Contract No:

PT. TRANSPORTASI GAS INDONESIA -

Document No:
GS3473-PM-MR-G-001
PT. PRATIWI PUTRI SULUNG
Page 1 of 5

UPGRADING H2S ANALYZER AT SIMPANG ABADI METERING STATION

MONTHLY REPORT KE – 1
PERIODE 19 JUNI – 03 JULI 2020

Approved

Approved With Comment

Resubmit For Approval

Reviewed (Not For Approval)

Reviewed With Comment


NOTES:
APPROVAL OF THIS DOCUMENT WILL NOT RELIEVE
KONTRAKTOR FROM ITS OBLIGATION TO COMPLETE
ALL THE WORK IN ACCORDANCE WITH THE TERMS AND
CONDITIONS OF THE CONTRACT

TGI-ENG TGI-PM

0 03-07-2020 ISSUED FOR APPROVAL DFI EAN BAS

DISIAPKAN DIPERIKSA DISETUJUI

Rev. Tanggal Uraian PT.PRATIWI PUTRI SULUNG


DAFTAR ISI
1 EXECUTIVE SUMMARY (PROGRESS TO DATE) .................................................................................... 3
2 PROGRESS SUMMARY (PROGRESS THIS PERIODE) .......................................................................... 3
2.1 PEKERJAAN PERSIAPAN ....................................................................................................................... 3
2.2 ENGINEERING ........................................................................................................................................... 3
2.3 PEKERJAAN PENGADAAN BARANG ................................................................................................. 3
2.4 PEKERJAAN KONSTRUKSI.................................................................................................................... 4
2.5 TESTING AND COMMISSIONING........................................................................................................ 4
2.6 PEKERJAAN AKHIR ................................................................................................................................. 4
3 ACTIVITY THIS PERIOD ....................................................................................................................................... 4
4 ACTIVITIES PLANNED FOR NEXT MONTH ............................................................................................ 4
5 HSE STATISTIK .................................................................................................................................................. 4
6 AREAS OF CONCERNS ..................................................................................................................................... 5
7 LAMPIRAN ........................................................................................................................................................... 5
7.1 HSE STATISTIK ......................................................................................................................................... 5
7.2 LAPORAN KEMAJUAN PROGRESS & S CURVE .............................................................................. 5
7.3 LAMPIRAN LAINNYA .............................................................................................................................. 5
PROJECT REPORT WEEKLY/BIWEEKLY/MONTHLY
TGI-WP-16-03-FO7

1. EXECUTIVE SUMMARY (PROGRESS TO DATE)


Dari rencana akumulasi progress 0,80%, total akumulasi progress pada periode ini sebesar 0,48%, dengan perincian :
Pekerjaan Persiapan 0,00% dari plan 0,80% deviasi -0,80%
Engineering 0,48% dari plan 0,00% deviasi 0,48%
Pekerjaan Pengadaan Barang 0,00% dari plan 0,00% deviasi 0,00%
Pekerjaan Konstruksi 0,00% dari plan 0,00% deviasi 0,00%
Testing dan Commisioning 0,00% dari plan 0,00% deviasi 0,00%
Pekerjaan Akhir 0,00% dari plan 0,00% deviasi 0,00%
2. PROGRESS SUMMARY (PROGRESS THIS PERIODE)

Dari rencana progress 0,80%, progress pada periode ini sebesar 0,48%, dengan perincian :

Pekerjaan Persiapan 0,00% dari plan 0,80% deviasi -0,80%


0,48% dari plan 0,00% deviasi 0,48%
Engineering
0,00% dari plan 0,00% deviasi 0,00%
Pekerjaan Pengadaan Barang
0,00% dari plan 0,00% deviasi 0,00%
Pekerjaan Konstruksi
0,00% dari plan 0,00% deviasi 0,00%
Testing dan Commisioning
0,00% dari plan 0,00% deviasi 0,00%
Pekerjaan Akhir
3. ACTIVITY THIS PERIOD
1. Penandatangan kontrak kerja pada tanggal 9 Juni 2020.
2. Pelaksanaan Kick Off Meeting pada tanggal 25 Juni 2020.
3. Submit dokumen engineering terutama yang terkait dengan survey lapangan dan peralatan utama.

4. ACTIVITIES PLANNED FOR NEXT WEEK/TWO WEEKS/MONTH


1. Submit dokumen engineering (Continue) terutama yang berkaitan dengan material utama.
2. Pembelian semua material sesuai dengan kontrak.
3. Pelaksanaan survey lapangan.

5. INFORMATION RECEIVED/REQUIRED FROM CLIENT

6. AREAS OF CONCERNS
1. Terkait dengan Pandemic COVID-19, proses untuk mendapatkan izin masuk ke area lapangan kerja/station harus mengikuti protokol alur skrining personil masuk ke Lokasi
Proyek.
2.Kemungkinan diperlukannya isolasi mandiri 14 hari kalender untuk mendapatkan surat sehat dari Rumah Sakit/PUSKESMAS daerah setempat.

7. ATTACHMENTS

1. Laporan kemajuan Monthly report ke 1


2. Project S curve
3. HSE Statistik
4. weekly report 1 - 3

ISSUED BY :
Contractor's Project Control : Dara Febrinna Irawani SIGNATURE :

Contractor's Project Manager : Bambang Andrianto SIGNATURE :

APPROVED BY :
TGI Project Manager : M. Abdul Mudlil SIGNATURE :

DATE OF CONT :
1 EXECUTIVE SUMMARY (PROGRESS TO DATE)
Pada periode ini adalah laporan bulanan (Monthly report) pertama dari kontrak kerja antara
PT. Transportasi Gas Indonesia (“TGI”) dengan PT. Pratiwi Putri Sulung (“PPS”) untuk pekerjaan
“Upgrading H2S Analyzer at Simpang Abadi Metering Station” dengan penandatanganan
kontrak pada tanggal 19 Juni 2020 dan Kick Off Meeting pada tanggal 25 Juni 2020.

Pada periode 19 Juni – 03 Juli 2020 kemajuan pekerjaan adalah sebesar 0,48% dari rencana
0,80% dengan deviasi -0,32%. Adapun rincian kemajuan pekerjaan sebagai berikut :
Progress
WB Weight
Description Unit Qty To Date PLAN DEVIASI
S Factor
%Progress % WF
A Pekerjaan Persiapan 0.80% 0.00% 0.00% 0.80% -0.80%
Survey Lapangan Ls 1 0.80% 0.00% 0.00% 0.80% -0.80%
B Engineering 1 1.75% 27.14% 0.48% 0.00% 0.48%
Engineering Ls 1 1.75% 27.14% 0.48% 0.00% 0.48%
C Pekerjaan Pengadaan Barang 79.51% 0.00% 0.00% 0.00% 0.00%
Pengadaan Material Ls 1 79.51% 0.00% 0.00% 0.00% 0.00%
D Pekerjaan Konstruksi 11.85% 0.00% 0.00% 0.00% 0.00%
Mobilisasi Material Ls 1 1.56% 0.00% 0.00% 0.00% 0.00%
Pekerjaan Pemasangan Ls 1 10.29% 0.00% 0.00% 0.00% 0.00%
E Testing dan Commisioning 3.36% 0.00% 0.00% 0.00% 0.00%
Pekerjaan Pengetesan Ls 1 3.36% 0.00% 0.00% 0.00% 0.00%
F Pekerjaan Akhir 2.73% 0.00% 0.00%% 0.00% 0.00%
Workshop Ls 1 1.64% 0.00% 0.00% 0.00% 0.00%
Pekerjaan Pelaporan & Ls 1 1.09% 0.00% 0.00% 0.00% 0.00%
Dokumentasi
TOTAL 100.00% 0.48% 0.80% -0.32%

2 PROGRESS SUMMARY (PROGRESS THIS PERIODE)


2.1 PEKERJAAN PERSIAPAN
Progress pekerjaan persiapan sampai dengan periode ini adalah sebesar:
Rencana : 0,80%
Aktual : 0,00%
Deviasi : -0,80%

Kendala :
Pada rencana kerja, pekerjaan survey lapangan akan dilaksanakan pada tanggal 30 Juni
2020, aktual pekerjaan dilapangan masih dalam tahap penyelesaian dokumen
engineering terutama terkait dengan pekerjaan survey lapangan.

2.2 ENGINEERING
Progress pekerjaan engineering sampai dengan periode ini adalah sebesar:
Rencana : 0,00%
Aktual : 0,48%
Deviasi : +0,48%

2.3 PEKERJAAN PENGADAAN BARANG


Progress pekerjaan pengadaan barang sampai dengan periode ini adalah sebesar:
Rencana : 0,00%
Aktual : 0,00%
Deviasi : 0,00%

2.4 PEKERJAAN KONSTRUKSI


Progress pekerjaan konstruksi sampai dengan periode ini adalah sebesar:
Rencana : 0,00%
Aktual : 0,00%
Deviasi : 0,00%

2.5 TESTING AND COMMISSIONING


Progress pekerjaan testing and commissioning sampai dengan periode ini adalah sebesar:
Rencana : 0,00%
Aktual : 0,00%
Deviasi : 0,00%

