Anda di halaman 1dari 26

23/LM/PROYEK/COLLECTION/V/22

Hasil ST Minggu Ini


No Lokasi Persentae Cheklist
1 KS2 No. 26 71,48%

2 KS2 No. 39 70,30%

3 KS2 No. 60 69,61%

4 KU2 No. 1 70,20%

Rencana ST Minggu Depan


No Lokasi Progres Pengawas Kontraktor/Mandor Kendala

1 KU3 No. 1 84,90% IMAM EKO

2 KU2 No. 6 88% IMAM JAMILUN

3 KU2 No. 12 88,40% IMAM UDIN

4 KS2 No. 51 84,70% IMAM DASEP

5 KS2 No. 88 68,50% IMAM SOLEH

6 KS1 No. 35 81% IMAM AHMAD

7 KU2 No. 18 75,50% IMAM RISMAWAN

8 KU1 No. 55 77,30% IMAM DINAMIKA

9 KU2 No. 15 76,80% IMAM DINAMIKA

10 KU3 No. 5 77,80% IMAM AGUS


No Pekerjaan Progres Pengawas Kontraktor/Mandor Kendala

1 Lean Concrete 95% IMAM / DIDIT

2 Rigid Pavement 95% IMAM / DIDIT


INERSIA BERKAH USAHA

3 Street Inlet 50% IMAM / DIDIT

4 Kanstin 60% IMAM / DIDIT

MONITORING CUACA MINGGU KE-3 JUNI 2022


Hari/Jam 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00
Senin
Selasa
Rabu
Kamis
Jum’at HJAN
RINGAN
KENDALA MATERIAL
NO
LOCATION DATE AGE (DAYS) PROBLEM PROGRESS CUT OFF
PR/PO

KERAMIK
MASIH ADA OUTSTANDING/MEMINTA 25 JUNI
PR 119 KENCANA 17 FEBRUARI 2022 128 LANTAI KM
GIRO MUNDUR. 2022
MANDI

KENDALA VENDOR DAN KOTRAKTOR


AGE
LOCATION DATE PROBLEM PROGRESS CUT OFF
(DAYS)
VENDOR KUSEN &
PINTU KAYU - MATERIAL
-SUDAH DIPANGGIL MANAGER LAPANGAN DARI
KENCANA 13/04/2022 73 UNTUK ST BULAN APRIL 25 JUNI 2022
VENDOR
& MEI BELUM TERKIRIM
SEMUA

