RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 0 - 15.

3 KM

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 750,000,000.00 750,000,000.00 1.45
1.1.2 Project Set Up Opration Ls 1.00 2,163,200,000.00 2,163,200,000.00 4.18
1.1.3 Safety Ls 1.00 35,000,000.00 35,000,000.00 0.07
Sub Total 2,948,200,000.00
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing M2 434,910.00 4,300.00 1,870,113,000.00 3.61
2.2 Striping M2 434,910.00 3,210.00 1,396,061,100.00 2.70
Sub Total 3,266,174,100.00
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 29,335.90 28,680.00 841,353,612.00 1.62
3.1.2 Cut & Fill 50 - 1000 M M3 339,338.51 39,110.00 13,271,529,126.10 25.62
3.1.3 Cut & Fill 1000 - 5000 M M3 192,658.75 43,110.00 8,305,518,712.50 16.03
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 23,562.00 583,023.73 13,737,205,126.26 26.52
Sub Total 36,155,606,576.86
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 154,560,000.00 154,560,000.00 0.30
Fuel (Solar) Ls 1.00 158,681,600.00 158,681,600.00 0.31
Mobilisasi dan Demobilisasi Ls 1.00 15,000,000.00 15,000,000.00 0.03
Upah Pekerja dan Uang Makan Ls 1.00 234,000,000.00 234,000,000.00 0.45
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 9 Unit m 262.00 4,013,100.00 1,051,432,200.00 2.03
1500 mm ---> 9 Unit m 262.00 4,908,881.25 1,286,126,887.50 2.48
2000 mm ---> 24 Unit m 942.00 6,557,118.75 6,176,805,862.50 11.92
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 51,519,000.00 51,519,000.00 0.10
Fuel --- 20 Liter/hr Ls 1.00 52,893,918.00 52,893,918.00 0.10
Mobilisasi dan Demobilisasi Ls 1.00 15,000,000.00 15,000,000.00 0.03
Upah Pekerja dan Uang Makan Ls 1.00 234,000,000.00 234,000,000.00 0.45
Sub Total 9,430,019,468.00
Total Keseluruhan 51,800,000,144.86 100.00
5,698,000,015.93
57,498,000,160.79
382,500,000.00 245,098,039.22 137,401,960.78
692,224,000.00 706,928,104.58
24,500,000.00 11,437,908.50 13,062,091.50

459,000 - 24,090.00 15000 0.03 3.45

30 8000 240,000
232,000 1.925869

187,000 1.158822
3.084691

1,817,088,000.00

5.05% 2,903,649,008.12
RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 504,901,960.78 504,901,960.78 #VALUE!
1.1.2 Project Set Up Opration Ls 1.00 1,456,271,895.42 1,456,271,895.42 #VALUE!
1.1.3 Safety Ls 1.00 23,562,091.50 23,562,091.50 #VALUE!
Sub Total 1,984,735,947.71 2,948,200,000.00
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing M2 285,243.16 4,300.00 1,226,545,603.37 #VALUE! 459,000 - 173,756.84 15000 0.05 5.26
2.2 Striping M2 313,391.62 3,210.00 1,005,987,100.58 #VALUE!
Sub Total 2,232,532,703.95 3,266,174,115.75
3 PEKERJAAN STRUKTUR JALAN 30 8000 240,000
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan 232,000 #VALUE!
3.1.1 Cut & Fill 0 - 50 M M3 19,749.00 28,680.00 566,401,320.00 #VALUE!
3.1.2 Cut & Fill 50 - 1000 M M3 228,443.57 39,110.00 8,934,428,022.70 #VALUE! 187,000 #VALUE!
3.1.3 Cut & Fill 1000 - 5000 M M3 192,658.75 43,110.00 8,305,518,712.50 #VALUE! #VALUE!
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 #VALUE! 583,023.73 #VALUE! #VALUE!
Sub Total #VALUE! #VALUE!
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary 1,223,268,392.16
Sewa Alat (Exca/Ponton) Ls 1.00 104,050,196.08 104,050,196.08 #VALUE!
Fuel (Solar) Ls 1.00 106,824,867.97 106,824,867.97 #VALUE!
Mobilisasi dan Demobilisasi Ls 1.00 10,098,039.22 10,098,039.22 #VALUE!
Upah Pekerja dan Uang Makan Ls 1.00 157,529,411.76 157,529,411.76 #VALUE! 5.05% #VALUE!
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 9 Unit m 132.00 4,013,100.00 529,729,200.00 #VALUE!
1500 mm ---> 3 Unit m 63.00 4,908,881.25 309,259,518.75 #VALUE!
2000 mm ---> 21 Unit m 871.00 6,557,118.75 5,711,250,431.25 #VALUE!
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 34,682,725.49 34,682,725.49 #VALUE!
Fuel --- 20 Liter/hr Ls 1.00 35,608,323.88 35,608,323.88 #VALUE!
Mobilisasi dan Demobilisasi Ls 1.00 10,098,039.22 10,098,039.22 #VALUE!
Upah Pekerja dan Uang Makan Ls 1.00 157,529,411.76 157,529,411.76 #VALUE!
Sub Total 7,166,660,165.39 9,314,525,050.35
Total Keseluruhan #VALUE! #VALUE!

