ANALYSA DUMP TRUK INDEX 9 MIN

PROJECK URUGAN TOL SLAWI-PEMALANG


OWNER PT.MNC
MAINKONT PT.WASKITA Tbk
SUBKONT
LOKASI SLAWI-PEMALANG
HARGA 85,000 Per M3
VOLUME RENCANA 500,000 M3

NO URAIAN KETERANGAN SAT 6 RIT


1 JARAK QUARY PP 20 KM
2 INDEK TRUK RENCANA 9 M3
VOLUME URUGAN PER TRUK/ 1 HARI M3 54
3 SEWA TRUK 2010 KE ATAS 450,000 Rp 75,000 450,000
5 SOLAR Asumsi 1 lt untuk 4 Km 27,500 Rp 27,500 165,000
6 HARGA TANAH/ RIT DIATAS TRUK - Rp - -
Asumsi per RIT 9 m3
7 SOPIR PER HARI 200,000 PER RIT 33,333 200,000
8 TIMBANGAN PER HARI Rp - -
9 LAIN2 Rp - -
135,833 815,000
PEMBAGI 9.00 M3 15,093
Harga Rata2 ANGKUT per m3 14,233

KESIMPULAN
PERHITUNGAN DUMP TRUK
Jumlah TRUK 50 Unit
Jarak 20 Km
Jumlah Ritase per hari 6.5 rit/ hr
Total Ritase per hari 325 rit/ hr
Rencana Vol per rit 9.0 m3
Kapasitas Produksi per hari CURAH 2,925 m3
Produksi per 28 hari (1 Bulan) 81,900 m3
HARGA TANAH
Harga Tanah di atas Truk @ 110.000 110,000 /rit
Harga per m3 diatas Truk 12,222 Per M3
Biaya Angkut padas per Rit 14,233 Per M3
TOTAL BIAYA ALL IN 26,455 Per M3
N

7 RIT

63
64,286 450,000
27,500 192,500
- -

28,571 200,000
- -
- -
120,357 842,500
13,373
6.5 RIT
ANALYSA ALAT BERAT
PROJECK URUGAN TOL SLAWI-PEMALANG
OWNER PT.MNC
MAINKONT PT.WASKITA Tbk
SUBKONT
LOKASI SLAWI-PEMALANG
HARGA 85.000/M3
VOLUME RENCANA 500.000 M3

NO SEWA ALAT BERAT Sewa per jam jam/hr Jumlah set Total/ hari hr/Bulan Total/ bln Bulan
1 Dozer D65 195,000 8 1,560,000 2 3,120,000 30 93,600,000 6
2 Vibro Kapasitas 12 T 170,000 8 1,360,000 2 2,720,000 30 81,600,000 6
3 SHEEP FOOT 200,000 8 1,600,000 2 3,200,000 30 96,000,000 6
4 EXCAVATOR 185,000 8 1,480,000 4 5,920,000 30 177,600,000 6
10 14,960,000 448,800,000
` LEMBUR 5%
TOTAL

NO GAJI OPERATOR PER HARI ORG Gaji/ hari Hari Gaji/ Bln BLN TOTAL
1 Dozer D65 200,000 2 400,000 30 12,000,000 6 72,000,000
2 Vibro Kapasitas 12 T 200,000 2 400,000 30 12,000,000 6 72,000,000
3 SHEEP FOOT 200,000 2 400,000 30 12,000,000 6 72,000,000
4 EXCAVATOR 200,000 4 800,000 30 24,000,000 6 144,000,000
10 2,000,000 60,000,000 360,000,000
LEMBUR 5% 18,000,000
TOTAL 378,000,000

NO BAHAN BAKAR Harga solar lt/Jam Rp Per hr Total Set alat Total/hari /bln
1 Dozer D65 11,000 23 253,000 8 2,024,000 2 4,048,000 30
2 Vibro Kapasitas 12 T 11,000 21 231,000 8 1,848,000 2 3,696,000 30
3 SHEEP FOOT 11,000 20 220,000 8 1,760,000 2 3,520,000 30
4 EXCAVATOR 11,000 20 220,000 8 1,760,000 4 7,040,000 30
7,392,000 10 18,304,000

REKAP BIAYA EXAVATOR


KETERANGAN JUMLAH PER HARI HARI PER BULAN BULAN TOTAL
SEWA ALAT BERAT 14,960,000 30 448,800,000 6 2,692,800,000
GAJI OPERATOR 2,000,000 30 60,000,000 6 360,000,000
BAHAN BAKAR 18,304,000 30 549,120,000 6 3,294,720,000
TOTAL 35,264,000 1,057,920,000 6,347,520,000
LEMBUR DAN Over HEAD 5 % 1,763,200 52,896,000 317,376,000
TOTAL 37,027,200 1,110,816,000 6,664,896,000