ALL UNIT
9/5/2022 47 KENDALA MATERIAL TERLAMBAT MEMBAYAR DP KEPADA VENDOR 25 JUNI 2022
DINAMIKA

VENDOR CAT
KENCANA 22/05/2022 4 KEKURANGAN BARU DATANG 4 PEL CAT INTERIOR 25 JUNI 2022
MATERIAL

VENDOR PLAFOND
KENCANA 29/05/2022 28 KEKURANGAN SUDAH DIKIRIM SITE MEMO 25 JUNI 2022
MATERIAL
Progres Pemasangan Meter Air
Meter Air Meter Air Meter Air
No Lokasi No Lokasi No Lokasi
1 KU1 51 23 KU2 17 45 KU3 21
2 KU1 57 24 KU1 11 46 KS1 38
3 KU5 15 25 KU2 22 47 KS2 12
4 KU3 25 26 KU3 8 48 KS2 21
5 KU3 27 27 KU3 23 49 KS2 28
6 KU2 5 28 KS2 1 50 KS2 30
7 KU2 26 29 KU2 8 51 KS3 56
8 KU2 27 30 KU2 20 52 KU2 52
9 KU2 29 31 KU2 38 53 KU2 56
10 KU2 50 32 KU3 3 54 KU3 10
11 KU1 50 33 KU2 37 55 KU2 28
12 KU1 58 34 KS1 27 56 KU1 36
13 KU1 60 35 KS1 70 57 KS1 36
14 KS1 29 36 KS2 78 58 KS2 39
15 KU1 56 37 ACACIA 11 59 KU3 1
16 KU1 59 38 ACACIA 21 60 KU3 1
17 KU1 51 39 KU2 1 61 KU3 5
18 KU2 37 40 KU2 2 62 KU3 9
19 KU2 39 41 KU2 32 63 KS2 21
20 KU2 51 42 KU5 3 64 KU3 22
21 KU2 23 43 KU3 15 65 KS2 26
22 KU2 21 44 KU3 19 66 KS2 60
67 KU2 12
Progres Pemasangan KWH
KWH PLN KWH PLN KWH PLN KWH PLN
No Lokasi No Lokasi No Lokasi No Lokasi
1 KU1 50 23 KU2 1 45 KU1 55 67 KS2 25
2 KU1 60 24 KU2 11 46 KU1 68 68 KS2 26
3 KU2 5 25 KU2 17 47 KU2 15 69 KS2 28
4 KU2 26 26 KU2 27 48 KU2 19 70 KS2 30
5 KU2 50 27 KU2 33 49 KU2 31 71 KS2 39
6 KU3 25 28 KU2 37 50 KS3 10 72 KS2 60
7 KU5 7 29 KU3 3 51 KU2 28 73 KS2 78
8 KU5 15 30 KU2 52 52 DK 17 74 KS2 80
9 KU5 1 31 KU2 20 53 DK 38 75 KS3 56
10 KU2 23 32 KU3 33 54 DM 8 76 KU2 7
11 KU3 23 33 KS2 1 55 Acacia 21 77 KU2 35
12 KU3 27 34 KU2 8 56 KU3 1 78 KS2 53
13 KU1 56 35 KU1 59 57 KU3 5 79 KS2 57
14 KU2 22 36 KU5 3 58 KU2 6 80 KS2 59
15 KU2 29 37 KS1 27 59 KS2 21 81 KS2 37
16 KU2 38 38 KU2 2 60 KS2 12 82 KS2 51
17 KU2 39 39 KU2 32 61 KU3 9 83 KS2 76
18 KU2 21 40 KU3 15 62 KU1 36 84
19 KU2 51 41 KU1 59 63 KS1 35 85
20 KU3 8 42 KU3 19 64 KS1 36 86
21 KS1 29 43 KU3 21 65 KS1 38 87
22 KU1 58 44 KU1 53 66 KS1 70 88
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
1 Compound gypsum plafond, KU2 No. 1 Awal Faisal (Project Team) 20/06/2022
2 Finish acian ban-banan tampak belakang, KU3 No. 5 Awal Faisal (Project Team) 20/06/2022
3 Finishing cat pintu, KU3 No. 1 Awal Faisal (Project Team) 20/06/2022
4 Pemasangan keramik carport, KU2 No. 10 Awal Faisal (Project Team) 20/06/2022
5 Pemasangan keramik dinding kamar mandi, KS2 No. 39 Awal Faisal (Project Team) 20/06/2022
6 Pemasangan keramik carport, KU2 No. 30 Awal Faisal (Project Team) 20/06/2022
7 Pemasangan keramik lantai, KS2 No. 88 Awal Faisal (Project Team) 20/06/2022
8 Pemasangan keramik tangga, KS2 No. 57 Awal Faisal (Project Team) 20/06/2022
9 Repair keramik tangga, KU3 No. 5 Awal Faisal (Project Team) 20/06/2022
10 Pemasangan lampu dinding, KU2 No. 1 Awal Supri (Project Team) 20/06/2022
11 Pemasangan lampu dinding, KU3 No. 1 Awal Supri (Project Team) 20/06/2022
12 Finish opening, DM No. 9 Awal Aries (Project Team) 21/06/2022
13 Tes rendam keramik kamar mandi, KS2 No. 51 Awal Faisal (Project Team) 21/06/2022
