,114.38 4.387 6737.490 7.925 6,737.490 7.925 - -
SUB TOTAL BAB 8 4.387 7.93 7.925 0.000
KONTRAK AWAL ADDENDUM FINAL PROGRES PEKERJAAN SISA

Mata
Uraian Pekerjaan Satuan S/D MINGGU INI S/D MINGGU INI
Pembayaran Bobot Bobot
Volume Volume
(%) (%)
BOBOT BOBOT
KUANTITAS (%)
KUANTITAS
(%)
Bab 9 Perkerasan

Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 hari,
9.10.(1).i m2 12,625.00 12.846 7409.771 18.427 7,409.771 18.427 - -
single wire mesh dia. 10 mm # 15 mm, t = 30 cm

Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 hari,
New Pay Item m2 181.807 0.501 181.807 0.501 - -
double wire mesh dia. 10 mm # 15 mm, t = 30 cm

Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3 hari,
9.10.(1).j m2 6,220.00 5.424 12488.704 26.617 12,488.704 26.617 - -
single wire mesh dia. 10 mm # 15 mm, t = 30 cm

Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3


m2 2597.547 4.832 2,597.547 4.832 - -
hari, tanpa wire mash, t = 30 cm

Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 7 hari,
9.10.(1).l m2 16,882.50 13.073 0.000 - - - -
single wire mesh dia. 10 mm # 15 mm, t = 30 cm

9.08.(1)b Perkerasan Beton fs 45 umur 28 hari, t = 30 cm m2 730.00 0.425 0.000 - - - -


New Pay Item Beton fs-45 umur 1 hari (Levelling) m3 4.416 0.027 4.416 0.027 - -
SK. 9.(01)a Bor Dowel titik 1,153.00 0.136 400.000 0.115 400.000 0.115 - -
SK. 9.(01)b Bor Tie Bar titik 12,435.00 1.170 6331.000 1.456 6,331.000 1.456 - -
New Pay Item Bor Shear Conector titik 144.000 0.016 144.000 0.016 - -
New Pay Item Baja Tulangan Ulir (Pelat Injak) Kg 754.632 0.024 754.632 0.024 - -
SUB TOTAL BAB 9 33.074 52.02 52.016 0.000
Bab 12 Pekerjaan Lain-Lain
12.08 Marka Jalan, Sementara m' 921.90 0.024 0.000 0.000 - - - -
Marka Jalan, Sementara m' 0.000 0.000 - - - -
0.000
SUB TOTAL BAB 12 0.024 0.000 0.000
C MARKA JALAN
Bab 1 Umum
1.20(1) Laboratorium lump sump 1.00 0.022 1.000 0.055 1.000 0.055 - -
SK. 10 Kelengkapan SMK3 Type B lump sump 1.00 0.011 1.000 0.027 1.000 0.027 - -
SUB TOTAL BAB 1 0.034 0.08 0.082 0.000
Bab 12 Pekerjaan Lain-Lain
SK12.08(1)a Marka Jalan Tipe (t=3mm) Thermoplastic Putih m2 8,172.63 1.829 1687.646 0.923 1,687.646 0.923 - -
SK12.08(1)b Marka Jalan Tipe (t=3mm) Thermoplastic Kuning m2 8,200.82 1.878 52.950 0.030 52.950 0.030 - -
SUB TOTAL BAB 12 3.707 0.95 0.9530 0.000
D PENGECATAN MARKA JALAN
Bab 1 Umum
S1.19 Pengamanan dan Pengaturan lalu lintas lump sump 1.00 0.006 1.000 0.014 1.000 0.014 - -
KONTRAK AWAL ADDENDUM FINAL PROGRES PEKERJAAN SISA

Mata
Uraian Pekerjaan Satuan S/D MINGGU INI S/D MINGGU INI
Pembayaran Bobot Bobot
Volume Volume
(%) (%)
BOBOT BOBOT
KUANTITAS KUANTITAS
(%) (%)
1.20(1) Laboratorium lump sump 1.00 0.003 1.000 0.008 1.000 0.008 - -
SK. 10 Kelengkapan SMK3 Type B lump sump 1.00 0.003 1.000 0.008 1.000 0.008 - -
SUB TOTAL BAB 1 0.012 0.03 0.030 0.000
Bab 12 Pekerjaan Lain-Lain
12.08(4) Penghapusan Marka Thermoplastik m2 960.50 0.092 584.595 0.137 584.595 0.137 - -
SK12.08(1)b Marka Jalan Tipe (t=3mm) Thermoplastic Kuning m2 960.50 0.220 638.295 0.357 638.295 0.357 - -
SUB TOTAL BAB 12 0.312 0.49 0.494 0.000
TOTAL 100.000 100.000 100.000 -

Konsultan Pengawas Kontraktor Pelaksana


Satuan Tugas
PT. Multi Phi Beta PT. Perkasa Adiguna Sembada
PT JasaMarga Tollroad
Maintanance.