2.6 PEKERJAAN AKHIR


Progress pekerjaan akhir sampai dengan periode ini adalah sebesar:
Rencana : 0,00%
Aktual : 0,00%
Deviasi : 0,00%

3 ACTIVITY THIS PERIOD


1. Penandatanganan Perjanjian Pekerjaan Upgrading H2S Analyzer at Simpang Abadi Metering
Station antara PT Transportasi Gas Indonesia dan PT Pratiwi Putri Sulung No. 1FAP-042683
pada tanggal 19 Juni 2020.
2. Pelaksanaan Kick Off Meeting pekerjaan Upgrading H2S Analyzer at Simpang Abadi
Metering Station pada tanggal 25 Juni 2020.
3. Submit dokumen engineering dengan rincian sebagai berikut :
a. Dokumen Project Management IFR 5 dokumen;
b. Dokumen data sheet IFR 2 dokumen;
c. Dokumen drawing IFR 4 dokumen;
d. Dokumen procedure QA/QC IFR 5 dokumen;
e. Dokumen HSE IFR 2 dokumen.

4 ACTIVITIES PLANNED FOR NEXT MONTH


➢ Pekerjaan Persiapan
Pelaksanaan survey lapangan
➢ Engineering
Submit dokumen engineering terutama yang terkait dengan peralatan utama.

5 HSE STATISTIK
Safe manhours pada periode 19 Juni – 03 Juli 2020 adalah sebesar 1.632 Jam dengan rincian
terlampir (Lampiran 6.1)

Laporan Bulanan Ke - 1 Halaman 4


6 AREAS OF CONCERNS
Wabah virus corona covid-19 telah menginfeksi hampir semua negara di dunia dengan cepat di
seluruh dunia, termasuk di Indonesia. Kasus virus corona pertama di Indonesia diumumkan
pada hari Senin tanggal 2 Maret 2020, hingga saat ini kasus virus corona di Tanah Air terus
melonjak tajam hingga totalnya mencapai 51.427 kasus pertanggal 26 Juni 2020.

Sebagai Langkah lanjut untuk mengurangi penyebaran wabah virus corona di Indonesia,
Pemerintah Indonesia telah menerbitkan Peraturan Pemerintah (“PP”) sebagai berikut :

1. Keppres Nomor 7 tahun 2020 tentang Gugus Tugas Percepatan Penanganan Covid-19.
2. Keppres Nomor 9 tahun 2020 yang mengubah atau merevisi beberapa pasal dalam
Keppres Nomor 7 tahun 2020.
3. Perpres Nomor 52 tahun 2020 tentang Pembangunan Fasilitas Observasi dan Penampungan
dalam Penanggulangan COVID-19 atau Penyakit Infeksi Emerging di Pulau Galang, Kota
Batam, Provinsi Kepulauan Riau.
4. Inpres Nomor 4 tahun 2020 tentang Refocussing Kegiatan, Realokasi Anggaran, serta
Pengadaan Barang dan Jasa Dalam Rangka Percepatan Penanganan Covid-19.
5. PP Nomor 21 tahun 2020 tentang Pembatasan Sosial Berskala Besar Dalam Rangka
Percepatan Penanganan Covid-19.
6. Keppres Nomor 11 tahun 2020 tentang Penetapan Status Kedaruratan Kesehatan
Masyarakat.
7. Perppu Nomor 1 tahun 2020 tentang Kebijakan Keuangan Negara dan Stabilitas Sistem
Keuangan Untuk Penanganan Covid-19
8. Perpres Nomor 54 tahun 2020 tentang Perubahan Postur dan Rincian APBN Tahun Anggaran
2020.
9. Keppres Nomor 12 tahun 2020 tentang Penetapan Bencana non-alam Penyebaran Covid-19
sebagai Bencana Nasional. (Sumber : https://www.liputan6.com/news/read/4227914/sederet-aturan-yang-dikeluarkan-jokowi-melawan-pandemi-virus-corona#)

Terkait dengan hal tersebut diatas, area of concern pada periode ini adalah :
1. Terkait dengan Pandemic COVID-19, proses untuk mendapatkan izin masuk ke area
lapangan kerja/station harus mengikuti protokol alur skrining personil masuk ke Lokasi
Proyek.
2. Kemungkinan diperlukannya isolasi mandiri 14 hari kalender untuk mendapatkan surat
sehat dari Rumah Sakit/PUSKESMAS daerah setempat.