#VALUE!

#VALUE!
#VALUE!
RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 0-5KM

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 245,098,039.22 245,098,039.22 2.80
1.1.2 Project Set Up Opration Ls 1.00 706,928,104.58 706,928,104.58 8.07
1.1.3 Safety Ls 1.00 11,437,908.50 11,437,908.50 0.13
Sub Total 963,464,052.29
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 05+000) M2 149,666.84 4,300.00 643,567,412.00 7.35 Topo sudah diambil
2.2 Striping (STA 00+000 - STA 05+000) M2 121,518.38 3,210.00 390,073,999.80 4.45 Topo sudah diambil
Sub Total 1,033,641,411.80
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 9,586.90 28,680.00 274,952,160.78 3.14
3.1.2 Cut & Fill 50 - 1000 M M3 110,894.94 39,110.00 4,337,100,967.92 49.53
3.1.3 Cut & Fill 1000 - 5000 M M3 - 43,110.00 0.00
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 - - - 0.00
Sub Total 4,612,053,128.70
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 50,509,803.92 50,509,803.92 0.58 2.10
Fuel (Solar) Ls 1.00 51,856,732.03 51,856,732.03 0.59
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.06
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.87
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 130.00 4,013,100.00 521,703,000.00 5.96 22.43
1500 mm ---> 9 Unit m 199.00 4,908,881.25 976,867,368.75 11.16
2000 mm ---> 3 Unit m 71.00 6,557,118.75 465,555,431.25 5.32
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls - - - 0.00
Fuel --- 20 Liter/hr Ls - - - 0.00
Mobilisasi dan Demobilisasi Ls - - - 0.00
Upah Pekerja dan Uang Makan Ls - - - 0.00
Sub Total 2,147,864,884.97
Total Keseluruhan 8,757,023,477.75 100.00
RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 0-5KM

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 245,098,039.22 245,098,039.22 2.87
1.1.2 Project Set Up Opration Ls 1.00 706,928,104.58 706,928,104.58 8.27
1.1.3 Safety Ls 1.00 11,437,908.50 11,437,908.50 0.13
Sub Total 963,464,052.29
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 05+000) M2 149,666.84 4,300.00 643,567,396.63 7.53 Topo sudah diambil
2.2 Striping (STA 00+000 - STA 05+000) M2 121,518.38 3,210.00 390,073,999.42 4.57 Topo sudah diambil
Sub Total 1,033,641,396.05
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 10,606.25 28,680.00 304,187,250.00 3.56
3.1.2 Cut & Fill 50 - 1000 M M3 101,768.25 39,110.00 3,980,156,257.50 46.58
3.1.3 Cut & Fill 1000 - 5000 M M3 - 43,110.00 0.00
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 7,700.00 583,023.73 - 0.00
Sub Total 4,284,343,507.50
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 50,509,803.92 50,509,803.92 0.59
Fuel (Solar) Ls 1.00 51,856,732.03 51,856,732.03 0.61
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.06
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.89
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 130.00 4,013,100.00 521,703,000.00 6.11
1500 mm ---> 9 Unit m 199.00 4,908,881.25 976,867,368.75 11.43
2000 mm ---> 3 Unit m 71.00 6,557,118.75 465,555,431.25 5.45
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 16,836,274.51 16,836,274.51 0.20
Fuel --- 20 Liter/hr Ls 1.00 17,285,594.12 17,285,594.12 0.20
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.06
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.89
Sub Total 2,263,359,302.61
Total Keseluruhan 8,544,808,258.46 100.00
RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 5-8,5 KM

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 0.00
1.1.2 Project Set Up Opration Ls 0.00
1.1.3 Safety Ls 0.00
Sub Total -
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 05+000) M2 96,119.86 4,300.00 413,315,398.00 53.75 Topo sudah diambil
2.2 Striping (STA 00+000 - STA 05+000) M2 69,972.99 3,210.00 224,613,297.90 29.21 Topo sudah diambil
Sub Total 637,928,695.90
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 0.00
3.1.2 Cut & Fill 50 - 1000 M M3 0.00
3.1.3 Cut & Fill 1000 - 5000 M M3 0.00
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 0.00
Sub Total -
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 36,003,388.24 36,003,388.24 4.68
Fuel (Solar) Ls 1.00 36,963,478.59 36,963,478.59 4.81
Mobilisasi dan Demobilisasi Ls 1.00 3,494,117.65 3,494,117.65 0.45
Upah Pekerja dan Uang Makan Ls 1.00 54,508,235.29 54,508,235.29 7.09
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 0.00
1500 mm ---> 9 Unit m 0.00
2000 mm ---> 3 Unit m 0.00
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 0.00
Fuel --- 20 Liter/hr Ls 0.00
Mobilisasi dan Demobilisasi Ls 0.00
Upah Pekerja dan Uang Makan Ls 0.00
Sub Total 130,969,219.77
Total Keseluruhan 768,897,915.67 100.00
RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 0-5KM

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 245,098,039.22 245,098,039.22 1.88
1.1.2 Project Set Up Opration Ls 1.00 706,928,104.58 706,928,104.58 5.42
1.1.3 Safety Ls 1.00 11,437,908.50 11,437,908.50 0.09
Sub Total 963,464,052.29
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 05+000) M2 149,666.84 4,300.00 643,567,396.63 4.94 Topo sudah diambil
2.2 Striping (STA 00+000 - STA 05+000) M2 121,518.38 3,210.00 390,073,999.42 2.99 Topo sudah diambil
Sub Total 1,033,641,396.05
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 10,606.25 28,680.00 304,187,250.00 2.33
3.1.2 Cut & Fill 50 - 1000 M M3 101,768.25 39,110.00 3,980,156,257.50 30.54
3.1.3 Cut & Fill 1000 - 5000 M M3 - 43,110.00 0.00
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 7,700.00 583,023.73 4,489,282,721.00 34.44
Sub Total 8,773,626,228.50
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 50,509,803.92 50,509,803.92 0.39
Fuel (Solar) Ls 1.00 51,856,732.03 51,856,732.03 0.40
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.04
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.59
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 130.00 4,013,100.00 521,703,000.00 4.00
1500 mm ---> 9 Unit m 199.00 4,908,881.25 976,867,368.75 7.49
2000 mm ---> 3 Unit m 71.00 6,557,118.75 465,555,431.25 3.57
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 16,836,274.51 16,836,274.51 0.13
Fuel --- 20 Liter/hr Ls 1.00 17,285,594.12 17,285,594.12 0.13
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.04
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.59
Sub Total 2,263,359,302.61
Total Keseluruhan 13,034,090,979.46 100.00
TIME SCHEDULE COAL

TOTAL HARGA BOBOT Mei Juni Juli


NO URAIAN PEKERJAAN UNIT VOLUME M1 (17-21) M2 (22-28) M3 (29-04) M4 (05-11) M5 (12-18) M6 (19-25) M7 (26-02) M8 (03-09) M9 (10-16) M10 (17-23) M11 (24-30) M12 (31-06)
(RP) (%) T A T A T A T A T A T A T A T A T A T A T A T

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 245,098,039.22 1.89 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08 0.24 0.08
1.1.2 Project Set Up Opration Ls 1.00 706,928,104.58 5.44 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18 0.43 0.18
1.1.3 Safety Ls 1.00 11,437,908.50 0.09 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 05+000) M2 147,936.54 636,127,139.20 4.90 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49 0.49
2.2 Striping (STA 00+000 - STA 05+000) M2 110,644.91 355,170,167.52 2.73 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 10,606.25 304,187,250.00 2.34 0.08 0.00 0.08 0.00 0.08 0.00 0.08 0.00 0.08 0.00 0.08 0.00 0.08 0.02 0.08 0.02 0.08 0.02 0.08 0.02 0.08
3.1.2 Cut & Fill 50 - 1000 M M3 101,768.25 3,980,156,257.50 30.64 1.23 0.00 1.23 0.00 1.23 0.00 1.23 0.00 1.23 0.00 1.23 0.00 1.23 0.00 1.23 0.00 1.23 0.00 1.23
3.1.3 Cut & Fill 1000 - 5000 M M3 -
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebal M3 7,700.00 4,489,282,721.00 34.55 1.57 0.00 1.57 0.00 1.57 0.00 1.57 0.00 1.57
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 50,509,803.92 0.39 0.04 0.09 0.04 0.09 0.04 0.00 0.04 0.00 0.04 0.00 0.04 0.09 0.04 0.09 0.04 0.09 0.04 0.09 0.04
Fuel (Solar) Ls 1.00 51,856,732.03 0.40 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 0.04 0.02 0.04 0.02 0.00
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 0.59 0.03 0.06 0.03 0.06 0.03 0.06 0.03 0.06 0.03 0.06 0.03 0.06 0.03 0.06 0.03 0.06 0.03 0.06 0.03
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 130.00 521,703,000.00 4.02 0.57 0.00 0.57 0.00 0.57
1500 mm ---> 9 Unit m 199.00 976,867,368.75 7.52
2000 mm ---> 3 Unit m 71.00 465,555,431.25 3.58
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 16,836,274.51 0.13
Fuel --- 20 Liter/hr Ls 1.00 17,285,594.12 0.13
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 0.04
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 0.59
Sub Total 2,263,359,302.61
Total Keseluruhan 12,991,746,890.12 100.00
Rencana Minggu Ini 0.27 1.11 2.43 2.43 2.43 2.44 2.44 4.01 4.01 4.58 4.60 3.81
Total Rencana Minggu Ini 0.27 1.38 3.81 6.23 8.66 11.10 13.54 17.55 21.56 26.14 30.74 34.55

Realisasi Minggu Ini 0.68 1.47 1.63 1.63 1.54 1.55 1.55 1.66 1.66 1.66 1.66
Total Realisasi Minggu Ini 0.68 2.15 3.78 5.41 6.94 8.49 10.04 11.70 13.36 15.01 16.67
Deviasi Rencana Terhadap Deviasi 0.42 0.77 -0.03 -0.83 -1.72 -2.61 -3.49 -5.85 -8.20 -11.13 -14.07
TIME SCHEDULE COAL HAULING ROAD SKC

Juli Agustus
M12 (31-06) M13 (07-13) M14 (14-20) M15 (21-27) M16 (28-03)
A T A T A T A T

0.21 0.08 0.00 0.08 0.00 0.08 0.08


0.43 0.18 0.00 0.18 0.00 0.18 0.18
0.04

0.14 0.08 0.29 0.08 0.29 0.08 0.08


0.00 1.23 0.04 1.23 1.60 1.23 1.23

0.00 1.57 0.00 1.57 0.00 1.57 1.57

0.11
0.11

0.11 0.03 0.00 0.03 0.00 0.03 0.03

0.00 0.57 0.00 0.57 0.00 0.57 0.57


1.50 1.50

3.73 3.73 5.23 5.23


38.28 42.01 47.24 52.47

1.14 0.32 1.89 0.00


17.81 18.13 20.02 20.02
-16.74 -20.15 -21.99 -27.22
TIM

Mei Juni
TOTAL HARGA BOBOT
NO URAIAN PEKERJAAN UNIT VOLUME M1 (17-21) M2 (22-28) M3 (29-04) M4 (05-11) M5 (12-18) M6 (19-25) M7 (26-02) M8 (03-09)
(RP) (%) T T T T T T T T

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 245,098,039.22 1.89 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
1.1.2 Project Set Up Opration Ls 1.00 706,928,104.58 5.44 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18
1.1.3 Safety Ls 1.00 11,437,908.50 0.09 0.01 0.01 0.01 0.01
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 05+000) M2 147,936.54 636,127,139.20 4.90 0.49 0.49 0.49 0.49 0.49 0.49 0.49
2.2 Striping (STA 00+000 - STA 05+000) M2 110,644.91 355,170,167.52 2.73 0.27 0.27 0.27 0.27 0.27 0.27 0.27
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 10,606.25 304,187,250.00 2.34 0.08 0.08 0.08 0.08 0.08 0.08 0.08
3.1.2 Cut & Fill 50 - 1000 M M3 101,768.25 3,980,156,257.50 30.64 1.23 1.23 1.23 1.23 1.23 1.23
3.1.3 Cut & Fill 1000 - 5000 M M3 -
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebal M3 7,700.00 4,489,282,721.00 34.55 1.57
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 50,509,803.92 0.39 0.04 0.04 0.04 0.04 0.04 0.04
Fuel (Solar) Ls 1.00 51,856,732.03 0.40 0.04 0.04 0.04 0.04 0.04 0.04
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 0.04 0.02
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 0.59 0.03 0.03 0.03 0.03 0.03 0.03
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 130.00 521,703,000.00 4.02
1500 mm ---> 9 Unit m 199.00 976,867,368.75 7.52
2000 mm ---> 3 Unit m 71.00 465,555,431.25 3.58
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 16,836,274.51 0.13
Fuel --- 20 Liter/hr Ls 1.00 17,285,594.12 0.13
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 0.04
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 0.59
Sub Total 2,263,359,302.61
Total Keseluruhan 12,991,746,890.12 100.00
Rencana Minggu Ini 0.27 1.11 2.43 2.43 2.43 2.44 2.44 4.01
Total Rencana Minggu Ini 0.27 1.38 3.81 6.23 8.66 11.10 13.54 17.55
TIME SCHEDULE COAL HAULING ROAD SKC

Juli Agustus
M9 (10-16) M10 (17-23) M11 (24-30) M12 (31-06) M13 (07-13) M14 (14-20) M15 (21-27) M16 (28-03)
T T T T T T T T

