UPAH DASAR UPAH PER JAM ASURANSI / UPAH JAM KERJA PEMBULATAN UPAH 1HARI,
NO KODE URAIAN SATUAN TUNJANGAN
(Rp./HARI) (Rp./JAM) JAMINAN EFEKTIF (Rp./JAM) 7 jam
(1) (2) (2a) (3) (4) = (3)/7 (5) = B x (4) (6) = A x (4) (7) = (4) + (5) + (6) (8) 9 = 7 x (7)
1 L01 Pekerja Biasa Jam 55,798.00 7,971.14 1992.79 975.67 10,939.60 10,940.00 76,577
2 L01.1 Pekerja Trampil Jam 65,734.00 9,390.57 2347.64 1149.41 12,887.62 12,890.00 90,213
3 L02.1 Tukang Jam 65,718.00 9,388.29 2347.07 1149.13 12,884.48 12,880.00 90,191
4 L02.2 Tukang Besi Jam 65,718.00 9,388.29 2347.07 1149.13 12,884.48 12,880.00 90,191
5 L02.3 Tukang Batu Jam 65,734.00 9,390.57 2347.64 1149.41 12,887.62 12,890.00 90,213
6 L02.4 Tukang Kayu Jam 65,734.00 9,390.57 2347.64 1149.41 12,887.62 12,890.00 90,213
7 L02.5 Tukang Listrik Jam 65,734.00 9,390.57 2347.64 1149.41 12,887.62 12,890.00 90,213
8 L03 Mandor Jam 85,607.00 12,229.57 3057.39 1496.90 16,783.86 16,780.00 117,487
9 L04 Operator Jam 85,607.00 12,229.57 3057.39 1496.90 16,783.86 16,780.00 117,487
10 L05 Pembantu Operator Jam 65,734.00 9,390.57 2347.64 1149.41 12,887.62 12,890.00 90,213
11 L06 Supir Jam 73,622.02 10,517.43 2629.36 1287.33 14,434.12 14,430.00 101,039
12 L07 Pembantu Supir Jam 48,643.16 6,949.02 1737.26 850.56 9,536.84 9,540.00 66,758
13 L08 Mekanik Jam 73,622.02 10,517.43 2629.36 1287.33 14,434.12 14,430.00 101,039
14 L09 Pembantu Mekanik Jam 48,643.16 6,949.02 1737.26 850.56 9,536.84 9,540.00 66,758
465537457.xls Upah
Pembangunan Area Parkir Terminal Baru Bandar Udara Sultan Syarif Kasim II Pekanbaru
Pekanbaru - Prop Riau
RINGKASAN HARGA DASAR BAHAN
0 0 M 0.00
518 M518 Saluran, Beton Precast U-5070 m1 0.00 DS - 3B
519 M519 Saluran, Beton Precast U-6080 m 1
506,084.60 DS - 6
520 M520 Saluran, Beton Precast U-8080 m1 0.00 DS - 6A
465537457.xls Alat
Pekanbaru
BIAYA BIAYA
Ket BIAYA PASTI DATA PRIMER RENTAL ALAT
PERAWATAN PEMILIKAN
PT.RATU
OWNING COST WIJAYA KARYA
TEKNIK
6 SK Gub. DKI SK Gub Jabar
(e1 + e2)
465537457.xls Alat
URAIAN ANALISA ALAT
RENCANA TEKNIK AKHIR JALAN TOL CINERE - JAGORAWI
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT E01
2. Tenaga Pw 0.0 HP
3. Kapasitas Cp 40.0 T/Jam
4. Alat Baru : a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 3,449,080,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 8.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,200.0 Jam Sewa Alat
c. Harga Alat (*) B' 3,449,080,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER E02
2. Tenaga Pw 90.0 HP
3. Kapasitas Cp 33.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,175,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 559,523,809.5 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER E03
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 800.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 190,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 5.0 Tahun Alat Baru
b. Jam Kerja Dalam 1 Tahun W' 2,000.0 Jam Alat Baru
c. Harga Alat (*) B' 190,000,000.0 Rupiah Alat Baru
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER 100-150 HP E04
2. Tenaga Pw 140.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,275,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 510,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR 4000-6500 L\M E05
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 10.0 Bar
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 175,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 70,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga Pw 15.0 HP
3. Kapasitas Cp 500.0 Liter
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 25,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 15,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CRANE 10-15 TON E07
2. Tenaga Pw 120.0 HP
3. Kapasitas Cp 15.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,157,500,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 463,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3-4 M3 E08
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 375,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 150,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 10 M3 E09
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 375,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 150,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 100-160 HP E10
2. Tenaga Pw 160.0 HP
3. Kapasitas Cp 1.3 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,025,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 683,333,333.3 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan FLAT BED TRUCK 3-4 M3 E11
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4.0 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 475,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 190,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan GENERATOR SET E12
2. Tenaga Pw 450.0 HP 1 HP=0.7 KVA
3. Kapasitas Cp 252.0 KVA RATE OUTPUT
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun =80 %
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 145,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 58,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 110.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 995,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 663,333,333.3 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TRACK LOADER 75-100 HP E14