7 LAMPIRAN
7.1 HSE STATISTIK
7.2 LAPORAN KEMAJUAN PROGRESS & S CURVE

7.3 LAMPIRAN LAINNYA

Laporan Bulanan Ke - 1 Halaman 5


7.1. HSE STATISTIK
ENGINEERING, PROCUREMENT, INSTALLATION AND COMMISSIONING (EPIC)
REPLACEMENT H2S ANALYZER AT SIMPANG ABADI METERING STATION
HSE WEEKLY REPORT

Report No. : 01/WR/HSE/PPS-TGI/2020 Periode : 17-19 Juni 2020


Pemilik Proyek : PT. Transportasi Gas Indonesia Minggu Ke : 1
Department : Operasi Tanggal : 19 juni 2020

A. HSE Performance
Last Week This Week Total Cumulative
No. Description of Incidents
Office Site Office Site Office Site
1 Fatality (Mati ) 0 0 0 0 0 0
2 Lost Time Injuries cacat permanen (LTI) = Berat 0 0 0 0 0 0
3 Lost Time Injuries tanpa cacat (LTI) = Sedang 0 0 0 0 0 0
4 Total LTI (3 days) 0 0 0 0 0 0
5 Lost Work Days 0 0 0 0 0 0
6 Lost Time Injury Frequency (LTIF) ((#4/27) x 106) 0 0 0 0 0 0
7 Severity Rate (SR) ((#5/27) x 106) 0 0 0 0 0 0
8 Case Severity (# 5/4) 0 0 0 0 0 0
9 No. of Restricted Work Case (RWC) = Ringan 0 0 0 0 0 0
10 Medical Treatment Case (MTC)= Ringan 0 0 0 0 0 0
11 Total RWC + MTC = Ringan 0 0 0 0 0 0
12 Reportable Incidents (# 9+4) 0 0 0 0 0 0
13 First Aid Injury 0 0 0 0 0 0
14 Near Misses 0 0 0 0 0 0
15 Fire/Explosions 0 0 0 0 0 0
16 Property Damage 0 0 0 0 0 0
17 Environmental Incident 0 0 0 0 0 0
18 Vehicle Accident 0 0 0 0 0 0
19 Total Distance Travel (km) 0 0 0 0 0 0
20 Safe driving (km) 0 0 0 0 0 0
21 Vehicle Acc. Frequency (per 100000 km)= ((#18/19) x 105) 0 0 0 0 0 0
22 Security Incidents 0 0 0 0 0 0
23 Total Number of Employees 0 0 12 0 12 0
24 Total Available workdays 0 0 7 0 7 0
25 Manhours 0 0 288 0 288 0
26 Safe Manhours 0 0 288 0 288 0
TOTAL SAFE MANHOURS 288

B. Pro-Active Measures:
Last Week This Week Total Cumulative
No. Description of Participation, Communication & Consultation
Office Site Office Site Office Site
1 Communication & Training
a. Induction 0 0 0 0 0 0
b. Toolbox Talk 0 0 0 0 0 0
c. Training 0 0 0 0 0 0
d. SHE Meeting 0 0 0 0 0 0
e. SHE Committee Meeting 0 0 0 0 0 0
f. Emergency Drill 0 0 0 0 0 0
2 Inspection & Audit
a. Tools Inspection / Inspeksi K3 0 0 0 0 0 0
b. HSE Audit 0 0 0 0 0 0
ENGINEERING, PROCUREMENT, INSTALLATION AND COMMISSIONING (EPIC)
REPLACEMENT H2S ANALYZER AT SIMPANG ABADI METERING STATION
HSE WEEKLY REPORT

Report No. : 02/WR/HSE/PPS-TGI/2020 Periode : 20-26 Juni 2020


Pemilik Proyek : PT. Transportasi Gas Indonesia Minggu Ke : 2
Department : Operasi Tanggal : 26 juni 2020

