Monitoring Paket : Sp. Medang - Na.

Mau
KONTRAKTOR = PT. RIYAN DASRI
KONSULTAN = PT. BAHANA CITRA KHATULISTIWA
KONTRAK
MINGGU LALU
NO URAIAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT
VOLUME
(Rp) (RP) (%) VOLUME

DIVISI 1 - UMUM
1.2 Mobilisasi Ls 1.00 453,600,000.00 453,600,000.00 4.073 -
1.8 Manajemen dan Keselamatan lalu lintas Ls 1.00 12,882,143.00 12,882,143.00 0.116 -
DIVISI 2 - DRAINASE
2.1 Galian untuk Selokan, Drainase dan Saluran Air M3 2,100.00 50,079.00 105,165,900.00 0.944 -
DIVISI 3 - PEKERJAAN TANAH
3.1.1 Galian Biasa M3 1,132.00 54,647.00 61,860,404.00 0.555 -
3.2.2 Timbunan Pilihan M3 5,825.00 113,850.00 663,176,250.00 5.955 -
3.3 Penyiapan Badan Jalan M² 13,550.00 3,006.00 40,731,300.00 0.366 -
DIVISI 5 - PERKERASAN BERBUTIR
5.1.1 Lapis Pondasi Agregat Kelas A M3 1,262.00 798,827.00 1,008,119,674.00 9.053
5.1.2 Lapis Pondasi Agregat Kelas B M3 6,128.00 662,769.00 4,061,448,432.00 36.471
5.6.(1) Lapis Pondasi Agregat dengan Semen (CTB) M3 650.00 752,058.00 488,837,700.00 4.390
5.6.(2) Semen Utk Lapis Pondasi Agregat dengan Semen Ton 146.30 2,163,240.00 316,482,012.00 2.842 -
A.5.7.1 Lapis Pondasi Telford M3 1,600.00 120,508.00 192,812,800.00 1.731 -
DIVISI 6 - PERKERASAN ASPAL
6.1.(1)(a) Lapis Resap Pengikat - Aspal Cair Ltr 6,256.00 16,882.00 105,613,792.00 0.948 -
6.1.(2)(a) Lapis Perekat - Aspal Cair Ltr 2,010.00 17,826.00 35,830,260.00 0.322 -
6.3.4a Lataston Lapis Pondasi (HRS-Base) Ton 1,088.00 886,829.00 964,869,952.00 8.664 -
6.3.8a Aspal Minyak Ltr 70.70 13,530,115.00 956,579,130.50 8.590 -
6.6.(2) Lapis Pondasi / Perata Penetrasi Macadam M3 160.00 1,378,258.00 220,521,280.00 1.980 -
DIVISI 7 - STRUKTUR
7.1.(6) Beton Mutu Sedang, ƒc '25 Mpa atau K-300 M3 62.50 1,917,750.00 119,859,375.00 1.076 -
7.1(7) Beton Mutu Sedang, ƒc '20 Mpa atau K-250 M3 15.00 1,669,727.00 25,045,905.00 0.225 -
7.1.(10) Beton mutu rendah, fc '10 Mpa atau K-125 M3 11.00 1,321,002.00 14,531,022.00 0.130 -
7.3.(1) Baja Tulangan U-24 Polos Kg 19,774.00 24,539.00 485,234,186.00 4.357 -
7.5.(1)a Pengangkutan Dan Pemasangan Jbt Rangka (Bailley) M' 18.00 7,556,827.00 136,022,886.00 1.221 -
7.6.(1) Pengadaan dan Pemancangan Cerucuk M' 360.00 58,396.00 21,022,560.00 0.189 -
7.9 Pasangan Batu M3 93.00 967,862.00 90,011,166.00 0.808 -
DIVISI 8 - PENGEMBALIAN KONDISI DAN PEK. MINOR
8.1.(5) Campuran Aspal Panas untuk Pekerjaan Minor M2 60.00 3,742,870.00 224,572,200.00 2.017 -
A.8.9 Perataan dan Pemadatan Jalan Tidak Beraspal/TUK-A M2 48,040.00 4,712.00 226,364,480.00 2.033 -
DIVISI 9 - PEKERJAAN HARIAN
9.1.1 Mandor Jam 120.00 13,842.86 1,661,143.20 0.015 -
9.1.2 Pekerja Biasa Jam 900.00 10,200.00 9,180,000.00 0.082 -
9.1.3 Tukang Kayu, Tukang Batu, dll Jam 300.00 11,657.14 3,497,142.00 0.031 -
9.1.(8) Motor Grader Min 100 PK Ls 84.00 602,664.00 50,623,776.00 0.455 -
A.9.1.22 Bahan Ls 1.00 40,000,000.00 40,000,000.00 0.359 -

