Anda di halaman 1dari 12

REKAPITULASI

Pekerjaan : Peningkatan Jalan Buya - Wakafia


Lokasi : Desa Fatce Kec. Sanana Kab. Kepulauan Sula
Tahun Anggaran : 2023

NO URAIAN PEKERJAAN JUMLAH HARGA


1 2 3
I DIVISI 1. UMUM 165,000,000.00

II DIVISI 3. PEKERJAAN TANAH 1,291,219,233.53

IV DIVISI 6. PERKERASAN ASPAL 1,678,535,601.89

A REAL COST 3,134,754,835.42

B PPN (11 % x A) 344,823,031.90

C JUMLAH (A + B) 3,479,577,867.32

D DIBULATKAN 3,479,577,867.00
(Tiga Milyar Empat Ratus Tujuh Puluh Sembilan Juta Lima Ratus Tujuh Puluh Tujuh
Terbilang :
Ribu Delapan Ratus Enam Puluh Tujuh Rupiah,- )

Manado, 10 Mei 2023


CV. BERKAT PORODISA

SEPTIAN MOSAL PIRADE


Direktur
DAFTAR KUANTITAS DAN HARGA

Pekerjaan : Peningkatan Jalan Buya - Wakafia


Lokasi : Desa Fatce Kec. Sanana Kab. Kepulauan Sula
Tahun Anggaran : 2023

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)

1 2 3 4 5 6
DIVISI 1. UMUM
1 Mobilisasi 1.00 Ls 165,000,000.00 165,000,000.00
JUMLAH HARGA PEKERJAAN DIVISI 1 165,000,000.00
DIVISI 3. PEKERJAAN TANAH
1 Timbunan Pilihan dari Sumber Galian 2,738.71 M3 409,168.63 1,120,594,209.31
2 Penyiapan Badan Jalan 13,650.00 M2 12,500.00 170,625,024.22
JUMLAH HARGA PEKERJAAN DIVISI 3 1,291,219,233.53
DIVISI 6. PERKERASAN ASPAL
1 Lapis Permukaan Penetrasi Macadam 661.50 M3 2,537,468.79 1,678,535,601.89
JUMLAH HARGA PEKERJAAN DIVISI 6 1,678,535,601.89
DAFTAR
HARGA DASAR SATUAN UPAH

HARGA YG
HARGA SATUAN
NO URAIAN KODE SATUAN DIGUNAKAN
(Rp.)
(Rp.)

1 Pekerja (L01) Jam 16,875.00 135,000.00


2 Tukang (L02) Jam 25,000.00 200,000.00
3 Mandor (L03) Jam 31,250.00 250,000.00
4 Operator (L04) Jam 25,000.00 200,000.00
5 Pembantu Operator (L05) Jam 18,750.00 150,000.00
6 Sopir / Driver (L06) Jam 25,000.00 200,000.00
7 Pembantu Sopir / Driver (L07) Jam 18,750.00 150,000.00
8 Mekanik (L08) Jam 25,000.00 200,000.00
9 Pembantu Mekanik (L09) Jam 18,750.00 150,000.00
10 Kepala Tukang (L10) Jam 31,250.00 250,000.00
11
12
13
14
15
DAFTAR
HARGA DASAR SATUAN BAHAN

HARGA SATUAN
NO URAIAN KODE SATUAN
(Rp)