A. HSE Performance
Last Week This Week Total Cumulative
No. Description of Incidents
Office Site Office Site Office Site
1 Fatality (Mati ) 0 0 0 0 0 0
2 Lost Time Injuries cacat permanen (LTI) = Berat 0 0 0 0 0 0
3 Lost Time Injuries tanpa cacat (LTI) = Sedang 0 0 0 0 0 0
4 Total LTI (3 days) 0 0 0 0 0 0
5 Lost Work Days 0 0 0 0 0 0
6 6
Lost Time Injury Frequency (LTIF) ((#4/27) x 10 ) 0 0 0 0 0 0
7 6
Severity Rate (SR) ((#5/27) x 10 ) 0 0 0 0 0 0
8 Case Severity (# 5/4) 0 0 0 0 0 0
9 No. of Restricted Work Case (RWC) = Ringan 0 0 0 0 0 0
10 Medical Treatment Case (MTC)= Ringan 0 0 0 0 0 0
11 Total RWC + MTC = Ringan 0 0 0 0 0 0
12 Reportable Incidents (# 9+4) 0 0 0 0 0 0
13 First Aid Injury 0 0 0 0 0 0
14 Near Misses 0 0 0 0 0 0
15 Fire/Explosions 0 0 0 0 0 0
16 Property Damage 0 0 0 0 0 0
17 Environmental Incident 0 0 0 0 0 0
18 Vehicle Accident 0 0 0 0 0 0
19 Total Distance Travel (km) 0 0 0 0 0 0
20 Safe driving (km) 0 0 0 0 0 0
21 5
Vehicle Acc. Frequency (per 100000 km)= ((#18/19) x 10 ) 0 0 0 0 0 0
22 Security Incidents 0 0 0 0 0 0
23 Total Number of Employees 12 0 12 0 12 0
24 Total Available workdays 7 0 7 0 14 0
25 Manhours 288 0 672 0 960 0
26 Safe Manhours 288 0 672 0 960 0
TOTAL SAFE MANHOURS 960

B. Pro-Active Measures:
Last Week This Week Total Cumulative
No. Description of Participation, Communication & Consultation
Office Site Office Site Office Site
1 Communication & Training
a. Induction 0 0 0 0 0 0
b. Toolbox Talk 0 0 0 0 0 0
c. Training 0 0 0 0 0 0
d. SHE Meeting 0 0 0 0 0 0
e. SHE Committee Meeting 0 0 0 0 0 0
f. Emergency Drill 0 0 0 0 0 0
2 Inspection & Audit
a. Tools Inspection / Inspeksi K3 0 0 0 0 0 0
b. HSE Audit 0 0 0 0 0 0
ENGINEERING, PROCUREMENT, INSTALLATION AND COMMISSIONING (EPIC)
REPLACEMENT H2S ANALYZER AT SIMPANG ABADI METERING STATION
HSE WEEKLY REPORT

Report No. : 03/WR/HSE/PPS-TGI/2020 Periode : 27 Juni- 3 Juli 2020


Pemilik Proyek : PT. Transportasi Gas Indonesia Minggu Ke : 3
Department : Operasi Tanggal : 3 Juli 2020

A. HSE Performance
Last Week This Week Total Cumulative
No. Description of Incidents
Office Site Office Site Office Site
1 Fatality (Mati ) 0 0 0 0 0 0
2 Lost Time Injuries cacat permanen (LTI) = Berat 0 0 0 0 0 0
3 Lost Time Injuries tanpa cacat (LTI) = Sedang 0 0 0 0 0 0
4 Total LTI (3 days) 0 0 0 0 0 0
5 Lost Work Days 0 0 0 0 0 0
6 Lost Time Injury Frequency (LTIF) ((#4/27) x 106) 0 0 0 0 0 0
7 Severity Rate (SR) ((#5/27) x 106) 0 0 0 0 0 0
8 Case Severity (# 5/4) 0 0 0 0 0 0
9 No. of Restricted Work Case (RWC) = Ringan 0 0 0 0 0 0
10 Medical Treatment Case (MTC)= Ringan 0 0 0 0 0 0
11 Total RWC + MTC = Ringan 0 0 0 0 0 0
12 Reportable Incidents (# 9+4) 0 0 0 0 0 0
13 First Aid Injury 0 0 0 0 0 0
14 Near Misses 0 0 0 0 0 0
15 Fire/Explosions 0 0 0 0 0 0
16 Property Damage 0 0 0 0 0 0
17 Environmental Incident 0 0 0 0 0 0
18 Vehicle Accident 0 0 0 0 0 0
19 Total Distance Travel (km) 0 0 0 0 0 0
20 Safe driving (km) 0 0 0 0 0 0
21 Vehicle Acc. Frequency (per 100000 km)= ((#18/19) x 105) 0 0 0 0 0 0
22 Security Incidents 0 0 0 0 0 0
23 Total Number of Employees 12 0 12 0 12 0
24 Total Available workdays 14 0 7 0 21 0
25 Manhours 960 0 672 0 1632 0
26 Safe Manhours 960 0 672 0 1632 0
TOTAL SAFE MANHOURS 1632

B. Pro-Active Measures:
Last Week This Week Total Cumulative
No. Description of Participation, Communication & Consultation
Office Site Office Site Office Site
1 Communication & Training
a. Induction 0 0 0 0 0 0
b. Toolbox Talk 0 0 0 0 0 0
c. Training 0 0 0 0 0 0
d. SHE Meeting 0 0 0 0 0 0
e. SHE Committee Meeting 0 0 0 0 0 0
f. Emergency Drill 0 0 0 0 0 0
2 Inspection & Audit
a. Tools Inspection / Inspeksi K3 0 0 0 0 0 0
b. HSE Audit 0 0 0 0 0 0
7. 2. LAPORAN KEMAJUAN
PROGRESS & S CURVE
Project : UPGRADING H2S ANALYZER AT SIMPANG ABADI METERING STATIONS