REALISASI (%) = 11,136,156,870.70 100.000


RENCANA (%) = 1,113,615,687.07 100.000
DEVIASI (%) = 12,249,772,557.77
12,249,772,000.00
Monitoring Paket : Sp. Medang - Na. Mau
KONTRAKTOR = PT. RIYAN DASRI
KONSULTAN = PT. BAHANA CITRA KHATULISTIWA
KONTRAK
MINGGU LALU
NO URAIAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT
VOLUME
(Rp) (RP) (%) VOLUME

DIVISI 1 - UMUM
1.2 Mobilisasi Ls 1.00 453,600,000.00 453,600,000.00 4.073 0.70
1.8 Manajemen dan Keselamatan lalu lintas Ls 1.00 12,882,143.00 12,882,143.00 0.116 0.70
DIVISI 2 - DRAINASE
2.1 Galian untuk Selokan, Drainase dan Saluran Air M3 2,100.00 50,079.00 105,165,900.00 0.944 300.00
DIVISI 3 - PEKERJAAN TANAH
3.1.1 Galian Biasa M3 1,132.00 54,647.00 61,860,404.00 0.555 100.00
3.2.2 Timbunan Pilihan M3 5,825.00 113,850.00 663,176,250.00 5.955 4,000.00
3.3 Penyiapan Badan Jalan M² 13,550.00 3,006.00 40,731,300.00 0.366 2,000.00
DIVISI 5 - PERKERASAN BERBUTIR
5.1.1 Lapis Pondasi Agregat Kelas A M3 1,262.00 798,827.00 1,008,119,674.00 9.053 -
5.1.2 Lapis Pondasi Agregat Kelas B M3 6,128.00 662,769.00 4,061,448,432.00 36.471 300.00
5.6.(1) Lapis Pondasi Agregat dengan Semen (CTB) M3 650.00 752,058.00 488,837,700.00 4.390 -
5.6.(2) Semen Utk Lapis Pondasi Agregat dengan Semen Ton 146.30 2,163,240.00 316,482,012.00 2.842 -
A.5.7.1 Lapis Pondasi Telford M3 1,600.00 120,508.00 192,812,800.00 1.731 -
DIVISI 6 - PERKERASAN ASPAL
6.1.(1)(a) Lapis Resap Pengikat - Aspal Cair Ltr 6,256.00 16,882.00 105,613,792.00 0.948 -
6.1.(2)(a) Lapis Perekat - Aspal Cair Ltr 2,010.00 17,826.00 35,830,260.00 0.322 -
6.3.4a Lataston Lapis Pondasi (HRS-Base) Ton 1,088.00 886,829.00 964,869,952.00 8.664 -
6.3.8a Aspal Minyak Ltr 70.70 13,530,115.00 956,579,130.50 8.590 -
6.6.(2) Lapis Pondasi / Perata Penetrasi Macadam M3 160.00 1,378,258.00 220,521,280.00 1.980 -
DIVISI 7 - STRUKTUR
7.1.(6) Beton Mutu Sedang, ƒc '25 Mpa atau K-300 M3 62.50 1,917,750.00 119,859,375.00 1.076 -
7.1(7) Beton Mutu Sedang, ƒc '20 Mpa atau K-250 M3 15.00 1,669,727.00 25,045,905.00 0.225 -
7.1.(10) Beton mutu rendah, fc '10 Mpa atau K-125 M3 11.00 1,321,002.00 14,531,022.00 0.130 -
7.3.(1) Baja Tulangan U-24 Polos Kg 19,774.00 24,539.00 485,234,186.00 4.357 -
7.5.(1)a Pengangkutan Dan Pemasangan Jbt Rangka (Bailley) M' 18.00 7,556,827.00 136,022,886.00 1.221 -
7.6.(1) Pengadaan dan Pemancangan Cerucuk M' 360.00 58,396.00 21,022,560.00 0.189 100.00
7.9 Pasangan Batu M3 93.00 967,862.00 90,011,166.00 0.808 -
DIVISI 8 - PENGEMBALIAN KONDISI DAN PEK. MINOR
8.1.(5) Campuran Aspal Panas untuk Pekerjaan Minor M2 60.00 3,742,870.00 224,572,200.00 2.017 -
A.8.9 Perataan dan Pemadatan Jalan Tidak Beraspal/TUK-A M2 48,040.00 4,712.00 226,364,480.00 2.033 -
DIVISI 9 - PEKERJAAN HARIAN
9.1.1 Mandor Jam 120.00 13,842.86 1,661,143.20 0.015 -
9.1.2 Pekerja Biasa Jam 900.00 10,200.00 9,180,000.00 0.082 -
9.1.3 Tukang Kayu, Tukang Batu, dll Jam 300.00 11,657.14 3,497,142.00 0.031 -
9.1.(8) Motor Grader Min 100 PK Ls 84.00 602,664.00 50,623,776.00 0.455 -
A.9.1.22 Bahan Ls 1.00 40,000,000.00 40,000,000.00 0.359 -