14 Tes rendam keramik kamar mandi, KS2 No. 88 Awal Faisal (Project Team) 21/06/2022
15 Tes rendam wp dak talang, KU2 NO. 9 Awal Faisal (Project Team) 21/06/2022
16 Tes rendam wp dak talang, KU2 NO. 16 Awal Faisal (Project Team) 21/06/2022
17 Tes fungsi elektrikal, KU2 No. 1 Awal Supri (Project Team) 21/06/2022
18 Tes fungsi sanitary, KS2 No. 26 Awal Faisal (Project Team) 21/06/2022
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
19 Tes fungsi sanitary, KU2 No. 1 Awal Faisal (Project Team) 22/06/2022
20 Tes gelontor dak talang, KS2 No. 51 Awal Faisal (Project Team) 22/06/2022
21 Tes gelontor dak talang, KS2 No. 60 Awal Faisal (Project Team) 22/06/2022
22 Tes gelontor kamar mandi, KS2 No. 51 Awal Faisal (Project Team) 22/06/2022
23 Tes rendam pipa, KS2 No. 51 Awal Faisal (Project Team) 22/06/2022
24 Tes rendam pipa, KU2 No. 15 Awal Faisal (Project Team) 22/06/2022
25 Serah Terima kepada Town Management, KS2 No. 26 Awal Imam (Project Team) 22/06/2022
26 Hasil ceklist finishing, KS2 No. 26 (71,48%) Awal Imam (Project Team) 22/06/2022
27 Pemasangan lampu downlight, KS2 No. 39 Awal Supri (Project Team) 22/06/2022
28 Compound gypsum plafond, KU2 No. 16 Awal Faisal (Project Team) 23/06/2022
29 Finishing cat eksterior, KS2 No. 39 Awal Faisal (Project Team) 23/06/2022
30 Pemasangan asksesoris pintu, KU2 No. 1 Awal Faisal (Project Team) 23/06/2022
31 Pemasangan kusen alumunium kamar utama, KU2 No. 18 Awal Faisal (Project Team) 23/06/2022
32 Repair balok kamar belakang, KU2 No. 12 Awal Faisal (Project Team) 23/06/2022
33 Sealant kusen alumunium, KS2 No. 51 Awal Faisal (Project Team) 23/06/2022
34 Tes gelontor drain AC, KS2 No. 39 Awal Faisal (Project Team) 23/06/2022
35 Tes gelontor drain AC, KS2 No. 60 Awal Faisal (Project Team) 23/06/2022
36 Pemasangan aksesoris listrik, KU3 No. 1 Awal Supri (Project Team) 23/06/2022
37 Serah Terima kepada Town Management, Parkiran Insitu Awal Imam (Project Team) 24/06/2022
38 Tes fungsi sanitary, KS2 No. 39 Awal Imam (Project Team) 24/06/2022
39 Tes fungsi sanitary, KS2 No. 60 Awal Imam (Project Team) 24/06/2022
40 Tes fungsi sanitary, KU2 No. 1 Awal Imam (Project Team) 24/06/2022
41 Serah Terima kepada Town Management, KS2 No. 39 Awal Imam (Project Team) 24/06/2022
42 Hasil checklist finishing, KS2 No. 39 (70, 3%) Awal Imam (Project Team) 24/06/2022
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
43 Serah Terima kepada Town Management, KS2 No. 60 Awal Imam (Project Team) 24/06/2022
44 Hasil checklist finishing, KS2 No. 60 (69, 61%) Awal Imam (Project Team) 24/06/2022
45 Serah Terima kepada Town Management, KS2 No. 39 Awal Imam (Project Team) 24/06/2022
46 Hasil checklist finishing, KS2 No. 39 (70, 3%) Awal Imam (Project Team) 24/06/2022
47 Pemasangan aksesoris listrik, KS2 No. 60 Awal Supri (Project Team) 24/06/2022
48 Tes fungsi elektrikal, KS2 No. 60 Awal Supri (Project Team) 24/06/2022
49 Tes fungsi elektrikal, KU3 No. 1 Awal Supri (Project Team) 24/06/2022
Foto Progres Pekerjaan Sampai 25 Juni 2022