QUANTITY CALCULATION REPORT


Monthly Report 1 Periode 19 Juni sampai dengan 03 Juli 2020

Progress
Weight
WBS Description Unit Qty Previous This Period To Date PLAN DEVIASI
Factor
%Progress % WF %Progress % WF %Progress % WF
A Pekerjaan Persiapan 0,80% 0,00% 0,00% 0,00% 0,00% 0,00% 0,000% 0,80% -0,799%
Survey Lapangan Ls 1 0,80% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,80% -0,80%
B Engineering 1 1,75% 0,00% 0,00% 27,14% 0,48% 27,14% 0,475% 0,00% 0,475%
Engineering Ls 1 1,75% 0,00% 0,00% 27,14% 0,48% 27,14% 0,48% 0,00% 0,48%
C Pekerjaan Pengadaan Barang 79,51% 0,00% 0,00% 0,00% 0,00% 0,00% 0,000% 0,00% 0,000%
Pengadaan Material Ls 1 79,51% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
D Pekerjaan Konstruksi 11,85% 0,00% 0,00% 0,00% 0,00% 0,00% 0,000% 0,00% 0,000%
Mobilisasi Material Ls 1 1,56% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Pekerjaan Pemasangan Ls 1 10,29% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
E Testing dan Commisioning 3,36% 0,00% 0,00% 0,00% 0,00% 0,00% 0,000% 0,00% 0,000%
Pekerjaan Pengetesan Ls 1 3,36% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
F Pekerjaan Akhir 2,73% 0,00% 0,00% 0,00% 0,00% 0,00% 0,000% 0,00% 0,000%
Workshop
Pekerjaan Pelaporan & Dokumentasi Ls 1 1,64% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Pekerjaan Pelaporan & Dokumentasi Ls 1 1,09% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
TOTAL 100,00% 0,00% 0,48% 0,48% 0,80% -0,32%

Dibuat Oleh, Disetujui Oleh,


PT. PRATIWI PUTRI SULUNG PT TRANSPORTASI GAS INDONESIA

( Bambang Andrianto ) ( )
OVERALL PROGRESS S-CURVE
UPGRADING H2S ANALYZER AT SIMPANG ABADI METERING STATION (SAMS)
100,00%

34,0%

32,0%
90,00%

30,0%

28,0% 80,00%

26,0%

70,00%
24,0% Incremental Plan
Incremental Actual
22,0% Cummulative Plan
Cummulative Actual 60,00%

20,0%

18,0%
50,00%

16,0%

14,0% 40,00%

12,0%

30,00%
10,0%

8,0%

20,00%

6,0%

4,0%
10,00%

2,0%

0,0% 0,00%

DESCRIPTION WEEK W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31
Incremental 0,00% 0,00% 0,80% 0,18% 19,58% 5,32% 0,32% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 31,80% 1,53% 0,52% 24,37% 3,13% 3,13% 3,13% 0,92% 2,35% 0,21% 2,73%
PLAN
Cummulative 0,00% 0,00% 0,80% 0,97% 20,55% 25,88% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 26,19% 58,00% 59,52% 60,04% 84,42% 87,54% 90,67% 93,79% 94,71% 97,06% 97,27% 100,00%
Incremental 0,00% 0,00% 0,48%
ACTUAL
Cummulative 0,00% 0,00% 0,48%
DEVIASI 0,00% 0,00% -0,32%
Monthly Report 1 Periode 19 Juni sampai dengan 03 Juli 2020