KESIMPULAN
KAPASITAS PRODUKSI CURAH PER HARI 2,925 M3
BIAYA ALAT BERAT PER HARI 37,027,200 Rupiah
BIAYA ALAT BERAT PER m3 12,659 Per M3
Total
561,600,000
489,600,000
576,000,000
1,065,600,000
2,692,800,000
134,640,000
2,827,440,000

Total bln Total bhn bakar


121,440,000 6 728,640,000
110,880,000 6 665,280,000
105,600,000 6 633,600,000
211,200,000 6 1,267,200,000
549,120,000 3,294,720,000
LEMBUR 5% 164,736,000
TOTAL 3,459,456,000
SARANA OPERASIONAL
PROJECK URUGAN TOL SLAWI-PEMALANG
OWNER PT.MNC
MAINKONT PT.WASKITA Tbk
SUBKONT
LOKASI SLAWI-PEMALANG
HARGA 85.000/M3
VOLUME RENCANA 500.000 M3

NO KETERANGAN JUMLAH QTY


PENDUKUNG
1 Pembuatan Direksi Kit 3 x 6 9,000,000 1
2 Beli Tanki Solar 5000 LT 9,500,000 1
3 1 Unit Genset Sedang + lampu 7,500,000 1
4 Wather tank 5,000,000 6
5 Mob DE Mob Alat berat 15,000,000 10

OPERASIONAL KANTOR
1 Sewa Kantor 15,000,000 1
2 Peralatan Kantor 10,000,000 1
3 Operasional kantor 2,500,000 6
4 Keamanan Polsek dan koramil, polres 5,000,000 6
5 Sumbangan masyarakat Sekitar 2,500,000 6
6 Sewa Mobil Operasional 4,000,000 6
7 Lain-lain(listrik/air)+ keamanan alat berat 20,000,000 1

OVER HEAD

KESIMPULAN
KAPASITAS PRODUKSI PER HARI 2,925 M3
TOTAL CASH OUT 2,171,296 RUPIAH
BIAYA Operasional Kantor/m3 742 PER M3
NA OPERASIONAL

SAT TOTAL KETERANGAN

UNIT 9,000,000
UNIT 9,500,000
UNIT 7,500,000
bln 30,000,000
UNIT 150,000,000

TAHUN 15,000,000
LS 10,000,000
BLN 15,000,000
BLN 30,000,000
BLN 15,000,000
Bulan 24,000,000
LS 20,000,000
TOTAL 335,000,000
5% 16,750,000
TOTAL 351,750,000
Per HARI 2,171,296
Per BULAN 58,625,000
GAJI KARYAWAN
PROJECK URUGAN TOL SLAWI-PEMALANG
OWNER PT.MNC
MAINKONT PT.WASKITA Tbk
SUBKONT
LOKASI SLAWI-PEMALANG
HARGA 85.000/M3
VOLUME RENCANA 500.000 M3

NO KETERANGAN STATUS JML KYW GAPOK/BLN


1 Pimpro Tetap 1 7,500,000
2 Manager Lapangan (Site Manager) Tetap 1 4,500,000
3 Site Enginer Tetap 1 3,500,000
4 Pelaksana Kontrak 2 3,000,000
5 Logistik Kontrak 1 2,500,000
6 Ceker Kontrak 6 2,000,000
7 Administrasi (Lapangan) Tetap+Kontrak 2 1,750,000
8 Administrasi (Kantor) Kontrak 1 1,500,000
9 Surveyor Kontrak 2 3,000,000
10 Keamanan Kontrak 2 1,500,000
19

KESIMPULAN
KAPASITAS PRODUKSI CURAH PER HARI 2,925 M3
TOTAL CASH OUT PER HARI 1,716,346 RUPIAH
BIAYA Per M3 587 PER M3
N

GAJI PER BLN KONTRAK TOTAL


7,500,000 6 45,000,000
4,500,000 6 27,000,000
3,500,000 6 21,000,000
6,000,000 6 36,000,000
2,500,000 6 15,000,000
12,000,000 6 72,000,000
3,500,000 6 21,000,000
1,500,000 6 9,000,000
6,000,000 6 36,000,000
3,000,000 6 18,000,000
42,500,000 TOTAL 255,000,000
Over Time 5% 12,750,000
TOTAL 267,750,000
Per hari 1,716,346
Per Bulan 44,625,000
SUMMARY RENCANA ANGGARAN PELAKSANAAN(RAP)
URUGAN PADAT VIBRO TOL SLAWI-PEMALANG