1 Pasir Pasang (Sedang) M01b M3 254,700.00


2 Pasir Beton (Kasar) M01a M3 254,700.00
3 Pasir Halus (untuk HRS) M01c M3 254,700.00
4 Pasir Urug (ada unsur lempung) M01d M3 254,700.00
5 Batu Kali M02 M3 339,200.00
6 Agregat Pecah Kasar M3 417,500.00
7 Agg. Halus LP A M3 417,500.00
8 Agregat Lolos # 1 " M3 417,500.00
9 Lolos screen1 ukuran ( 0 - 5) M3 417,500.00
10 Lolos screen2 ukuran ( 0 - 5) M3 417,500.00
11 Lolos screen2 ukuran ( 5 - 9,5) M3 417,500.00
12 Lolos screen2 ukuran ( 9.5 - 19,0) M3 417,500.00
13 Filler M05 Kg
14 Batu Belah / Kerakal M06 M3 417,500.00
15 Gravel M07 M3 417,500.00
16 Bahan Tanah Timbunan M08 M3 120,000.00
17 Bahan Timbunan Pilihan M09 M3 173,000.00
18 Aspal M10 KG 11,000.00
19 Kerosen / Minyak Tanah M11 LITER 14,300.00
20 Semen / PC (50kg) M12 Zak 119,000.00
21 Semen / PC (kg) M12 Kg 2,380.00
22 Besi Beton M13 Kg 23,800.00
23 Kawat Beton M14 Kg 28,600.00
24 Kawat Bronjong M15 Kg 102,300.00
25 Sirtu M16 M3 148,800.00
26 Cat Marka (Non Thermoplas) M17a Kg 22,500.00
27 Cat Marka (Thermoplastic) M17b Kg 27,500.00
28 Paku M18 Kg 29,800.00
29 Kayu Perancah M19 M3 2,142,000.00
30 Bensin M20 LITER 14,300.00
31 Solar M21 LITER 13,100.00
32 Minyak Pelumas / Olie M22 LITER 53,600.00
33 Plastik Filter M23 M2 15,000.00
34 Pipa Galvanis Dia. 1.6" M24 Batang 154,000.00
35 Pipa Porus M25 M' 40,000.00
36 Agr.Base Kelas A M26 M3 460,000.00
37 Agr.Base Kelas B M27 M3 460,000.00
38 Agr.Base Kelas C M28 M3 460,000.00
39 Agr.Base Kelas C2 M29 M3 0.00
40 Geotextile M30 M2 27,500.00
41 Aspal Emulsi M31 Kg 5,000.00
42 Gebalan Rumput M32 M2 3,500.00
43 Thinner M33 LITER 12,000.00
44 Glass Bead M34 Kg 28,600.00
45 Pelat Rambu (Eng. Grade) M35a BH 176,000.00
46 Pelat Rambu (High I. Grade) M35b BH 216,500.00
47 Rel Pengaman M36 M' 412,500.00
48 Beton K-250 M37 M3 2,463,223.07
49 Baja Tulangan (Polos) U24 M39a Kg 23,800.00
50 Baja Tulangan (Ulir) D32 M39b Kg 25,800.00
51 Kapur M40 M3 40,000.00
52 Chipping M41 M3 0.00
53 Chipping (kg) M41kg Kg 0.00
52 Cat M42 Kg 27,500.00
53 Pemantul Cahaya (Reflector) M43 Bh. 12,600.00
54 Pasir Urug M44 M3 165,800.00
55 Arbocell M45 Kg. 32,000.00
56 Baja Bergelombang M46 Kg 12,500.00
57 Beton K-125 M47 M3 1,714,536.10
58 Baja Struktur M48 Kg 11,000.00
59 Tiang Pancang Baja M49 M' 25,247.37
60 Tiang Pancang Beton Pratekan M50 M3 423,957.93
61 Kawat Las M51 Dos 16,000.00
62 Pipa Baja M52 Kg 15,000.00
63 Minyak Fluks M53 Liter 6,237.00
64 Bunker Oil M54 Liter 3,000.00
65 Asbuton Halus M55 Ton 325,000.00
66 Baja Prategang M56 Kg 8,000.00
67 Baja Tulangan (Polos) U32 M57a Kg 8,400.00
68 Baja Tulangan (Ulir) D39 M39c Kg 8,450.00
69 Baja Tulangan (Ulir) D48 M39d Kg 9,000.00
70 PCI Girder L=17m M58a Buah 86,000,000
71 PCI Girder L=21m M58b Buah 97,000,000
72 PCI Girder L=25m M58c Buah 124,000,000
73 PCI Girder L=32m M58d Buah 157,000,000
74 PCI Girder L=36m M58e Buah 168,000,000
75 PCI Girder L=41m M58f Buah 192,000,000
76 Beton K-300 M59 M3 2,599,305.52
77 Beton K-175 M60 M3 1,881,209.65
78 Cerucuk M61 M 15,000
79 Elastomer M62 buah 300,000
80 Bahan pengawet: kreosot M63 liter 5,000
81 Mata Kucing M64 buah 75,000
82 Anchorage M65 buah 480,000
83 Anti strpping agent M66 Kg 24,000.00
84 Bahan Modifikasi M67 Kg 1,000.00
85 Beton K-500 M68 M3 3,498,461.39
86 Beton K-400 M69 M3 3,202,532.19
87 Ducting (Kabel prestress) M70 M' 150,000
88 Ducting (Strand prestress) M71 M' 50,000
89 Beton K-350 M72 M3 3,089,312.94
90 Multipleks 12 mm M73 Lbr 181,500.00
91 Elastomer jenis 1 M74a buah 385,500.00
92 Elastomer jenis 2 M74b buah 650,000.00
93 Elastomer jenis 3 M74c buah 838,000.00
94 Expansion Tipe Joint Asphaltic Plug M75d M 1,000,000.00
95 Expansion Join Tipe Rubber M75e M 1,200,000.00
96 Expansion Join Baja Siku M75f M 275,000.00
97 Marmer M76 Buah 400,000.00
98 Kerb Type A M77 Buah 45,000.00
99 Paving Block M78 Buah 40,000.00
100 Mini Timber Pile M79 Buah 27,000.00
101 Expansion Joint Tipe Torma M80 M1 1,200,000.00
102 Strip Bearing M81 Buah 229,500.00
103 Joint Socket Pile 35x35 M82 Set 607,500.00
104 Joint Socket Pile 16x16x16 M83 Set 67,500.00
105 Mikro Pile 16x16x16 M84 M1 60,750.00
106 Matras Concrete M85 Buah 405,000.00
107 Assetilline M86 Botol 229,500.00
108 Oxygen M87 Botol 114,750.00
109 Batu Bara M88 Kg 600.00
110 Pipa Galvanis Dia 3" M24a M 20,000.00
111 Pipa Galvanis Dia 1,5" M24b M 15,000.00
112 Agregat Pecah Mesin 0-5 mm M91 M3 320,000.00
113 Agregat Pecah Mesin 5-10 & 10-20 mm M92 M3 320,000.00
114 Agregat Pecah Mesin 20-30 mm M93 M3 320,000.00
115 Joint Sealent M94 Kg 34,100.00
116 Cat Anti Karat M95 Kg 35,750.00
117 Expansion Cap M96 M2 6,050.00
118 Polytene 125 mikron M97 Kg 19,250.00
119 Curing Compound M98 Ltr 38,500.00
120 Kayu Acuan M99 M3 2,142,000.00
121 Additive M67a Ltr 38,500.00
122 Casing M100 M2 9,000.00
123 Pasir Tailing M3 259,000.00
124 Polimer 45,000.00
125 Batubara kg 500.00
126 Kerb jenis 1 Buah 45,000.00
127 Kerb jenis 2 Buah 50,000.00
128 Kerb jenis 3 Buah 55,000.00
129 Bahan Modifikasi Kg 75,000.00
130 Aditif anti pengelupasan Kg 30,000.00
131 Bahan Pengisi (Filler) Tambahan Kg 3,600.00
132 Asbuton yang diproses Kg 30,000.00
133 Elastomer Alam Kg 30,000.00
134 Elastomer Sintesis Kg 30,000.00
137 Anchorage
135 - hidup bh 750,000.00
136 - mati bh 400,000.00
140 Kabel Prategang Kg
141 - Selongsong M' 0.00
137 - Baja Prategang Kg 8,000.00
DAFTAR BIAYA PERALATAN