UPGRADE H2S ANALYZER AT SIMPANG ABADI METERING STATION


ACTUAL DATE ACTUAL PERCENTAGE PROGRESS
No DOCUMENT NUMBER DOCUMENT TITLE QTY WF (%) IFR IFA IFC IFR IFA IFC PREV. CUM %WF Remark
THIS MONTH
1,75% Date Date Date 40% 30% 30%
A PROJECT MANAGEMENT 0,31% 0,13%
A.1 GS3473-PM-PRO-G-001 Project Master Schedule 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
A.2 GS3473-PM-PRO-G-002 S Curve Baseline 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
A.3 GS3473-PM-PRO-G-003 Progress Measurement Rules 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
A.4 GS3473-PM-PRO-G-004 Engineering Delivereable List 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
A.5 GS3473-PM-PRO-G-005 Project Execution Plan 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
B ENGINEERING 0,69% 0,15%
B.1 DATA SHEET 0,25% 0,05%
B.1.1 GS3473-EN-DST-IN-001 Data Sheet H2S Analyzer 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
B.1.2 GS3473-EN-DST-IN-002 Data Sheet Sampling Regulating System 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
GS3473-EN-DST-IN-003 Data Sheet Arrester 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
GS3473-EN-DST-IN-004 Data Sheet Enclousere 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
B.2 DRAWING 0,38% 0,10%
B.2.1 GS3473-EN-DWG-IN-001 Installation Drawing 1 0,06% 01-Jul-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
B.2.2 GS3473-EN-DWG-IN-002 Wiring Diagram 1 0,06% 01-Jul-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
B.2.3 GS3473-EN-DWG-IN-003 Piping & Instrument Diagram 1 0,06% 01-Jul-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
B.2.4 GS3473-EN-DWG-IN-004 Layout H2S Analyzer 1 0,06% 01-Jul-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
B.2.5 GS3473-EN-DWG-IN-005 Cable Layout 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
B.2.6 GS3473-EN-DWG-IN-006 Layout Grounding & Proteksi Petir 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
B.3 LIST 0,06% 0,00%
B.3.1 GS3473-EN-LST-IN-001 2 Years Sparepart Analyzer 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
C QA/QC 0,63% 0,15%
C.1 PROCEDURE 0,31% 0,13%
C.1.1 GS3473-QA-PRO-G-001 Survey Procedure 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
C.1.2 GS3473-QA-PRO-G-002 Dismantling and Installation Procedure 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
C.1.3 GS3473-QA-PRO-G-003 Factory Acceptance Test Procedure 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
C.1.4 GS3473-QA-PRO-G-004 SAT / Commissioning Procedure 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
C.1.5 GS3473-QA-PRO-G-005 Material Take Off 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
C.2 REPORT 0,31% 0,03%
C.2.1 GS3473-QA-REP-G-001 FAT Report 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
C.2.2 GS3473-QA-REP-G-002 SAT / Commissioning Report 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
C.2.3 GS3473-QA-REP-G-003 Material Certificate 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
C.2.4 GS3473-QA-REP-G-004 Operation & Maintenance Manual 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
C.2.5 GS3473-QA-REP-G-005 Survei Report 1 0,06% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
D HSE 0,13% 0,05%
D.1 GS3473-HS-PRO-G-001 HSE Plan 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
D.2 GS3473-HS-PRO-G-002 Emergency Respone Team 1 0,06% 30-Jun-20 40,00% 0,00% 0,00% 0,00% 40,00% 40,00% 0,03%
B. ENGINEERING 28 1,75% 0,00% 27,14% 27,14% 0,48%
PROCUREMENT STATUS
Monthly Report 1 Periode 19 Juni sampai dengan 03 Juli 2020
Paket : UPGRADE H2S ANALYZER AT SIMPANG ABADI METERING STATION
Lokasi Proyek : SIMPANG ABADI - JAMBI
Tanggal & No. Kontrak : 19 JUNI 2018 & 1FAP-042683
Tanggal Akhir Pekerjaan : 15 JANUARI 2021
Kontraktor : PT. Pratiwi Putri Sulung

Issued PO Evi- Inspeksi Material Evi- Material On Site Evi- Progress


30% dent 40% dent 30% dent Previ-ous This To Date
No Description Unit Qty WF (%) Qty % WF x Sta-tus Qty % Progress WF x 0,4 Sta- Qty % Progress WF x 0,3 Sta- Period Remark
PO Progress 0,3 PO Ship- tus Ship- tus
ment Deli- ment Deli-
very very
C Procurement 79,51% 0,00% 0,00% 0,00%
H2S Analyzer Unit 2 58,53% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Assesories dan material Support Set 2 4,99% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Material Sample Conditionig System (SCS) Unit 2 7,34% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Enclosure Unit 2 8,65% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Total 79,51% 0,00% 0,00% 0,00%
Project : UPGRADING H2S ANALYZER AT SIMPANG ABADI METERING STATIONS