2. Tenaga Pw 90.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,127,500,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 451,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 E15
2. Tenaga Pw 105.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,050,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 420,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan THREE WHEEL ROLLER 6-8 T E16
2. Tenaga Pw 55.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,253,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 501,200,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T. E17
2. Tenaga Pw 50.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 975,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 390,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER 8-10 T. E18
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,800.0 Jam
c. Harga Alat B 875,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,440.0 Jam Sewa Alat
c. Harga Alat (*) B' 350,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp 7.0 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,008,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 604,800,000.0 Rupiah Sewa Alat
B. BIAYA PASTI PER JAM KERJA BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 100,800,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE VIBRATOR E20
2. Tenaga Pw 10.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 3,125,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 800.0 Jam Sewa Alat
c. Harga Alat (*) B' 1,875,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan STONE CRUSHER E21
2. Tenaga Pw 220.0 HP
3. Kapasitas Cp 30.0 T/Jam
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 925,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 616,666,666.7 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm E22
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 800.0 Jam
c. Harga Alat B 6,534,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 640.0 Jam Sewa Alat
c. Harga Alat (*) B' 4,356,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. E23
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 285,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 190,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan PEDESTRIAN ROLLER E24
2. Tenaga Pw 11.0 HP
3. Kapasitas Cp 0.980 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,600.0 Jam
c. Harga Alat B 42,500,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,280.0 Jam Sewa Alat
c. Harga Alat (*) B' 17,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TAMPER E25
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 0.170 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 4,750,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 800.0 Jam Sewa Alat
c. Harga Alat (*) B' 2,850,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan JACK HAMMER E26
2. Tenaga Pw 3.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 3,500,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 800.0 Jam Sewa Alat
c. Harga Alat (*) B' 2,100,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan FULVI MIXER E27
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 713,200,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 285,280,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE PUMP E28
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 8.00 M3
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,125,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 535,714,285.7 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TRAILER 20 TON E29
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 20.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,404,998,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 4.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 669,046,666.7 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan PILE DRIVER + HAMMER E30
2. Tenaga Pw 25.0 HP
3. Kapasitas Cp 2.50 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,240,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 496,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CRANE ON TRACK 35 TON E31
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 35.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,256,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 358,857,142.9 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WELDING SET E32
2. Tenaga Pw 40.0 HP
3. Kapasitas Cp 250.00 Amp
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 75,600,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 30,240,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan BORE PILE MACHINE E33
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 2,000.00 Meter
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,240,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 354,285,714.3 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT LIQUID MIXER E34
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 1,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 30,000,000 Rupiah
5. Alat Yang Dipakai : a. Umur Ekonomis A' 3.0 Tahun Sewa Alat
b. Jam Kerja Dalam 1 Tahun W' 1,600.0 Jam Sewa Alat
c. Harga Alat (*) B' 18,000,000.0 Rupiah Sewa Alat
E. LAIN - LAIN
1. Tingkat Suku Bunga i 20.00 % / Tahun
2. Upah Operator / Sopir U1 16,780.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,890.00 Rp./Jam
4. Bahan Bakar Bensin Mb 4,583.00 Liter
5. Bahan Bakar Solar Ms 4,583.00 Liter
6. Minyak Pelumas Mp 22,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan