PT.

INTI BANGUN SARANA


HAULING ROAD PROJECT SECTION A
DESA AMMPELU MUDO DAN DESA TENAM

Laporan Harian (Daily Report) Section A


Nama Proyek Hauling Road Project Section A (STA 32+850 - STA 44+661)

Nama Kontraktor PT. Inti Bangun Sarana Tuesday, August 1, 2023


Lingkup Pekerjaan Mobilisasi, Land Clearing, Cut and Fill, CSP Installation, bund wall, dan Perkerasan Base Coarse

A. AKTIVITAS PEKERJAAN B. PEMAKAIAN ALAT BERAT


a - 1 Pekerjaan Mayor Item Status
Jumlah
No Jenis Alat Berat Keterangan
Unit
No Item Pekerjaan Mayor Sat. Status Volume Keterangan Ready Stand by BD
3 Unit Sec -
2 Land Clearing and Top Soil Stripping 1 Komatsu PC-210 0 0 0 0
B
Perbatasan
2.1 - Land Clearing m2 On Progress 1.3 km 2 Compactor Sakai Sheep Foot Roller 0 0 0 0 Sec-B
Lahan Jony
Perbatasan
2.1 - Top Soil Striping m2 On Progress 1.3 km 3 Compactor Liu Gong 6611E 0 0 0 0 Sec-B
Lahan Jony
3 Cut and Fill , Sub-Base Coarse 4 Grader Liu Gong 4215D 0 0 0 0 Stand by
Perbatasan
3.1 Cut & Fill m3 On Progress 1.3 km 5 Dozer Dressta TD-25M 0 0 0 0 Sec-B
Lahan Jony
3.2 Penghamparan Base Coarse (Include Material) m3 Not yet - 6 Dozer Komatsu D-155 0 0 0 0 BD

4 General Work 7 Dozer Komatsu D-85 0 0 0 0 Sec-B

8 Dump Truck CAMC 0 0 0 0 Sec-B

4.1 Pembuatan Jembatan Temporary ls On Progress - 9 Dump Truck HINO 0 0 0 0 BD

4.2 Pemasangan CSP (Incule Material) ls On Progress 2 lane Jumlah 0 0 0 0

4.3 Pembuatan Tanggul Jalan ls On Progress -


C. MATERIAL ON SITE
a - 2 Pekerjaan Lain - lain Keterangan
No Material
No Item Pekerjaan Status Lokasi Keterangan Sat. Jumlah Lokasi

1 CSP Diameter 1,5m STA. 32+750

2 CSP Diameter 2m STA. 32+750

7
D. PERSONEL PROYEK
Keterangan 8
No Tugas/Jabatan
Sat. Jumlah Lokasi 9

1 Project Manager org 1 Site 10

2 Supervisor org 1 Site


E. BENCANA ALAM/KEJADIAN PENGHAMBAT PEKERJAAN
3 Pengawas org 0 Site Keterangan
No Jenis
4 Senior Surveyor org 0 Site Jam Lokasi Akibat

5 Surveyor org 2 Site 1

6 Helper Survey org 2 Site 2

7 Logistic org 0 Site 3

8 Operator org 0 Site 4

9 Pekerja Harian org 0 Site 5

10 Fuelman org 0 Site 6

Jumlah 6 7

F. PERMASALAHAN GENERAL
No Masalah Solusi* Status Keterangan
1 Terdapat banyak jalur air, sehingga elevasi penimbunan tidak bisa memasang corrugated steel pipe pada aliran tersebut, sehingga penimbunan bisa mencapai
terlalu tinggi elevasi yang sudah ditentukan On Procces

2 Masih belum melakukan land clearing, karena beberapa lahan belum Menunggu lahan dibebaskan
dibebaskan On Procces

Dibuat Oleh Mengetahui

Nama : Muhammad Ma'ruf Nama: Bambang Subagio Wiyono


PT. INTI BANGUN SARANA
HAULING ROAD PROJECT SECTION A
DESA AMMPELU MUDO DAN DESA TENAM

Stripmap Pekerjan Section A

Nama Proyek Hauling Road Project Section A (STA 32+850 - STA 44+661)

Nama Kontraktor PT. Inti Bangun Sarana Tuesday, August 1, 2023


Lingkup Pekerjaan Mobilisasi, Land Clearing, Cut and Fill, CSP Installation, bund wall, dan Perkerasan Base Coarse

STA. 44+661
STA. 32+850 STA. 42+500 STA. 43+850

Tembesi
STA. 43+842

STA. 43+859
Arah
STA. 34+150

STA. 34+825

STA. 35+475

STA. 36+425
PELABUHAN
Camp Solar
(Cross 3 Ampelu Mudo)