BIAYA SEWA
NO URAIAN KODE HP KAP. HARGA ALAT ALAT / JAM (di luar KET.
PPN)

1 ASPHALT MIXING PLANT E01 294.0 60.0 T/Jam 5,482,600,000 6,989,309.09

2 ASPHALT FINISHER E02 72.4 10.0 Ton 1,832,300,000 474,578.73

3 ASPHALT SPRAYER E03 4.0 850.0 Liter 207,000,000 71,315.06

4 BULLDOZER 100-150 HP E04 155.0 - - 1,502,000,000 819,763.62

5 COMPRESSOR 4000-6500 L\M E05 60.0 5,000.0 CPM/(L/m) 449,400,000 184,393.83

6 CONCRETE MIXER 0.3-0.6 M3 E06 20.0 500.0 Liter 25,000,000 169,519.36

7 CRANE 10-15 TON E07 138.0 15.0 Ton 1,123,500,000 646,626.79

8 DUMP TRUCK 3.5 TON E08 100.0 3.5 Ton 450,000,000 300,000.00

9 DUMP TRUCK 10 TON E09 190.0 10.0 Ton 750,000,000 545,797.00

10 EXCAVATOR 80-140 HP E10 133.0 0.9 M3 1,298,700,000 571,301.00

11 FLAT BED TRUCK 3-4 M3 E11 190.0 10.0 ton 750,000,000 491,747.19

12 GENERATOR SET E12 180.0 135.0 KVA 1,146,000,000 452,989.72

13 MOTOR GRADER >100 HP E13 135.0 10,800.0 - 1,568,500,000 651,097.00

14 TRACK LOADER 75-100 HP E14 70.0 0.8 M3 1,092,300,000 297536.97

15 WHEEL LOADER 1.0-1.6 M3 E15 96.0 1.5 M3 1,470,000,000 591,483.16

16 THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 750,000,000 219,335.60

17 TANDEM ROLLER 6-8 T. E17 82.0 8.1 Ton 542,100,000 410,260.92

18 TIRE ROLLER 8-10 T. E18 100.5 9.0 Ton 834,300,000 378,138.67

19 VIBRATORY ROLLER 5-8 T. E19 82.0 7.1 Ton 896,400,000 343,003.00

20 CONCRETE VIBRATOR E20 5.5 25.0 - 20,000,000 45,285.68

21 STONE CRUSHER E21 220.0 60.0 T/Jam 2,009,200,000 941,417.73

22 WATER PUMP 70-100 mm E22 6.0 - - 15,000,000 44,843.53

23 WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 623,800,000 302,236.47

24 PEDESTRIAN ROLLER E24 8.8 835.00 Ton 168,900,000 126,236.47

25 TAMPER E25 4.7 121.00 Ton 50,000,000 48,242.20

26 JACK HAMMER E26 0.0 1,330.00 - 249,100,000 35,408.56

27 FULVI MIXER E27 345.0 2,005.00 - 2,441,600,000 1,367,981.35

28 CONCRETE PUMP E28 100.0 8.00 M3 580,500,000 298,830.60

29 TRAILER 20 TON E29 175.0 20.00 Ton 1,130,700,000 550,479.19

30 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 1,000,000,000 169,133.55

31 CRANE ON TRACK 35 TON E31 125.0 35.0 Ton 6,648,300,000 431,151.32

32 WELDING SET E32 40.0 250.0 Amp 256,600,000 118,312.40

33 BORE PILE MACHINE E33 150.0 2,000.0 Meter 2,430,000,000 808,789.97

34 ASPHALT LIQUID MIXER E34 5.0 1,000.0 Liter 94,800,000 41,488.18

35 TRONTON E35 150.0 15.0 Ton 772,600,000 541,091.26

36 COLD MILLING E36 248.0 1,000.0 m 4,451,000,000 1,665,566.59

37 ROCK DRILL BREAKER E37 3.0 - - 1,623,100,000 293,942.51

38 COLD RECYCLER E38 900.0 2,200.0 M 17,550,000,000 3,963,621.57

39 HOT RECYCLER E39 400.0 3.0 M 26,325,000,000 7,469,096.84

40 AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M 1,355,300,000 536,352.37

41 ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter 901,400,000 364,803.75