0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08


0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18
0.01 0.01 0.01

0.49 0.49 0.49


0.27 0.27 0.27

0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08


1.23 1.23 1.23 1.23 1.23 1.23 1.23 1.23

1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57

0.04 0.04 0.04 0.04


0.04 0.04 0.04 0.04
0.02
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

0.57 0.57 0.57 0.57 0.57 0.57 0.57


1.50 1.50

4.01 4.58 4.60 3.81 3.73 3.73 5.23 5.23


21.56 26.14 30.74 34.55 38.28 42.01 47.24 52.47
Catatan :
Progress pengerjaan dalam bentuk nominal Rupiah
Capaian 30 Juli Konversi
(A) Bobot A thd RABKonversi
0-5 km Bobot
No Item Pekerjaan 0 - 5 Km 5-8,3 Km Bobot T RAB 5km Nilai Rp A : 0-5km Nilai Rp A : 5-8,3km Volume (Teoritis) Pengajuan Yali 5-8km Volume (Yali)
Bobot Nilai Rupiah V1 V2 0-5km 5-8,3km
1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Rp230,915,663 Rp152,404,337 0.74 Rp383,320,000.00 4.38 4.38 2.64 1.74 1.89 Rp230,915,662.65 Rp152,404,337.35 -
1.1.2 Project Set Up Opration Rp415,024,096 Rp273,915,904 1.33 Rp688,940,000.00 7.87 7.87 4.74 3.13 5.44 Rp415,024,096.39 Rp273,915,903.61 -
1.1.3 Safety Rp15,602,410 Rp10,297,590 0.05 Rp25,900,000.00 0.30 0.30 0.09 0.21 0.09 Rp7,709,666.31 Rp18,190,333.69 -
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing Rp643,567,412 Rp371,712,588 1.96 Rp1,015,280,000.00 11.59 11.59 4.90 6.70 4.90 Rp428,778,388.30 Rp586,501,611.70 136395.72 Rp456,309,980.00 106118.60
2.2 Striping Rp390,074,000 Rp112,386,000 0.97 Rp502,460,000.00 5.74 5.74 2.73 3.00 2.73 Rp239,400,715.08 Rp263,059,284.92 81949.93 Rp281,782,146.00 87782.60
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M Rp6,240,964 Rp4,119,036 0.02 Rp10,360,000.00 0.12 0.12 0.07 0.05 2.34 Rp6,240,963.86 Rp4,119,036.14 -
3.1.2 Cut & Fill 50 - 1000 M - - - - - - - - 30.64 - - -
3.1.3 Cut & Fill 1000 - 5000 M - - - - - - - - - - -
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm - - - - - - - - 34.55 - - -
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Rp46,807,229 Rp30,892,771 0.15 Rp77,700,000.00 0.89 0.89 0.53 0.35 0.39 Rp46,807,228.92 Rp30,892,771.08 1.00 Rp36,003,388.24 1.00
Fuel (Solar) Rp56,168,675 Rp37,071,325 0.18 Rp93,240,000.00 1.06 1.06 0.40 0.67 0.40 Rp34,953,776.71 Rp58,286,223.29 1.00 Rp36,963,478.59 1.00
Mobilisasi dan Demobilisasi Rp3,120,482 Rp2,059,518 0.01 Rp5,180,000.00 0.06 0.06 0.04 0.02 0.04 Rp3,120,481.93 Rp2,059,518.07 1.00 Rp3,494,117.65 1.00
Upah Pekerja dan Uang Makan Rp46,807,229 Rp30,892,771 0.15 Rp77,700,000.00 0.89 0.89 0.53 0.35 0.59 Rp46,807,228.92 Rp30,892,771.08 1.00 Rp54,508,235.29 1.00
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit - - - - - - - - 4.02 - - -
1500 mm ---> 9 Unit - - - - - - - - 7.52 - - -
2000 mm ---> 3 Unit - - - - - - - - 3.58 - - -
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) - - - - - - - - 0.13 - - -
Fuel --- 20 Liter/hr - - - - - - - - 0.13 - - -
Mobilisasi dan Demobilisasi - - - - - - - - 0.04 - - -
Upah Pekerja dan Uang Makan - - - - - - - - 0.59 - - -
Total Rp1,854,328,159 Rp1,025,751,841 5.56 Rp2,880,080,000.00 32.89 32.89 16.67 16.22 Rp1,459,758,209.04 Rp1,420,321,790.96 Rp869,061,345.77
Rp2,880,080,000
DP = Rp5,180,000,000 Total Project 15.3 = Rp51,800,000,000
Nilai Proyek 0 - 5 KM = Rp8,757,023,478 Total Project 5 = Rp8,757,023,478
Bobot DP adalah = Rp5.180.000.000/Rp8.544.808.258*100%
= 59.15%
Opnam baru bisa diberikan jika progress pekerjaan PT. Yali telah mencapai 5% diatas bobot DP yaitu sebesar = 60,62% + 5%
64.15%
RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 0-5KM

