PROYEK

PEMBANGUNAN PASAR DHARMASRAYA SUMATERA BARAT

Tanggal mulai : 18/12/2023


Tanggal Selesai : 12/12/2024 ABM-AT.11

LAPORAN HARIAN
PERIODE
TANGGAL MINGGU KE HARI KE SISA HARI
3/30/2024 16 104 256
JML VOLUME BOBOT
PERSONIL KONTRAKTOR PEKERJAAN YANG DILAKSANAKAN SAT RENC. PERSEN
DEVIASI KETERANGAN
Org
STAF LAPANGAN 1 TBM - - -
1 PEM 1 2 PEMANCANGAN TIANG PANCANG m' 120
2 PPM 1 3 PEK PEMASANGAN PONDASI BATU BELAH PLAT DUIKER m3 64.68
3 PFM 1 4
3 QHSE 1 5
4 HSE 1 6
5 QC 2 7
6 QS 2 8
7 DCC 1 9
8 DRAFTER 1 10

9 SCHEDULER 1 11

10 SURVEY 2 12

11 SECURITY 3 13

12 OB 2 14

13 LOGISTIK 2 15

14 PI 1

15 BIM 1

16 COST CONTROL 1

16 SUPERVISOR 1 ]
17 AKUNTAN 1 ]
18 MEKANIK 1

JUMLAH 27

PEKERJA MATERIAL YANG DIGUNAKAN VOL. MATERIAL YANG DATANG JMLH


1 MANDOR 3 1 MINI PILE 6M 16 btg 1

2 WAKIL MANDOR 1 2 MINI PILE 3M 8 btg 2


3 HARIAN K3 1 3 3
4 PEKERJA 12 4 4
5 5 5
6 6 6
7 7 7
JUMLAH 17

OPERATOR/ SUPIR ALAT


1 HSPD 4 1 HSPD 1

2 2
3 3
4 4
5 5 1

JUMLAH 4 KEADAAN CUACA HARI INI


Pekerjaan dimulai jam 08.00 s/d jam 17.00 PAGI 08.00-10.00 WIB SIANG 30-03-2024 JAM 10.00-14.00 WIB SORE 30-03-2024 JAM 14.00-17.00
Jam kerja (sepenuhnya dapat/sebagian tidak dapat digunakan
CERAH CERAH CERAH
untuk bekerja) karena -

Catatan : Mengetahui, Dharmasraya, 30 Maret 2024


PT. BENTAREKA CIPTA PT. ADHI PERSADA GEDUNG

EKO WAHYUDI
Project Manager
FOTO DOKUMENTASI
TANGGAL : 30 Maret 2024
HARI KE : 104

TBM

PEKERJAAN PEMANCANGAN TIANG PANCANG

PEK PEMASANGAN PONDASI BATU BELAH PLAT DUIKER