37/LM/PROYEK/COLLECTION/IX/22

Hasil ST Minggu Ini


No Lokasi Persentae Cheklist
1 KS1 No. 63 82.3%

Rencana ST Minggu Depan

No Lokasi Progres Pengawas Kontraktor/Mandor Kendala

1 KU3 No. 18 86, 50 % IMAM TEGUH

2 KU3 No. 20 76,50 % IMAM TEGUH

3 KS2 No. 57 83,50 % IMAM TEGUH


MONITORING CUACA MINGGU KE-4 SEPTEMBER 2022
Hari/Jam 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00
Senin
Selasa
Rabu
Kamis
Jum’at
KENDALA VENDOR DAN KOTRAKTOR
AGE
LOCATION DATE PROBLEM PROGRESS CUT OFF
(DAYS)
MANDOR AHMAD SUDAH DIKIRIM SITE MEMO, SEBAGIAN UNIT 01 OKTOBER
KENCANA 04/07/2022 89
TIDAK ADA PEKERJA SUDAH TAKE OVER KONTRAKTOR 2022
VENDOR CAT PEKERJA
HANYA 1 DAN 01 OKTOBER
KENCANA 10/08/2022 52 REKOMENDASI CUT OFF SPK KEDADA QS
KEKURANGAN CAT 2022
EXTERIOR
MANDOR HERU BEBERAPA BELUM ADA MANDOR, PROSES QS 01 OKTOBER
KENCANA 10/08/2022 52
TIDAK ADA PEKERJA MENCARI PENGGANTI 2022
KURANGNYA MAN SUDAH DIKIRIM SITE MEMO, SUDAH ADA
01 OKTOBER
KENCANA 24/08/2022 38 POWER DI UNIT PENAMBAHAN MAN POWER
2022
MANDOR TEGUH
Progres Pemasangan Meter Air
Meter Air Meter Air Meter Air Meter Air Meter Air
No Lokasi No Lokasi No Lokasi No Lokasi No Lokasi
1 KU1 51 23 KU2 17 45 KU3 21 67 KU2 12 89 KU1 53
2 KU1 57 24 KU1 11 46 KS1 38 68 KU2 6 90 KS2 76
3 KU5 15 25 KU2 22 47 KS2 12 69 KU2 12 91 KS2 88
4 KU3 25 26 KU3 8 48 KS2 21 70 KU2 18 92 KU2 36
5 KU3 27 27 KU3 23 49 KS2 28 71 KU1 35 93 KS3 2
6 KU2 5 28 KS2 1 50 KS2 30 72 KU2 10 94 KS1 58
7 KU2 26 29 KU2 8 51 KS3 56 73 KU2 16 95 KS1 52
8 KU2 27 30 KU2 20 52 KU2 52 74 KU3 2 96 KS1 60
9 KU2 29 31 KU2 38 53 KU2 56 75 KU3 2 97 KS1 66
10 KU2 50 32 KU3 3 54 KU3 10 76 KU3 6 98 KS2 80
11 KU1 50 33 KU2 37 55 KU2 28 77 KU3 12 99 KU1 68
12 KU1 58 34 KS1 27 56 KU1 36 78 KU3 16 100 KU1 52
13 KU1 60 35 KS1 70 57 KS1 36 79 KU1 55 101 KS1 63
14 KS1 29 36 KS2 78 58 KS2 39 80 KU2 15
15 KU1 56 37 ACACIA 11 59 KU3 1 81 KU3 18
16 KU1 59 38 ACACIA 21 60 KU3 1 82 KU3 17
17 KU1 51 39 KU2 1 61 KU3 5 83 KU3 28
18 KU2 37 40 KU2 2 62 KU3 9 84 KU2 9
19 KU2 39 41 KU2 32 63 KS2 21 85 KU2 7
20 KU2 51 42 KU5 3 64 KU3 22 86 KU2 19
21 KU2 23 43 KU3 15 65 KS2 26 87 KU2 30
22 KU2 21 44 KU3 19 66 KS2 60 88 KU2 31
Progres Pemasangan KWH Meter Listrik
KWH Meter Listrik KWH Meter Listrik KWH Meter Listrik KWH Meter Listrik KWH Meter Listrik KWH Meter Listrik
No Lokasi No Lokasi No Lokasi No Lokasi No Lokasi No Lokasi
1 KU1 50 23 KU2 1 45 KU1 55 67 KS2 25 89 KS2 82 111 KU3 17
2 KU1 60 24 KU2 11 46 KU1 68 68 KS2 26 90 KS3 31
3 KU2 5 25 KU2 17 47 KU2 15 69 KS2 28 91 KS2 88