REALISASI (%) = 11,136,156,870.70 100.000


RENCANA (%) = 1,113,615,687.07 100.000
DEVIASI (%) = 12,249,772,557.77
12,249,772,000.00
MINGGU KE : ………..
TANGGAL : ………..
PROGRESS
MINGGU LALU MINGGU INI s/d MINGGU INI
BOBOT BOBOT BOBOT
VOLUME VOLUME
(%) (%) (%)

- 0.70 2.851 0.70 2.851


- 0.70 0.081 0.70 0.081

- 300.00 0.135 300.00 0.135

- 100.00 0.049 100.00 0.049


- 4,000.00 4.089 4,000.00 4.089
- 2,000.00 0.054 2,000.00 0.054

- - - -
300.00 1.785 300.00 1.785
- - -
- - - -
- - - -

- - - -
- - - -
- - - -
- - - -
- - - -

- - - -
- - - -
- - - -
- - - -
- - - -
- 100.00 0.052 100.00 0.052
- - - -

- - - -
- - - -

- - - -
- - - -
- - - -
- - - -
- - - -

9.097
17.867
8.769
MINGGU KE : ………..
TANGGAL : ………..
PROGRESS
MINGGU LALU MINGGU INI s/d MINGGU INI
BOBOT BOBOT BOBOT
VOLUME VOLUME
(%) (%) (%)

2.851 - 0.70 2.851


0.081 - 0.70 0.081

0.135 - 300.00 0.135

0.049 - 100.00 0.049


4.089 - 4,000.00 4.089
0.054 - 2,000.00 0.054

- - - -
1.785 - 300.00 1.785
- - - -
- - - -
- - - -

- - - -
- - - -
- - - -
- - - -
- - - -

- - - -
- - - -
- - - -
- - - -
- - - -
0.052 - 100.00 0.052
- - - -

- - - -
- - - -

- - - -
- - - -
- - - -
- - - -
- - - -

9.097
-
(9.097)