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 245,098,039.22 245,098,039.22 1.25
1.1.2 Project Set Up Opration Ls 1.00 706,928,104.58 706,928,104.58 3.60
1.1.3 Safety Ls 1.00 11,437,908.50 11,437,908.50 0.06
Sub Total 963,464,052.29
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 08+450) M2 236,600.00 4,300.00 1,017,380,000.00 5.18 Topo sudah diambil
2.2 Striping (STA 00+000 - STA 06+000) M2 168,000.00 3,210.00 539,280,000.00 2.75 Topo sudah diambil
Sub Total 1,556,660,000.00
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan 0.00
3.1.1 Cut & Fill 0 - 50 M M3 9,586.90 28,680.00 274,952,292.00 1.40
3.1.2 Cut & Fill 50 - 1000 M M3 110,990.49 39,110.00 4,340,838,063.90 22.12
3.1.3 Cut & Fill 1000 - 5000 M M3 62,960.38 43,110.00 2,714,221,981.80 13.83
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 7,700.00 589,348.73 4,537,985,221.00 23.13
Sub Total 11,867,997,558.70
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 50,509,803.92 50,509,803.92 0.26
Fuel (Solar) Ls 1.00 51,856,732.03 51,856,732.03 0.26
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.02
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.39
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 275.00 4,013,100.00 1,103,602,500.00 5.62
1500 mm ---> 9 Unit m 420.00 4,908,881.25 2,061,730,125.00 10.51
2000 mm ---> 3 Unit m 270.00 6,557,118.75 1,770,422,062.50 9.02
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 16,836,274.51 16,836,274.51 0.09
Fuel --- 20 Liter/hr Ls 1.00 17,285,594.12 17,285,594.12 0.09
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.02
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.39
Sub Total 5,234,988,190.11
Total Keseluruhan 19,623,109,801.10 100.00
Catatan :
Progress pengerjaan dalam bentuk nominal Rupiah
Capaian 30 Juli (A) Konversi Bobot A thd RAB 0-5 km Konversi Bobot
No Item Pekerjaan 0 - 5 Km 5-8,3 Km Bobot T RAB 5km Nilai Rp A : 0-5km Nilai Rp A : 5-8,3km
Bobot Nilai Rupiah V1 V2 0-5km 5-8,3km
1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Rp230,915,663 Rp152,404,337 0.74 Rp383,320,000.00 1.95 1.95 1.18 0.78 1.25 Rp230,915,662.65 Rp152,404,337.35
1.1.2 Project Set Up Opration Rp415,024,096 Rp273,915,904 1.33 Rp688,940,000.00 3.51 3.51 2.11 1.40 3.60 Rp415,024,096.39 Rp273,915,903.61
1.1.3 Safety Rp15,602,410 Rp10,297,590 0.05 Rp25,900,000.00 0.13 0.13 0.06 0.07 0.06 Rp11,437,908.50 Rp14,462,091.50
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing Rp602,000,000 Rp413,280,000 1.96 Rp1,015,280,000.00 5.17 5.17 3.09 2.09 3.09 Rp605,583,333.33 Rp409,696,666.67
2.2 Striping Rp449,400,000 Rp53,060,000 0.97 Rp502,460,000.00 2.56 2.56 2.29 0.27 2.29 Rp449,400,000.00 Rp53,060,000.00
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M Rp6,240,964 Rp4,119,036 0.02 Rp10,360,000.00 0.05 0.05 0.03 0.02 1.40 Rp6,240,963.86 Rp4,119,036.14
3.1.2 Cut & Fill 50 - 1000 M - - - - - - - - 22.12 - -
3.1.3 Cut & Fill 1000 - 5000 M - - - - - - - - 13.83 -
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse 0.00
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm - - - - - - - - 23.13 - -
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Rp46,807,229 Rp30,892,771 0.15 Rp77,700,000.00 0.40 0.40 0.24 0.16 0.26 Rp46,807,228.92 Rp30,892,771.08
Fuel (Solar) Rp56,168,675 Rp37,071,325 0.18 Rp93,240,000.00 0.48 0.48 0.26 0.21 0.26 Rp51,856,732.03 Rp41,383,267.97
Mobilisasi dan Demobilisasi Rp3,120,482 Rp2,059,518 0.01 Rp5,180,000.00 0.03 0.03 0.02 0.01 0.02 Rp3,120,481.93 Rp2,059,518.07
Upah Pekerja dan Uang Makan Rp46,807,229 Rp30,892,771 0.15 Rp77,700,000.00 0.40 0.40 0.24 0.16 0.39 Rp46,807,228.92 Rp30,892,771.08
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit - - - - - - - - 5.62 - -
1500 mm ---> 9 Unit - - - - - - - - 10.51 - -
2000 mm ---> 3 Unit - - - - - - - - 9.02 - -
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) - - - - - - - - 0.09 - -
Fuel --- 20 Liter/hr - - - - - - - - 0.09 - -
Mobilisasi dan Demobilisasi - - - - - - - - 0.02 - -
Upah Pekerja dan Uang Makan - - - - - - - - 0.39 - -
Total Rp1,872,086,747 Rp1,007,993,253 5.56 Rp2,880,080,000.00 14.68 14.68 9.52 5.16 Rp1,867,193,636.51 Rp1,012,886,363.49