4 KU2 26 26 KU2 27 48 KU2 19 70 KS2 30 92 KS1 60
5 KU2 50 27 KU2 33 49 KU2 31 71 KS2 39 93 KU3 13
6 KU3 25 28 KU2 37 50 KS3 10 72 KS2 60 94 KU3 16
7 KU5 7 29 KU3 3 51 KU2 28 73 KS2 78 95 KU3 18
8 KU5 15 30 KU2 52 52 DK 17 74 KS2 80 96 KU1 52
9 KU5 1 31 KU2 20 53 DK 38 75 KS3 56 97 KU2 56
10 KU2 23 32 KU3 33 54 DM 8 76 KU2 7 98 KS3 66
11 KU3 23 33 KS2 1 55 Acacia 21 77 KU2 35 99 KS1 63
12 KU3 27 34 KU2 8 56 KU3 1 78 KS2 53 100 KS1 61
13 KU1 56 35 KU1 59 57 KU3 5 79 KS2 57 101 KU2 30
14 KU2 22 36 KU5 3 58 KU2 6 80 KS2 59 102 KU2 9
15 KU2 29 37 KS1 27 59 KS2 21 81 KS2 37 103 KU3 6
16 KU2 38 38 KU2 2 60 KS2 12 82 KS2 51 104 KS3 2
17 KU2 39 39 KU2 32 61 KU3 9 83 KS2 76 105 DM 9
18 KU2 21 40 KU3 15 62 KU1 36 84 KU2 10 106 DR 20
19 KU2 51 41 KU1 59 63 KS1 35 85 KU2 12 107 KS5 18
20 KU3 8 42 KU3 19 64 KS1 36 86 KU2 16 108 KU2 36
21 KS1 29 43 KU3 21 65 KS1 38 87 KU2 18 109 KS1 52
22 KU1 58 44 KU1 53 66 KS1 70 88 KU3 2 110 KS1 66
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
1 Tes gelontor dak talang, KS2 No. 70 Awal Faisal (Project Team) 26/09/2022
2 Tes gelontor drain AC, KS2 No. 70 Awal Faisal (Project Team) 26/09/2022
3 Tes gelontor kamar mandi, KS2 No. 70 Awal Faisal (Project Team) 26/09/2022
4 Tes rendam pipa, KS2 No. 70 Awal Faisal (Project Team) 26/09/2022
5 Tes gelontor dak talang, KU3 No. 16 Awal Faisal (Project Team) 26/09/2022
6 Tes gelontor dak talang, KU3 No. 18 Awal Faisal (Project Team) 26/09/2022
7 Tes gelontor dak talang, KU3 No. 26 Awal Faisal (Project Team) 26/09/2022
8 Finish cat, DR No. 20 Awal Irman (Project Team) 26/09/2022
9 Keramik lantai kamar mandi, KS1 No. 65 Awal Irman (Project Team) 26/09/2022
10 Serah terima kepada Town Management, Shopping Street Pasar Alam Awal Didit (Project Team) 27/09/2022
11 Serah terima kepada Town Management, Turap Batu Kali H Djole Awal Didit (Project Team) 27/09/2022
12 Acian dinding pagar belakang, KU3 No. 20 Awal Faisal (Project Team) 27/09/2022
13 Finish acian bawah meja dapur, KU3 No. 28 Awal Faisal (Project Team) 27/09/2022
14 Finish acian pedestal, KS2 No. 57 Awal Faisal (Project Team) 27/09/2022
15 Finish tali air dinding, KS2 No. 53 Awal Faisal (Project Team) 27/09/2022
16 Pemasangan keramik carport, KS2 No. 70 Awal Faisal (Project Team) 27/09/2022
17 Pemasangan keramik carport, KU3 No. 20 Awal Faisal (Project Team) 27/09/2022
18 Pemasangan keramik lantai kamar mandi lantai 1, KU3 No. 26 Awal Faisal (Project Team) 27/09/2022
19 Pemasangan keramik tangga, KU3 No. 28 Awal Faisal (Project Team) 27/09/2022
20 Pemasangan kusen alumunium, KS2 No. 70 Awal Faisal (Project Team) 27/09/2022
21 Pengecatan dinding, KU3 No. 18 Awal Faisal (Project Team) 27/09/2022
22 Repair openingan jendela koridor, KU3 No. 20 Awal Faisal (Project Team) 27/09/2022
23 Pemasangan lampu downlight, KS2 No. 53 Awal Supri (Project Team) 27/09/2022
24 Tes tekan air bersih, KS1 No. 63 Awal Supri (Project Team) 27/09/2022
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
25 Acian tali air dinding, KS2 No. 53 Awal Faisal (Project Team) 28/09/2022
26 Compound plafond listplank, KS2 No. 70 Awal Faisal (Project Team) 28/09/2022
27 Pemasangan hebel pedestrial, KS2 No. 70 Awal Faisal (Project Team) 28/09/2022
28 Pemasangan keramik lantai kamar mandi lantai 2, KS2 No. 53 Awal Faisal (Project Team) 28/09/2022
29 Pemasangan keramik tangga, KS2 No. 70 Awal Faisal (Project Team) 28/09/2022
30 Pemasangan kusen alumunium, KS2 No. 53 Awal Faisal (Project Team) 28/09/2022
31 Pengecetan dinding tampak depan, KU2 No. 9 Awal Faisal (Project Team) 28/09/2022
32 Tes gelontor dak talang, KS3 No. 33 Awal Faisal (Project Team) 28/09/2022
33 Tes rendam dak talang, KS3 No. 33 - 2 Awal Faisal (Project Team) 28/09/2022
34 Tes rendam dak talang, KS3 No. 33 Awal Faisal (Project Team) 28/09/2022
35 Finishing cat tampak depan, DR No. 20 Awal Irman (Project Team) 28/09/2022
36 Pemasangan keramik meja dapur, KS1 No. 65 Awal Irman (Project Team) 28/09/2022
37 Serah terima kepada Town Management, KS1 No. 63 Awal Faisal (Project Team) 30/09/2022
38 Hasil checklist finishing, KS1 No. 63 (82.3%) Awal Faisal (Project Team) 30/09/2022
39 Pengecatan, Green Line Kencana Awal Imam (Project Team) 30/09/2022
40 Finishing cat tampak, DM No. 9 Awal Irman (Project Team) 30/09/2022
41 Finishing cat dinding belakang, DM No. 9 Awal Irman (Project Team) 30/09/2022
42 Finishing cat tampak belakang, DM No. 9 Awal Irman (Project Team) 01/10/2022
43 Pemasangan keramik carport, KS1 No. 65 Awal Irman (Project Team) 01/10/2022
44 Finish acian bak kontrol, KS2 No. 70 Awal Faisal (Project Team) 01/10/2022
45 Finish ekspos bawah tangga, KS2 No. 70 Awal Faisal (Project Team) 01/10/2022
46 Hamplas pintu kayu, KU3 No. 20 Awal Faisal (Project Team) 01/10/2022
47 Pemasangan hebel siripan tampak depan, KU3 No. 26 Awal Faisal (Project Team) 01/10/2022
48 Pemasangan pagar pembatas, KS2 No. 59 Awal Faisal (Project Team) 01/10/2022
49 Repair dinding kamar anak lantai 2, KS2 No. 53 Awal Faisal (Project Team) 01/10/2022
Foto Progres Pekerjaan Sampai 01 Oktober 2022