(Crossing Pesantren)
Jalan Desa Tenam
Jalan TMD

UNDERPASS
SEC B
LAHAN JOHAN I LAHAN PENDI LAHAN JOHAN II BRS

675.00 650.00 950.00 LAHAN


Pak H. FUAD

Bulian
Arah
2275.00 (100 Meter)

9,650.00 1,342.00 16.50 802.50

11,811.00
32+850

44+661
34+150
Land Clearing dan Striping

1,300 10,511
32+850

44+661
34+150

Cutt & Fill

1,300 10,511
32+850

44+661
Penghamparan Base Coarse

11,811

Rencana : 11,811 m
Land Clearing dan Striping Realisasi : 1,300 m
Deviasi : -10,511 m

Rencana : 11,811 m
Cutt & Fill Realisasi : 1,300 m
Deviasi : -10,511 m

Rencana : 11,811 m
Penghamparan Base Coarse Realisasi : 0 m
Deviasi : -11,811 m

LEGENDA :

= LOKASI LAHAN BELUM BEBAS → 2,375.00 Mtr

= LOKASI PEKERJAAN HAULING ROAD SECTION-A → 9,419.50 Mtr

= LOKASI KONSTRUKSI UNDERPASS TENAM → 16.50 Mtr

TOTAL 11,811 Mtr

= CAMP SOLAR

= QUARRY TANAH

= QUARRY TANAH
PT. INTI BANGUN SARANA
HAULING ROAD PROJECT SECTION A
DESA AMMPELU MUDO DAN DESA TENAM

Laporan Cuaca

Nama Proyek Hauling Road Project Section A (STA 32+850 - STA 44+661)

Nama Kontraktor PT. Inti Bangun Sarana Tuesday, August 1, 2023

Lingkup Pekerjaan Mobilisasi, Land Clearing, Cut and Fill, CSP Installation, bund wall, dan Perkerasan Base Coarse

Jam
Jml Jam Bisa
Hari dan Tanggal
Bekerja
06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 00:00 01:00 02:00 03:00 04:00 05:00

Sabtu, 01 Juli 2023 0 Presentase Jam Bekerja Harian

Minggu, 02 Juli 2023 Jumlah Jam Kerja / Hari = 10.00 Jam

Senin, 03 Juli 2023 Jumlah Jam Bisa Kerja = 0.00 Jam

Selasa, 04 Juli 2023 Jumlah Jam Tidak Bekerja = 10.00 Jam

Rabu, 05 Juli 2023


Presentase Jam Bekerja
Kamis, 06 Juli 2023 Tuesday, August 1, 2023 = 0.00%

Jumat, 07 Juli 2023

Sabtu, 08 Juli 2023 Presentase Jam Bekerja Harian Komulatif

Minggu, 09 Juli 2023 Jumlah Jam Kerja / Hari = 10.00 Jam

Senin, 10 Juli 2023 Jumlah Jam Bisa Kerja = 0.00 Jam

Selasa, 11 Juli 2023 Jumlah Jam Tidak Bekerja = 10.00 Jam

Rabu, 12 Juli 2023


Presentase Jam Bekerja Sampai Dengan
Kamis, 13 Juli 2023 Tuesday, August 1, 2023 = 0.00%

Jumat, 14 Juli 2023

Sabtu, 15 Juli 2023

Minggu, 16 Juli 2023

Senin, 17 Juli 2023

Selasa, 18 Juli 2023

Rabu, 19 Juli 2023

Kamis, 20 Juli 2023

Jumat, 21 Juli 2023

Sabtu, 22 Juli 2023

Minggu, 23 Juli 2023

Senin, 24 Juli 2023

Selasa, 25 Juli 2023

Rabu, 26 Juli 2023

Kamis, 27 Juli 2023

Jumat, 28 Juli 2023

Sabtu, 29 Juli 2023

Minggu, 30 Juli 2023

Senin, 31 Juli 2023

: Cerah : Mendung : Gerimis ● : Hujan □ : Kondisi Licin dan Basah


PT. INTI BANGUN SARANA
HAULING ROAD PROJECT SECTION A
DESA AMMPELU MUDO DAN DESA TENAM

Dokumentasi

Nama Proyek Hauling Road Project Section A (STA 32+850 - STA 44+661)

Nama Kontraktor PT. Inti Bangun Sarana Tuesday, August 1, 2023

Lingkup Pekerjaan Mobilisasi, Land Clearing, Cut and Fill, CSP Installation, bund wall, dan Perkerasan Base Coarse