TO :
• PROJECT MANAGER PEKERJAAN JASA EPC DESALINASI DAN DEMINERALISASI WATER SUMBAWA
• TIM PT AMMIN
UP TO OKTOBER 2023
WEEK – 13 ( 19 s.d 25 September 2022)
Disiapkan oleh: Diperiksa oleh : Disetujui oleh:
WEEKLY PROGRES
No Descriptions Volume Unit Bobot Last Week This Week Comulative Deviation Remark
3 Pre - Treatment 1 Ls 16.08% 0.0000% 0.0000% 0.0000% 2.0432% 0.0000% 1.4376% -1.4376%
4 Main Treatment 1 Ls 36.55% 0.0000% 0.0000% 0.0000% 6.9936% 0.0000% 6.9936% -6.9936%
5 Post Treatment 1 Ls 4.21% 0.0000% 0.0000% 0.0000% 0.5298% 0.0000% 0.5298% -0.5298%
6 Waste Water Treatment 1 Ls 0.50% 0.0000% 0.0000% 0.0000% 0.0394% 0.0000% 0.0394% -0.0394%
7 Electrikal & Instrumentasi 1 Ls 16.32% 0.0000% 0.0000% 0.0000% 0.4876% 0.0000% 0.4876% -0.4876%
3 Bangunan ruang pompa 0.0000% Belum dapat mengerjakan pekerjaan, Menunggu finalisasi AMNT
0.1773% masih menunggu finalisasi AMNT
11 Cartridge RO CIP Module kap 288 0.0380% 0.0000% Belum bisa release PO, menunggu finalisasi AMNT Menunggu finalisasi AMNT
m3/jam
Progress tidak tercapai
(Post Treatment)
NO Uraian Pekerjaan Plan (%) Aktual (%) Penyebab Tindaklanjut
12 Pompa Regenerasi MBP Regen 0.0500% 0.0000% Belum bisa release PO, menunggu finalisasi AMNT Menunggu finalisasi
Pumps kap. 8 m3/hr @5 bar AMNT
13 Tangki Kimia HCl 2 m3 HDPE 0.0022% 0.0000% Belum bisa release PO, menunggu finalisasi AMNT Menunggu finalisasi
AMNT
14 Tangki Kimia NaOH 3 m3 HDPE 0.0036% 0.0000% Belum bisa release PO, menunggu finalisasi AMNT Menunggu finalisasi
AMNT
15 Fume scrubber 0.0126% 0.0000% Belum bisa release PO, menunggu finalisasi AMNT Menunggu finalisasi
AMNT
(Waste Water
Treatment)
NO Uraian Pekerjaan Plan (%) Aktual (%) Penyebab Tindaklanjut
1 Pompa Transfer Wastewater kap 5 Belum bisa release PO, menunggu Menunggu finalisasi AMNT
m3/jam @4 bar SS316 0.0394 0.0000% finalisasi AMNT
(Waste Water
Treatment)
NO Uraian Pekerjaan Plan (%) Aktual (%) Penyebab Tindaklanjut
1 Transformer
0.3916% 0.0000% Belum bisa release PO, menunggu Menunggu finalisasi AMNT
finalisasi AMNT
2 LVMDP 0.0360% 0.0000% Belum bisa release PO, menunggu Menunggu finalisasi AMNT
finalisasi AMNT
3 Panel ATS Belum bisa release PO, menunggu Menunggu finalisasi AMNT
0.0332% 0.0000% finalisasi AMNT
4 'Panel MCC
0.0268% 0.0000% Belum bisa release PO, menunggu Menunggu finalisasi AMNT
finalisasi AMNT
PLAN PROGRESS
Data Belum Bisa Release PO
Data Belum Bisa Release PO
Data Belum Bisa Release PO
Data yang akan Release PO
Last Activity
1 Pekerjaan pagar :
- Pemasangan kawat BRC 28/9/2022
Open
- Fabrikasi gerbang 29/9/2022
- Pemasangan gerbang on site 30/9/2022
7 Pengajuan data :
1. BRMS Tenaga security
2/10/2022 Open
2. Pengajuan Mobil Escort
3. Pengajuan Pelatihan Perancah
8 Release PO :
1. Housing vessel SWRO ROPV
2. Membran SWRO type
SW30HRLE-440
29/9/2022 Open
3. Housing vessel BWRO ROPV
4. Membran BWRO type BW30-400
5. Resin Cation H
6. Resin Anion OH
LAPORAN HSE
Weekly SHES Performance & Statistics Report (Week 5)
Period: Sept 17th - Sept 23th , 2022
29
Day of
Tool Non Conformance B 1 work
1. Boox 24 7 31 6. K3L/ anomaly 0 0
7 36
Kali 0 Kali ( a) ( b) (c) =( a+b )
(akumulatif jumlah laporan
harian)
3.290,00
K3L Inspeksi
2. Meeting 2 1 3 7. K3L 0 0 B 2 Manho
urs
1.078,00 4.368,00 121,33
Kali 0 Kali
0
B 5 Occupational
Ilness
0 0,00
Monitoring
5. linkg 0 0 0 10. JHA 3 7 (m) (n) (o)= (m +n )
(akumulatif jumlah laporan harian)
Kali 4 Kali
Weekly Performance and Statistic EHS
Period 17 – 23 September 2022
0
Period 17 - 23 September 2022
Manpower VS Manhours
6000
5000
4000
3000
2000
1000
0
week 1 week 2 week 3 week 4 week 5
Manhours 584 2090 2362 3290 4368
Manpower 85 204 311 443 593
Period 17 - 23 September 2022
WEATHER
10
9
8
7
6
5
4
3
2
1
0
week 1 week 2 week 3 week 4 week 5
Sunny 8 8 8 8 9
Rainy 0 0 2 1.5 1
SHES CONCERNS
1. Implementation fences
PPE(Need safety Goolges & gloves)
2. Foundation direction keet
- molen machine
3. Temporary Building
- Post Security
- Toilet portable
4. Safety sign need to apply at site area project
- Area for Material
LAPORAN HR
Team KTI :
Team PHB :
Team KK :
LAPORAN HR
Tenaga kerja lokal :
Worker PHB :
LAPORAN HR
Security
LAPORAN HR
Tenaga kerja lokal pekerjaan direksi keet :
Dapat kami informasikan dari total jumlah Tenaga Staff PHB : 9 orang, Staff KTI : 3 Orang,
Konsultan KK : 4 Orang, Tenaga kerja local : 17 orang, Worker PHB : 8 orang, Worker sondir
boring : 4 orang, security : 1 orang
LAPORAN HR (Belum Safety Induction)
Worker PHB :
DOKUMENTASI
Daily Morning TBM
Monitoring of KTI activity
Monitoring & HSE Meeting
Dokumentasi
Pekerjaan pemasangan kawat harmonika
Dokumentasi