Artiningsih Sigit Yuwono


Mariance Napitupulu
PT. PERKASA ADIGUNA SEMBADA

DOKUMENTASI MINGGU 39
PEKERJAAN PEMELIHARAAN PERIODIK (SFO), REKONSTRUKSI PERKERASAN DAN
MARKA JALAN PADA JALAN TOL JAKARTA - BOGOR - CIAWI TAHUN
2020

Dokumentasi : Pekerjaan Patching

Dokumentasi : Pekerjaan Expantion Joint


PT. PERKASA ADIGUNA SEMBADA

GRAFIK PROGRES

PEKERJAAN PEMELIHARAAN PERIODIK (SFO), REKONSTRUKSI PERKERASAN DAN

MARKA JALAN PADA JALAN TOL JAKARTA - BOGOR - CIAWI TAHUN 2020

GRAFIK PROGRES

100.000 100.000

(0.000)
RENCANA (%) REALISASI (%) DEVIASI (%)

GRAFIK WAKTU TERPAKAI

WAKTU TERPAKAI ( Hari )


SISA WAKTU ( Hari )

270
PT. PERKASA ADIGUNA SEMBADA

PEKERJAAN PEMELIHARAAN PERIODIK SFO, REKONSTRUKSI PERKERASAN DAN MARKA JALAN


PADA JALAN TOL JAKARTA - BOGOR - CIAWI TAHUN 2020

JUMLAH HARI Rencana (%) Realisasi (%) Deviasi (%)


MINGGU
PERIODE Sd Mgg Sd Mgg Sd Mgg
KE Mgg Ini Sisa Mgg Ini Sisa Mgg Ini Sisa Mgg Ini Sd Mgg Ini
Ini Ini Ini
2 3 4 5 6.000 7.000 8 9.000 10.000 11.000 12= 9-6 13 = 10 - 7
1 20-Mar - 22-Mar 3 3 267 0.229 0.229 99.771 0.229 0.229 99.771 0.000

2 23-Mar - 29-Mar 7 10 260 0.344 0.573 99.427 0.366 0.595 99.405 0.022 0.022

3 30-Mar - 5-Apr 7 17 253 0.301 0.874 99.126 0.304 0.899 99.101 0.003 0.025
4 6-Apr - 12-Apr 7 24 246 0.441 1.315 98.685 0.613 1.512 98.488 0.171 0.196
5 13-Apr - 19-Apr 7 31 239 0.340 1.655 98.345 1.205 2.717 97.283 0.866 1.062

6 20-Apr - 26-Apr 7 38 232 0.8015 2.456 97.544 0.808 3.525 96.475 0.006 1.068

7 27-Apr - 3-May 7 45 225 0.732 3.188 96.812 1.124 4.649 95.351 0.392 1.461

8 4-May - 10-May 7 52 218 0.910 4.099 95.901 1.283 5.932 94.068 0.373 1.834

9 11-May - 17-May 7 59 211 0.910 5.009 94.99 2.283 8.215 91.785 1.372 3.206

10 18-May - 24-May 7 66 204 0.011 5.020 94.98 0.418 8.633 91.367 0.408 3.614

11 25-May - 31-May 7 73 197 0.011 5.030 94.97 0.094 8.727 91.273 0.083 3.697

12 1-Jun - 7-Jun 7 80 190 2.790 7.821 92.18 1.676 10.404 89.596 (1.114) 2.583

13 8-Jun - 14-Jun 7 87 183 2.785 10.606 89.39 1.142 11.545 88.455 (1.643) 0.940

14 15-Jun - 21-Jun 7 94 176 2.836 13.442 86.56 3.052 14.598 85.402 0.216 1.155

15 22-Jun - 28-Jun 7 101 169 2.836 16.279 83.72 2.815 17.413 82.587 (0.021) 1.134
JUMLAH HARI Rencana (%) Realisasi (%) Deviasi (%)
MINGGU
PERIODE Sd Mgg Sd Mgg Sd Mgg
KE Mgg Ini Sisa Mgg Ini Sisa Mgg Ini Sisa Mgg Ini Sd Mgg Ini
Ini Ini Ini
2 3 4 5 6.000 7.000 8 9.000 10.000 11.000 12= 9-6 13 = 10 - 7
16 29-Jun - 5-Jul 7 108 162 2.842 19.120 80.88 0.378 17.790 82.210 (2.464) (1.330)