Total Project 15.3 = Rp51,800,000,000


Total Project 5 = Rp19,623,109,801
PERBANDINGAN RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 0-5KM

TOTAL HARGA TOTAL HARGA 5KM TOTAL HARGA YALI TOTAL KERJA YALI
VOLUME VOLUME VOLUME HARGA SATUAN BOBOT 15,3 BOBOT 5 IBS BOBOT YALI
NO URAIAN PEKERJAAN UNIT 15.3KM IBS 24/08 PER 30 JULI KETERANGAN
15.3 KM 5KM IBS 5KM YALI
(RP) (RP) (%) (RP) (%) (RP) (%) (RP)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 1.00 1.00 245,098,039.22 750,000,000.00 1.45 245,098,039.22 1.89 245,098,039.22 1.25 Rp383,320,000.00
1.1.2 Project Set Up Opration Ls 1.00 1.00 1.00 706,928,104.58 2,163,200,000.00 4.18 706,928,104.58 5.44 706,928,104.58 3.60 Rp688,940,000.00
1.1.3 Safety Ls 1.00 1.00 1.00 11,437,908.50 35,000,000.00 0.07 11,437,908.50 0.09 11,437,908.50 0.06 Rp25,900,000.00
Sub Total 2,948,200,000.00 963,464,052.29 963,464,052.29
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 05+000) M2 434,910.00 147,936.54 236,600.00 4,300.00 1,870,113,000.00 3.61 636,127,139.20 4.90 1,017,380,000.00 5.18 Rp1,015,280,000.00
2.2 Striping (STA 00+000 - STA 05+000) M2 434,910.00 110,644.91 168,000.00 3,210.00 1,396,061,100.00 2.70 355,170,167.52 2.73 539,280,000.00 2.75 Rp502,460,000.00
Sub Total 3,266,174,100.00 991,297,306.72 1,556,660,000.00
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan
3.1.1 Cut & Fill 0 - 50 M M3 29,335.90 10,606.25 9,586.90 28,680.00 841,353,612.00 1.62 304,187,250.00 2.34 274,952,292.00 1.40 Rp10,360,000.00
3.1.2 Cut & Fill 50 - 1000 M M3 339,338.51 101,768.25 110,990.49 39,110.00 13,271,528,961.84 25.62 3,980,156,257.50 30.64 4,340,838,063.90 22.12
3.1.3 Cut & Fill 1000 - 5000 M M3 192,658.75 - 62,960.38 43,110.00 8,305,518,712.50 16.03 - - 2,714,221,981.80 13.83
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 23,562.00 7,700.00 7,700.00 583,023.73 13,737,205,148.44 26.52 4,489,282,721.00 34.55 4,537,985,221.00 23.13
Sub Total 36,155,606,434.78 8,773,626,228.50 11,867,997,558.70
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 1.00 1.00 50,509,803.92 154,560,000.00 0.30 50,509,803.92 0.39 50,509,803.92 0.26 Rp77,700,000.00
Fuel (Solar) Ls 1.00 1.00 1.00 51,856,732.03 158,681,600.00 0.31 51,856,732.03 0.40 51,856,732.03 0.26 Rp93,240,000.00
Mobilisasi dan Demobilisasi Ls 1.00 1.00 1.00 4,901,960.78 15,000,000.00 0.03 4,901,960.78 0.04 4,901,960.78 0.02 Rp5,180,000.00
Upah Pekerja dan Uang Makan Ls 1.00 1.00 1.00 76,470,588.24 234,000,000.00 0.45 76,470,588.24 0.59 76,470,588.24 0.39 Rp77,700,000.00
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 262.00 130.00 275.00 4,013,100.00 1,051,432,200.00 2.03 521,703,000.00 4.02 1,103,602,500.00 5.62
1500 mm ---> 9 Unit m 262.00 199.00 420.00 4,908,881.25 1,286,126,887.50 2.48 976,867,368.75 7.52 2,061,730,125.00 10.51
2000 mm ---> 3 Unit m 942.00 71.00 270.00 6,557,118.75 6,176,805,862.50 11.92 465,555,431.25 3.58 1,770,422,062.50 9.02
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 1.00 1.00 16,836,274.51 51,519,000.00 0.10 16,836,274.51 0.13 16,836,274.51 0.09
Fuel --- 20 Liter/hr Ls 1.00 1.00 1.00 17,285,594.12 52,893,918.00 0.10 17,285,594.12 0.13 17,285,594.12 0.09
Mobilisasi dan Demobilisasi Ls 1.00 1.00 1.00 4,901,960.78 15,000,000.00 0.03 4,901,960.78 0.04 4,901,960.78 0.02
Upah Pekerja dan Uang Makan Ls 1.00 1.00 1.00 76,470,588.24 234,000,000.00 0.45 76,470,588.24 0.59 76,470,588.24 0.39
Sub Total 9,430,019,468.00 2,263,359,302.61 5,234,988,190.11
Total Keseluruhan 51,800,000,002.78 100.00 12,991,746,890.12 100.00 19,623,109,801.10 100.00

