PROYEK

PEMBANGUNAN PASAR DHARMASRAYA SUMATERA BARAT

Tanggal mulai : 18/12/2023


Tanggal Selesai : 11/12/2024 ABM-AT.11

LAPORAN HARIAN
PERIODE
TANGGAL MINGGU KE HARI KE SISA HARI
8/3/2024 13 82 278
JML VOLUME BOBOT
PERSONIL KONTRAKTOR PEKERJAAN YANG DILAKSANAKAN SAT DEVIASI KETERANGAN
Org RENC. PERSEN
STAF LAPANGAN 1 TBM - - -
1 PEM - 2 PEMANCANGAN TIANG PANCANG M' 150
2 PPM 1 3 URUGAN EMBUNG M3 386,69
3 QHSE 1 4
4 HSE 1 5
5 QC 2 6
6 QS 2 7
7 DCC 1 8
8 DRAFTER 1 9
12 SCHEDULER 1 10

13 SURVEY 2 11

14 SECURITY 3 12

15 OB 2 13

16 LOGISTIK 2 14

17 PI 1

18 BIM 1

19 SUPERVISOR 1

20
21
22
JUMLAH 22

PEKERJA MATERIAL YANG DIGUNAKAN VOL. MATERIAL YANG DATANG JMLH


1 MANDOR 1 1 MINI PILE 6M 20 1
2 WAKIL MANDOR 1 2 MINI PILE 3M 10 2
3 HARIAN K3 2 3 3
4 PEKERJA 4 4 4
5 5 5
6 6 6
7 7 7
8 8 8
9 9 9
10 10 10
11 11 11
12 12 12
JUMLAH 8

OPERATOR/ SUPIR ALAT


1 OPERATOR HSPD 4 1 HSPD 1

2 BULDOZER 1 2 BULDOZER 1

3 EXCAVATOR 200 1 3 EXCAVATOR 200 1

4 EXCAVATOR 75 1 4 EXCAVATOR 75 1

5 5
JUMLAH 7 KEADAAN CUACA HARI INI
Pekerjaan dimulai jam 08.00 s/d jam 17.00 PAGI 08.00-10.00 WIB SIANG 7-03-2024 JAM 10.00-14.00 WIB SORE 7-03-2024 JAM 14.00-17.00
Jam kerja (sepenuhnya dapat/sebagian tidak dapat digunakan
MENDUNG CERAH HUJAN
untuk bekerja) karena -

Catatan : Mengetahui, Dharmasraya, 8 Maret 2024


PT. BENTAREKA CIPTA PT. ADHI PERSADA GEDUNG

____________ EKO WAHYUDI


Tim Leader Project Manager