KANTOR TURSINA
R R
Date 07-Jun-23
BARAT Sheet 3 of 4
R Rev 0
:
Harga Satuan Sub Total
a b c d e=axc f=axd
I PEKERJAAN PERSIAPAN
1 Pemasangan Bouwplank 80 m
152.315 12.185.200 12.185.200
Jumlah 12.185.200 - 12.185.200
V PEKERJAAN LANTAI
1 Wiremesh M6 (Double)
IX PENGECATAN
Pengecatan Dinding Baru
275, 4.6 12. 1.295. 3.547. 4.843.
1 m2
(1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
80 97 864 433 891 324
Pengecetan Plafon 137, 25.1 22. 3.466. 3.161. 6.627.
2 m2
(1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
90 35 924 117 220 336
Jumlah 4.761.549 6.709.111 11.470.660
XI PEKERJAAN SANITASI
-
Memasang Kran Air 10 Unit 27.568 17.600 275.680 176.000 451.680
-
Wastafel 1 Unit 621.878 405.625 621.878 405.625 1.027.503
Jumlah 14.695.100
Terbilang : Tiga Ratus Empat Puluh Dua Juta Delapan Ratus Ribu Rupiah