Anda di halaman 1dari 2

Form .

Prod 10

DIVISI : Infrastructure 1 Edisi : Mei 2020 Rev : 01


: REMEDIAL DAN PENANGANAN SEDIMENTASI BENDUNGAN DI SUMBAWA -IV ( Woro, Lasi II,
PROYEK Soncolopi, Oi Toi, Jambu, Tolotangga, Kesi, Lananga, Sangupasante, Paradokanca, Sumi, Laju, Waworada,
Roi Roka, Kempo )

NO. AB :

RENCANA BULAN JULI-DES. :


BAGIAN PEKERJAAN :

PROGRAM PENGADAAN SUMBER DAYA BULANAN JULI -DESEMBER


NO JENIS MATERIAL / ALAT / KUANT.KEBTHN EST. TERSEDIA PROGRAM PENGADAAN KET
SAT
TENAGA TOTAL AKHIR BL INI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER DESEMBER
1 2 3 4 5 6 7 8 9 10 10 11

I. MATERIAL
1 Batu kali untuk rip rap m3 Rencana 6,915 1,680 5,229 - 6 - -
2 Batu kali pasangan batu m3 Rencana 2,264 274 274 1,329 36 229 121
3 Pasir pasang m3 Rencana 746 120 120 327 26 100 53
4 Pasir cor m3 Rencana 1,057 13 13 202 215 597 18
5 Koral / batu pecah m3 Rencana 1,559 18 18 299 317 880 27
6 Semen @50Kg zak Rencana 22,869 2,523 2,673 7,172 263 9,909 329
7 Besi D 10 -1200 ( lonjor ) Ljr Rencana 126 - 24 48 54 - -
8 Besi dia 12 Ljr Rencana 74 - - - - 64 10
9 Besi dia 16 Ljr 5 - - - 5 - - -
10 Wire mesh D8 - - - - - - - -
11 U-dicth 40 x40 Bh Bh 375 - - - - 375 - -
12 Kawat bronjong 200 x 100 x 50 Bh 496 - - 496 - - -
13 BESI H 200 X 200X18-12 M Ljr 1 - 1 - - - -

II. ALAT KONSTRUKSI


1 Excavator unit Rencana 180 5 25 42 46 44 20

2 Dump Truck unit Rencana 902 23 123 209 230 219 100

3 Dozer unit Rencana 27 1.00 4.00 6.00 6.00 5.00 5.00

4 Beton Molen 350 ltr unit Rencana - - - - - - -

5 Vibrator unit Rencana

6 Genset unit Rencana

7 Pompa air 2" unit Rencana

III. TENAGA KERJA


1 Pelaksana Org Rencana 42 7.00 7.00 7.00 7.00 7.00 7.00
Org Realisasi
2 Surveyor Org Rencana 42 7.00 7.00 7.00 7.00 7.00 7.00
` Org Realisasi
3 Operator Org Rencana 207 6 29 48 52 49 25
Org Realisasi
4 Mekanik Org Rencana 42 7.00 7.00 7.00 7.00 7.00 7.00
Org Realisasi
5 Sopir DT Org Rencana 902 23 123 209 230 219 100
Org Realisasi
6

Bima ,
Diketahui / Disetujui : Dibuat oleh :
PM SOM

Surahman Made Rasma


ACTION PLAN FEBRUARI 2022
REMEDIAL DAN PENANGANAN SEDIMENTASI BENDUNGAN DI SUMBAWA -IV ( Woro, Lasi II, Soncolopi, Oi Toi, Jambu, Tolotangga, Kesi,
Lananga, Sangupasante, Paradokanca, Sumi, Laju, Waworada, Roi Roka, Kempo )

RINCIAN PEKERJAAN

Bedunaga Sumi

JULI AGUSTUS SEPTERBER OKTOBER NOPEMBER DESEMBER


Pekerjaan

Bedunaga Sumi
1 PASANGAN BATU 1:4
2 PASANGAN BRONJONG
3 PLESTERAN
4 ACIAN
5 BETON K175
6 BETON K225 5.60
7 RIP-RAP
8 BESI H 200 X 200X18
9 BESI D 10
10 BESI D 12
11 BESI D 16
12 WIREMESH
13 Galian sidimen 45500 45500 11631.42