CONSTRUCTION AND INSTALLATION STATUS


Monthly Report 1 Periode 19 Juni sampai dengan 03 Juli 2020

Unit Contract Progress Remarks


WBS Description Weight Previous This Period To Date
Qty
Factor Qty %Progress % WF Qty %Progress % WF Qty %Progress % WF
A Pekerjaan Persiapan 0,80% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Survey Lapangan Ls 1,00 0,80% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
D Pekerjaan Kontruksi 11,85% 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
Mobilisasi Material 1,56% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Pengiriman Material ke Site Ls 1,00 1,56% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
Pekerjaan Pemasangan Ls 1,00 10,29% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Instalasi Material Ls 1,00 3,67% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
Flow Computer Integration and Modification Ls 1,00 6,63% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
E Pekerjaan Pengujian Ls 1,00 3,36% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
FAT di workshop PPS Ls 1,00 1,01% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
SAT Ls 1,00 1,01% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
Commisioning Ls 1,00 1,34% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
F Pekerjaan Akhir Ls 1,00 2,73% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
Workshop Ls 1,00 1,64% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
Pekerjaan Pelaporan & Dokumentasi Ls 1,00 1,09% - 0,00% 0,00% - 0,00% 0,00% 0,00% 0,00%
TOTAL 18,74% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
7.3. LAMPIRAN LAINNYA
DOCUMENT TRANSMITTAL

PROJECT : UPGRADING H2S ANALYZER AT SIMPANG ABADI METERING STATION

TO : PT. Transportasi Gas Indonesia Issued : 30-Jun-20


ATTN : Bpk. Rahmat Sitompul Transmittal No : TR/H2S/PPS-TGI/001
CC :
SUBJECT :
p PRINTS  ORIGINAL p COPIES
THE FOLLOWING :
p VENDOR DOCS p PPS ENG DOCS

ARE TRANSMITTED HEREWITH FOR : p APPROVAL p REVIEW  INFORMATION

DOCUMENT NO DOCUMENT TITLE ISSUED


NO Description REV REMARK
PURPOSE
1 001/MOM/TGI-PPS/GS3473/06.20 ORIGINAL - Kick of Meeting -

Project Management

1 GS3473-PM-PRO-G-001 ORIGINAL A Project Master Schedule IFR

2 GS3473-PM-PRO-G-002 ORIGINAL A S Curve IFR

3 GS3473-PM-PRO-G-003 ORIGINAL A Progress Measurement Rules IFR

4 GS3473-PM-PRO-G-004 ORIGINAL IFI Engineering Deliverable List IFI

5 GS3473-PM-PRO-G-005 ORIGINAL A Project Execution Plan IFR

Instrument Documents

1 GS3473-EN-DST-IN-001 ORIGINAL A Data Sheet H2S Analyzer IFR

2 GS3473-EN-DST-IN-002 ORIGINAL A Data Sheet Sampling Regulating System IFR

QA/QC

1 GS3473-QA-PRO-G-001 ORIGINAL A Survey Procedure IFR

2 GS3473-QA-PRO-G-002 ORIGINAL A Dismantling and Installation Procedure IFR

3 GS3473-QA-PRO-G-003 ORIGINAL A Factory Acceptance Test Procedure IFR

4 GS3473-QA-PRO-G-004 ORIGINAL A SAT Commissioning Procedure IFR

5 GS3473-QA-PRO-G-005 ORIGINAL A Material Take Off IFR

6 GS3473-QA-REP-G-004 ORIGINAL A Operation & Maintenance Manual 6020UV IFR

HSE

1 GS3473-HSE-PRO-G-001 ORIGINAL A HSE Plan IFR

2 GS3473-HSE-PRO-G-002 ORIGINAL A Emergency Respone Team IFR

Signature, Counter Signature,

Name : Marsono Name :


Date : 30-Jun-20 Date :

1 of 1
DOCUMENT TRANSMITTAL

PROJECT : UPGRADING H2S ANALYZER AT SIMPANG ABADI METERING STATION

TO : PT. Transportasi Gas Indonesia Issued : 01-Jul-20


ATTN : Bpk. Rahmat Sitompul Transmittal No : TR/H2S/PPS-TGI/002
CC :
SUBJECT :
p PRINTS  ORIGINAL p COPIES
THE FOLLOWING :
p VENDOR DOCS p PPS ENG DOCS

ARE TRANSMITTED HEREWITH FOR : p APPROVAL p REVIEW  INFORMATION


ISSUED
NO DOCUMENT NO Description REV DOCUMENT TITLE REMARK
PURPOSE
Instrument Documents

1 GS3473-EN-DWG-IN-001 ORIGINAL A Installation Drawing IFR

2 GS3473-EN-DWG-IN-002 ORIGINAL A Wiring Diagram IFR

3 GS3473-EN-DWG-IN-003 ORIGINAL A Piping & Instrument Diagram IFR

4 GS3473-EN-DWG-IN-004 ORIGINAL A Layout Analyzer IFR

Signature, Counter Signature,

Name : Marsono Name :


Date : 01-Jul-20 Date :

1 of 1