17 6-Jul - 12-Jul 7 115 155 2.801 21.922 78.08 1.587 19.378 80.622 (1.214) (2.544)

18 13-Jul - 19-Jul 7 122 148 2.797 24.719 75.28 0.958 20.336 79.664 (1.839) (4.383)

19 20-Jul - 26-Jul 7 129 141 2.797 27.516 72.48 1.435 21.771 78.229 (1.362) (5.745)

ADDENDUM 1 3.267 49.566 50.43

20 27-Jul - 2-Aug 7 136 134 0.105 49.671 50.33 0.297 49.863 50.137 0.192 0.192

21 3-Aug - 9-Aug 7 143 127 2.499 52.169 47.83 2.345 52.208 47.792 (0.154) 0.038

22 10-Aug - 16-Aug 7 150 120 2.489 54.658 45.34 2.501 54.708 45.292 0.012 0.050

23 17-Aug - 23-Aug 7 157 113 0.105 54.763 45.24 0.132 54.840 45.160 0.027 0.077

24 24-Aug - 30-Aug 7 164 106 2.480 57.244 42.76 3.183 58.023 41.977 0.703 0.780

25 31-Aug - 6-Sep 7 171 99 2.485 59.7289 40.27 2.829 60.8518 39.148 0.343 1.1229

26 7-Sep - 13-Sep 7 178 92 4.457 64.186 35.81 4.385 65.237 34.763 (0.072) 1.050

27 14-Sep - 20-Sep 7 185 85 4.457 68.643 31.36 3.608 68.845 31.155 (0.849) 0.201

28 21-Sep - 27-Sep 7 192 78 4.449 73.092 26.91 6.872 75.717 24.283 2.424 2.625

29 28-Sep - 4-Oct 7 199 71 4.454 77.546 22.45 4.198 79.915 20.085 (0.255) 2.370

30 5-Oct - 11-Oct 7 206 64 3.295 80.840 19.16 2.507 82.422 17.578 (0.787) 1.582

31 12-Oct - 18-Oct 7 213 57 3.226 84.067 15.93 3.441 85.863 14.137 0.214 1.796

32 19-Oct - 25-Oct 7 220 50 3.308 87.374 12.63 1.629 87.492 12.508 (1.679) 0.118

ADDENDUM 2 1.736 93.207 6.79

33 26-Oct - 1-Nov 7 227 43 1.024 94.231 5.77 0.388 93.594 6.406 (0.637) (0.637)

34 2-Nov - 8-Nov 7 234 36 1.024 95.255 4.75 1.982 95.576 4.424 0.958 0.321
JUMLAH HARI Rencana (%) Realisasi (%) Deviasi (%)
MINGGU
PERIODE Sd Mgg Sd Mgg Sd Mgg
KE Mgg Ini Sisa Mgg Ini Sisa Mgg Ini Sisa Mgg Ini Sd Mgg Ini
Ini Ini Ini
2 3 4 5 6.000 7.000 8 9.000 10.000 11.000 12= 9-6 13 = 10 - 7
35 9-Nov - 15-Nov 7 241 29 1.432 96.687 3.31 1.524 97.100 2.900 0.092 0.413

36 16-Nov - 22-Nov 7 248 22 1.405 98.092 1.91 1.017 98.117 1.883 (0.388) 0.025

37 23-Nov - 29-Nov 7 255 15 0.963 99.055 0.94 0.944 99.061 0.939 (0.019) 0.006

38 30-Nov - 6-Dec 7 262 8 0.473 99.528 0.47 0.519 99.580 0.420 0.046 0.052

39 7-Dec - 14-Dec 8 270 0 0.473 100.000 (0.00) 0.420 100.000 - (0.052) (0.000)
JADWAL RENCANA KERJA
Pekerjaan Pemeliharaan Periodik (Scrapping Filling Overlay), Rekonstruksi Perkerasan dan Marka Jalan
Pada Jalan Tol Jakarta Bogor Ciawi
Tahun 2020 PT. PERKASA ADIGUNA SEMBADA