Bendungan Oi Toi
1 PASANGAN BATU 1:4 228.48 228.48 228.48 30.19 77.35
2 PASANGAN BRONJONG
3 PLESTERAN 49.23 49.23 49.23 100.00 36.60
4 ACIAN 28.92 28.92 28.92 46.25 14.00
5 BETON K175 100.00 100.00
6 BETON K225 17.67 17.67 17.67 82.00 710.80 2.20 848.00
7 RIP-RAP 1400.00 2500.00
8 BESI H 200 X 200X18 347.00 347.00
9 BESI D 10 181.00 181.00 400.00
10 BESI D 12 108.00
11 BESI D 16
12 WIREMESH
13 Galian sidementasi 26460.00 87500.00 87500.00 87500.00 87500.00 75129.34

Bendungan Laju
1 PASANGAN BATU 1:4
2 PASANGAN BRONJONG
3 PLESTERAN
4 ACIAN
5 BETON K175
6 BETON K225
7 RIP-RAP
8 BESI H 200 X 200X18
9 BESI D 10
10 BESI D 12
11 BESI D 16
12 WIREMESH
13 Galian sidementasi 17500.00 9557.98

BENDUNGAN WORO
1 PASANGAN BATU 1:4
2 PASANGAN BRONJONG
3 PLESTERAN 134 324 17
4 ACIAN 7 67
5 BETON K175 43 43 21
6 BETON K225
7 RIP-RAP 988.15 5.20
8 BESI H 200 X 200X18
9 BESI D 10
10 BESI D 12
11 BESI D 16
12 WIREMESH
13 Galian sidementasi 19,600.00 35,000.00 23,400.00
14 Pagar pengaman BRC 35.78

BENDUNGAN TOLOTANGGA
1 PASANGAN BATU 1:4 234 191 23.635
2 PASANGAN BRONJONG
3 PLESTERAN 12 0.01932
4 ACIAN 9.2
5 BETON K175
6 BETON K225 69.35 167.47 3.4 18.0808
7 RIP-RAP 869.267868
8 BESI H 200 X 200X18
9 BESI D 10 172.5
10 BESI D 12 680
11 BESI D 16
12 WIREMESH
13 Galian sidementasi 19600 35000 35000 45274.63594

BENDUNGAN PARADOKANCA
1 PASANGAN BATU 1:4 149.025
2 PASANGAN BRONJONG
3 PLESTERAN 186.2845
4 ACIAN 186.2845
5 BETON K175 55.135
6 BETON K225 90.9520356
7 RIP-RAP
8 BESI H 200 X 200X18
9 BESI D 10
10 BESI D 12
11 BESI D 16 93.89494272
12 WIREMESH
13 Galian sidementasi 35000 35000 35000 4944

BENDUNGAN WAWORADA
1 PASANGAN BATU 1:4
2 PASANGAN BRONJONG
3 PLESTERAN
4 ACIAN
5 BETON K175
6 BETON K225
7 RIP-RAP
8 BESI H 200 X 200X18
9 BESI D 10
10 BESI D 12
11 BESI D 16
12 WIREMESH
13

BENDUNGAN ROI ROKA


1 PASANGAN BATU 1:4
2 PASANGAN BRONJONG 496
3 PLESTERAN
4 ACIAN
5 BETON K175
6 BETON K225 9.00 5.10 5.10 5.10
7 RIP-RAP
8 BESI H 200 X 200X18
9 BESI D 10
10 BESI D 12
11 BESI D 16
12 WIREMESH 42.50 42.50 42.50
13 Galian sidementasi 43,750.00 43,750.00 43,750.00 25,544.30

REKAP
1 PASANGAN BATU 1:4 228.48 228.48 611.51 30.19 191.00 100.99 1,390.646
2 PASANGAN BRONJONG - - 496.00 - - - 496.000
3 PLESTERAN 49.23 49.23 381.52 424.00 17.00 36.62 957.604
4 ACIAN 28.92 28.92 222.20 113.25 9.20 14.00 416.485
5 BETON K175 - - 98.14 43.00 121.00 - 262.135
6 BETON K225 17.67 17.67 186.97 260.17 719.30 25.38 1,227.153
7 RIP-RAP 1,400.00 4,357.42 - 5.20 - - 5,762.620
8 BESI H 200 X 200X18 - 347.00 347.00 - - - 694.000
9 BESI D 10 - 181.00 353.50 400.00 - - 934.500
10 BESI D 12 - - - - 680.00 108.00 788.000
11 BESI D 16 - - 93.89 - - - 93.895
12 WIREMESH - - - 42.50 42.50 42.50 127.500