1. Compound gypsum plafond, KU2 No. 1 2. Finish acian ban-banan tampak 3. Finishing cat pintu, KU3 No. 1
belakang, KU3 No. 5

4. Pemasangan keramik carport, KU2 No. 5. Pemasangan keramik dinding kamar 6. Pemasangan keramik carport, KU2 No.
10 mandi, KS2 No. 39 30
Foto Progres Pekerjaan Sampai 25 Juni 2022

7. Pemasangan keramik lantai, KS2 No. 88 8. Pemasangan keramik tangga, KS2 No. 9. Repair keramik tangga, KU3 No. 5
57

10. Pemasangan lampu dinding, KU2 No. 1 11. Pemasangan lampu dinding, KU3 No. 1 12. Finish opening, DM No. 9
Foto Progres Pekerjaan Sampai 25 Juni 2022

13. Tes rendam keramik kamar mandi, KS2 14. Tes rendam keramik kamar mandi, KS2 15. Tes rendam wp dak talang, KU2 NO. 9
No. 51 No. 88

16. Tes rendam wp dak talang, KU2 NO. 16 17. Tes fungsi elektrikal, KU2 No. 1 18. Tes fungsi sanitary, KS2 No. 26
Foto Progres Pekerjaan Sampai 25 Juni 2022

19. Tes fungsi sanitary, KU2 No. 1 20. Tes gelontor dak talang, KS2 No. 51 21. Tes gelontor dak talang, KS2 No. 60

22. Tes gelontor kamar mandi, KS2 No. 51 23. Tes rendam pipa, KS2 No. 51 24. Tes rendam pipa, KU2 No. 15
Foto Progres Pekerjaan Sampai 25 Juni 2022

2 5 . S e r a h Te r i m a k e p a d a To w n 26. Hasil ceklist finishing, KS2 No. 26 27. Pemasangan lampu downlight, KS2
Management, KS2 No. 26 (71,48%) No. 39

28. Compound gypsum plafond, KU2 No. 16 29. Finishing cat eksterior, KS2 No. 39 30. Pemasangan asksesoris pintu, KU2 No. 1
Foto Progres Pekerjaan Sampai 25 Juni 2022

31. Pemasangan kusen alumunium kamar 32. Repair balok kamar belakang, KU2 No. 12 33. Sealant kusen alumunium, KS2 No. 51
utama, KU2 No. 18

34. Tes gelontor drain AC, KS2 No. 39 35. Tes gelontor drain AC, KS2 No. 60 36. Pemasangan aksesoris listrik, KU3 No.
1
Foto Progres Pekerjaan Sampai 25 Juni 2022

3 7 . S e r a h Te r i m a k e p a d a To w n 38. Tes fungsi sanitary, KS2 No. 39 39. Tes fungsi sanitary, KS2 No. 60
Management, Parkiran Insitu

40. Tes fungsi sanitary, KU2 No. 1 4 1 . S e r a h Te r i m a k e p a d a To w n 42. Hasil checklist finishing, KS2 No. 39
Management, KS2 No. 39 (70, 3%)
Foto Progres Pekerjaan Sampai 25 Juni 2022

4 3 . S e r a h Te r i m a k e p a d a To w n 44. Hasil checklist finishing, KS2 No. 60 4 5 . S e r a h Te r i m a k e p a d a To w n


Management, KS2 No. 60 (69, 61%) Management, KS2 No. 39

46. Hasil checklist finishing, KS2 No. 39 (70, 47. Pemasangan aksesoris listrik, KS2 No. 48. Tes fungsi elektrikal, KS2 No. 60
3%) 60
Foto Progres Pekerjaan Sampai 25 Juni 2022

49. Tes fungsi elektrikal, KU3 No. 1


Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Selatan 2 No. 26

Genteng Penutup Atap Finishing Dak Talang

Roof Drain Lisplang


Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Selatan 2 No. 26

Depan Kanan

Belakang Kiri
Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Selatan 2 No. 39

Genteng Penutup Atap Finishing Dak Talang

Roof Drain Lisplang


Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Selatan 2 No. 39

Sisi Depan Depan

Samping Kanan/Kiri Belakang


Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Selatan 2 No. 60

Genteng Penutup Atap Finishing Dak Talang

Roof Drain Lisplang


Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Selatan 2 No. 60

Depan Belakang

Belakang Sisi Kiri


Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Utara 2 No. 1

Genteng Penutup Atap Finishing Dak Talang

Roof Drain Lisplang


Created by : Approved by :

Awaludin Mawardani Paksi Handoyo


Project Manager Deputy General Manger