WAKTU PELAKSANAAN
No Mata Volume Harga Satuan Jumlah Harga Bobot MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER
Uraian Pekerjaan Satuan Ket
Pembayaran Addendum 2 (Rp) (Rp) M1 M2 M3 M4 M5 M6 M7 M8 M9 M10
M1 M1 M13 M14 M1 M16 M1 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M30 M31 M32 M33 M34 M35 M36 M37 M38 M39
1 2 5 7
(%) 20 - 22 23 - 29 30 - 5 6 - 12 13 - 19 20 - 26 27 - 3 4 - 10 11 - 17 18 - 24 25 - 31 1 - 8 - 14 15 - 21 22 - 28 29 - 5 6 - 12 13 - 19 20 - 26 27 - 2 3-9 10 - 16 17 - 23 24 - 30 31 - 6 7 - 13 14 - 20 21 - 27 28 - 4 5 - 11 12 - 18 19 - 25 26 - 2 -8 9 - 15 16 - 22 23 - 29 30 - 6 7 - 14
7 1

Bab 1 Umum
1.20(1) Laboratorium lump sump 1.000 136,400,000.000 136,400,000.000 0.337 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 100%
1.20(2) Mobilisasi dan Demobilisasi lump sump 1.000 105,600,000.000 105,600,000.000 0.261 0.027 0.027 0.016 0.016 0.016
1.20.(3)b Kendaraan Operasional Satgas 2 (dua) Kendaraan / bulan Kantor bulan 9.000 17,600,000.000 158,400,000.000 0.391 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.009 0.009 0.009 0.009 0.009 0.009 0.009
1.20.(3).c Operasional Lapangan bulan 9.000 12,540,000.000 112,860,000.000 0.279 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.005 0.005 0.005 0.005 0.005 0.005 0.005
1.19(3)a Pasang Spanduk Pemberitahuan Pasang set 4.000 2,058,000.000 8,232,000.000 0.020 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.010
1.19(3)b Selebaran lembar 500.000 14,000.000 7,000,000.000 0.017 0.001 0.001 0.001 0.001 0.003 0.003 0.003 0.017
1.35 Asbuilt Drawing lump sump 1.000 42,900,000.000 42,900,000.000 0.106 0.034 0.034 0.034
SK. 1.02(1) Pengamanan dan Pengaturan Lalu lintas Tipe A tim - hari 24.000 2,506,000.000 60,144,000.000 0.148 0.006 0.006 0.006 0.006 0.025 0.025 0.025 0.025 0.025 0.025 0.025 0.025
SK. 1.02(2) Pengamanan dan Pengaturan Lalu lintas Tipe B tim - hari 90.631 1,521,000.000 137,850,131.250 0.340 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.005 0.005 0.005 0.005 0.005 0.005 0.005
SK. 1.03(1) Pergerakan Peralatan Pengaspalan kali 24.000 12,100,000.000 290,400,000.000 0.717 0.031 0.031 0.031 0.031 0.122 0.122 0.122 0.122 0.122 0.122 0.122 0.122
SK. 1.03(2) Pergerakan Peralatan Scrapping Kelengkapan kali 24.000 5,500,000.000 132,000,000.000 0.326 0.014 0.014 0.014 0.014 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056
SK. 10 SMK3 Type A Pembongkaran lump sump 1.000 74,800,000.000 74,800,000.000 0.185 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005 0.005
Bab 3
3.01.(3)a Bongkar Perkerasan Jalan Aspal (Cold Milling Machine / Road Cutter) m3 1,060.845 435,000.000 461,467,676.355 1.139 0.035 0.035 0.035 0.035 0.139 0.139 0.139 0.139 0.139 0.139 0.139 0.139 -0.044 -0.044
Bab 9 Perkerasan
9.05 Bitumen Lapis Pengikat (Tack Coat) ltr 6,929.644 13,000.000 90,085,372.000 0.222 0.010 0.010 0.010 0.010 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.039 0.001 0.001
9.07(3) Asphalt Concrete Wearing Course ton 2,227.963 744,000.000 1,657,604,639.549 4.091 0.170 0.170 0.170 0.170 0.681 0.681 0.681 0.681 0.681 0.681 0.681 0.681 -0.005 -0.005
9.07(4) Semen Aspal (Asphalt Cement) ton 134.670 8,470,000.000 1,140,655,742.836 2.815 0.119 0.119 0.119 0.119 0.478 0.478 0.478 0.478 0.478 0.478 0.478 0.478 -0.015 -0.015
Bab 12 Pekerjaan Lain-Lain 75%
12.08 Marka Jalan, Sementara m' 4,439.000 26,000.000 115,414,000.000 0.285 0.002 0.002 0.002 0.002 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.005 0.005 0.005
12.14.(1) Patching Type 1 (Permanen) m3 362.525 5,711,000.000 2,070,380,275.000 5.109 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.198 0.088 0.088 0.088 0.088 0.088 0.088 0.088 0.088 0.088 0.088 0.088 0.088 0.088 0.181 0.181 0.181 0.181 0.181 0.181 0.181
12.14.(3) Patching Type 3 (Asphalticplug), tebal = 5 cm m2 - 2,611,000.000 - - 0.052 0.052 0.052 0.005 0.005 0.005
12.14.(4) Pengadaan Aspal Instan (Cold Mix) kemasan 25 kg zak 2,900.000 220,000.000 638,000,000.000 1.575 0.075 0.075 0.075 0.075 0.075 0.380 0.380
SK. 3.06.(1) Perbaikan Expansion Joint Aspal (Asphaltic Plug Joint) m' 200.292 1,589,000.000 318,263,988.000 0.785 0.109 0.109 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.112 0.112 0.112 0.112 0.112 0.112 0.112
SK9.03(3) Asphaltic Joint Filler (Sealant) m' - 27,000.000 - - 0.001 0.001 0.001 0.001 0.001
B REKONSTRUKSI PERKERASAN
Bab 1 Umum
1.20(1) Laboratorium lump sump 1.000 205,150,000.000 205,150,000.000 0.506 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.013 0.013 0.013 0.013 0.013 0.013 0.013
1.20(2) Mobilisasi dan Demobilisasi lump sump 1.000 157,300,000.000 157,300,000.000 0.388 0.040 0.040 0.036 0.036
1.20.(3).b Kendaraan Operasional Satgas 2 (dua) Kendaraan / bulan Kantor bulan 6.500 17,600,000.000 114,400,000.000 0.282 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011