OWNER : PT.MNC
MAINTCOND : PT. WASKITA TOL
PEKERJAAN : URUGAN CURAH PADAT VIBRO
PANJANG : Sta21 s/d Sta 56
KETINGGIAN MINIMAL URUGAN : 1.5 M
KETINGGIAN MAKSIMAL URUGAN : 2.5 M
KETINGGIAN RATA-RATA : 2.0 M
LAYER : 4.0 Rata2
JARAK QUARY TERJAUH : 20 KM
JARAK QUARY TERDEKAT : 15 KM
VOLUME PADAT RENCANA : 500,000 M3
HARGA PADAT : 85,000 Rupiah (minimal bersih ke kita)
NILAI PROYEK : 42,500,000,000 Milyard
JAMINAN PEMBAYARAN : SCF
INVOICE PER : 3 MINGGU
JANGKA WAKTU PELAKSANAAN : 180 HARI
: 6.0 BULAN
TARGET PELAKSANAAN : 6.0 BULAN
TOTAL TANAH PADAT VIBRO : 500,000 M3
Rencana Laiyer maks : 4 kali
Prosentase kehilangan : 30%
VOLUME CURAH : 650,000 M3
JUMLAH ARMADA : 50 Unit
Muatan Rencana Per 1 DT : 9.0 m3
Dalam 1 Hari 1 DT : 6.5 Rit
TOTAL RITASE PER HARI : 325 Rit
TOTAL PRODUKSI CURAH PER HARI : 2,925 M3
Produksi dalam 1 Bulan (28 hari) : 81,900 M3
Produksi curah : 650,000 M3
Produksi padat Vibro : 7.9 Bulan
: 6 Bulan
BIAYA PRODUKSI ONGKOS ALL IN DT
Harga Tanah Diatas Dump truk : 12,222 per M3 12,222
Ongkos Angkut sampai Lokasi : 14,233 per M3 14,233
Biaya Alat Berat : 12,659 per M3 BULAT
TOTAL : 39,114 per M3
Prosentase Kehilangan Laiyer : 30%
: 11,734 per M3
JUMLAH TOTAL : 50,848 per M3

OPERASIONAL
Biaya Operasional Kantor : 742 per M3
Gaji Pegawai : 587 per M3
TOTAL : 1,329 per M3

TOTAL BIAYA YANG DIKELUARKAN : 52,177 per M3


KOMITMEN FEE MEDIASI : 4,000 per M3
TOTAL RAP : 56,177 per M3
Di Bulatkan : 56,000 per M3
HARGA DARI PT. WASKITA : 85,000 PER M3
RAP : 56,000 PER M3
KEUNTUNGAN NETTO : 29,000 PER M3 (blm termasuk Biaya SCF&PPH)

KEUNTUNGAN RENCANA

TOTAL CASH OUT


Volume padat Rencana : 500,000 m3
Biaya per m3 : 56,000 m3
Total Biaya Keluar : 28,000,000,000 m3

TOTAL CASH IN
Volume padat Rencana : 500,000 m3
Penjualan m3 : 85,000 m3
Total Biaya Keluar : 42,500,000,000 m3

KEUNTUNGAN : 14,500,000,000 Rupiah

KEBUTUHAN MODAL
INVOICE PER : 3 Minggu

RENCANA PRODUKSI
Kapasitas Produksi per hari : 2,925 m3
Rencana produksi : 21 hari
Total Produksi : 61,425 m3
Ukur + Administrasi : 10 Hari
SETELAH INVOICE DI BAYAR MUNDUR : 30 Hari
OVER HEAD : 5 Hari
Total Turn Over : 66 Hari

Produksi Rencana Per hari : 2,925 m3


Biaya per m3 : 56,000
Biaya dikeluarakan per hari : 163,800,000 Rupiah

MODAL YANG RENCANA YANG DIPUTAR : 10,810,800,000 Milyard


TOTAL KEUNTUNGAN RENCANA : 14,500,000,000
PROSENTASE KEUNTUNGAN : 134%
Waktu pelaksanaan : 6
Keuntungan : 22.4% Perbulan

KEBUTUHAN ALAT BERAT


BULDOZER D65 : 2 Unit ( Lokasi Buangan)
VIBRO 12 T : 2 Unit ( Lokasi Buangan)
DT INDEX 9 : 50 Unit (lokasi Tambang)
SHEEP FOOT : 2 Unit (lokasi Tambang)
EXCAVATOR : 4 Unit (lokasi Tambang)
(RAP)

al bersih ke kita)

ONGKOS ALL IN DT
26,455

27,000
(blm termasuk Biaya SCF&PPH)
( Lokasi Buangan)
( Lokasi Buangan)
(lokasi Tambang)
(lokasi Tambang)
(lokasi Tambang)