1. Tes gelontor dak talang, KS2 No. 70 2. Tes gelontor drain AC, KS2 No. 70 3. Tes gelontor kamar mandi, KS2 No. 70

4. Tes rendam pipa, KS2 No. 70 5. Tes gelontor dak talang, KU3 No. 16 6. Tes gelontor dak talang, KU3 No. 18
Foto Progres Pekerjaan Sampai 01 Oktober 2022

7. Tes gelontor dak talang, KU3 No. 26 8. Finish cat, DR No. 20 9. Keramik lantai kamar mandi,
KS1 No. 65

1 0 . S e r a h t e r i m a k e p a d a To w n 1 1 . S e r a h t e r i m a k e p a d a To w n 12. Acian dinding pagar belakang, KU3 No.


Management, Shopping Street Pasar Alam Management, Turap Batu Kali H Djole 20
Foto Progres Pekerjaan Sampai 01 Oktober 2022

13. Finish acian bawah meja dapur, 14. Finish acian pedestal, KS2 No. 57 15. Finish tali air dinding, KS2 No. 53
KU3 No. 28

16. Pemasangan keramik carport, 17. Pemasangan keramik carport, 18. Pemasangan keramik lantai kamar
KS2 No. 70 KU3 No. 20 mandi lantai 1, KU3 No. 26
Foto Progres Pekerjaan Sampai 01 Oktober 2022

19. Pemasangan keramik tangga, KU3 No. 28 20. Pemasangan kusen alumunium, KS2 21. Pengecatan dinding, KU3 No. 18
No. 70

22. Repair openingan jendela koridor, 23. Pemasangan lampu downlight, 24. Tes tekan air bersih, KS1 No. 63
KU3 No. 20 KS2 No. 53
Foto Progres Pekerjaan Sampai 01 Oktober 2022

25. Acian tali air dinding, KS2 No. 53 26. Compound plafond listplank, KS2 No. 27. Pemasangan hebel pedestrial, KS2 No.
70 70

28. Pemasangan keramik lantai kamar 29. Pemasangan keramik tangga, KS2 No. 70 30. Pemasangan kusen alumunium,
mandi lantai 2, KS2 No. 53 KS2 No. 53
Foto Progres Pekerjaan Sampai 01 Oktober 2022

31. Pengecetan dinding tampak depan,


KU2 No. 9 32. Tes gelontor dak talang, KS3 No. 33 33. Tes rendam dak talang, KS3 No. 33 - 2

34. Tes rendam dak talang, KS3 No. 33 35. Finishing cat tampak depan, 36. Pemasangan keramik meja dapur,
DR No. 20 KS1 No. 65
Foto Progres Pekerjaan Sampai 01 Oktober 2022

37. Serah terima kepada Town Management, 38. Hasil checklist finishing, KS1 No. 63 39. Pengecatan, Green Line Kencana
KS1 No. 63 (82.3%)

40. Finishing cat tampak, DM No. 9 41. Finishing cat dinding belakang, DM 42. Finishing cat tampak belakang,
No. 9 DM No. 9
Foto Progres Pekerjaan Sampai 01 Oktober 2022

43. Pemasangan keramik carport, KS1 No. 65 44. Finish acian bak kontrol, KS2 No. 70 45. Finish ekspos bawah tangga,
KS2 No. 70

46. Hamplas pintu kayu, KU3 No. 20 47. Pemasangan hebel siripan tampak 48. Pemasangan pagar pembatas, KS2 No.
depan, KU3 No. 26 59
Foto Progres Pekerjaan Sampai 01 Oktober 2022

49. Repair dinding kamar anak lantai 2, KS2 50. Pemasangan meter air, KS1 No. 63
No. 53
Pengecekan Pekerjaan Finishing Dak Talang
Cluster Kencana, Jalan Kencana Selatan 1 No. 63

Roof Tile Finishing Dak Talang Depan

List Plank Belakang


Roof Drain
Created by : Approved by :

Awaludin Mawardani Paksi Handoyo


Project Manager Deputy General Manger