LIBUR HARI RAYA


1.20.(3).c Operasional Lapangan bulan 9.000 10,450,000.000 94,050,000.000 0.232 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006
1.19(3).a Pasang Spanduk Pemberitahuan set 4.000 2,058,000.000 8,232,000.000 0.020 0.002 0.002 0.002 0.002 0.005 0.005
Pasang Spanduk Pemberitahuan (Harga Timpang) set 1.000 1,559,338.000 1,559,338.000 0.004 0.001 0.001 0.001 0.001 0.001
1.35 Asbuilt Drawing lump sump 1.000 37,400,000.000 37,400,000.000 0.092 0.031 0.031 0.031
SK. 1.02(1) Pengamanan dan Pengaturan Lalu lintas Tipe A tim - hari 182.679 2,847,000.000 520,087,226.880 1.284 0.004 0.004 0.004 0.004 0.004 0.004 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.030 0.031 0.031 0.031 0.031 0.062 0.062 0.062 0.062 0.041 0.041 0.041
Rekayasa Lalu Lintas ( Contra Flow ) Pekerjaan Rekonstruksi 41.000 4,396,000.000 180,236,000.000 0.445 0.026 0.026 0.026 0.026 0.053 0.053 0.053 0.053 0.035 0.035 0.035
SK. 10 Kelengkapan SMK3 Type A lump sump 1.000 74,800,000.000 74,800,000.000 0.185 0.000 0.000 0.000 0.000 0.000 0.000 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.005 0.005 0.005 0.005 0.010 0.010 0.010 0.010 0.007 0.007 0.007 0.009 0.009 0.009 0.009 0.009 0.009 0.009
Bab 3 Pembongkaran 50%
3.01.(3).a Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) m3 3,505.750 459,000.000 1,609,139,250.000 3.971 0.005 0.005 0.005 0.005 0.005 0.005 0.036 0.036 0.036 0.036 0.036 0.036 0.036 0.036 0.046 0.046 0.046 0.046 0.092 0.092 0.092 0.092 0.061 0.061 0.061 0.108 0.108 0.108 0.108 0.108
Bongkar Perkerasan Jalan Aspal (Excavator Hidrolic/Jack Hammer) m3 96.498 416,293.000 40,171,610.096 0.099 0.020 0.020 0.020 0.020 0.020
(Harga Timpang)
3.01.(3).b Bongkar Perkerasan Jalan Beton (Excavator Hidrolic/Jack Hammer) Bongkar m3 4,456.815 468,000.000 2,085,789,403.339 5.148 0.000 0.000 0.000 0.000 0.000 0.000 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.230 0.230 0.230 0.230 0.460 0.460 0.460 0.460 0.307 0.307 0.307
3.01.(4) Lapis Pondasi Aggregat Kelas A m3 3,418.454 192,000.000 656,343,148.224 1.620 0.006 0.006 0.006 0.006 0.006 0.006 0.040 0.040 0.040 0.040 0.040 0.040 0.040 0.040 0.095 0.095 0.095 0.095 0.189 0.189 0.189 0.189 0.126 0.126 0.126 0.028 0.028 0.028 0.028 0.028
Bab 4 Pekerjaan Tanah
4.03.(2) Galian Biasa Untuk Dibuang m3 2,074.623 131,000.000 271,775,657.055 0.671 0.003 0.003 0.003 0.003 0.003 0.003 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.006 0.006 0.006 0.006 0.011 0.011 0.011 0.011 0.008 0.008 0.008 0.002 0.002 0.002 0.002