VOLUME
RENCANA ANGGARAN BIAYA COAL HAULING ROAD SKC 0-5KM

HARGA SATUAN TOTAL HARGA BOBOT


NO URAIAN PEKERJAAN UNIT VOLUME KETERANGAN
(RP) (RP) (%)

1 PEKERJAA PERSIAPAN
1.1 Project Set Up
1.1.1 Material, Equitment and Ancillaries Ls 1.00 245,098,039.22 245,098,039.22 1.25
1.1.2 Project Set Up Opration Ls 1.00 706,928,104.58 706,928,104.58 3.60
1.1.3 Safety Ls 1.00 11,437,908.50 11,437,908.50 0.06
Sub Total 963,464,052.29
2 PEKERJAAN LAND CLEARIG DAN STRIPPING
2.1 Land Clearing (STA 00+000 - STA 08+450) M2 236,600.00 4,300.00 1,017,380,000.00 5.18 Topo sudah diambil
2.2 Striping (STA 00+000 - STA 06+000) M2 168,000.00 3,210.00 539,280,000.00 2.75 Topo sudah diambil
Sub Total 1,556,660,000.00
3 PEKERJAAN STRUKTUR JALAN
3.1 Pek. Penimbunan dan Pemadatan Tanah Pilihan 0.00
3.1.1 Cut & Fill 0 - 50 M M3 9,586.90 28,680.00 274,952,292.00 1.40
3.1.2 Cut & Fill 50 - 1000 M M3 110,990.49 39,110.00 4,340,838,063.90 22.12
3.1.3 Cut & Fill 1000 - 5000 M M3 62,960.38 43,110.00 2,714,221,981.80 13.83
3.2 Pek. Penghamparan dan Pemadatan Sub - Base Coarse
3.2.1 Penghamparan Base Coarse (Include Material) Ketebalan 20cm M3 7,700.00 589,348.73 4,537,985,221.00 23.13
Sub Total 11,867,997,558.70
4 PEKERJAAN GENERAL
4.1 Pembuatan Jembatan Temporary
Sewa Alat (Exca/Ponton) Ls 1.00 50,509,803.92 50,509,803.92 0.26
Fuel (Solar) Ls 1.00 51,856,732.03 51,856,732.03 0.26
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.02
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.39
4.2 Pemasangan Armco (Include Material)
1200 mm ---> 6 Unit m 275.00 4,013,100.00 1,103,602,500.00 5.62
1500 mm ---> 9 Unit m 420.00 4,908,881.25 2,061,730,125.00 10.51
2000 mm ---> 3 Unit m 270.00 6,557,118.75 1,770,422,062.50 9.02
4.3 Pembuatan Tanggul dan Dermaga
Sewa Alat (Exca) Ls 1.00 16,836,274.51 16,836,274.51 0.09
Fuel --- 20 Liter/hr Ls 1.00 17,285,594.12 17,285,594.12 0.09
Mobilisasi dan Demobilisasi Ls 1.00 4,901,960.78 4,901,960.78 0.02
Upah Pekerja dan Uang Makan Ls 1.00 76,470,588.24 76,470,588.24 0.39
Sub Total 5,234,988,190.11
Total Keseluruhan 19,623,109,801.10 100.00
Striping
STA. 00+000 - 00+200 = 5,317.17 m2
STA. 00+200 - 00+400 = 10,235.78 m2
STA. 00+400 - 00+600 = 15,269.90 m2
STA. 00+600 - 00+800 = 20,554.98 m2
STA. 00+800 - 01+000 = m2
STA. 01+000 - 01+200 = m2
STA. 01+200 - 01+400 = m2
STA. 01+400 - 01+600 = m2
STA. 01+600 - 01+800 = m2
STA. 01+800 - 02+000 = m2
STA. 02+000 - 02+200 = m2
STA. 02+200 - 02+400 = m2
STA. 02+400 - 02+600 = m2
STA. 02+600 - 02+800 = m2
STA. 02+800 - 03+000 = m2
STA. 03+000 - 03+200 = m2
STA. 03+200 - 03+400 = m2
STA. 03+400 - 03+600 = m2
STA. 03+600 - 03+800 = m2
STA. 03+800 - 04+000 = m2
STA. 04+000 - 04+200 = m2
STA. 04+200 - 04+400 = m2
STA. 04+400 - 04+600 = m2
STA. 04+600 - 04+800 = m2
STA. 04+800 - 05+000 = m2

Anda mungkin juga menyukai