42 SLIP FORM PAVER E42 105.0 2.5 M 998,500,000 536,616.61


43 CONCRETE PAN MIXER E43 134.0 600.0 Liter 1,318,800,000 651,460.57

44 CONCRETE BREAKER E44 290.0 20.0 m3/jam 1,800,100,000 837,662.98

45 ASPAHLT TANKER E45 190.0 4,000.0 liter 1,284,800,000 556,068.66

46 CEMENT TANKER E46 190.0 4,000.0 liter 1,191,200,000 516,086.66

47 CONDRETE MIXER (350) E47 20.0 350.0 liter 457,100,000 75,128.75

48 VIBRATING RAMMER E48 4.0 80.0 KG 261,800,000 136,568.74

49 TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 1,393,600,000 641,769.15

50 BORE PILE MACHINE E50 125.0 60.0 CM 2,430,000,000 656,857.27

51 CRANE ON TRACK 75-100 TON E51 200.0 75.0 Ton 8,085,800,000 634,662.98

52 BLENDING EQUIPMENT E52 50.0 30.0 Ton 675,200,000 147,300.02

53 ASPHALT LIQUID MIXER E34a 40.0 20,000.0 Liter 94,800,000 113,238.18


FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.2.(2a)


JENIS PEKERJAAN : Timbunan Pilihan Dari Sumber Gaian
SATUAN PEMBAYARAN : M3

HARGA
PERKIRAAN
NO. KOMPONEN SATUAN SATUAN JUMLAH HARGA (Rp.)
KUANTITAS
(Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.9749 16,875.00 16,450.89


2. Mandor (L03) Jam 0.3137 31,250.00 9,803.65

JUMLAH HARGA TENAGA 26,254.55

B. BAHAN

1. Bahan Timbunan Pilihan (M09) M3 1.3980 173,000.00 241,854.00

JUMLAH HARGA BAHAN 241,854.00

C. PERALATAN
1. Wheel Loader (E15) Jam 0.0047 591,483.16 2,760.25
2. Dump Truck (E09) Jam 0.2437 300,000.00 73,115.08
3. Motor Grader (E13) Jam 0.0040 651,097.00 2,583.72
3. Tandem (E17) Jam 0.0161 410,260.92 6,607.05
4. Water Tanker (E23) Jam 0.0070 302,236.47 2,124.15
5. Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 87,690.26

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 355,798.81


E. OVERHEAD & PROFIT 15.0 % x D 53,369.82
F. HARGA SATUAN PEKERJAAN ( D + E ) 409,168.63

Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 3.3.(1)


JENIS PEKERJAAN : Penyiapan Badan Jalan
SATUAN PEMBAYARAN : M2

HARGA
PERKIRAAN
NO. KOMPONEN SATUAN SATUAN JUMLAH HARGA (Rp.)
KUANTITAS
(Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0719 16,875.00 1,213.39


2. Mandor (L02) jam 0.0630 31,250.00 1,968.01

JUMLAH HARGA TENAGA 3,181.40

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN
1. Motor Grader (E13) jam 0.0113 651,097.00 7,331.35
2. Vibro Roller (E19) jam 0.0010 343,003.00 356.82
3 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 7,688.17

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 10,869.57


E. OVERHEAD & PROFIT 15.0 % x D 1,630.44
F. HARGA SATUAN PEKERJAAN ( D + E ) 12,500.00

Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 6.6.(1)


JENIS PEKERJAAN : Lapis Permukaan Penetrasi Macadam
SATUAN PEMBAYARAN : M3

HARGA
PERKIRAAN
NO. KOMPONEN SATUAN SATUAN JUMLAH HARGA (Rp.)
KUANTITAS
(Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2417 16,875.00 4,079.42


2. Mandor (L03) Jam 0.0142 31,250.00 442.95

JUMLAH HARGA TENAGA 4,522.37

B. BAHAN

1. #REF! (M03) M3 2.0446 417,500.00 853,640.49


2. Agregat Halus (M04) M3 0.4265 417,500.00 178,054.93
3 #REF! (M10) Kg 103.0000 10,000.00 1,030,000.00

JUMLAH HARGA BAHAN 2,061,695.42

C. PERALATAN

1. Wheel Loader E15 Jam 0.0071 591,483.16 4,191.94


2. Dump Truck E09 Jam 0.1824 545,797.00 99,534.39
3. 3-Wheel Roller E16 Jam 0.0435 219,335.60 9,537.19
4. Asp. Sprayer E03 Jam 0.3788 71,315.06 27,013.28
5. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 140,276.81

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 2,206,494.60


E. OVERHEAD & PROFIT 15.0 % x D 330,974.19
F. HARGA SATUAN PEKERJAAN ( D + E ) 2,537,468.79

Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

Anda mungkin juga menyukai