Bab 5 Galian Struktur
6.09.(3) Pipa Berlubang Banyak Untuk Pekerjaan Drainase Bawah Permukaan m' 1,897.510 271,000.000 514,225,210.000 1.269 0.001 0.001 0.001 0.001 0.001 0.001 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.010 0.062 0.062 0.062 0.062 0.124 0.124 0.124 0.124 0.083 0.083 0.083 0.051 0.051 0.051 0.051 0.051
SK. 6.(01) Pengeboran Pipa Horizontal Sub Drain m' 386.840 244,000.000 94,388,960.000 0.233 0.001 0.001 0.001 0.001 0.001 0.001 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.032 0.032 0.032 0.032 0.064 0.064 0.064 0.064 0.042 0.042 0.042
new pay item Pipa vertikal 12" m' 32.000 609,000.000 19,488,000.000 0.048 0.010 0.010 0.010 0.010 0.010
SK. 6.(01)a Pengeboran Horizontal Vertical Drain dia. 12" m' 32.000 2,804,000.000 89,728,000.000 0.221 0.000 0.000 0.000 0.000 0.000 0.000 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.044 0.044 0.044 0.044 0.044
Pengeboran Vertical Drain m' 225.080 244,000.000 54,919,520.000 0.136 0.001 0.001 0.001 0.001 0.003 0.003 0.003 0.003 0.002 0.002 0.002 0.009 0.009 0.009 0.009 0.009
6.10 Geotextile Non Woven m2 3,193.920 33,000.000 105,399,360.000 0.260 0.000 0.000 0.000 0.000 0.000 0.000 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 -0.014 0.000 0.000 0.000 0.000 0.000
Geotextile Non Woven m2 10,556.206 26,842.000 283,349,677.157 0.699 0.036 0.001 0.001 0.001 0.001
Bab 7 Sub Grade
7.01 Penyiapan Tanah Dasar m2 22,728.216 19,000.000 431,836,111.600 1.066 0.002 0.002 0.002 0.002 0.002 0.002 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.016 0.026 0.026 0.026 0.026 0.053 0.053 0.053 0.053 0.035 0.035 0.035 0.001 0.001 0.001 0.001
Bab 8 Lapis Pondasi Agregat
8.01(1) Lapis Pondasi Agregat Kelas A m3 6,769.548 473,000.000 3,201,996,062.739 7.902 0.015 0.015 0.015 0.015 0.015 0.015 0.097 0.097 0.097 0.097 0.097 0.097 0.097 0.097 0.178 0.178 0.178 0.178 0.285 0.285 0.285 0.285 0.285 0.285 0.285 0.073 0.073 0.073 0.073 0.073
Bab 9 Perkerasan
9.10.(1).i Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 hari, single wire
m2 7,543.854 1,000,000.000 7,543,854,300.000 18.617 0.043 0.043 0.043 0.043 0.043 0.043 0.285 0.285 0.285 0.285 0.285 0.285 0.285 0.285 0.887 0.887 0.887 0.887 1.775 1.775 1.775 1.775 1.183 1.183 1.183 0.139 0.139 0.139 0.139
mesh dia. 10 mm # 15 mm, t = 30 cm

Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 1 m2


new pay item hari, double wire mesh dia. 10 mm # 15 mm, t = 30 cm 240.434 1,108,000.000 266,400,872.000 0.657 0.131 0.131 0.131 0.131 0.131

Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3 hari, single wire
9.10.(1).j m2 12,488.704 857,000.000 10,702,819,713.650 26.413 0.121 0.121 0.121 0.121 0.121 0.121 0.121 0.121 0.077 0.077 0.077 0.077 0.153 0.153 0.153 0.153 0.102 0.102 0.102
mesh dia. 10 mm # 15 mm, t = 30 cm
Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 3
m2 2,597.547 748,000.000 1,942,965,156.000 4.795 0.277 0.277 0.277 0.277 0.554 0.554 0.554 0.554 0.369 0.369 0.369
hari, tanpa wire mash, t = 30 cm
9.10.(1).l Perkerasan Beton Cepat Setting (SCC) Non Shrink, fs 45, umur 7 hari, m2 - 761,000.000 - - 0.022 0.022 0.022 0.022 0.022 0.022 0.291 0.291 0.291 0.291 0.291 0.291 0.291 0.291 25%
single wire mesh dia. 10 mm # 15 mm, t = 30 cm
9.08.(1)b Perkerasan Beton fs 45 umur 28 hari, t = 30 cm m2 - 572,000.000 - - 0.001 0.001 0.001 0.001 0.001 0.001 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009

new pay item Beton fs-45 umur 1 hari (Levelling) m3 4.416 2,425,000.000 10,708,800.000 0.026 0.005 0.005 0.005 0.005 0.005
SK. 9.(01)a Bor Dowel titik 431.000 116,000.000 49,996,000.000 0.123 0.000 0.000 0.000 0.000 0.000 0.000 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.004 0.004 0.004 0.004 0.009 0.009 0.009 0.009 0.006 0.006 0.006 0.003 0.003 0.003 0.003 0.003
SK. 9.(01)b Bor Tie Bar titik 6,302.000 92,500.000 582,935,000.000 1.439 0.004 0.004 0.004 0.004 0.004 0.004 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.026 0.031 0.031 0.031 0.031 0.062 0.062 0.062 0.062 0.041 0.041 0.041 0.036 0.036 0.036 0.036 0.036
new pay item Bor Shear Conector titik 144.000 45,600.000 6,566,400.000 0.016 0.003 0.003 0.003 0.003 0.003
new pay item Baja Tulangan Ulir (Pelat Injak) kg 754.632 13,000.000 9,810,216.000 0.024 0.005 0.005 0.005 0.005 0.005
Bab 12 Pekerjaan Lain-Lain
12.08 Marka Jalan, Sementara m' - 26,000.000 - - 0.000 0.000 0.000 0.000 0.000 0.000 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.003 0.003 0.003 0.003 0.006 0.006 0.006 0.006 0.004 0.004 0.004
Marka Jalan, Sementara m' - 9,105.800 - - 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Bab 1 Umum
1.20(1) Laboratorium lump sump 1.000 22,000,000.000 22,000,000.000 .054 0.004 0.004 0.004 0.004 0.004 0.004 0.008 0.008 0.008 0.008 0.008 0.008 0.004 0.004 0.004 0.004 0.004 0.004 0.004
0 .027 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.002 0.002 0.002 0.002 0.002 0.002 0.002
SK. 10 Kelengkapan SMK3 Type B lump sump 1.000 11,000,000.000 11,000,000.000
0
.814 0.210 0.210 0.210 0.210 0.210 0.210 0.210 0.210 0.210 0.210 0.210 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Bab 12 Pekerjaan Lain-Lain
.278 0.040 0.040 0.040 0.040 0.040 0.040 0.040
SK12.08(1)a Marka Jalan Tipe (t=3mm) Thermoplastic Putih m2 1,500.000 220,000.000 330,000,000.000
0
.014 0.001 0.001 0.001 0.006 0.006 0.002 0.002 0.002 0.002 0.002 0.002 0.002
SK12.08(1)b Marka Jalan Tipe (t=3mm) Thermoplastic Kuning m2 500.000 225,000.000 112,500,000.000
0 .008 0.001 0.001 0.001 0.001 0.001 0.001 0.004 0.004 0.001 0.001 0.001 0.001 0.001 0.001 0.001
Bab 1 Umum .008 0.000 0.000 0.000 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
S1.19 Pengamanan dan Pengaturan lalu lintas lump sump 1.000 5,500,000.000 5,500,000.000
0 .223 0.015 0.015 0.015 0.052 0.052 0.052 0.032 0.032 0.032 0.032 0.032 0.032 0.032
1.20(1) Laboratorium lump sump 1.000 3,300,000.000 3,300,000.000 .533 0.100 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0%
0
SK. 10 Kelengkapan SMK3 Type B lump sump 1.000 3,300,000.000 3,300,000.000
0
Bab 12 Pekerjaan Lain-Lain
12.08(4) Penghapusan Marka Thermoplastik m2 960.500 94,000.000 90,287,000.000
0
SK12.08(1)b Marka Jalan Tipe (t=3mm) Thermoplastic Kuning m2 960.500 225,000.000 216,112,500.000
0
RENCANA KEMAJUAN PEKERJAAN 0.229 0.344 0.301 0.441 0.340 0.801 0.732 0.910 0.910 0.011 0.011 2.790 2.785 2.836 2.836 2.842 2.801 2.797 2.797 2.849 4.989 5.014 4.974 4.965 4.940 5.016 4.953 5.036 5.012 5.036 3.728 3.805 3.779 3.806 2.146 0.622 0.624 0.607 0.581
KONTRAK

KUMULATIF RENCANA KEMAJUAN PEKERJAAN 0% 0.229 0.573 0.874 1.315 1.655 2.456 3.188 4.099 5.009 5.020 5.030 7.821 10.606 13.442 16.279 19.120 21.922 24.719 27.516 30.365 35.354 40.368 45.342 50.307 55.248 60.264 65.217 70.253 75.265 80.301 84.029 87.834 91.614 95.419 97.565 98.188 98.812 99.419 100.0
REALISASI PEKERJAAN 0.229 0.366 0.304 0.613 1.205 0.808 1.124 1.283 2.283 0.418 0.094 1.676 1.142 3.052 2.815 0.378 1.587 0.958 1.435
KUMULATIF REALISASI PEKERJAAN 0% 0.229 0.595 0.899 1.512 2.717 3.525 4.649 5.932 8.215 8.633 8.727 10.404 11.545 14.598 17.413 17.790 19.378 20.336 21.771
DEVIASI 0.000 0.022 0.003 0.171 0.866 0.006 0.392 0.373 1.372 0.408 0.083 -1.114 -1.643 0.216 -0.021 -2.464 -1.214 -1.839 -1.362
KUMULATIF DEVIASI 0% 0.000 0.022 0.025 0.196 1.062 1.068 1.461 1.834 3.206 3.614 3.697 2.583 0.940 1.155 1.134 -1.330 -2.544 -4.383 -5.745
RENCANA KEMAJUAN PEKERJAAN 3.267 0.105 2.499 2.489 0.105 2.480 2.485 4.457 4.457 4.449 4.454 3.295 3.226 3.308 3.443 3.386 3.376 0.671 0.638 0.662 0.450
ADDENDUM 1

KUMULATIF RENCANA KEMAJUAN PEKERJAAN 0% 49.566 49.671 52.169 54.658 54.763 57.244 59.729 64.186 68.643 73.092 77.546 80.840 84.067 87.374 90.817 94.203 97.579 98.250 98.888 99.550 100.0
REALISASI PEKERJAAN 3.267 0.297 2.345 2.501 0.132 3.183 2.829 4.385 3.608 6.872 4.198 2.507 3.441 1.629
KUMULATIF REALISASI PEKERJAAN 0% 49.566 49.863 52.208 54.708 54.840 58.023 60.852 65.237 68.845 75.717 79.915 82.422 85.863 87.492
DEVIASI 0.000 0.192 -0.154 0.012 0.027 0.703 0.343 -0.072 -0.849 2.424 -0.255 -0.787 0.215 -1.679
ADDENDUM 2

KUMULATIF DEVIASI 0.000 0.192 0.038 0.050 0.077 0.780 1.123 1.050 0.201 2.625 2.370 1.582 1.797 0.118
1.736 1.024 1.024 1.432 1.405 0.963 0.473 0.473
0% RENCANA KEMAJUAN PEKERJAAN
KUMULATIF RENCANA KEMAJUAN PEKERJAAN 0% 93.207 94.231 95.255 96.687 98.092 99.055 99.528 100.0
REALISASI PEKERJAAN 1.736 0.388 1.982 1.524 1.017 0.944 0.519 0.420
KUMULATIF REALISASI PEKERJAAN 0% 93.207 93.594 95.576 97.100 98.117 99.061 99.580 100.0
DEVIASI 0.000 -0.637 0.958 0.092 -0.388 -0.019 0.046 -0.052
KUMULATIF DEVIASI 0% 1/4 waktu 0.000 -0.637 0.321 0.413 0.025 1/2 waktu
3/4 waktu 0.006 0.052 0.000

5,030 % 49,671 % 80,840 %